joint health and safety committee report on b.c. place stadium roof

Upload: bobmackin

Post on 09-Apr-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/8/2019 Joint Health and Safety Committee Report on B.C. Place Stadium roof

    1/82

    InvestigationReport: BCPlaceRoofDeflationIncidentof

    January5,2007

    CompletedbytheInvestigationSubcommittee

    SubmittedbytheBCPlaceJointHealthandSafetyCommittee

    December21,2007

  • 8/8/2019 Joint Health and Safety Committee Report on B.C. Place Stadium roof

    2/82

    ThisreportsprincipalauthorsaretheInvestigationSubcommitteeconsistingof:

    JimHughes,CSP

    JackieIng

    JamesSwank

    Thisreportwasreviewed,finalizedandsubmittedbytheBCPlaceJointHealth&Safety

    Committee.

  • 8/8/2019 Joint Health and Safety Committee Report on B.C. Place Stadium roof

    3/82

    InvestigationReport:BCPlaceRoofDeflationIncidentofJanuary5,20071

    TableofContents

    ExecutiveSummary............................................................................................................. 3

    IntroductionandOverview................................................................................................. 6

    SequenceofEvents............................................................................................................. 8

    CommentaryonSequenceofEvents................................................................................ 16

    EventAnalysisandDiscussion .......................................................................................... 17

    Weather ........................................................................................................................ 17

    RoofLoading ................................................................................................................. 19

    RoofFabric .................................................................................................................... 28

    PressureExcursion ........................................................................................................ 28

    Equipment..................................................................................................................... 34

    CrisisIdentificationandManagement.......................................................................... 36

    Policies,ProceduresandTraining ................................................................................. 38

    CultureIssues ................................................................................................................ 41

    CausalAnalysisMethodologies ........................................................................................ 42

    RootCause .................................................................................................................... 51

    DirectCause#1 ............................................................................................................. 52

    DirectCause#2 ............................................................................................................. 52

    Conclusion ......................................................................................................................... 54

    Recommendations ............................................................................................................ 54

    Appendices........................................................................................................................ 57

    AppendixA RoofSupportPressureControlSystemsDescription .......................... 58

    AppendixBBCPlaceRoofLoadingCalculations .................................................... 61

    AppendixCRoofSupportSnowMeltSystem ........................................................ 67

    AppendixD InvertedPanelLoadingCalculations.................................................... 69

    AppendixE WeatherData ....................................................................................... 72

    AppendixFEmergencySnowMeltProcedures,Nov15,2006 .............................. 76

    AppendixGGeigerEngineersReportData,Sept14,2007,#207813 ................... 79

    AppendixHListingofPhotographsandVideoClips,inCDformat ........................ 80

  • 8/8/2019 Joint Health and Safety Committee Report on B.C. Place Stadium roof

    4/82

    InvestigationReport:BCPlaceRoofDeflationIncidentofJanuary5,20072

  • 8/8/2019 Joint Health and Safety Committee Report on B.C. Place Stadium roof

    5/82

    InvestigationReport:BCPlaceRoofDeflationIncidentofJanuary5,20073

    Executive Summary

    Aftersustainingdamagetoawesttriangleroofpanel,thebuildingareaunderthedome

    ofB.C.Placewassafelyevacuated,andthentheroofofBCPlacewassafelydeflatedina

    controlledmanneratabout12:49pmonJanuary5,2007. Therewasnoinjuryasresult

    ofthedeflation.

    AttherequestofBCPlaceManagement,acomprehensiveinvestigationwasconducted

    bymembersoftheJointHealth&SafetyCommitteeguidedbyanexperienced,external,

    OHSConsultant. Theinvestigationsubcommitteehadthecompletecooperationof

    buildingmanagement,union,staffandcontractors. Thisinvestigationteamalsoworked

    closelywithKrisP.Hamilton,P.ENG,ofGeigerEngineering,thefirmthatdesignedthe

    stadiumroof.

    Theinvestigationisbasedonfactualdataandinformationandeventsleadinguptothe

    deflation. Thepurposeofthisinvestigationwastofindfactsanduncoverrootcauses

    thatweredirectlyresponsiblefortheevent,nottoassignblames,orfingerpoint.

    Recommendationsinthisreportaimtopreventsimilarincidentsfromhappeninginthe

    future.

    Bypiecingalltheinformationtogether,thisreportpresentsapictureofwhattookplace

    andthesequenceofeventsleadinguptothedeflation. Reconstructionofthedays

    eventswerebasedonanumberofinformationsourcesincludingeyewitnessaccounts

    boththroughinterviewsandwrittenreports,weatherreports,internalrecordsand

    charts,newsmedia,inspectorsandprivateindividualsvideofootageandphotographs,

    and

    engineers

    testing,

    findings

    and

    preliminary

    reports.

    Thisreportgoesdeeperthansimplyrecordingthestepsoftheevent. WhiletheGeiger

    Engineersreportcoverstheengineeringtechnicalaspectsoftheincident,the

    InvestigationSubcommitteeexaminedabroadrangeofcausalfactorsthatwere

    identifiedduringtheanalysisphaseofinvestigation. Inadditiontodealingwithmany

    complextechnicalaspectsoftheevent,thesubcommitteealsolookedcloselyintothe

    operationalside. BoththeEngineersreportandthisinvestigationreporttaken

    together,addressthecompletescopeoftheroofdeflationincident.

    EventDescription

    Simplystated,heatandthenumberoffanscirculatingairattheroofwerenot

    increased,whensnowwasimminent,norweretheyincreasedwhensnowwas

    observed. Asthesnowaccumulated,unchecked,theroofbecameheavilyloadedtothe

    pointitstartedtoloseitsshape.Thechangeintheroofwasnotnoticeduntilthemain

    speakerclusterwasobservedtobeverylow,andthecenteroftheroofappearedvery

    flatontheinside.

  • 8/8/2019 Joint Health and Safety Committee Report on B.C. Place Stadium roof

    6/82

    InvestigationReport:BCPlaceRoofDeflationIncidentofJanuary5,20074

    Atthispointbuildingpersonnelreactedbyincreasingbuildingpressureandactivating

    thesnowmeltroofheatingsystem. Theroofshapedidnotappeartoberecoveringas

    expectedbecausetherequestedcomputersystemspressuresettingwasconflictingwith

    thebuildingspneumaticcontrolsystems.Thiscausedthereliefventstobleedoffthe

    intendedpressureincrease. Atthispointthepressuresetpointonthepneumatic

    controlsystemwasincreased. Whenthesystemsfinallyreactedtothecommands,the

    combinationofsetpointincreaseandotherfactorscausedabriefpressureexcursion,

    substantiallyabovetherequestedpressuresetpoint,whichquicklybutbrieflyrestored

    therooftoahigherthannormalprofile. Thebuildingspneumaticreliefsystemwasvery

    slowtoreact,butafterafewminutesitbroughtthepressurebackdowntotheset

    pointpressure. Bynowitwastoolateastheunstablemassorpond,consistingof

    water,snowandicetomovetowardsthewesttrianglepanel. Itwasthemovementof

    water,snowandicefrompaneltopanelthatcausedtheinvertedpanelstopopup,

    creatingveryloudsoundsrecountedbywitnesses. Asthemassreachedtheendofits

    travelatthewesttrianglepanel,theresultingavalanchecausedthewesttrianglepanel

    tobulgeinwardabout7.5to8feet. Atthesametime,thismasshittheringbeamarea

    belowthewestpanelwithatremendousforcewellbeyondtheroofpanelmaterials

    designloading. Atearonthewesttrianglepaneloccurred.

    Asthedamagedpanelcontinuedtotear,itwasnolongerpracticaltomaintain

    adequateinternalpressureasfurtherdamagewasimminent. Thedecisionwasmadeto

    safelyevacuatethebuilding,andtostartturningoffpressuresupportsystemswhich

    easedtheroofdownintoitsconstructionpositioninasafemanner. Theroofslowly

    defaultedtoitsconstructionpositionapproximately6metersabovetheStadiumfloor

    andseats.

    Oncetheroofwasstableinitsconstructionposition,asafetyandstructuralassessment

    wasconducted. Aseachareawasdeemedsafe,workersweredirectedtobegin

    assessmentandwatercontrol. Anumberofprofessionalswereonsitetoassessthe

    damagebothupontheringbeamandinsidetheStadium.

    CausalAnalysisandDiscussion

    Basedonthefactualinformationanddata,keyfactorsarehighlightedandexaminedto

    determinehowtheyhadcontributedtotheincident. Thesefactorsareweather,roof

    loading,rooffabric,equipment,policiesandprocedures,Stadiumculture,andcrisis

    management. Differentcausalanalysismethodologieswereusedinfleshingoutthe

    detailsandultimatelypinpointingtherootcause.

    Itisimportanttonotethatevidencecollectedduringthisinvestigationclearlydispels

    anynotionthatpersonnelotherthanthecontrolroomoperatorwereflippingdifferent

    switchesatthesametimeinattemptingtorecovertheroofincrisis. Allcommands

    wereinitiatedbythecontrolroomoperatorthroughthebuildingautomationcomputer

    andnotbypersonnelturningonfanswithswitchesfromtherearHoneywellpanel.All

    therequestedpressuresettingswerewellwithintheknownsafeoperatingrangeofthe

    building.

  • 8/8/2019 Joint Health and Safety Committee Report on B.C. Place Stadium roof

    7/82

    InvestigationReport:BCPlaceRoofDeflationIncidentofJanuary5,20075

    RootCause

    Thecausalanalysisofthiseventpointsdirectlytothelackofeffectivepolicies,

    proceduresandtrainingastherootcauseofthisincident.

    Furthermore,ageneralblindnessandlackofunderstandingandtrainingrelatedto

    theroofsupportsystems,operatingwithinanenvironmentwherepoliciesand

    procedureswerefullofholes,hadallowedsnowaccumulationtogounnoticed. Pooror

    verylittleroofincrisisidentification,assessmentandtrainingalongwithconflicting

    controlroomsystemsallcameintoplaytocausethedamagetothewesttrianglepanel.

    Recommendations

    Thecorrectiveactionsclearlysupportedbythisinvestigationcanbebrokenintothe

    following5categories:

    1.Create,inform,implementandpostaNoSnowAccumulationpolicyforthe

    roof. ThispolicywouldbecomethegoalfortheStadiuminkeepingtheroofup.

    Itdefinesthefacilityphilosophyandmakesitcleartoallpartiesthateveryeffort

    willbemadetopreventsnowfromaccumulatingontheroof.

    2.Withoutfurtherdelay,completeanexternalauditofStadiumOperationsto

    focusonpolicies,proceduresandtrainingthenimmediatelyimplementthe

    correctiveactions. ThisincludesriskidentificationandmanagementinStadium

    maintenanceandoperations.

    3.Immediatelyhaveaqualifiedperson,assistedbyaqualifiedtestinglaboratory

    conductaphysicalassessmentoftheroofmaterialandseamsadjacenttothe

    ringbeamstartingwitheachofthetrianglepanels.Makethenecessary

    corrections.

    4.Haveaqualifiedperson,knowledgeableintheseroofsystems,assess,modify

    andupdateroofsupportcontrolsystemsincludingamethodforthecontrol

    roomtoseetheroofandknowwhenitisincrisis.

    5.Completeacomprehensiveindependentexternal,auditoftheOccupational

    Health&Safetyprogramofthisfacilityandimplementrecommendations.

  • 8/8/2019 Joint Health and Safety Committee Report on B.C. Place Stadium roof

    8/82

    InvestigationReport:BCPlaceRoofDeflationIncidentofJanuary5,20076

    IntroductionandOverview

    ThereportsummarizestheJointHealth&SafetyCommitteesincidentinvestigationof

    theBCPlaceroofdeflationincidenttookplaceonJanuary5,2007.

    FollowingthecontrolleddeflationonJan5,2007,attherequestofBCPlace

    Management,aninternalinvestigationwasconductedbymembersoftheJointHealth

    &SafetyCommitteewiththeassistanceofanexternalOHSConsultant. The

    investigationisbasedonfactualdataandinformationandeventsleadinguptothe

    deflation. Membersontheinvestigationsubcommitteeandthejointhealth&safety

    committeelefttheirmanagementorunionhatsoutsidetheinvestigationdoortoensure

    theinvestigationwasdonethroughanobjective,impartiallens. Thepurposeofthis

    investigationwastofindfactsanduncoverrootcausesthatweredirectlyresponsible

    fortheevent,nottoassignblames,orfingerpoint. Therecommendationsputforthat

    the

    end

    of

    the

    document

    aim

    to

    prevent

    similar

    events

    from

    happening

    in

    the

    future.

