jpt1999 04 da series

Upload: saravanan-shanmugam

Post on 05-Apr-2018

217 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/2/2019 JPT1999 04 DA Series

    1/4

    D I S T I N G U I S H E D A U T H O R S E R I E S

    84 APRIL 1999

    APPLICATION OF TRANSIENT-MULTIPHASE-FLOW TECHNOLOGYDale D. Erickson, SPE, and Michael C. Mai, SPE, Multiphase Solutions Inc.

    INTRODUCTION

    The challenges associated with multiphase flow are as old as the oil

    business itself. The natural flow from most wells consists of some

    mixture of oil, gas, and water. Historically, separators were placedas close to the wellhead as possible to avoid problems associated

    with multiphase-flow behavior. However, as production has moved

    into more hostile environments and project and operating philoso-

    phies have changed, use of multiphase transport in oil and gas pro-duction operations has increased. For example, in the production

    scenario in Fig. 1, all production (gas, condensate, and water) from

    the subsea wells and the wellhead platforms is transported com-mingled to the central platform. At the central platform, liquid/gas

    separation is performed so that the gas can be compressed and theliquid pumped. The fluids (liquid and compressed gas) are thenremixed and transported as a multiphase mixture in a single

    pipeline to shore. Onshore, the fluids are separated to sales specifi-

    cation. In this scheme, methanol may be needed at the wellhead to

    prevent formation of hydrates. The methanol is removed from the

    water phase onshore and sent back offshore for reuse. If methanolis not required in the infield network, the water can be separated

    on the central platform and disposed of offshore.

    To make production scenarios like this one both feasible and reli-

    able, transient-multiphase-flow modeling is used in many differentways. This paper provides brief descriptions of these techniques

    that are based on our experience with more than 200 individual

    studies of multiphase pipelines and related facilities worldwide.

    These applications include conventional offshore, deepwater, arc-

    tic, and desert production and transportation systems.

    LINE SIZING

    Selecting the line size for a single-phase pipeline is relatively direct.

    The greatest anticipated flow rate should be established, the avail-

    able pressure driving force should be determined, and pressure-

    drop relationships should be used to select a line size large enoughto transport the required flow. Typically, economics may drive the

    line size to still greater values to accommodate future production

    or third-party fluids.

    The line-sizing problem in multiphase flow is more problematicbecause bigger is not necessarily better. Fig. 2, which shows theenvelope of operability, explains this concept. The envelope has

    three main curves. The snake-like curve shows how production is

    expected to change with water cut (as the field matures and addi-

    tional wells are brought on line). These production numbers reflect

    total liquid flow rates. The upper curve establishes the throughput

    limit of the pipeline on the basis of pressure-drop constraints, as

    governed by expected flowing wellhead pressures. The region below

    the lower curve establishes the production and water-cut combina-tions where terrain slugging occurs. The region between the curves

    is the envelope of operability. In this case, production over most of

    the field life is inside the envelope. Increasing the line size moves the

    envelope up, and decreasing the line size moves it down. In this way,

    operational impacts of different line sizes can be assessed.The key to making the envelope of operability a reliable design

    tool is to use an accurate dynamic model to calculate the bound-

    aries. In preliminary engineering, a design engineer often usessteady-state simulators (or other correlations based on low-pres-

    sure, small-diameter, air/water laboratory data). These relation-ships should be used with caution. In one case that we encountered

    while working on a subsea pipeline, transient-model predictions

    for the pipeline pressure drops were 30% greater than the steady-

    state-model predictions (with similar differences in predicted liq-uid holdups). On the basis of the transient-model results, the line

    size was reduced by 2 in. from the size initially recommended on

    the basis of steady-state-model results. Field data subsequently

    confirmed that the transient-model predictions were within 8% of

    the actual values. If the larger line size had been installed, thepipeline would have been in the terrain-slugging region under nor-

    mal flowing conditions, creating substantial operational problems.

