jorge l. quijano - fidic 2014 - plenary 8... · fidic international infrastructure conference....
TRANSCRIPT
Jorge L. QuijanoAdministrator/CEOPanama Canal AuthoritySeptember 30, 2014
Jorge L. QuijanoAdministrator/CEO
Panama Canal AuthoritySeptember 30, 2014
Large infrastructure projects: The Panama Canal experience
FIDIC InternationalInfrastructure Conference
Large infrastructure projects: The Panama Canal experience
Transits and TonnageAF1915 - AF2005
14,011
279.1
0
5,000
10,000
15,000
20,000
25,000
30,000
35,000
40,000
45,000
50,0001
91
6
19
18
19
20
19
22
19
24
19
26
19
28
19
30
19
32
19
34
19
36
19
38
19
40
19
42
19
44
19
46
19
48
19
50
19
52
19
54
19
56
19
58
19
60
19
62
19
64
19
66
19
68
19
70
19
72
19
74
19
76
19
78
19
80
19
82
19
84
19
86
19
88
19
90
19
92
19
94
19
96
19
98
20
00
20
02
20
04
0
50
100
150
200
250
300
Año Fiscal
20
05
Trn
sits
To
ns i
n m
illi
on
s
21%
231
170.1
64%4,832 9,931 18,940 22,064
FY 1955 FY 1975 FY 1995 FY 2005
The ExpansionProgram waspreceded by more than five years of studies
More than a 100 studies
International Contractors led the effort.
International and Local experts
Met rigorous international Standards
The Panama Canal experience regarding implementation ofLarge Infrastructure Projects
The Panama Canal experience regarding implementation ofLarge Infrastructure Projects
People, processes and tools… in that order
The Panama Canal experience regarding implementation ofLarge Infrastructure Projects
Promotion / Project marketing. Early Access to sites.
People, processes and tools… in that order
Marketing of the Panama Canal Expansion ProgramExpocomer Infoconference - March 2007
Participants: 806Companies: 324Countries: 29Continents: Americas, Asia and Europe
Post Panamax LocksPacific
Deepening and widening of the
Atlantic Entrance
17.66 M m3
Deepening and Widening of
Pacific Entrance
8.7 M m3
Increase the maximum operating level of Gatun Lake
26.7 m 27.1 m
Deepening and widening of the Gatun Lake Channels and Deepening of the Culebra Cut
Pacific Access Channel to the new Locks 49 M m3
New Pacific
Locks
►
Access
Channel ►
PresentLocks▼
Post Panamax Locks - Atlantic
PresentLocks▼
Expansion Program Subprojects
Early Access to Project Sites
Work PackageProject delivery
method
Number of
contractsDesigner Contract type
Dredging of Pacific entrance Design-Bid-Build 1 ACPNegotiated lowest bid
Dredging of Atlantic entrance Design-Bid-Build 1 ACPNegotiated lowest bid
Dredging of Culebra Cut Performed by ACP N/A ACP ACP
Dredging of Gatun Lake Performed by ACP N/A ACP ACP
Dry excavation of the navigational channel
Design-Bid-Build 4 ACP / URS Lowest bid
Increase the maximum operating level of Gatun Lake
Design-Bid-Build Various minorACP /
contractorsLowest bid
Construction of the Atlantic and Pacific post-Panamax locks
Design-Build 1 ContractorBest value non negotiated with pre-qualification
Contracting transparency of utmost importance to lure top international contractors
Selection of Project delivery method and contract type
Choice of FIDIC Contract for Locks Design and Build Project
Determine precise project scope and exerciseextreme discipline to adhere to it during contractexecution.
Total transparency in managing the bid process, evaluation and award of the Contract.
People, processes and tools… in that order
Promotion / Project marketing. Early Access to sites.
The Panama Canal experience regarding implementation ofLarge Infrastructure Projects
PAC-4
Dredging Atlantic
Entrance
Design & Construction of
the Locks
PAC-3
DredgingPacific Entance
PAC-2
PAC-1
DredgingGatun Lake
North Reaches
PAC-0
Bid Price of theMain Expansion Contracts
Integration of the roles of the Owner’s Project Manager and Contracting Officer.
Early participation of the Project and Contract/ClaimsManagement Team (owner and contractor)
People, processes and tools… in that order
Promotion / Project marketing. Early Access to sites.
Determine precise project scope and exercise extreme discipline to adhere to it during contract execution.
Total transparency in managing the bid process, evaluation and award of the Contract.