    Bypiecingalltheinformationtogether,thisreportpresentsaclearpictureofwhattook

    placeandthesequenceofeventsleadinguptothedeflation. Reconstructionofthe

    dayseventswerebasedonanumberofinformationsourcesincludingeyewitness

    accountsboththroughinterviewsandwrittenreports,weatherreports,internalrecords

    andcharts,controlroomlogs,newsmedia,inspectorsandprivateindividualsvideo

    footageandphotographs,andengineerstesting,findingsandpreliminaryreports.

    Thisreportgoesdeeperthansimplyrecordingthestepsoftheevent. WhiletheGeiger

    Engineersreportcoverstheengineeringtechnicalaspectsoftheincident,the

    InvestigationSubcommitteeexaminedabroadrangeofcausalfactorsthatwere

    identifiedduringtheanalysisphaseofinvestigation. Inadditiontodealingwithmuch

    Stadiumspecifictechnicalinformation,thesubcommitteealsolookedcloselyintothe

    operationalside. BoththeEngineersreportandthisinvestigationreporttaken

    togetheraddressthecompletescopeoftheroofdeflationincident.

    Thisinvestigationreportconsistsofvarioussections,startingoffwithadetailedaccount

    ofthedaysevent,followedbycommentariesandindepthdiscussionsonkeyelements

    andfactorstodeterminetheirsignificanceintheroofdeflationincident. Casualanalysis

    employingdifferentmethodologieswasusedtoidentifyrootcausesandassociated

    contributingcauses.

    AsthisreportcontainsmanytechnicaltermsspecifictotheBCPlacesroofsupport

    system,whichmightbeunfamiliartosomereaders,pleaserefertoAppendixA Roof

    SupportPressureControlSystemsDescription. Forthepurposeofkeepingthemain

    reportsuccinct,technicaldataandsupportinginformationaremadeavailableinthe

    appendices.

  • 8/8/2019 Joint Health and Safety Committee Report on B.C. Place Stadium roof

    9/82

    InvestigationReport:BCPlaceRoofDeflationIncidentofJanuary5,20077

    Thisinternalinvestigationhadthecompletecooperationofbuildingmanagement,

    union,staff,contractors,professionalsandprivatecitizens. Thisinvestigationteamalso

    workedcloselywithKrisP.Hamilton,P.ENG,ofGeigerEngineering,thefirmthat

    designedthestadiumroof. Wewishtoexpressourappreciationtoallthesepartiesin

    theirassistanceintheinvestigatingprocess.

  • 8/8/2019 Joint Health and Safety Committee Report on B.C. Place Stadium roof

    10/82

    InvestigationReport:BCPlaceRoofDeflationIncidentofJanuary5,20078

    SequenceofEvents

    TheControlroomoperatesina12hrrotation,0700to1900asdayshift,1900tonext

    day0700asnightshift. ThissequenceofeventsinitiatesfromthenightshiftofJan4

    (1900ofJan4/07to0700ofJan5/07). Atypicalcontrolroomshiftisatwostaff

    memberteam:aControlRoomOperatorwhoisresponsibleforthemonitoringof

    systemsandcontrolsofthebuildingandanEastAirlockSecuritywhoisresponsiblefor

    internalandexternalsecurityandpatrolofthebuilding.

    Thedatacollectedduringtheinvestigationsupportsthefollowingscenario:

    Jan4

    Theshiftwasdescribedtohavestartedlikeanyother,normal,uneventfulnightshift.

    23:13 alowtemperatureoutsidealarmcameinindicatingandprintingoutnearfreezing

    outsidetemp,watchforsnow.

    Jan5

    04:10, Smokealarmonfirepanel,Zone3,sentEastAirlock(EAL)Securitytocheckitout.

    Showerincoachslockerroomwasleftonandsteamsetoffalarm. Turnedoffshower.

    04:20, ControlRoom(CR)Operatortriedtoresetalarm,butthewholepanellituplikea

    Christmastree. Allindicatorlightscameon.

    04:25, CROperatorcalledsupervisorbutcouldnotgethimathome,socalledthe2nd

    supervisorathome,andleftmessageonmachineastherewasnoanswer.

    04:27, Becausetheyhadnoideawhythefirepanelwasalllitupthesecuritypersondecidedto

    goonactivefirewatch.

    04:29, 1stsnowconditionalarmcamein. 1hourdelaystartedtocountdown(systemdefault

    setting).TheCROperatoractivatedthe15hourdelayontherearHoneywellpanel.(See

    AppendixCRoofSupportSnowMeltSystem)

    04:30, TheroofsensorsentamoisturealarmandprintedPrecipitationdetectedatroof

    sensors. (thesystemisconfirmingthatbothlowtemperatureandmoistureexist,

    showingarealpossibilityofsnow).

    04:31, CROperatorwentoutsideofeastairlocktoobserveweather.Itwassnowinglightlybut

    hecouldnotseeanyaccumulationontheroof.

    04:40, CROperatorcalledEnvironmentCanadaweatherofficeforreport. Theweatherreport

    wasgivenasfollows:GREATERVANCOUVER.TODAY.PERIODSOFSNOWCHANGINGTOPERIODSOFRAINTHISMORNING.

    RAINFALLAMOUNT20TO30MM.BECOMINGWINDY.HIGH8.TONIGHT.PERIODSOFRAINENDING

    OVERNIGHTTHENCLOUDYWITH30PERCENTCHANCEOFSHOWERS.AMOUNT10MM.WINDY.LOWPLUS

    5.

    05:00, Bythistime,neitherofthesupervisorshadcalledback,sotheCROperatordecidedto

    calltheDirectorofOperationsregardingthefirealarm,andsnowconditionalarm.The

    DirectoraskedtheOperatortoresetthefirepanelandwastoldCRhadtriedthat,but

    thewholefirepanellituplikeaChristmastree. Directorsaidhewouldbetherearound

    6:15to06:30.

    05:05, Engineeringsupervisor(2nd

    call)calledbackinresponsetothemessagetheyleft.CR

    Operatortoldhimhehadalreadyspokentothedirectorandhewasonhiswayin.

  • 8/8/2019 Joint Health and Safety Committee Report on B.C. Place Stadium roof

    11/82

    InvestigationReport:BCPlaceRoofDeflationIncidentofJanuary5,20079

    Supervisordiscussedfirepanelproblemandhadtoldthemnottoworryaboutitand

    thetechnicianwouldfixitwhenhegetsinat08:00.

    05:42, UnbeknownsttotheCROperator,theEnvironmentCanadaweatherofficehadnow

    issuedanewreportat0542:GREATERVANCOUVER. TODAY. PERIODSOFSNOWCHANGINGTOPERIODSOFRAINTHISMORNING.

    SNOWFALLAMOUNT2CM. RAINFALLAMOUNTS20TO30MM. BECOMINGWINDY. HIGH8. TONIGHT.

    PERIODSOFRAINENDINGOVERNIGHTTHENCLOUDYWITH30PERCENTCHANCEOFSHOWERS.AMOUNT

    10MM.WINDY.LOWPLUS5.

    05:53 1stsnowconditionalarmcancelleditself,indicatingsnowconditionshavecleared.

    05:59, 2nd

    snowconditionalarmcameinfromthesensors,1hourdelaystartedtocountdown

    bydefaultofthesystemandthe15hourdelaybuttonwasmanuallyactivated.

    06:09, 2ndsnowconditionalarmcancelleditself,indicatingsnowconditionshavecleared.

    06:14, 3rdsnowconditionalarmcamein,1hourdelaystartedtocountdownbydefaultofthe

    systemandthe15hourdelaybuttonwasmanuallyactivated.

    06:20, TheDirectorarrived,reviewedsituationwiththeCROperator,thenwentintothe

    Operationsofficeandprintedoutthelatestweatherreport.

    06:27, 3rdsnowconditionalarmcancelleditself,indicatingsnowconditionshavecleared.

    Itshouldbenotedatthispointthatallstaffandsupervisorsthatwereinterviewedhadspecificallynotedsnowaccumulationofupto2inchesofslushywetsnowonthegroundoutside

    ofthestadiumastheywerestartingtoarriveatwork. Somereportedrain,somesleetandsome

    snowbutallnotedtheaccumulationontheground.

    06:45, ThedirectorspoketothenextshiftCROperator(07:0019:00)ashehadshowedup

    earlyforhisshift. GavehimacopyoftheEnvironmentCanadaweatherreportissuedat

    05:42whichhehadprintedoutwhenhegotin.HealsoreiteratedwiththeCROperator

    towatchtheweatherandapplyheatathisdiscretion.

    06:45, Atthistime,theEnvironmentCanadaweatherofficeissuedanupdatedadvisory

    indicatingthefollowingbutitwasunknowntostaff.GREATERVANCOUVER,SNOWFALLWARNINGINEFFECT.

    TODAYPERIODSOFSNOWCHANGINGTOPERIODSOFRAINTHISMORNING. SNOWFALLAMOUNT2CM

    EXCEPT10CMOVERHIGHERTERRAIN.RAINFALLAMOUNT20TO30MM.WINDY.HIGH8,

    TONIGHT.PERIODSOFRAINENDINGOVERNIGHTTHENCLOUDYWITH30PERCENTCHANCEOFSHOWERS

    AMOUNT10MM.WINDY.LOW,PLUS5.

    06:57, Controlroomshiftchange,newoperatorsignedon.

    Itshouldbenotedatthispointthatmostoftheinterviewedstaff,commentedthatthe

    temperatureinsidethebuildingthatmorningwascoolerthanusual.Duringthemorningof

    January5,2007,theinsidebuildingtemperaturewassetat10degreecelcius. Thisisthe

    minimumtemperaturesettingallowed. Therewere2adjustablespeedfans(ASDs),#10inFan

    Room#5inFanRoom#8.Thecomputersetpointwassetat250Pa. Becauseitwasa

    turfupday,toincreaseventilationforthedieselpoweredforklift,twoconstantspeedfans

    (CSFs)#4inFanRoom2,fan#14inFanRoom7wereturnedon.These2constantspeedfans

    areinrecirculationmodebecausethebuildingpressureismaintainedbythecomputerdriven

    AdjustableSpeedDrives. Thecomputerpressuresetpointwasat250Pa,thepressureandrelief

    controllers,onthemanualHoneywellcontrolpanelweresetat250Paforthepressure

    controllersandat300Paforthereliefcontroller. Thisappearstofollowthebuildingsprocedure

    manual. Soupuntil12.33,therewere2ASDsand2CSFsinoperation.

    08:10, Shortlyaftershiftbriefing,oneworkerfromtheTurfupcrewcommentedtotheCR

    Operatorandasupervisor:WhyamInotwearingmytshirtinsidethismorning?The

  • 8/8/2019 Joint Health and Safety Committee Report on B.C. Place Stadium roof

    12/82

    InvestigationReport:BCPlaceRoofDeflationIncidentofJanuary5,200710

    responsewaseconomicsdictatewedonotneedtheheat. (Theworkerherereferredto

    whensnowmeltison,theStadiumwouldbeheatedandwarmenoughtowearonlyat

    shirt).

    08:16, CROperatorturnedonconstantspeedfan4inroom2.Thisisastandardprocedurefor

    turfupoperation.

    08:17, 4thsnowconditionalarmcamein.1hourdelaystartedtocountdown.

    08:18, CROperatorturnedonconstantspeedfan14inroom7.Thisisalsopartofthestandardprocedureforturfupoperation.

    08:34, the15hourdelayforsnowmeltwasmanuallyactivated.

    09:00, AworkerhadbeenworkingonLevel2andnoticedoutsidesnowaccumulation. Worker

    thenwentintoControlRoomandaskedwhysnowmeltwasnton.

    10:05, 4thsnowconditionalarmcleareditself,indicatingsnowconditionshavecleared.

    10:15, Aturfupworkernoticedthespeakerclusterwashangingataveryoddandcrooked

    angle.

    10:30, DutyManager(DM)whendoingroundsonlevel2,notedabout2inchesofwetsnowon

    theplazadeckwithwhatappearedtobeverywetlookingfootprintsinit. Whenrounds

    werefinishedtheDMwentintothecontrolroomandreportedherobservationtothe

    CROperator.TheCROperatorlookedinthecameraattheroofandsawnosnow,so

    toldtheDMthatthesnowhadslidoffoftheroofandnottoworry.Whatwasnot

    realizedwasthattheroofareavisibletothecamerawasabovethesectionofthe

    stadiumaffectedbyFanRoom#2. Assuchtheresidualheatcombinedwiththeair

    circulationfromthefaninFanRoom#2hadmeltedthesnowinthatarea. Thecamera

    didnotseetherestoftheroofwhichwasstillcoveredwithsnowandpossiblyfrozen

    snow.