    LINE PACK/UNPACK

    Gas is difficult to store in large quantities unless converted to liq-

    uefied products. Therefore, offshore gas production typically is reg-

    ulated to match onshore demand. Because of the storage (com-pressibility) and resistive properties (friction loss) of the pipeline, a

    time lag occurs between changes in the gas flow rate into the

    pipeline and corresponding changes in the gas flow rate out of the

    pipeline. To maintain deliveries during short offshore shutdowns,

    the pipeline may be operated in a packed condition. Packed inthis sense refers to the additional gas that can be stored in the

    pipeline by increasing operating pressures. These operating pres-

    sures are higher than the driving force required simply to transport

    the gas to shore given the minimum allowable arrival pressure.Moreover, an oversized line has been used in some cases to providethe line packing necessary to ensure uninterrupted onshore deliv-

    ery during temporary offshore shutdowns. In multiphase systems,

    this issue becomes more complicated because the liquid reduces

    the volume available for gas compression. Furthermore, increasesin flow rate can produce the intended gas volumes but may also

    yield problematic quantities of liquid.

    Beyond design considerations, commercial and operations peo-

    ple need to know the delivery capacity of the system throughout the

    day. On-line models have been developed to provide an accurateassessment of potential performance. For example, an operator

    knows that the compressor offshore will be down for 4 hours in the

    afternoon for planned maintenance activities. The on-line modeltakes the current state of the pipeline (continuously calculated from

    Copyright 1999 Society of Petroleum Engineers

    This is paper SPE 52757. Distinguished Author Series articles are general, descriptive repre-sentations that summarize the state of the art in an area of technology by describing recentdevelopments for readers who are not specialists in the topics discussed. Written by individu-als recognized as experts in the area, these articles provide key references to more definitivework and present specific details only to illustrate the technology. Purpose:to inform the gen-

    eral readership of recent advances in various areas of petroleum engineering. A softboundanthology, SPE Distinguished Author Series: Dec. 1981Dec. 1983, is available from SPEsCustomer Service Dept.

  • 8/2/2019 JPT1999 04 DA Series

    2/4

    APRIL 1999 85

    production data) and the current gas-nomination profile and fore-

    casts the size of the shortfall (or surplus) that may be expected in

    the contract period. In addition, if the operator wants to sell gas onthe spot market, the on-line model can forecast the volume of sur-

    plus gas currently available as line pack (and any ramp-up limita-tions governed by liquid holdup in the line). Similarly, if production

    is increased offshore, the amount of gas that can be made available

    at the sales point can be forecast as a function of time.

    SAFETY-SYSTEM ANALYSIS

    There are several applications for transient-multiphase-flow tech-

    nology in the area of safety-system analysis. These include high-

    integrity pressure-shutdown systems, pressure-relief systems, lineruptures, surge analysis, and leak detection. Again, the presence of

    two phases substantially affects the flow transients and the dynam-

    ics of pressure buildup or bleed-down. The following example

    illustrates a typical type of analysis.

    A live (volatile) -condensate pipeline was simulated to determineacceptable closure times for a shutdown valve, which protects a

    pipeline in case of line breaks. Simulations showed that, without a

    fast-closing shutdown valve in place, more than half the pipeline

    inventory would leave the pipeline. Gas is formed as the pressure inthe pipeline falls, thereby pushing additional liquid out of the

    pipeline. This type of failure is the worst case of all the fire scenar-

    ios because condensate density is much higher than gas density.

    Consequently, fast-closing valves were required. Multiphase-flow

    simulations then were used to determine whether the valve seatscould handle the surge stress imposed by the rapid valve closure.

    SLUG-CATCHER SIZING

    One problem with multiphase flow is that increasing the distance

    between the separator and the multiphase-flow source increases thelikelihood that liquid will arrive at a variable rate. For this reason,large separators, called slug catchers, are located at the end of

    multiphase flowlines. The required slug-catcher size depends on the

    liquid-handling or drawdown rate, frequency with which the

    pipeline is to be pigged, and range of swing in anticipated flow rates.

