Page 1: JLab preparations for upgrade, FY05 budget Elton Smith Hall D Collaboration Meeting May 20-22, 2004

JLab preparations for upgrade,FY05 budget

Elton Smith

Hall D Collaboration Meeting

May 20-22, 2004

Page 2: JLab preparations for upgrade, FY05 budget Elton Smith Hall D Collaboration Meeting May 20-22, 2004

Contract Status

All FY04 contracts awarded IU contract to evaluate Pb glass and pmts

awarded this week Budget spent

Page 3: JLab preparations for upgrade, FY05 budget Elton Smith Hall D Collaboration Meeting May 20-22, 2004

795

0

155

40

43

25

60

78

50

50

235

59

FY04budget

602

28

50

33

0

10

78

52

37

255

59

FY04actual

Forward calorimeter

CDC

Fiber tracker

Total

Operations

Jlab staff

Cerenkov Counter

FDC

Upstream Veto

Barrel calorimeter module (Vitaly)

TOF shields and slab prototype

Tagger (Guangliang)+ collimator

Solenoid Refurbishment

Computing

Item

Page 4: JLab preparations for upgrade, FY05 budget Elton Smith Hall D Collaboration Meeting May 20-22, 2004

Producing the 12-GeV CDR

Updating pCDR reenergized by CD-0 Cardman to outline process to go to CDR at

summer User’s Group Meeting Create a new editorial board

Suggestions requested from User’s Group for membership

CDR will consist of pCDR + updates with sections of recent interest + cost/schedule/performance document (ala G0)

Page 5: JLab preparations for upgrade, FY05 budget Elton Smith Hall D Collaboration Meeting May 20-22, 2004

Producing the 12-GeV CDR (cont.) Open process

Experimental equipment available to anyone with scientifically viable idea, e.g. new experiments in Hall D.

Page 6: JLab preparations for upgrade, FY05 budget Elton Smith Hall D Collaboration Meeting May 20-22, 2004

Management of 12-GeV Project Project management structure

Allison Lung has been appointed (interim) project director for the 12-GeV project

Project services office to track progress Management structure will parallel the current

management for 6-GeV operations Three associate project managers (accelerator, physics

and civil) Below this level, appoint “matrixed” staff as deputies Search for a Hall D manager

Page 7: JLab preparations for upgrade, FY05 budget Elton Smith Hall D Collaboration Meeting May 20-22, 2004

Management of 12-GeV Project (cont.) Adjust staffing to scope of WBS structure

Careful to not put 6-GeV program at risk Management structure clarified within about one

month

Page 8: JLab preparations for upgrade, FY05 budget Elton Smith Hall D Collaboration Meeting May 20-22, 2004

Budget profiles

Now that the project has begun with CD-0, a careful line must be drawn between operations and 12-GeV project spending.

(Cost) baseline for 12-GeV project will not be established till CD-1

CD-1 (Lehman Review) will take place in summer of 2005

The entire community must focus on passing this review.

Page 9: JLab preparations for upgrade, FY05 budget Elton Smith Hall D Collaboration Meeting May 20-22, 2004

Budget profiles (cont.)

Project director (Allison Lung) will conduct discussions with DOE (Joanne Simon-Gillo) to obtain a proposed schedule target milestones, etc.

Discussions with DOE specifically about

Hall D management structure regarding guidelines for creating the group rate of hires

Page 10: JLab preparations for upgrade, FY05 budget Elton Smith Hall D Collaboration Meeting May 20-22, 2004

Hall D proposed staffing

131313131053Total

6Beamline111111 Beamline/tagger

5trig11111 Electronics

6PID111111 PID

4Calor1111 Calorimetry

5Tracking11111 Tracking

7Proj Man

1111111Coordinator (Detector/Electronics)

5Slow Controls

11111 Slow Controls

4Online1111 Level 3 Farm

5Offline11111 Offline

5Online11111 Online

4DAQ1 111 DAQ

7Proj Man1111111Coordinator (Computing/DAQ)

7Proj Man

1111111Group Leader

Man-yrSystem43210-1-2Year

Page 11: JLab preparations for upgrade, FY05 budget Elton Smith Hall D Collaboration Meeting May 20-22, 2004

Hall D Budget for FY05

Budget for next year $600 K + incremental 12-GeV funds, depending on

funding and determined by 12-GeV management R&D will be prioritized for entire project

Can become upgrade-specific Priority will be given to activities which will

establish technical feasibility of project