    10:55, Thepressuredialchartchanged. ThisisadailyactivityintheControlRoom,pressure

    dialchartsarechangedevery24hoursat1100. OnJanuary5,timeindicatedonthe

    chartseemstobeslightlyoutofsyncwhencomparedtothecomputerdataprintout

    logs. Thechartappearstobeabout3or4minutesbehindtheactualtimeline.

    11:00, UnbeknownsttotheControlRoom,EnvironmentCanadaweatherofficeissuedagaina

    snowfalladvisory: GREATERVANCOUVERSNOWFALLWARNINGINEFFECT

    TODAY.PERIODSOFRAINATTIMESMIXEDWITHSNOWNEARNOON. SNOWFALLAMOUNT2CMEXCEPT

    10CMOVERHIGHERTERRAIN.RAINFALLAMOUNT20TO30MMWINDSOUTH40TO60KM/HBECOMING

    SOUTHWEST30GUSTINGTO60EARLYTHISAFTERNOON,HIGH6

    11:01, 5thsnowconditionalarmcamein. 1hourdelaystartedtocountdown,andthe15hour

    delaybuttonwasmanuallyactivated.

    11:20, EastAirlockSecurityandtheDirectorofOperationswentoutsidetotheTerryFoxplaza

    todealwithavagrant. EALSecurityreportedtherewaswetsnowfallingandnoticeda

    littlesnowstickingtorooflookingupfromTerryFoxarea.

    11:30, TwoworkersfromtheturfupcrewwentoutsideattheDisabledEntrancebytheturf

    storageareaandnoticedheavy,bigflakesofwetsnowwasfalling.

    Lunchbreak,from12noonto12:30sonoonewasworkingonthefieldduringthistime.

    12:06, 5thsnowconditionalarmcleareditself,indicatingsnowconditionshavecleared.

    12:10, CROperatorlefttheControlRoomtograbapop,hewalkedouttotheeastfield

    entranceandlookedupattheroof. Herememberstherooflookednormaltohim.

    12:20, Contractworkercamebackearlyfromlunchandnoticedthelowspeakercluster,(about

    15or20feetoffoffieldlevel). Hewatchedforafewminutesnoticedtheroofwasvery

  • 8/8/2019 Joint Health and Safety Committee Report on B.C. Place Stadium roof

    13/82

    InvestigationReport:BCPlaceRoofDeflationIncidentofJanuary5,200711

    flat(flatterthanhehadeverseenit)thenwastoldtostaybackfromthefieldandto

    remainintheconcourse.

    12:31, Astaffmembernoticedwhenreturningfromlunch,walkingonthefieldthroughthe

    EastAirlock,themainspeakerclusterwasverylow,about10feetabovethefield. He

    thenlookedupattheroofandnoticedsomethingveryodd.Herealizedtheentiretop

    areaoftheroofwasflat.Hedefineditwasflatfromtheinsideanchorpointofthe

    suspensioncablesofthesatellitespeakerswhicharelocatedaroundtheperimeteroftheroof.HethenwenttotheDutyManagerandreportedthis.Itwasalsoobservedthat

    3or4ofthediamondsectionsaroundtheareaofthespeakerclusterwereinverted.

    12:32, DutyManagernoticedworkersstaringattherooffromtheEastAirLock,whenshe

    returnedfromlunch. Sheobservedthespeakerclusterwasactuallysittingonthefield

    atthispointandshethoughtitwasoddbecauseitwouldblocktheforkliftaccessfor

    theturfupoperation. Thenshenoticedtheroofwasflatlikeapancake.Shetold

    workerstostayclearofthefieldandthenwenttotheControlRoomtoreportthe

    situation.

    Atthispointseveralstaffhadnowcomebackfromlunchandnoticedthegrowingcrowdof

    peoplewatchingtheroofasitseemedveryeerie. Aroundthebuildingatvariouslocations

    staffshadnoticedtheroofflatandlowandwerenowstartingtowatchwhatwashappening.

    Thoseinterviewedwitnesseswhowereonsitethatday,allreportedseeingtheroofbeingflat

    andunusuallylow,aswellas:flatlikeapancake,wrinkledlikeaprune,couldnotseethe

    sideoftheringbeam,onesidepusheduplookinglikeintestines,speakerclustertiltedata

    45degreeangleandwaterwasdrippingthroughthevents,theroofwasdimpling,etc..

    12:33, Twoworkersreturnedfromlunch,andreportedthesituationtosupervisors

    immediately. BothengineeringsupervisorsandastaffmemberranintotheControl

    Room. TheyimmediatelyalertedtheCROperatorthattheroofwascomingdown.

    12:33, Itisnowapparentthattheroofisincrisis. OnesupervisorinstructedtheCROperatorto

    increasethepressureto300Paandpreparethebuildingforsnowmelt. Theother

    supervisorwenttothebackwiththeotherworkertochecktheMagnehelicPressure

    Gauge.

    SeveraladditionalstaffandsupervisorsarenowintheControlRoom. Ithasbeendetermined

    thatatleast5people(supervisors,workerandCROperator)wereintheControlRoom. TheCR

    Operatornotonlyhavingtodealwiththeroofincrisis,buthenowhasagroupofpeople

    offeringwellintentionedassistanceandprovidinginstructions.

    ITMUSTBENOTED,theonlypersonissuingcomputercommands,andadjustingtheHoneywellpressureandreliefcontrollers,intheControlRoomuptothepointofthepanelfailure,wasthe

    CROperator.

    Thecomputerpressuresetpointwasincreasedfrom250Pato300Pa. Thissetsthe

    pressureparameterfortheadjustablespeed(ASD)fans. Atthistime,therewereonly2

    ASDfansrunning. TheASDfanswerenowworkingtoincreasepressuretowards300Pa.

    The2constantspeedfanswhosedampersarecontrolledbytheHoneywell

    pressure/reliefcontrollerswereinrecirculationmode,astheyhaveachievedthe

    controllersetpointof250Pa.ThepressurecontrollerontheHoneywellpaneliskeeping

    theoutsideairdampersclosed,asithasthe250Paitissetfor.Itisimportantto

  • 8/8/2019 Joint Health and Safety Committee Report on B.C. Place Stadium roof

    14/82

    InvestigationReport:BCPlaceRoofDeflationIncidentofJanuary5,200712

    understandthattheconstantspeedfandampers(CSFs)taketheirpressuresettings

    fromtheHoneywellpressurecontrolleronly,andcomputersetpointchangesdonot

    affectCSFs.

    **note,Basedonwitnessaccountsandanalysis,thepressureandreliefcontrollersonthe

    HoneywellPanelatthebackofthecontrolroomdidnotappeartohavebeenchangedtoreflect

    theincreaseincomputersetpointfrom250to300Pa.Theprocedurewhenchangingthe

    computerASDsetpointto300PaistoimmediatelygotherearHoneywellpaneland

    changethepressurecontrollersetpointto300Paandtochangethereliefcontrollerset

    pointto350Pa. WhenASDfansarerunningthereliefcontrollersetpointmustalways

    be50Pahigherthanthecomputer/pressure controllersetpoint.

    12:34, Fan#7(ASD)inroom4wasturnedonbycomputercommandbytheCROperator. This

    fanwastakingitssettingfromthecomputersetpointof300Pa. Forabriefperiodof

    30secondsto1minute,therewillbeairlosscausingasmalldropinpressure,(atypical

    occurrenceafterafanisturnedon),butshortlyafterthat,all3ASDfansshouldbe

    rampingupto300Pa.

    EvidenceindicatesthatbecausetheASDfanstaketheirpressuresettingfromthecomputerset

    point,whichisbasedonanaveragefromareadingtakenineachofthe8fanrooms,they

    usuallyshootalittlehigher(8to10Pa)thantheMagnehelicpressuregaugethatcontrolsthe

    relief.Asettingof300Paonthecomputerisreallyabout310Pa.ontheMagnehelic.Thisisnot

    achievablebecausetheHoneywellpressurecontrollerwasnotresetto300andtherelief

    controllerto350. Theywerestillontheoldsettingsof250and300. ThismeanttheASDfans

    werenotgoingtobeabletohitthedesiredpressureof300Pabecausethereliefdamperswill

    openanddrainoffthepressurebeforetheASDscouldreachthesetpointof300Pa.Therelief

    systembeingpneumaticallycontrolledissoslowtoreact,needsabout2minutestoopenand1.5

    minutestoclose,thatthemaximumpressuretheASDfanscouldhopetoachieveisabout270to

    280Pa.

    12:36, CROperatorcalledthesteamplanttoaskforsteamtogotosnowmeltmode.Hegot

    theOKasthesteamplanthadbeenpreparedforhiscall. Hethenoverrode

    temperatureandmoisturesettingsontheEnergratedcomputerinpreparationfor

    immediatesnowmelt.

    12:36, 15hrdelaytimerforsnowmeltwasactivatedonthebackHoneywellpanel.Atthispointtherewasgrowingconcern,becausewith3ASDfansrunningat100%toincrease

    thepressurebuttherewasverylittlemovementintheroof,andthepressurehasbarelymoved

    up. Noonerealizedreliefsettingsonthepressureandreliefcontrollerswereconflictingwiththe

    computersetpointfortheASDfans. Thereliefcontrollerwasopeningthereliefdampersto

    reducepressurebeforethecomputersetpointcouldbeachieved.

    12:37, Aworkerhadgoneouttothefieldandobserved3invertedpanelsabovethespeaker

    clusterandreportedthisinformationtoControlRoom. Engineeringsupervisoratthis

    pointdecidedtoruntotheTechShopandgetatechniciansassistance. Heknewthe

    technicianwashavinghislunchthere. Heranintotheshopandtoldthetechnicianthat

    theRoofwasfallingandhemustgointothecomputerandraisethepressureto400

    Pa.

  • 8/8/2019 Joint Health and Safety Committee Report on B.C. Place Stadium roof

    15/82

    InvestigationReport:BCPlaceRoofDeflationIncidentofJanuary5,200713

    Thetechnicianfollowedhissupervisorsinstructionsandproceededtologontothe

    computersystemfromhisshopandmakethechanges. Ittookabout4minutestoenter

    thedata.

    Itshouldbenotedthecomputersetpointchangedbythetechnicianwouldnothave

    beeneffectiveforthesamereasonabove. BecauseHoneywellreliefcontrollerwasstill

    at300Pa,thereliefsystemwouldreacttoreducepressure;andthereforeprevented

    theASDfansfromachievethis400Pasetpoint.

    12:37to12:38, meanwhileintheControlRoom,CSFs#12,then#5wereturnedonatthe

    computer.

    12:39, ASD#2wasturnedonatthecomputer.Forabriefperiodof30secondsto1minute,

    therewillbeairlosscausingasmalldropinpressureasthisASDfancomesonline.

    12:40, theCROperatoratthispointactivatedsnowmelttoapplyheatdirectlytotheroof.

    Activationofsnowmeltatthispointimmediatelyoverrodethecommandsfromthe

    technician,asittakespriorityoverandsetsthecomputersetpointimmediatelyto300

    Pa. Theremotesetpointrequesttoputpressureupto400wouldhaveatbestbeenin

    effectverybriefly. Atthispointthecomputersystemwasunderseverestressandsome

    datawasnotevenacknowledged.Muchofthedatabeingprintedfromthecomputerin

    thecontrolroomwasoutofsequence.

    Justpriortotheprevious3fansrampinguptospeed,theHoneywellpressurecontroller

    andthereliefcontrollerwereresetto350Parespectively.Thishappenedjustasthe

    pressurelosswasineffectfromASD#2startingup.

    Nowallthingsarechanging.AssoonasthesettingswereontheHoneywellpanel. Therelief

    systemswouldbegintoclosedowntopreventairloss,the4ASDfanswouldhavequickly

    achievedtheprevioussetpointof300Pa. LikelybythetimetheASDfansachievedthesetpoint

    of300Pa.,thereliefdamperswerecompletelyclosedandthe4constantspeedfanswerenow

    gettingfulloutsideairastheywerepumpingpressuretoasetpointof350. Withallfourcsf

    fansworkingtowards350Pa,itwaslikelythissetpointwasachievedveryquickly.