The Panama Canal experience regarding implementation ofLarge Infrastructure Projects
Locks Design and ConstructionTimeline of the Contracting Plan
New Datefor Last Individual Meeting with the Consortia 16-JAN-09
AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DIC JAN FEB MAR APR MAY JUN JUL AUG SEP
2007 2008 2009
Request For Qualifications Issued27-AUG-07
Draft Issue of the Terms of Reference21-DEC-07
Receipt of Qualifications15-NOV-07
Short List Selection14-DEC-07
Individual Meetings with the Consortia29-JAN-08
Homologation of the Terms of Reference26-MAR-08
Final Terms of Reference Issued18-APR-08
Designation of the Technical Evaluation Board
14 months
Preview Conference13-SEP-07
Receipt of Proposals3-MAR-09
Contract Award15 -JUL-09
Proposals evaluation advisorsidentified9-FEB-09
Prequalification
Performance & Payment Bonds received11-AUG-09
• Allow enough time for contractors to fully assess project and risks.• As many prebid meetings as necessary (joint and individual).• Should result in more competitive bids and less claims.
Consortia consisting of numerous members presentconsiderable challenges for projects. One must be a major shareholder.
The Panama Canal experience regarding implementation ofLarge Infrastructure Projects
Consortium Members Designers Gate fabricators
C.A.N.A.L.
ACS Servicios, Comunicaciones y Energía, S.L. – Leader Sener Ingeniería y Sistemas
ACS Servicios, Comunicaciones y Energía, S.L.
Acciona Infraestructuras, S.A. Haskoning Nederland BV
Fomento de Construcciones y Contratas, S.A. Mott Macdonald Limited
Hochtief Construction AG Hochtief Consult
Constructoras ICA S.A. de C.V.
Atlántico-Pacífico de
Panamá
Bouygues Travaux Publics – Leader
AECOM – LeaderALSTOM Hydro Energia Brasil
Bilfinger Berger
VINCI Construction Grands Projets
Construcoes e Comercio Camargo Correa S.A.
Construtora Andrade Gutierrez S.A.
Construtora Queiroz Galvao S.A.
ALSTOM Hydro Energia Brasil
BARDELLA Ind. Mecánicas
Bechtel, Taisei,
Mitsubishi
Corporation
Bechtel Internacional, Inc. – Leader
Bechtel Internacional, Inc. –Leader
Wuchang Shipyard Taisei Corporation
Mitsubishi Corporation
Grupo Unidos por el
Canal
Sacyr Vallehermoso S.A. – Leader Montgomery Watson Harza (MWH) –Leader
Heerema Fabrication GroupImpregilo S.p.A.
Jan de Nul n.v. IV-Groep
Constructora Urbana, S.A. Tetra Tech
Prequalified Consortia
Consortium Members Designers Gate fabricators
C.A.N.A.L.
ACS Servicios, Comunicaciones y Energía, S.L. – Leader Sener Ingeniería y Sistemas
ACS Servicios, Comunicaciones y Energía, S.L.
Acciona Infraestructuras, S.A. Haskoning Nederland BV
Fomento de Construcciones y Contratas, S.A. Mott Macdonald Limited
Hochtief Construction AG Hochtief Consult
Constructoras ICA S.A. de C.V.
Bechtel, Taisei,
Mitsubishi
Corporation
Bechtel Internacional, Inc. – Leader
Bechtel Internacional, Inc. –Leader
Wuchang Shipyard Taisei Corporation
Mitsubishi Corporation
Grupo Unidos por el
Canal
Sacyr Vallehermoso S.A. – Leader Montgomery Watson Harza (MWH) –Leader
Heerema Fabrication GroupImpregilo S.p.A.
Jan de Nul n.v. IV-Groep
Constructora Urbana, S.A. Tetra Tech
Consortia that submitted proposals on March 3, 2009
Atlántico-Pacífico de Panamá
Bouygues Travaux Publics – Leader
AECOM – LeaderALSTOM Hydro Energia Brasil
Bilfinger Berger
VINCI Construction Grands Projets
Construcoes e Comercio Camargo Correa S.A.
Construtora Andrade Gutierrez S.A.
Construtora Queiroz Galvao S.A.
ALSTOM Hydro Energia Brasil
BARDELLA Ind. Mecánicas
Bechtel-Mitsubishi-Taisei CANAL GUPC
Consortia consisting of numerous members presentconsiderable challenges for projects. One must be a major shareholder.
The Panama Canal experience regarding implementation ofLarge Infrastructure Projects
Integration of members in the Contractor’sManagement Team - aware of the diversity of corporate cultures, languages, nationalities, safety culture, etc.
In Design – Build Projects the Designer firm should be part of the consortium even though its liability may be limited. It must not be a mere subcontractor.
Main Contractor must secure firm subcontractor pricingprior to bidding for Project.
Contractors firms must prepare accurate estimates to submit adequate bids and avoid the temptation to underbid under the assumptions that change orders or variations of the contract will occur to offset underbidding.
Contractors should use stipend and time to perform required field investigations to reduce risk profile.
Contractors must not underestimate need for timely submittal of documentation, specially in government projects. Some paper work is strictly necessary prior to commence work.
Expect that owners will enforce full compliance with safety, quality and environmental requirements.