    In gas/condensate pipelines, the primary cause of slug-catcherflooding is ramp-up slugs. Ramp-up slugs are not true slugs but

    waves of liquid caused by the increase in gas flow rate (which

    sweeps liquid out of the pipeline). These ramp-up liquid slugs are

    a problem because of their potential to fill (flood) the slug catcher,

    causing a costly system shutdown. Ramp-up slugs are particularlyharmful because they occur when the flow rate is increasing and

    the gas is in high demand. The following procedure is used to sizea slug catcher for this type of service.

    First, steady-state simulations are run at a number of flow rates.

    Next, the flow rate is ramped up from these initial states and theliquid flow rate leaving the pipeline recorded. This information is

    sent to a slug-catcher model, which calculates the maximum

    required slug-catcher size for a range of assumed liquid-handlingrates. Fig. 3 shows this information for several cases. Once theslug-catcher/liquid-handling rate is selected, a curve can be gener-

    ated that shows how high the flow rate can be ramped up for a

    given initial steady-state flow rate. Because many systems achieve

    steady-state infrequently, on-line models have been developed2 to

    predict accurately how fast the flow rate can be increased given the

    current pipeline condition (on the basis of historical field data).

    The on-line model then controls the flow rate by controlling thechoke position of each well in the field.

    Sizing a slug catcher for a pipeline that is pigged regularly is rel-

    atively straightforward. First, a graph (Fig. 4) is generated with

    information from approximately 50 transient-multiphase-flow sim-

    ulations. Fig. 4 shows slug sizes for various pigging intervals asfunctions of flow rate. A cost/benefit analysis is then performed to

    balance pigging frequency with slug-catcher size. The transient

    pigging analyses used in design work usually are based on steady-

    state starting conditions (liquid holdups). On-line models can be

    used in field operations to predict pigging requirements accuratelyon the basis of a current assessment of the state of the pipeline

    (which may be far from steady state).

    In oil systems, terrain and hydrodynamic slugs dominate liquid

    arrival rates and are the design basis for slug-catcher sizing. Terrain

    Fig. 1Wet-gas gathering and transmission. Fig. 2Envelope of operability.

    Fig. 3Ramp-up slugging behavior in a 14-in. North Sea flow-line at 265 psia.

  • 8/2/2019 JPT1999 04 DA Series

    3/4

    86 APRIL 1999

    slugs typically can be controlled by means of gas lift, control valves

    at the top of the riser, or line-size selection. Fig. 2 shows that the

    envelope of operability expands when gas lift is used. Field obser-

    vations have shown that the multiphase-flow simulations of these

    strategies accurately predict this behavior. For example, slug-con-trol valves work best when they control pipeline backpressure and

    a large reset time constant is used to dampen the dynamics of thecontrol moves.

    For hydrodynamic slugging, a model capable of tracking indi-vidual slugs is used. The output from the slug-tracking model is fed

    into the slug-catcher model to determine whether the slug catcher

    floods. An additional twist with hydrodynamic slugs is that slug

    sizes are not uniform but follow a frequency distribution. Slug size

    also is affected by fluctuations in boundary conditions. Therefore,under these conditions, slug-catcher sizing requires some proba-

    bilistic information, such as typical variance in slug-catcher pres-

    sure and the design-slug basis. The design-slug basis is defined as

    the maximum slug size the system must handle (e.g., the 1 in 1,000

    slug or the 1 in 1,000,000 slug). Slug-catcher size is selected so that

    its cost is balanced with the cost of a slug-induced shutdown.