    Thisistheturningpointfromanoverloadedrooftoanavalanche.Thestagewasset.WithbothHoneywellpressureandreliefcontrollerssetat350Pa,thishadsetuptheperfectsituation

    forthepneumaticreliefcontrolsystemtocauseapressureovershootabovethesetpoint.

    12:41to12:42

    Pressurerapidlyincreasedto520Paorapprox68%onpressurechart.Ananalysisofthe

    Honeywelldialchartshowsittookabout2minutesforthepressuretokickupto520

    Pa. Bythetimethereliefcontrollercouldreactandopendamperstoreducepressure,

    thebuildingpressurehasnowreached520Pa.

    Thereliefcontrollerisonapneumaticsystem;thereforeitwouldhavetaken2minutesforallofthedamperstoopen. Thisdelayedthesystemsabilitytodrainoffexcess

    pressure. Oncethepressurehadpeakedat520Pa,thereliefcontrollerwouldnowhave

    allreliefdampersfullyopentoreducepressure,andthepressurecontrollerwouldnow

    fullyblockedoutsideairandonrecirculationfortheconstantspeedfans. TheASDfans

    wouldbeatidlespeed. Thepressurethenbegantodroprapidlybackdowntotheset

    point. Thepressureundershotbelowthesetpointreachingalowpointof33%or247

    Pa. Asthepressuredroppedbelowthesetpoint,computercontrolledASDfansreacted

    quicklyandbegantoraisepressure.

  • 8/8/2019 Joint Health and Safety Committee Report on B.C. Place Stadium roof

    16/82

    InvestigationReport:BCPlaceRoofDeflationIncidentofJanuary5,200714

    SeeanalysisonPressureExcursion

    12:43, AnavalanchewasheardbywitnessesontheTerryFoxplazasideoftheroof. (Section7

    10)Witnessesreportedalow,rumblinghummingsound.

    12:44to12:46 Staffnowstartedhearingthesoundofsnowmovingontheroof. Theyreporteditasa

    lowroar,Thump,thump,thump,roofwasshakinglikeablanket,agiantwas

    runningontheroof,jetplanestakingoffandothersequatedittothesoundofan

    elephantrunningthroughthelivingroomtowardsthewestendandanotherdescribed

    therewasawhooshingsound. Oneverydetailedaccountsaidthatheobservedalarge

    bulbouspillowormass,likeafistbeingpusheddownontherooffromabove,moving

    throughthediamondpanelsonebyonethenitmovedontothetopofthewesttriangle

    andinvertedit,thenitmoveddowntowardstheringbeamatatremendousspeed.This

    bulgewaslargeenoughthatitcompletelyblockedtheviewoftheclockwhenitgotto

    thebottomofthetrianglepanel,(atleast7or8feetdeep).Hesaidwhateverthebulge

    washadalotofweightinit. Inrapidsuccessiontherewasaloudcracklikesound,sort

    oflikethesnappingofabullwhip,thentheSeikoclockexplodedandatearappearedin

    thebottomcenterofthewestpaneljustabovetheringbeam.Thetearseemedtostop,

    momentarily,atabout12feetinlengththenwaterandicecamepouringin.Thetear

    thentookoffacrossthebottomthenuptheleftside. Asthewaterandicecontinuedto

    pourin,peoplecontinuedtoobservethetearopenedtotheleftthenrightandthen

    peeledopenlikeacanofsardines,youcouldhearaveryloudcrackingorflapping

    soundasthepanelwaswhippedbytheairrushingoutofthebuilding.

    12:46, Thepressurewasonitswaybackuptothesetpointof300Pawhenthewesttriangle

    panelfailed. Atthispointthepressurewasabout37%or277Pa.Itappearsthataspan

    ofabout12minuteselapsedfromtheinitiatingcorrectiveactiontothepanelfailure.

    12:48, Atthispoint,thesystemisunabletomaintainadequateinternalpressuretosupport

    theroof,andfurtherdamagewasimminent. Thedecisionforacontrolleddeflationwas

    made.TheevacuationannouncementwasmadebytheDutyManagerandthenthe

    controlroomoperatorplayedtheevacuationrecordingoverthePAsystem.

    12:49, Fans#4,5,12&14weresequentiallyturnedofftoallowacontrolledandgentle

    deflationoftheroof.

    12:50, Whenthepressurewentbelow180Pa,thecomputerautomaticallyturnedonan

    additional10fans.ThetechnicianhadtologontotheEnergratedComputerSystemto

    maketherequiredsoftwarechangestoallowallfanstobeturnedoff. Thiswas

    completedat12:51.

    Atthispointtheroofwasdown. Barricadeswereplacedatallfieldentrancesandstaffweretoldtoremainintheconcourseareaundertheconcreteroof.

    Onesupervisoralongwithtwoworkers,werethefirstonesupontheringbeamtoassessthe

    damage.Whentheyarrivedonthetopthroughthewesthatch,theynoticedsnow/ice/slush,

    withaccumulationuptotheeliminatorframes.Therailingswereallstillinplaceandthedrains

    wereallfrozenandpluggedwithiceandslush.Theyhadtouseshovelstoclearthedrains.When

    theygottheshovelsoutoftheroofboxes,theyobserved2inchesofveryheavy,frozensnowon

    topoftheseboxes.Thelidsweresoheavytheycouldbarelyliftthem.

  • 8/8/2019 Joint Health and Safety Committee Report on B.C. Place Stadium roof

    17/82

    InvestigationReport:BCPlaceRoofDeflationIncidentofJanuary5,200715

    Otherauthorizedpersonnelwentuptotheringbeamshortlyafterthedeflationwhichconsisted

    ofBCPlace&PavCoemployees,architect,structuralengineers,Cityinspectors,rescue

    professionals. Theircommentsincluded:lotsandlotsofsnow, asurprisingamountofsnow,

    veryslippery,snowstillstuckonsomepanels,moresnowonthewestthantheeast,

    cablesappearedcrooked,watersnowandiceontheseatsrightunderthehole,etc.. Some

    ofthesepeoplewereabletotakephotographsofthedamageandtheroofconditionwhichgreatlyassistedtheinvestigationprocess.

    Meanwhile,backinsidetheStadium,oncetheroofwasstableinitsconstructionposition,the

    assessmentprocessthenkickedinandcallsweremadetobringinassessmentstaff,engineers,

    riggersandsafetyprofessionalsetc.tocomeupwithanactionplan

    Theabovesequenceofeventssummarizesthedatacollectedbytheinvestigationsub

    committee. Itisthefoundationoftheinvestigationandhasformedthebasisforthe

    causalanalysisoftheeventtodetermineoutcomesandrecommendations.

  • 8/8/2019 Joint Health and Safety Committee Report on B.C. Place Stadium roof

    18/82

    InvestigationReport:BCPlaceRoofDeflationIncidentofJanuary5,200716

    CommentaryonSequenceofEvents

    AsthesnowmeltalarmscameinonthemorningofJanuary5th

    ,thesnowandsleet

    begantoaccumulateonthefabricsurfaceoftheroof. TheStadiumtemperatureset

    point

    remained

    at

    the

    lowest

    possible

    setting

    of

    10

    degrees

    C

    and

    the

    internal

    pressure

    setpointremainedat250Pa.

    ManyStaffcommentedonhowcolditwasinthestadium. Whensnowwasobserved

    fallingandaccumulatingonthePlazadecks,somestaffwereconcernedenoughabout

    thelackofheat,thattheywenttothecontrolroomtoinquirewhytheheatwasnot

    increasedorthesnowmeltsystemturnedon. The4th

    and5th

    snowmeltalarmscamein

    at8:17and11:01thatmorningandbothtimestheoperatorpushedthe15hourdelay

    timertopostponetheactivationofthesnowmeltsystem.

    Atapproximately10:30adutymanagerwenttothecontrolroomandvoicedconcernto

    theoperatorbecausetherewas2inchesofwetslushysnowontheplazadecks. The

    controlroomoperatorlookedattheringbeammountedcameratocheckthecondition

    oftheroof. Heinformedthedutymanagerthatthesnowhadslidofftheroofandnot

    toworry.(SeeEquipmentsectionphotosoftheviewsforthiscamera)

    Itshouldbenotedthatat08:18,constantspeedfan#4inFanroom2wasturnedon. As

    theoutsideairtemperaturewascloseto0degrees,uponstartupandforaperiodof

    time,thisfanroomwouldhavebeendeliveringasignificantamountofheatedairuntil

    thereturnairtemperaturecameuptothesetpointof10degreesC. Theotherfactoris

    thatfan#4isaconstantspeedfanandthereforewouldhavebeendeliveringaconstant

    100,000CFM(cubicfootperminute)ofairflowasopposedtotheASDfanswhichwouldonlybeoutputtingmuchlowervolumesofair.

    Thelevel5dischargedamperforfanroom#2islocatedatsection10ofthestadium.

    Thisistheexactstadiumsectionthattheringbeammountedcameraislocated. A

    significantamountofheatedairwouldhavebeendischargedfromthisdamperwhile

    thetemperaturecontrolsystemopenedthesteamvalvetoraisethereturnair

    temperaturetotheminimumvalueof10degrees. Thisheatedairwouldhaverisento

    heattherooffabricintheimmediatevicinityofthecamera. Thereforewhenthe

    operatorsawthismeltingeffectonthesmallareaoftheroofvisiblefromthecamera,

    hewasonlygettingthesmallpicture. Inrealityonlythissmallsectionoftheroofwas

    sheddingsnowduetotheheatingeffectcausedbyfan#4.(Thiseffectwouldhavebeen

    mirroredinFanroom#7astherewasalsooneconstantspeedfanningrunninginthis

    fanroomaswell.)

    Contrarytowhatthecontrolroomoperatorwasobservingthroughthelimitedview

    affordedbytheringbeamcamera,themajorityoftheroofsurfacewasactually

    accumulatingsignificantamountsofheavywetsnow.

  • 8/8/2019 Joint Health and Safety Committee Report on B.C. Place Stadium roof

    19/82

    InvestigationReport:BCPlaceRoofDeflationIncidentofJanuary5,200717

    EventAnalysisandDiscussion

    Weather

    Withminimalheatandaircirculation,theroofoutsidesurfacetemperaturewas

    hovering

    around

    the

    freezing

    point.

    The

    weather

    on

    the

    morning

    of

    January

    5

    th

    was

    comingfromanortheasterlydirection.Thenearestofficialweathermonitoringstation

    wastheGVRDKitsilanoHighSchoolstation. Therecordedtemperatureshovered

    around1degreeCfrom4AMtoNoon,therecordedprecipitationduringthistime

    periodwas17.6mmandthewindswererelativelylightwithamaximumwindspeedof

    14KPHfrom4AMto3PMonthatday.

    TheStadiumwindspeedsensorslocatedatboththeEastandWestRingbeamlevelof

    theroofdidnotgenerateanyhighwindwarnings(greaterthan30KPH),andnohigh

    windwarningwasrecordedonEnergratedcomputerprintout. Wecansafelyconclude

    thewindswerelessthan30KPH. Windsdidpickupmuchlaterintheeveningof

    January5th

    withwindspeedsincreasingto25KPHbetween10:00PMandmidnight.

    Thereisnoevidencesupportthetheorythathighwindswereafactorinthecollapseof

    theroof.

    Photo#1 CamerapointsNorthWest

    Steamplumeindicating

    winddirectionfromthe

    northeast

  • 8/8/2019 Joint Health and Safety Committee Report on B.C. Place Stadium roof

    20/82

    InvestigationReport:BCPlaceRoofDeflationIncidentofJanuary5,200718

    Acompletesetofweatherdata,sourcedfromGVRD,EnvironmentCanadacanbefound

    inAppendixE WeatherData.

    Snowsquallsconsistingofheavywetsnow,sleetandrainmixedwithsnowfellonthe

    stadiumthatmorningandafternoon. TimelapsevideosuppliedbyTomasSvabat

    23degrees.netgivesagoodpictureoftheweatherincludingtimingandmagnitudeof

    snowsquallsandwinddirection. (SeeAppendixHListingofPhotographsandVideo

    Clips,inCDformat)

    Inaddition,evidenceindicatesthatthetemperaturedroppedbelowfreezingfora

    periodoftime,attheringbeamandroofduringthemorningofJanuary5th

    . Witnesses

    reportedfrozensnowandiceonthelidsofequipmentboxeslocatedontheringbeam

    shortlyaftertheroofwasdeflated. Photographicandvideoevidenceshowssnowand

    icefrozentothefabricoftheroof.