The Panama Canal experience regarding implementation ofLarge Infrastructure Projects
Program Execution 2007 – 2015Environmental and Social Monitoring and Control
Environmental Impact Assessment
Ecological Compensation paid to ANAM
Wildlife Rescue Plan
Archeological Rescue
Paleontological Resources Studies
Reforestation
Air and Water Quality Monitoring
Noise and vibrations monitoring
Meetings with communities according to project
advance
Report and inspection by independent consultant
Inspections by ANAM
Public Reporting on the Progress of the Expansion Program
20
06
20
07
20
08
20
09
Thirty-one Quarterly Reports
Twenty Reports to the Nation
20
10
20
11
20
12
20
13
20
14
Contractor’s Claims Steps:
Dispute Settlement Process
1. Employer’s Representative Determination
2. Dispute Adjudication Board Determinationbased on law
3. Arbitration at the International Chamber of Commerce tribunal in Miami, Florida, USA under Panamanian Law
Step 1 - Contractor’s Claims :
• The Contractor has 28 days to notify the intent of submitting a claim since he was notified or shouldhave been notified of the event, and 42 days tosubmit the details and full supporting particulars.
• ACP has 42 days to respond with its approval ordisapproval of claim. If it agrees with the claim, a variation is issued, and if it rejects the claim, the Contractor may take it to the Dispute Adjudication Board (DAB).
Dispute Settlement Process
• The Locks Contract established that disputes between the parties shall be adjudicated by the Dispute Adjudication Board (DAB).
• The DAB is composed by three members.
• Disputes submitted by the Contractor to the DAB: 11
• Disputes settled to date: 10
• Peter Chapman, President• Robert Smith, nominated by ACP• Pierre Genton, nominated by GUPCSA
Composition of Dispute Adjudication Board (ADB)
Step 2 - DAB (Dispute Adjudication Board) :
• The Contractor does not have a fixed term to submit its dispute to the DAB. However, itcannot invoke arbitration without exhaustingadministrative remedies.
• The Parties have 28 days after they receive the DAB’s decision to give notice to the other Party of its dissatisfaction. If none of the Parties has given notice of its dissatisfaction, the decisionwill become final and arbitration cannot be invoked.
Dispute Settlement Process
Dispute Adjudication Board (DAB)
• The disputes arising from the Contract or the execution of the Works, including any dispute as to any determination, instruction, opinion orvaluation of the ACP’s Representative, shall be settled by the DAB, nota DRB.
• Any of the Parties may refer the dispute in writing to the DAB for itsdecision. No opinions, recommendations or advice.
Step 3 - International Arbitration:
• The arbitration shall be decided in law (within the meaningof Panamanian law) and shall be conducted in English, and settled by three arbitrators who shall all be lawyers. The Rules of Arbitration of the International Chamber of Commerce (ICC) will be applied. The venue of the arbitration shall be Miami, Florida – USA.
• The arbitration shall be conducted according to the International Bar Association Rules on the Taking of Evidence, and the arbitration agreement and arbitrationshall be governed by the United States Federal ArbitrationAct.
Dispute Resolution Process
Initial intentions of claims are not pursued in a timely manner
Information provided to support claims is normally insufficient to process in a timely and effective manner
Contractors appear to inflate claim costs and request excessive amounts of additional time to perform the work under the claim
Changes in field managers during the execution of theProject make the claim assessment more difficult
In Design - Build projects the designer’s performance may provoke claims against the owners
Other Dispute Resolution Issues
Panama Canal Expansion Update
200
1550 50 100 150 200 250
Current Expansion
Original
1886 1909
2008 2007
In million of cubic meters
78%
Volumes of excavation and dredging
3.4
4.4Current Panama Canal Expansion
Original Construction
In million cubic meters
Existing Locks
129%
New Locks
Volume of concrete for the construction of the Locks
1 2 3 4 5 60
Summary Schedule of Main Projectsas of September 2014
Activity by quarter (Q) % Progress
Lock
s Specifications and locks models 100%
Design and build post-Panamax locks 76.5%
Acc
ess
ch
ann
el Pacific access channel - phase 1 100%
Pacific access channel - phase 2 100%
Pacific access channel - phase 3 100%
Pacific access channel - phase 4 75.7%
Dre
dgi
ng
Dredging of the Pacific entrance 100%
Deepening and widening of Gatun Lake and deepening of Culebra Cut 86.8%
Dredging of the Atlantic entrance 100%
Increase operating level of Gatun Lake 92.5%
Expanded Canal begins operations
Expansion Program progress 80.3%
Bidding and contracting ExecutionSpecifications and design
Baseline* Baseline Baseline
Beginning of operationsContingency
against baseline
* Baseline from 31 December 2006 including contingency
2007 2008 2009 2010 2011 2012 2013 2014 2015 2016Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
The Panama Canal ExpansionFIDIC International Infrastructure Conference
Jorge L. QuijanoAdministrator/CEO
Panama Canal AuthoritySeptember 30, 2014