    CORROSION-INHIBITOR TRANSPORT

    Most operators prefer to use carbon-steel pipelines because of thelower material cost compared with pipes made of special alloys. In

    multiphase service, however, the danger of internal corrosion

    always exists. Corrosion inhibitors typically are added at levelsbetween 10 and 1,000 ppm. For a corrosion inhibitor to function

    properly, it must cover the entire surface of the pipeline at the cor-rect concentration. Multiphase-flow simulation aids the corrosion

    engineer by estimating the concentration of the inhibitor at various

    locations along the pipeline length.3 One problem is that corrosion

    inhibitor is carried in the bulk phase. At some locations, conden-

    sation occurs that dilutes the inhibitor concentration. Under cer-tain flow conditions, liquid flow is stagnant in some locations and

    solids (sand) can deposit. The corrosion potential is higher in these

    locations. Multiphase modeling can determine whether the solids

    can be re-entrained or whether the pipeline should be pigged to

    facilitate solids removal.

    HYDRATE/PARAFFIN CONTROL

    At low temperatures, hydrate and paraffin formation is possible.

    Both of these solids have the potential to plug a flowline. Typically,

    any subsea well or flowline at shut-in conditions may be in the

    hydrate-formation region.4

    Pipelines often are buried and/or insulated to lower heat lossesand keep temperatures elevated. However, this does not cure start-

    up and shutdown problems. To study these problems, a transient,

    soil-heat-conduction model was developed.5 For a subsea pipeline,

    the model showed that the pipeline cools down to hydrate-forma-

    tion temperature in approximately 24 hours (previous simplifiedmodels predicted cooldown times of 4 hours). To prevent hydrate

    formation after this period, the pipeline is depressurized; however,if the depressurization is too rapid, the temperature drops because

    of Joule-Thompson cooling. Therefore, the depressurization

    process is modeled to examine minimum fluid and well tempera-tures along the length of the pipeline.

    Long lag times also are seen for warmups. It may take days or

    weeks to raise temperatures to steady-state values in buried

    pipelines. The problem from a hydrate perspective is that the pres-

    sure builds up in a matter of minutes. High pressures and low tem-peratures increase hydrate-formation potential. In some cases,

    operating procedures can be developed to keep the fluids out of

    the hydrate region. In other cases, methanol injection is required

    during startup.

    Heated bundles also may be used to provide protection.6 Bundlesoften are considered when it is impossible to maintain the steadytemperatureabove the hydrate- or wax- formation temperature and

    chemical inhibitors are not cost-effective. Bundles are simply large

    heat exchangers. However, they are much more difficult to design

    than standard heat exchangers because of the significant external

    heat losses. If the flow rate for the heating medium is chosen incor-rectly and the flow is countercurrent, the temperature in the bun-

    dle reaches a minimum. This minimum can be close to the ambi-

    ent temperature even when temperatures at the inlet and outlet of

    the pipeline remain high. With an incorrect design, hydrates can

    then form at the middle of the pipeline, the least desirable locationbecause of the difficulty in removing the plug. To improve perfor-

    mance, the return line may be insulated; however, performancedrops if too much insulation is used.

    Fig. 4Pigging intervals with line pack.

  • 8/2/2019 JPT1999 04 DA Series

    4/4

    PIPELINE STRESS

    In multiphase flowlines, the volume andmass rate of liquid in a given pipeline sec-

    tion changes with time. As a result, the

    dynamic load on the pipeline changes. If a

    multiphase pipeline is not anchored down,it can move. Normally, the structural engi-

    neer designs the riser and piping supports

    using the sum of the individual phase den-

    sities multiplied by the effective phase

    velocities. In the past, when informationwas not available, loads would be calculat-

    ed with the liquid density multiplied by the

    maximum gas velocity. For most pipelines

    (especially gas/condensate pipelines), this

    practice yielded predicted stresses that weretwo to five times too high. Consequently,

    more piping support was added than was

    required. Conversely, if phase densities and

    velocities are used and slugging events arenot accounted for accurately, insufficient

    support and excessive vibration, or even

    failure, can occur.