    Photo#2taken45minutesafterdeflationfromringbeam

    Inadditionthereisevidencetosupportthattherewasaliquidcomponentconsistingof

    waterandslushontheroofaswell. Witnesseswhowereontheroofimmediately

    followingthedeflationobservedandwalkedthroughslushontheringbeamdescribing

    astheconsistencyofa711slushy. Underneaththisslushwasacoatingoficethatalso

    frozeandblockedtheringbeamdrainsandalsomadeitveryslippery. ACityofficial

    Photo#2

  • 8/8/2019 Joint Health and Safety Committee Report on B.C. Place Stadium roof

    21/82

    InvestigationReport:BCPlaceRoofDeflationIncidentofJanuary5,200719

    indicatedhowslipperythewalkwaywasashemadehiswayfromtheEastringbeam

    hatchtothewestsideoftheroof.

    RoofLoading

    ThestagewassetforcumulativeloadingoftheroofstructureonthemorningofJanuary

    5th.

    Beforewelookatloading,itisimportantthatthereaderunderstandthatthestadium

    roofsupportsystemisbasedonaconstantpressureenvironment. Thisisdifferentfrom

    theexampleofaninflatableexerciseball. Theexerciseballisaconstantvolume

    environment.

    Inthecaseoftheexerciseball,ifyousitontheball,yourweightpressingdownonthe

    ballwillcausetheinternalpressureoftheballtoincrease. Thisisbecausethevolume

    oftheballremainsconstant.Yourincreasedweightissupportedbytheincreasein

    pressureandconsequentlytheballbecomesmorerigidwhenyousitonit.

    However,intheconstantpressureenvironmentofthestadium,astheloadingonthe

    roofinincreased,thecontrolsystemwillacttomaintainaconstantpressure. Asthe

    loadincreasedandpresseddown,thecontrolsystemwouldbleedoffthepressure

    increasecausedbyweighttomaintaintheconstantpressure. Asthereisnoincreasein

    internalpressureduetoloadingoftheroof,thepressureremainsconstantasdoesthe

    safetyloadmargin. Oncethesafetyloadmarginisexceededduetotheadditional

    weightofsnow,theroofwillnolongerbeabletosupportitselfandwillbegintodeform

    anddropinelevation.

    Atanoperatingpressureof250Pascals,theroofloadsafetymarginwascalculatedto

    beapproximately324tons. Thisisbasedonanevenlydistributedloadovertheentire

    roofarea. (SeeAppendixBBCPlaceRoofLoadingCalculationsfordetailed

    calculationsandanalysis)

    Asprecipitationintheformofhighdensitysnow,sleetandrainbegantoaccumulateon

    thefabricsurfacesoftheroof,theweightofthismaterialbegantoapproachthesafety

    marginload.

    Basedonphotographicevidence,thesnowloadontherooffabricwasuniformly

    distributedovertheentireroofarea. Asdiscussedintheprevioussectiononweather

    conditions,thereweretwoseparateformsofprecipitationontheroofthemorningof

    thecollapse. Thefirstbeingauniformcoatingofwetsnowthateventuallyfrozetothe

    rooffabric. Thesecondformconsistedofamoremobilemixtureofrainandslushthat

    fellontopofthefrozenlayerofsnow. Thethreephotographsbelowillustratethe

    uniformsnowcoverageontheroof.

  • 8/8/2019 Joint Health and Safety Committee Report on B.C. Place Stadium roof

    22/82

    InvestigationReport:BCPlaceRoofDeflationIncidentofJanuary5,200720

    1stof3photostakenfromapartmentoppositestadium

    Thissequenceofphotosillustratesthemovementofsnowoffthepanelsastheroof

    camedown.

    Photo#2ofsequenceshowsastheroofdropped,snowbeginstomigrateoffsomeroof

    panelsslidingintothecenterofthebowl.

    Uniformsnowloading

    onthemajorityofroof

    anels

    Snowhasnowslidoffthis

    rectangularpanel

    Snowhasslidoffthe

    lowerpartofthis

    rectanglepanel

    Theremainderoftheroofis

    stillevenlycoveredwithsnow

    Snowbeginsto

    slideoffsome

    ofroofpanels

    inthisarea

    WaterMarkonringbeamcaused

    bythespilloveroftheavalanche

    contentsofwater,iceandsnow

    Photo#3

    Photo#4

  • 8/8/2019 Joint Health and Safety Committee Report on B.C. Place Stadium roof

    23/82

    InvestigationReport:BCPlaceRoofDeflationIncidentofJanuary5,200721

    Thirdphotoinsequenceillustratesfurthermigrationofsnowoffroofpanels.

    PhototakenfromRingbeam45minutesafterdeflation

    Piecesof

    ice\frozen

    snowbroken

    awayfrom

    fabric

    Majorityof

    easttriangle

    isnowclear

    Centerdiamond

    panelsstillcovered

    insnow

    Northtrianglenow

    mostlyclearofsnow

    Photo#5

    Photo#6 Secondarydamageto

    rectangularroofpanelPilesofsnow/icethat

    haveslidoff

    rectangularroofpanels

    downintothebowl,

    theroofcableline

    actedasabarrier

  • 8/8/2019 Joint Health and Safety Committee Report on B.C. Place Stadium roof

    24/82

    InvestigationReport:BCPlaceRoofDeflationIncidentofJanuary5,200722

    Astheroofloadbegantoapproachthebalancepoint,theentiretopsectionoftheroof

    begantoflatten. Astheroofapproachescriticalloading,itbecomesverysoft

    structurallyandsmallincreasesinloadingpastthispointfurtherexacerbatethe

    deformation. Themainspeakerclusterwhichissuspendeddirectlyunderneaththe

    westernsectionoftheroofwastheextraweightpullingdownthealreadyoverloaded

    roof. Thiscausedatleast3diamondpanelsinthisareatobecomeinverted.

    Theinvertedareabecameacollectionpointwherewaterandslushbegantodraininto

    thisareacreatingapond. Shortlybeforethewestpanelwasdamaged,witnesses

    observed invertedpanelsinadditiontoseeingtheroofcablesinthisareabent

    downwardandwaterpouringoutofonetheroofdomevents.

    Thephotographonnextpageillustrateshowthemainspeakerclusterissuspendedand

    anchoredtotheroofcables.

  • 8/8/2019 Joint Health and Safety Committee Report on B.C. Place Stadium roof

    25/82

    InvestigationReport:BCPlaceRoofDeflationIncidentofJanuary5,200723

    Mainspeakerclustercablesupportanddiamondpanelsinthepond/inversionarea.

    Themainspeakerclusterhangsinsidethestadiumsupportedby4cablesthatattachto

    themainroofcablesjusteastofthewesttrianglepanel.

    Mainspeaker

    clustersupport

    framecable

    attachmentpoints

    Roofdamper

    reliefvents.

    Witnesses

    observed

    waterpouring

    outofthese

    vents

    indicativeof

    panel

    inversion.

    TopofWest

    trianglepanel.

    Thisisthepanel

    thatfailed.

    MainSpeaker

    clusterat15

    meterposition

    These4panels

    withinthered

    boundarywerein

    distressandatleast

    3ofthesepanels

    wereinverted.

    Avalancheor

    pondtraveled

    inthedirection

    ofarrow

    towardsthe

    westtriangle

    roofpanel.

    Photo#7

  • 8/8/2019 Joint Health and Safety Committee Report on B.C. Place Stadium roof

    26/82

    InvestigationReport:BCPlaceRoofDeflationIncidentofJanuary5,200724

    Theoriginaloperatingproceduresforthebuildingmakereferencetoloweringthemain

    speakerclustertoavoidpanelorroofinversioninasignificantevent. Byloweringthe

    mainspeakerclustertotheground,theweightwillberemovedfromtheroof,reducing

    theloadinginthisareaoftheroof. Thisincreasestheabilitytowithstandmoreloading

    withcausingdeformation.

    Thisspecificareaunderthemainspeakerclusterhasanincreasedloadcausedbythe

    weightofthespeakercluster. Hence,itwilltakelessofasnowloadthanotherroof

    sectionstocauseeitherdepressionorpanelinversion. Asloadingcontinuesandmore

    waterandslushfallsin,thepondorinversiongrowsinsize.

    OnthedayofJanuary5th

    ,themainspeakerclusterwassetatits15meterdefault

    position. Astheroofbecameoverloaded,witnessesobservedthemainspeakercluster

    atvariousheightslowerthanthedefaultsetting. Thefollowingphotographillustrates

    themainspeakerclusteratthedefault15metersetting,alongwithlowerpositions

    observedbywitnesses.

    ThisphotowastakenfromtheEastfieldentranceshowingthemainspeakerclusterat

    15meterposition.

    Speakercluster15

    metersor49feet

    aboveturf. Thiswas

    thepositionsetting

    oftheclusteron

    January5,2007.

    Photo#8

  • 8/8/2019 Joint Health and Safety Committee Report on B.C. Place Stadium roof

    27/82

    InvestigationReport:BCPlaceRoofDeflationIncidentofJanuary5,200725

    Itisclearfromthephotographicevidencethatby12:24theloadingontheroofhad

    exceededthesafetyloadmarginandtheroofbeganitsdecent. Atonepointatabout

    12:24pmaphotographshowsthewestpanelinvertedatthetop. At12:25orsothe

    roofwasabout50feetlowerthanitsnormalprofile.

    This

    photo

    represents

    the

    normal

    profile

    of

    B.C.

    Place

    at

    250

    Pa.

    Thisphotowastakenabout20minorsobeforetheavalanche.

    Pondorpanel

    inversionin

    thisarea

    TopofVancity

    officebuilding

    West

    Triangle

    PanelTop

    5

    floors

    ofVancity

    Buildingnow

    visible

    Photo#9

    Photo#10

  • 8/8/2019 Joint Health and Safety Committee Report on B.C. Place Stadium roof

    28/82

    InvestigationReport:BCPlaceRoofDeflationIncidentofJanuary5,200726

    Noticethedifferenceintheelevationaswellashowflattheroofisonthetopsections.

    Theroofprofileinthe2ndphotoisabout50feetlowerthanitshouldbe. Thewitness

    thattookthispicturedidsobecausehethoughtitwasstrangethathecouldseethe

    upperportionoftheVancitytowerlocatedatQuebecandTerminal. Normallyhecould

    onlyseetheflagpolefromhisapartmentwindowandthispromptedhimtobegin

    takingphotos.

    Oncetheweighthadaccumulatedontheroofandthepondwasallowedtoaccumulate,

    itwasinevitablethatoncethepressurewasrapidlyincreased,theunstablepond

    consistingofwater,iceandsnowwasgoingtomovesomewhere.

    Therewasarapidincreaseinpressurecausedbyapressureovershootinthebuilding

    controlsystem(RefertofulldetailsonPressureExcursion). Thissuddenincreasein

    pressurecausedtherooftoregainitsnormalprofile. Atthesametime,thiscauseda

    suddenandinstantmovementofaminimumof8,000to11,000lbsofwater,iceand

    snowtomovesuddenlyandquicklydowntheWesttrianglepanel.(SeeAppendixD

    InvertedPanelLoadingCalculations)

    Thislargemassinvertedthewesttrianglepanelasittraveledwestward,causingthe

    paneltodepress6to8feetlowerthannormal. Asthemassmoveddownthewest

    panelitfinallyhittheinsideringbeamandSeikoClockwithsuchtremendousforce,it

    tooktheroofpanelwellpastitsdesignbreakingstrength.

    Theresultwasafailureintheweakestspotwhichwasafieldweldwheretheskirting

    hadbeenweldedtothefabric. Thisfindingwasdeterminedbytheengineer;see

    AppendixGGeigerEngineersReportData,Sept14,2007,#207813. Hadtheweld

    notbeenthere,thepanelfailurewouldhavefailedinthenextweakestspot,etc. The

    forcelikelywaslargeenoughtofailevenanewpanel.Thekeytothispanelfailurewas

    theavalancheofsnow,waterandicewhichshouldhavenotbeenallowedto

    accumulateonthesurfaceoftheroof. Itshouldalsobenotedthatarectangularroof

    panelwasalsodamagedonthesoutheastsideoftheroof. Photograph#6above

    clearlyshowsarippedpanel. Thismayhavebeencausedbysnowandiceslidinginward

    downintothebowlastheroofdeflated.

  • 8/8/2019 Joint Health and Safety Committee Report on B.C. Place Stadium roof

    29/82

    InvestigationReport:BCPlaceRoofDeflationIncidentofJanuary5,200727

    Fiberglassfibers(rooffabricmaterial)werefoundimbeddedinthemetalhousingon

    whatwasremainingoftheSeikoClockadpanel.

    SeikoClockhousing Seikoclockframe

    Inadditionsomeoftheinchmountingboltssecuringtheclocktotheconcretewereshearedoff. Thisgivesthereadersomeideaofthemagnitudeofthecollisionforces

    thatweregeneratedwhentheavalancheormovingpondstruckboththeSeikoclock

    andtheconcreteringbeam.

    glassfibers

    imbeddedin

    damaged

    metalclock

    panel

    Strandof

    glassfiberon

    Seikoclock

    housing

    6feethighconcrete

    ringbeam

    Noticehowmetalstructureis

    deformedandpushedinasa

    resultoftheavalanchecollision

    forces. Thisiswherethe

    committeeobservedinchanchor

    boltsthatwereshearedoff.

    Thispanelis

    undamaged. Notice

    howthefaceofthe

    structureisflush

    withtheringbeam

    RemainsofSeiko

    clockinternal

    electronics/wiring

    Rooffabricattachestoring

    beamhere. Thearcgivesan

    ideaofhowfardownbelow

    theringbeamtheavalanche

    causedthepaneltomove.

    Photo#11

    Photo#13

    Photo #12

  • 8/8/2019 Joint Health and Safety Committee Report on B.C. Place Stadium roof

    30/82

    InvestigationReport:BCPlaceRoofDeflationIncidentofJanuary5,200728

    RoofFabric

    Theengineerhadconductedextensivetestingofthefabric. PleaserefertoGeiger

    Engineersdraftreportonthefindings(AppendixGGeigerEngineersReportData,

    Sept14,2007,#207813).

    It

    is

    determined

    fabric

    weakness

    did

    not

    play

    a

    significant

    role

    in

    the

    initial

    failure

    of

    the

    panel. Themovingweightofslush,snowandicethatwasexperiencedonJanuary5/07

    wouldhavebeenenoughtodamageamuchnewerrooffabric. Duringthe

    investigation,theengineersharedinformationonasimilarroofdeflationincident

    happenedin1982attheMetrodomeStadiuminMinneapolis. IntheMetrodome

    incident,thethenoneyearoldairsupportedroofbecameloadedwithsnowandice

    withsomepanelsinverted. Operatingstaffincreasedinternalpressuretoomuchand

    tooquickwhichledtoanavalancheofsnowandicethatcausedroofpanelruptureand

    consequentlyatotalroofdeflation. TheMetrodomeexampleillustratesthatevena

    practicallynewroofcansustainpanelfailureduetomovingroofloadsofsnowandice.

    BCPlaces23yearoldroofmayhavedeterioratedandevenweakenedatsomespots,

    butthatwouldnothaveresultedinapanelfailureonitsown. Itwastheheavyloading

    ofrain,snowandicethatcompromisedtheintegrityoftheroofstructure.

    PressureExcursion

    ThissectioncontainstechnicalinformationwhichisuniquetoBCPlacesroofsupport

    systems. Tofullyunderstandthebehaviorsandimpactsofinternalpressureincreases,

    pleaserefertoAppendixA RoofSupportPressureControlSystemsDescription.

    ThecausalanalysisoftheroofdeflationatBCPlaceStadiumonJanuary05,2007points

    toarapidincreaseinbuildingpressure,abovesetpointof350Pa,asasecondary,

    precipitating,contributingevent.Althoughthiswasnotthedirectcauseofthedeflation

    itdoesappeartohaveplayedamajorroleinthegenerationofthepanelfailure. The

    computerlogsandinterviewsofcontrolroomstaffandsupervisorsalongwithvarious

    witnessaccountssupportthefollowingscenario:

    OnJanuary5,2007justpriortotheroofcollapse,theroofsupportsystemwasusing

    bothASDandCSFcontrolsystemsforpressurecontrol. ThereweretwoASDfans

    runningandtwoconstantspeedfansrunning. Thepressuresetpointwas250Paon

    boththecomputerandthepneumaticpressurecontroller. Asperprocedure,therelief

    controllerwassetto300Pa. Inanalyzingthecircularpressurechartrecorder,wecan

    seethatthepressurewasverystablepriortostaffrealizingthattheroofwasincrisis.

  • 8/8/2019 Joint Health and Safety Committee Report on B.C. Place Stadium roof

    31/82

    InvestigationReport:BCPlaceRoofDeflationIncidentofJanuary5,200729

    PressureRecorderChartfromJanuary5,2007

    EnergratedComputerConsolelocatedinthefrontareaofthecontrolroom

    FullScale100%=750Pa

    Inset:

    Seebelowfor

    detail

    ThisistheEnergrated

    computerusedtomakeset

    pointchangesforASDfans

    aswellasmonitoringand

    controllingawidevarietyof

    building/roofsupport

    systemparameters.

    Photo#14

    Photo#13

  • 8/8/2019 Joint Health and Safety Committee Report on B.C. Place Stadium roof

    32/82

    InvestigationReport:BCPlaceRoofDeflationIncidentofJanuary5,200730

    HoneywellControlPanellocatedintherearareaofthecontrolroom

    Whenitwasdiscoveredthattheroofwasincrisis,thecontrolroomoperatorwasinstructedtoincreasepressuresetpointto300Paandtoprepareforsnowmelt

    operation. Theoperatorincreasedthesetpointonthecomputerto300Pa. Duringthe

    crisisenvironmentinthecontrolroomasstafftriedtoevaluatewhatwashappening,

    thenextstepoftheprocedure,namelytoincreasetheHoneywellpressurecontroller

    setpointto300PatomatchthecomputersetpointandthentoraisetheHoneywell

    reliefto350Patoisolateitfromthesystem,didnothappen. Thissetpointchange

    requiresthattheoperatorleavetheEnergratedcomputerconsoleandgotothe

    Honeywellpanelthatislocatedattherearofthecontrolroom. Inthecrisis

    environmentitisunderstandablehowthisstepcouldhavebeenmissed.

    WiththeomissionofchangingthesettingsontherearHoneywellpneumatic

    controllers,thetwoseparatecontrolsystemsbegantointeractinaconflictingmanner.

    AstheASDfansrampedupto100%speedtotryandraisethestadiumpressureto300

    Pa,thepneumaticreliefcontrollerbegantoworkagainstthisactionoftheASDfansby

    openingupreliefdampers. Theconstantspeedfandamperscontrolledbythepressure

    controllerwerenowinrecirculationmodebecausethecontrollersetpointof250Pa

    hadbeenachieved. Hencetheconstantspeedfanswerenotworkingtoincrease

    stadiumpressure,insteadidlingat250Pa.

    Pressure

    Chart

    Recorder

    Honeywell

    Pressure

    ControllerHoneywellRelief

    damper

    controller

    SnowMelt

    delaytimers

    15hoursnow

    meltdelay

    button

    Photo#15

    Magnehelic

    PressureGauge

  • 8/8/2019 Joint Health and Safety Committee Report on B.C. Place Stadium roof

    33/82

    InvestigationReport:BCPlaceRoofDeflationIncidentofJanuary5,200731

    Insetofpressurechart: Pressureovershootanalysis

    Asmorefanswereturnedoninpreparationforsnowmeltoperations,thepressureonly

    increasedtoapproximately270to280Pabasedontheanalysisofthepressurechart

    recorder. Asthebuildingpressurewasnotrespondingtothenewsetpointchangeof300Pa,andtheroofwasstillfalling,asupervisorrandowntotheTechShopwherethe

    seniorcontroltechnicianwashavinghislunch. Heinstructedthetechniciantogointo

    hiscomputerandincreasetheASDsetpointto400Pa. Ittookthetechnicianafew

    minutestomakethesesoftwarechangestothesystem. Basedonanalysisitwas

    determinedthattwofactorswereatworktocancelthissetpointchangetotheASDs.

    Thefirstbeingthereliefdamperswhichwouldhavebeenopeninguptoreducethe

    pressureonceitroseabove300Paandthesecondiswhenthesnowmeltsystemwas

    turnedon. Itwasdeterminedthatwhentheroofsupportsystemwentintosnowmelt

    mode,thesnowmeltsetpointof300Patookpriorityandcancelledthe400Pasetpoint

    changemadebytheTechnician.

    Meanwhilebackinthecontrolroom, directionsweregiventothecontrolroom

    operatortoraisethesetpointto350Pa,themaximumpressuresettingallowedonthe

    Honeywellpressureandreliefcontrollers.

    TheoperatorthenchangedtheHoneywellpressureandreliefcontrollersto350Pa.

    Withcomputerpressurecontroller,sinceitwasalreadyinsnowmeltmode,pressure

    Pressureat270280Pajust

    priortocontrollersetpoint

    changeto350Pa

    Pressurepriorto

    crisis=262Pa

    Setpoint =250Pa

    PeakPressure=520Pa

    LowpointofundershootwhenASD

    fansbegantorespond=247Pa

    Fansare

    turnedoffto

    deflateroof

    West

    TriangleFails

    Numbersrepresent

    percentageof750Pa.

    Fullscale

    70=.7x750=525Pa

    Photo#16

  • 8/8/2019 Joint Health and Safety Committee Report on B.C. Place Stadium roof

    34/82

    InvestigationReport:BCPlaceRoofDeflationIncidentofJanuary5,200732

    setpointwaslockedat300PafortheASDfans. Theconditionswerenowsetupfora

    largepressuresetpointovershoot.

    Oncetheoperatormadethesechangesanumberofpressurerelatedeventsoccurred.

    TheHoneywellpressurecontrollerbegantorespondtotheincreaseinsetpoint. Asthe

    stepchangeinsetpointwas100Pa(250to350Pa)thepressurecontrolleroutput

    veryquicklyincreasedfromzerooutput(fullrecirculation)to100%pneumaticoutput.

    This100%signalcausedthefanroomdamperstoswitchfromfullrecirculationtonow

    callingfor100%outsideair.

    Simultaneously,thereliefcontrollerwhichalsohaditssetpointchangedto350Pa

    begantooutputitspneumaticsignaltocloseallofthereliefdampers. Theneteffectof

    theseactionscreatedarapidincreaseinpressure. ThefourASDfanswererunningat

    closeto100%,thefourconstantspeedfanswerenowdrawinginoutsideairat

    maximumrates. Wenowhaveeightfansdrivingthepressuretowardstheirrespective

    setpoints. Asthepressureroseto300Pa,theASDfanswouldhavesloweddown,as

    theirsetpointvaluewasnowachieved. Thefourconstantspeedfanscontinueddriving

    thepressureupwardtowardstheirsetpointof350Pa.

    Thisiswherethecharacteristicsofapneumaticsystemworkedtoamplifythepressure

    overshoot. Asthepressureroseabove350Pa,thepressurecontrolleroutputwould

    nowstarttodecrease. Butsinceitisapneumaticsignal,ittakestimeforthesignalto

    propagatethroughthepneumaticsystemoverthelargedistancesfromthecontrol

    roomtothefanrooms. Insomecasesthisdistanceis800feet. Consequentlyittook

    timeforthesignaltoreachthedampersandtobegintoreducetheamountofoutside

    airbeingbroughtin(thisincreasedpressure)andswitchtorecirculationmode. During

    thistimelagthepressureinthestadiumcontinuedtorisewellabove350Pa.

    Inparalleloperation,thepneumaticreliefcontrollerisnowsensingthepressurerising

    aboveitssetpointof350Pa. Asthepressurerisesabovethesetpointthepneumatic

    controlleroutputsendsasignalouttostartopeningthebanksofreliefdampers.

    TypicallyduetothelocationofthereliefdampersonLevel4andattheringbeamlevel

    5ofthestadium(distancesofcloseto1000feet)thetimedelayforfullyopeningthe

    reliefdampersistwominutes. Whilethisdelayisineffectthepressureisstillrising.

    Bythetimethereliefdampersbecameeffectiveandhaltedtheupwardpressure

    overshoot,thepressurehadrisento68%onthepressurechartwhichrepresentsapeak

    pressureof520Pa. Forsuchalarge100Paincreaseinpressuresetpoint,combined

    withtherapidturnonofadditionalfans,thisisnotanunreasonableovershootabove

    thesetpoint.