    SYSTEM MONITORING AND

    OPTIMIZATION

    Multiphase flow technology is now beingapplied to system monitoring and opti-

    mization.2,7 On-line modeling provides

    information about pressures, temperatures,

    densities, liquid holdup (volume fraction),

    and mass rates throughout the pipeline.With these data, continuous forecasting

    provides the operator with information

    about allowable ramp-up rates (slugging

    dangers), pigging requirements, gas-com-

    position tracking, and paraffin-/hydrate-formation potential. Moreover, control

    algorithms can be used to regulate individ-

    ual well flows, riser control volumes, and

    compressor speed. Properly designed con-trol algorithms can prevent well sandout or

    liquid loadup, excessive erosion in valves

    and manifold piping, and problematic liq-

    uid slugging in gathering flowlines and

    pipelines. These same techniques can beused to optimize blending and gas-com-

    pression requirements and to evaluate gas

    deliverability on the day while considering

    system performance and planned or

    unplanned shutdowns.

    CONCLUSIONS

    During the last 10 years, explosive growth

    has occurred in the application of multi-

    phase-flow technology for design, operation,

    and optimization of offshoreproduction sys-tems. Increasing utilization of the technolo-

    gy has allowed operators to save capital costs

    and reduce life-cycle operating and overhead

    costs. Moreover, recent use of this technolo-

    gy in on-line monitoring and control sys-tems is allowing operators to push existing

    systems further, thereby achieving addition-al profits and/or cost savings.

    REFERENCES

    1. Erickson, D. and Danielson, T.: A

    Comparison of ConOlga with Field Data from

    a Gas Condensate Pipeline, Proc., Eighth Intl.

    Conference Multiphase Flow, Cannes, France

    (1997) 19.

    2. Erickson, D. and Twaite, D.: A Pipeline

    Integrity Monitoring System for Leak

    Detection, Control, and Optimization for Wet-

    Gas Pipelines, paper SPE 36607 presented at

    the 1996 SPE Annual Technical Conference

    and Exhibition, Denver, Colorado, 69

    October.

    3. Erickson, D., Buck, E., and Kolts, J.:

    Corrosion Inhibitor Transport in Wet-Gas

    Pipelines, J. Materials Performance

    (September 1993) 32, 49.

    4. Erickson, D. and Brown, T.: Occurrence of

    Hydrates in Multiphase Flowlines, Proc.,

    New York Academy of Sciences Intl.

    Conference on Natural Gas Hydrates, New

    York City (April 1994) 715, 40.

    5. Erickson, D. and Mai, M.: A Transient

    Multiphase Temperature-Prediction Program,

    paper SPE 24790 presented at the 1992 SPE

    Annual Technical Conference and Exhibition,

    Washington, DC, 47 October.

    6. Brown, T. et al.: Application of a Transient-

    Heat-Transfer Model for Bundled Multiphase

    Pipelines, paper SPE 36610 presented at the

    1996 SPE Annual Technical Conference and

    Exhibition, Denver, Colorado, 69 October.

    7. Lamey, M.F. and Wasden, F.: Dynamic

    Simulation Model Aids Mensa Development,

    Oil & Gas J. (10 August 1998) 96, 72.

    SI METRICCONVERSION FACTORS

    bbl1.589 873 E01=m3

    ft32.831 685 E02=m3

    Dale D. Erickson is a principal consul-

    tant with Multiphase Solutions Inc. in

    Houston, where he has developed real-

    time, transient-multiphase flow simula-

    tors and control/optimization software

    for multiphase pipelines. He has con-

    ducted technical studies on transient

    multiphase flow worldwide. Erickson

    holds BS and MS degrees from theColorado School of Mines and a PhD

    degree from Rice U., all in chemical

    engineering. Michael C. Maiis a princi-

    pal consultant with Multiphase Solutions

    Inc. in Houston where he has developed

    on-line, forecasting, and optimization

    software for pipelines and related

    process equipment. He has conducted

    technical studies worldwide on transient

    multiphase flow in oil and gas systems.

    Mai holds a BS degree from the U. of

    Notre Dame and MS and PhD degrees

    from the U. of Texas at Austin, all inchemical engineering.

    APRIL 1999 87