    Theonlyproblemwasthesignificantroofoverloadingandsubsequentpanelinversions

    thatcreatedalargeunstablemassonthewestendoftheroof. Oncethepressurewas

    increased,theroofbegantoregainitsnormalprofile. Asthepressurecontinued

    towardsitspeakof520Pa,eventuallytheinternalpressurewasenoughtoovercome

  • 8/8/2019 Joint Health and Safety Committee Report on B.C. Place Stadium roof

    35/82

    InvestigationReport:BCPlaceRoofDeflationIncidentofJanuary5,200733

    thedeformationoftheroof. Asthishappened,themassofsnow,waterandicebegan

    tomovedownwardaccordingtotheprincipalsofgravity. Themasswasslidingfrom

    paneltopanelpickingupweightandvelocityasitmoved. Theresultwastheavalanche

    ofsnow,waterandicethatresultedinacatastrophiccollisionwiththeringbeam. The

    rooffabricatthispointwassustainingatremendousweight,andfinallybrokenatits

    weakestspotresultinginthefailureofthewesttrianglepanelandtheexplosionofthe

    Seikoclock.

    Oncethetearoccurred,itwastoolate. Activitiesrecappedbelowweresimplysystem

    defaultreactionstothepressurelossduetoaholeintheroof,buthadnoeffectsin

    rescuingthedamagedroof. Thereliefsystemhasnowfullyopenedallofthedampers,

    thepressurecontrollersignalispositioningtheconstantspeedfandampersforfull

    recirculationandthepressureisdecreasing. Bythetimethepressuredropsbelow300

    PatheASDfancontrollernowrespondsandtheASDfansbegintospeeduptocounter

    thepressuredrop.Thepressurefellbelowthesetpointreachingalowpointof33%or

    247Pa. Asthepressuredroppedbelowthesetpoint,computercontrolledASDfans

    reactedquicklyandbegantoraisepressure.Thepressurewasonitswaybackuptothe

    setpointof300Pawhenthewesttrianglepaneltotallyfailed. Atthispointthe

    pressurewasabout37%or277Pa.

    Thistechnicalanalysisofthedatasupportstheconclusionthatthenotedaccidental

    rapidpressurizationofthebuildingwaslikelytheresultofanovershootinthe

    pneumaticdamperpressure/reliefcontrolsystem. Throughoutthehistoryofthis

    building,therehavebeenseveralsimilarpressureexcursionsupwardsof100Paabove

    setpointundervariouscircumstances.

    Itisimportanttonote,duringthehandlingoftheroofincrisis,noStadiumpersonnel

    wereflippingdifferentswitchestocausetherapidpressureincrease.

  • 8/8/2019 Joint Health and Safety Committee Report on B.C. Place Stadium roof

    36/82

    InvestigationReport:BCPlaceRoofDeflationIncidentofJanuary5,200734

    Equipment

    Thecausalanalysisrevealedanumberofdeficienciesthatwererelatedtoequipment.

    1.Theabilityofthecontrolroomtoeffectivelyanalyzeandseetheactualroof

    conditionswaslessthanadequate. Theexistingcamera(picturebelow)located

    outsideontheringbeamofthestadiumwasonlyabletoseeasmallportionofthe

    rooffabriclessthan10feetupfromtheringbeam. Consequentlythecontrolroom

    operatorwasunabletoobservethecumulativesnowloadingoftheroof.

    RingbeamCameraatsection10(TerryFoxPlaza)

    Photo#17rightpanview Photo#19 leftpanview Photo#29 centerview

    Theabovearephotosoftheactualscreeninthecontrolroomthatoperatorsuseto

    viewthecamera.

    2.Thecausalanalysisalsohighlightedtheinabilityoftheexistingcontrolsystemto

    senseadropinroofelevation. Henceastheroofbegandroppingfrom12:00to

    12:30,thecontrolroomoperatorwastotallyunaware.

    3.Thecausalanalysisidentifieddirectcause#2asthefailuretoincreasepressureand

    effectivelyapplyheat. Twoofthekeyaspectsrelatedtocause#2wereboththe

    absenceofapushedautomatedweatheradvisoryservicetonotifyoperatorsof

    significantweathereventsthatcouldimpactstadiumoperationsaswellasthetotal

    Ringbeam

    mounted

    camera

    Photo#16

  • 8/8/2019 Joint Health and Safety Committee Report on B.C. Place Stadium roof

    37/82

    InvestigationReport:BCPlaceRoofDeflationIncidentofJanuary5,200735

    lackofaccesstorealtimeweatherinformation. Bothoftheseserviceshadbeenin

    placeinthepast,butwerediscontinued.

    4.Thecausalanalysisconductedbythecommitteeidentifiedarapidincreasein

    pressureasasecondary,precipitating,contributingeventanditwasafactorinthe

    generationofthewesttrianglepanelfailure. Theanalysisoftherapidpressure

    increaseidentifiedbothhumanelementsrelatingtocontrolsystemsettingsaswell

    ascontrolsysteminteractionsandconflictsastherootcauseoftherapidpressure

    increase.

    5.Themechanismtolowerthemainspeakerclusterwasnotlocatedinthecontrol

    room. Inanemergencysituation,thisdelaystheresponsetimefortheoperatorto

    lowerandunweightthespeakertothegroundinanextremeloadingsituation.

    6.Whileitisknownthatthesnowmeltingsystemcanhandlevirtuallyanyamountof

    snowandkeeptheroofclearwhenoperatedproperly,thecommitteeidentifiedthe

    potentialriskofsystemfailuresthatcouldrenderthissnowmeltingsystem

    ineffective. Intheearlyeighties,roofhotwaterdispersionsystemwasinstalledto

    beusedincontingencysituationsforsnowremovalfromtheroof. Inadditiontothe

    hotwatersystem,therewasavarietyofspecializedequipmentstoredinequipment

    boxesontheroofthatwasreadyforuseinemergencysituations. Someofthis

    equipmentincludedpumpsfordrainingpanelinversionsorponds,emergency

    generators,snowblowersandshovelsforringbeamclearing,roofrepairequipment

    andmaterialforeffectingtemporaryrepairstotherooffabric.

  • 8/8/2019 Joint Health and Safety Committee Report on B.C. Place Stadium roof

    38/82

    InvestigationReport:BCPlaceRoofDeflationIncidentofJanuary5,200736

    CrisisIdentificationandManagement

    Fromthemomentthatstaffwereinformedthattheroofwasindistress,therewasa

    lackofcoordinationandassessmentoftheproblem. Supervisorsandstaffrantothe

    controlroom. Onesupervisorstayedatthefrontofthecontrolroomandimmediately

    instructedthecontrolroomoperatortoraisethepressuresetpointto300Paandget

    readyforsnowmeltsystemactivation. Theothersupervisorandaworkerwenttothe

    backofthecontrolroomtolookattheMagnehelicpressuregauge,believingthatthe

    problemwiththeroofmayberelatedtopressure. Oneoftheworkersleftthecontrol

    roomtogooutseewhatwasgoingonwiththeroof. Hereturnedtoreportthatthere

    werenumerousinvertedroofpanelsnearthespeakercluster. Atthispoint,whenit

    wasidentifiedtheroofwasincrisis,multiplepartieswereinvolvedindoingtheirbestto

    dealwiththesituationindependentlywithoutengaginginacoordinatedprocess.

    Afterseeingthatthestadiumpressuredidnotseemtoberisingtothenewsetpointof

    300Pa,asupervisorrandowntothetechshoptoinstructaseniortechnicianto

    increasethesystempressureto400Paviahisshopcomputer. Unknowntothe

    supervisorandthetechnician,thesettingsforthepressureandreliefcontrollerswere

    adjustedforthenewcomputersetpointof300Pa. Consequentlythepressuresetpoint

    initiatedbythetechnicianwasnullifiedbythereliefdampercontrolleraction.

    Asstaffweredoingtheirbesttodealwithacrisissituation,thereseemedtobealackof

    coordinationintheirefforts. Thisclearlyrelatestothefactthatstaffhadnothadany

    formalizedtrainingrelatingtocrisismanagement. Therewasnocrisisassessment

    proceduretofollow,andconsequentlytheeffectivenessoftheirwellintentioned

    actionsanddecisionswasreduced.

    Thepoliciesandproceduresdocumentrelatingtoroofinversionwasnotavailableinthe

    controlroom. Thisdocumentwasnotalivingdocumentasithadnotbeenupdated

    andstaffhadnotbeentrainedinitsapplication.

    Whencontrolroomoperatorsreceivedinformationthatsomeroofpanelswere

    inverted,ifalivingpoliciesandproceduresmanualwereinplace,theycouldhave

    quicklylookeduptheproceduretodealwiththisproblemandidentifiedthatstabilizing

    thepressureandkeepingitat300Pawasthebestcourseofaction.

    TheactivitiesfortheControlroomoperatorsareroutineforthemajorityofthetime. It

    isonlyperiodicallythattheoperatorsexperiencesignificanttechnicaleventsthat

    requirefastdecisionmakingandactionontheirparttodealwiththeproblemorcrisis.

    Acomparativejobanalogycanbemadetocommercialairlinepilots. Forthemostpart,

    thejobofapilotisveryroutineandstructuredinnature. However,whenproblems

    arise,pilotsareextremelywelltrainedindealingwithcontingencysituations. Pilotsrely

    onspecificproceduresandpolicieswhendealingwithawidevarietyofinflight

    emergencies. Theyreceivemandatoryregulartrainingsessionsthatsimulateavast

  • 8/8/2019 Joint Health and Safety Committee Report on B.C. Place Stadium roof

    39/82

    InvestigationReport:BCPlaceRoofDeflationIncidentofJanuary5,200737

    arrayofpossibleinflightemergenciesandpracticetheproceduresandactionsto

    successfullydealwiththeseemergencies. Acomponentoftheirtrainingfocuseson

    crisismanagementandcockpitresourcemanagementwhichtrainsthemtoworkasan

    effectiveteamwithinthecockpitenvironment. Consequentlywhenrealemergencies

    doarise,pilotsareverysuccessfulatdealingwiththeseemergenciesandmitigating

    potentiallossoflifeordamagetoaircraft.

    Overtheyearsthestadiumcontrolroomoperatorshaveexperiencedavarietyof

    seriousincidentsthathavecompromisedintegrityoftheroof. Theseincidentsincluded

    numerouspowerfailures,overloadingoftheroofduetosnowaccumulationandfailure

    ofkeycontrolequipment.

    Ifthecontrolroomoperatorsandmanagementstaffaretobesuccessfulatdealingwith

    thesepotentialcrisissituationsinthefuture,theremustbeongoingtrainingand

    refreshersessionsthatgivethemtheskillsnecessarytoworkasateamanddealwith

    thecrisiseffectively.

  • 8/8/2019 Joint Health and Safety Committee Report on B.C. Place Stadium roof

    40/82

    InvestigationReport:BCPlaceRoofDeflationIncidentofJanuary5,200738

    Policies,ProceduresandTraining

    TheInvestigationSubcommitteelookedatdocumentsrelatedtocontrolroompolicies

    andproceduresandtraining. Therewerepoliciesandprocedurescoveringthevarious

    aspectsofoperationsrelatingtothedaysevent. Withpoliciesandproceduresalready

    inplace,itisnecessarytoexaminewhypoliciesandprocedureswerenotfollowed.

    Letsfirstlookatthepoliciesandproceduresmanual,theBCPlaceControlRoom

    OperationsManualwasdevelopedbackin1987. Overtheyears,whileControlRoom

    hadgonethroughupgrades,therehadbeenverylittleupdatesmadetothewritten

    manual. Manyofthecontentsinthemanualwerenolongerreflectingthesystemsand

    operationsintheControlRoomatthetimeoftheincident. Theneedtoupdatethe

    manualhadbeenrecognizedduringanemergencyevacuationexerciseinNovember

    2005,sincethenthemainpolicyandproceduremanualforthecontrolroomhadbeen

    removedforupdating. Thereweretwokeypprocedurescontainedinthemanualthat

    wouldhavebeenmostrelevanttotheroofcrisissituationonthedayoftheincident:

    PartialRoofPanelInversion,andTotalRoofPanelInversion. Unfortunatelyboth

    procedureswerenotavailableinthecontrolroomastheyhadnotyetbeenrevised.

    ThefollowingaretheRoofpanelinversionprocedures:

    VIII21 PartialRoofPanelInversion

    ControlRoomStaffwillslowlyturnonmorefans. Thenumberoffanstobeturnedonis

    dependentonthesizeoftheinversionandisuptothejudgmentofthecontrolroomoperator.

    (1) WatchStadiumairpressureverycarefully. DONOToverpressure(i.e.keeppressureunder300Pa.)

    (2) Trytostabilizethepressurearound250Pa.(3) ReporttotheDutySupervisorimmediately

    VIII22 TotalRoofPanelInversion

    (1) ControlRoomStaffwillslowlyturnonallsixteen(16)fans.(2) Watchstadiumairpressureverycarefully. DONOToverpressure (i.e.keep

    pressureunder300Pa.)

    (3) Trytostabilizethepressurearound250Pa.(4) ControlRoomStaffwillinformalldepartmentstohavealldoorsclosed,especially

    bothairlockdoors.

    (5) ReporttotheDutySupervisorImmediately

    Andforupdatingpurposes,somepartsoftheP&PwereremovedfromtheControl

    Roomcopyofthemanual. Oneparticularsectionwhichwasrelevanttotheroof

    situation,Howtodealwiththepanelinversion,wasmissinginthemanual.

    Itshouldbenotedthatduringtheinvestigation,thecommitteediscoveredthatthese

    procedureshadbeendevelopedbasedonthefindingsofadeflationincidentin1982at

  • 8/8/2019 Joint Health and Safety Committee Report on B.C. Place Stadium roof

    41/82

    InvestigationReport:BCPlaceRoofDeflationIncidentofJanuary5,200739

    theMetrodomeStadiuminMinneapolis. TheMetrodomeisanairsupportedstadium

    verysimilartoB.C.Place. SeeRoofFabricsectionfordetailsoftheMetrodomeincident.

    Basedonthelessonslearnedfromthisincident,B.C.PlaceManagementimplemented

    theaboveprocedureswhenthestadiumfirstopenedin1983toavoidasimilarmishap.

    Overtheyearstheknowledgethatresultedintheadoptionofthesepanelinversion

    procedureshadbeenlostbyStadiumPersonnel. Asaresultwhenthestadiumstaff

    werefacedwithanoverloadedroofandpanelinversions,theydidnothavethese

    procedurestofollow. Iftheseprocedureswerelivingdocuments,thestaffmayhave

    avoidedthenaturalinstincttoraiseinternalpressuretocombattheroofloadingand

    panelinversion,buttakenthestepsoutlinedintheprocedures.

    Itisnotthecommitteesintenttosecondguessthedecisionsmadeinsuchacrisis

    situation. However,wewanttoillustratetheimportanceofproperlivingpoliciesand

    proceduresandhowtheymayhaveassistedindealingwitharoofincrisis.

    AsnowmeltprocedurehadjustbeenintroducedrecentlyonNovember15,2007.

    See

  • 8/8/2019 Joint Health and Safety Committee Report on B.C. Place Stadium roof

    42/82

    InvestigationReport:BCPlaceRoofDeflationIncidentofJanuary5,200740

    AppendixFEmergencySnowMeltProcedures,Nov15,2006. Theprocedurewason

    theinsidecoveroftheP&Pmanualwithastickynoteonitsayingpleaseread. When

    askedwhethertheywereawareofthenewprocedure,allControlRoomOperators

    interviewedrespondedyes,buttheyalsoindicatedtheywerenotexplainednor

    trainedonthenewprocedure.Furthermore,someofthecontrolroomoperatorshad

    notevenreceivedtrainingontheoldsnowmeltprocedures. Inaddition,therewasno

    seasonalrefresherforallcontrolroompersonnel.

    WhileitwasimpliedthattheSnowMeltProcedureswastocombataccumulationson

    theroof,butthepurposewasneverclearlystatedforallcontrolroomstafftoknowand

    follow. Itappearsanoverarchingoperationalmissionwasamiss: keeptheroofup.

    Onmanyoccasions,inspiteofthewrittenpolicythatclearlyindicatesthatifitis

    snowing,thebuildingtemperatureistoberaisedtoitsmaximumtemperatureof23

    degreesC,theoperatorsfelteitherthat,theydidnothavetheautonomytoexecutethis

    policy;orthat,theyhadseenworseweatherconditionsbefore,needtofollowthe

    policywasirrelevant.

    Thecommitteefoundaculturewherebothstaffandmanagementdidnotfollowthe

    writtenprocedures. Theunwrittenproceduresprevailedwhenitcametothe

    applicationofheatduringsnowconditions.

    Hencethatiswhylackofeffectivelyimplementedpolicies,proceduresandtrainingis

    therootcauseoftheroofdeflation.

  • 8/8/2019 Joint Health and Safety Committee Report on B.C. Place Stadium roof

    43/82

    InvestigationReport:BCPlaceRoofDeflationIncidentofJanuary5,200741

    CultureIssues

    Organizationalcultureplayedamajorroleintheroofdeflationincident. Organizational

    cultureisthepersonalityoftheorganization. Theculturecanbeassumptions,beliefs,

    practicesandnormsoforganizationmembersandtheirbehaviors.Culturecanbe

    difficulttoexpressdistinctly,buteveryoneknowsitsexistence.

    AcloselookatthecultureofBCPlacesmaintenanceandoperationsrequiresan

    impartialbutcriticalintrospection. Thereseemedtobeanunwrittenoperational

    guidelinecostminimization;applyingheatwhenitisabsolutelynecessary;turningon

    heatrequiresmanagementapproval. Overtime,controlroomoperatorsdefaultedto

    managementdirectionswhenitcametotheapplicationofheat.

    Theculturewasnottofollowprocedure,buttoseekpermissiontoapplyheat. Ithas

    beenalongpracticethatlittleheatorevennoheatwouldbeapplied,aswehave

    weatheredmanyborderlinesnow/sleetconditions. Thispracticeengenderedan

    unhealthycultureofcomplacency:leavingdecisionmakingtoothers,henceany

    responsibilitiesandconsequencesassociatedwiththedecisionbelongedtosomeone

    else. Thiscultureofcomplacencycorrelateswithalowlevelofemployeeengagement

    andempowerment. Engagementisthedegreetowhichworkersidentifywith,are

    motivatedby,andarewillingtoexpendextraeffortfortheiremployer. Empowerment

    iswhenworkersbelievetheyhaveautonomousdecisionmakingforthebestinterest

    andbenefitoftheirorganization.

    ThefollowingisanexamplethatillustratesthecultureexistedinBCPlace:

    Atasnowrelatedeventinlate2006wheretheoperator,believingthathedidnothave

    the

    authority

    to

    turn

    on

    the

    heat,

    worked

    with

    staff

    and

    the

    Event

    to

    get

    permission

    to

    turnontheheat. Thisillustratestheunwrittenpolicyorculturerelatingtotheuseof

    heat. Hadtheoperatornotturnedonsomeheatduringthisheavywetsnowfall,itis

    likelythattheroofwouldhavebeenincrisisonthatdate. Inspiteofthewrittenpolicy

    thatclearlyindicatesthatifitissnowing,thebuildingtemperatureistoberaisedtoits

    maximumtemperatureof23degreesC,theoperatorsfeelthattheydonothavethe

    autonomytoexecutethispolicy.

    InthisdeflationincidentofJanuary507,complacencycontinuedtobeafactoras

    personnelinvolvedintheoversightandoperationoftheroofsupportsystemshadlost

    theirknowledgeofbasicyetcriticalinformationrelatedtotheroof. Thisincludesissues

    suchasloadingandsafetymargins,knowledgegainedbyincidentsatotherair

    supportedfacilitiesandkeybehaviorsofairsupportedroofsinavarietyofweather

    conditions. Asaresultofthelossknowledge,alongwithverylimitedvisionoftheroof

    condition,operatorsmayhavereliedoninstincts.

    Itisnotuntilwerecognizethatacultureofcomplacencyexists,thatwecanthenstart

    tacklingitthroughacollectivekeeptheroof upmission,effectivepolicies,

    proceduresandtraining.

  • 8/8/2019 Joint Health and Safety Committee Report on B.C. Place Stadium roof

    44/82

    InvestigationReport:BCPlaceRoofDeflationIncidentofJanuary5,200742

    CausalAnalysisMethodologies

    CausalAnalysisistheprocessofidentifyingdirectandindirectcausesoftheroof

    deflation. TheCausalanalysisflowedoutofthecausedriversthatwereidentifiedinthe

    process

    that

    built

    the

    fishbone

    diagram.

    FishBoneDiagram

    TheFishboneorIshikawadiagram,formedthefoundationofcauseandeffectanalysis

    conductedbythecommittee. Thediagramshowsthecauseofanevent. Theendresult

    oreventwasthedeflationofthestadium. TheanswerstothequestionWhydidthe

    roofofB.C.Placedeflatebecamethecausesthatdrovethefinalresultofadeflated

    roof. Inallphasesoftheinvestigation,thefishbonediagrambecamethereference

    pointortouchstoneforthecommittee.

  • 8/8/2019 Joint Health and Safety Committee Report on B.C. Place Stadium roof

    45/82

    InvestigationReport:BCPlaceRoofDeflationIncidentofJanuary5,200743

    CausalEventPathDiagram

    Thefollowingisacausaleventpathdiagramthatgivesaroadmapofthepaththatled

    toPanelfailureandultimatelydeflationofthestadiumroof.

    West PanelFailure

    Avalanche

    No Roof in

    Crisis actionplan!

    NoRoof in Crisis

    training! NoAssessment

    Training

    Roof

    Overloaded

    WithSnow, Ice

    &Water

    Pressure Increase

    To520 Pa.

    No awareness or

    assessment of roofconditions!

    Failure to follow

    Pre-snow, Snow meltpolicy

    Lack of new proceduretraining re pre-snow

    procedure.

    Lack ofEffective policy,procedure and

    training

    CultureUnwritten NO-HEAT Policy

    Failure toincrease

    pressure andeffecively apply

    heat.

    No

    PhysicalRoofMonitoring

    NoPhysical

    RoofMonitoring

    No

    ApplicationOf snow-melt

    Start Here

    To follow the

    Causal Event Path

    Lack of

    SnowAbatement

    CausalAnalysisChart

    ThefollowingCausalcharttakesthedirectandindirectcausesandidentifiesour

    analysisforeachandthentherecommendedcorrectiveaction.

    Definitions:

    CausalFactor: Aconditionoraneventthatresultsinaneffect.

    DirectCause:Thecausethatdirectlyresultedintheoccurrence.

    ContributingCause: Acausethatcontributedtoanoccurrencebutbyitselfwouldnot

    havecausedtheOccurrence.

    RootCause: Thecausethat,ifcorrected,wouldpreventrecurrenceofthisandsimilar

    occurrences.(Doesnotusuallyapplytothisoccurrenceonly,butisgenericinnatureas

    itappliestoabroadgroupofpossibleoccurrences).Quiteoftensystemic.

  • 8/8/2019 Joint Health and Safety Committee Report on B.C. Place Stadium roof

    46/82

    InvestigationReport:BCPlaceRoofDeflationIncidentofJanuary5,200744

    DirectCause#1 Causeanalysis RecommendedCorrectiveAction

    WestTriangle

    PanelFailure.

    Avalanche(caused

    severetrauma)

    (Unprovenbutlikely)

    Possiblepreexisting

    wear/damage(most

    exposedandlikelythe

    moststressedpanelon

    entireroof)

    Havetherooftechnician

    conductassessmentofthe

    areaimmediatelyadjacent

    totheringbeam,theentire

    perimeterandunderthe

    skirt.Ensurerepairsare

    conductedtocorrectany

    damagefound.

    Haveanapprovedagency

    conducttestsonthe

    remainingtrianglepanelsin

    thebuildingthenmakeany

    necessaryrepairsor

    replacement.

    Trainacrewinemergency

    repairandmaintainarepair

    planandrepairkitinthe

    buildingattheroof.

    Conductadetailed

    assessmentoftheroofthen

    developareplacement

    program.

    DirectCause#1 Causeanalysis RecommendedCorrectiveAction

    Avalanche

    Overloadedroof,severe

    snow,ice&water

    accumulation

    Toomuchpressuretoo

    fastandthesubsequent

    automatedquick

    pressuredropbackto

    normalsettings.

    FailureofEnergrated

    controlsystemto

    preventconflictwith

    pneumaticcontrolled

    reliefsystem.

    Failuretoconduct

    assessmentofroofin

    crisis.

    Lackofsnow

    abatement.

    Noroofincrisisaction

    plan

    Noroofincrisistraining

    Updatepressurecontrol

    systems

    to

    prevent

    CSV

    vs.

    ASDoverruns.

    Trainstaffandsupervisors

    inroofincrisisassessment

    andsafereco