jpt1999 04 da series
TRANSCRIPT
-
8/2/2019 JPT1999 04 DA Series
1/4
D I S T I N G U I S H E D A U T H O R S E R I E S
84 APRIL 1999
APPLICATION OF TRANSIENT-MULTIPHASE-FLOW TECHNOLOGYDale D. Erickson, SPE, and Michael C. Mai, SPE, Multiphase Solutions Inc.
INTRODUCTION
The challenges associated with multiphase flow are as old as the oil
business itself. The natural flow from most wells consists of some
mixture of oil, gas, and water. Historically, separators were placedas close to the wellhead as possible to avoid problems associated
with multiphase-flow behavior. However, as production has moved
into more hostile environments and project and operating philoso-
phies have changed, use of multiphase transport in oil and gas pro-duction operations has increased. For example, in the production
scenario in Fig. 1, all production (gas, condensate, and water) from
the subsea wells and the wellhead platforms is transported com-mingled to the central platform. At the central platform, liquid/gas
separation is performed so that the gas can be compressed and theliquid pumped. The fluids (liquid and compressed gas) are thenremixed and transported as a multiphase mixture in a single
pipeline to shore. Onshore, the fluids are separated to sales specifi-
cation. In this scheme, methanol may be needed at the wellhead to
prevent formation of hydrates. The methanol is removed from the
water phase onshore and sent back offshore for reuse. If methanolis not required in the infield network, the water can be separated
on the central platform and disposed of offshore.
To make production scenarios like this one both feasible and reli-
able, transient-multiphase-flow modeling is used in many differentways. This paper provides brief descriptions of these techniques
that are based on our experience with more than 200 individual
studies of multiphase pipelines and related facilities worldwide.
These applications include conventional offshore, deepwater, arc-
tic, and desert production and transportation systems.
LINE SIZING
Selecting the line size for a single-phase pipeline is relatively direct.
The greatest anticipated flow rate should be established, the avail-
able pressure driving force should be determined, and pressure-
drop relationships should be used to select a line size large enoughto transport the required flow. Typically, economics may drive the
line size to still greater values to accommodate future production
or third-party fluids.
The line-sizing problem in multiphase flow is more problematicbecause bigger is not necessarily better. Fig. 2, which shows theenvelope of operability, explains this concept. The envelope has
three main curves. The snake-like curve shows how production is
expected to change with water cut (as the field matures and addi-
tional wells are brought on line). These production numbers reflect
total liquid flow rates. The upper curve establishes the throughput
limit of the pipeline on the basis of pressure-drop constraints, as
governed by expected flowing wellhead pressures. The region below
the lower curve establishes the production and water-cut combina-tions where terrain slugging occurs. The region between the curves
is the envelope of operability. In this case, production over most of
the field life is inside the envelope. Increasing the line size moves the
envelope up, and decreasing the line size moves it down. In this way,
operational impacts of different line sizes can be assessed.The key to making the envelope of operability a reliable design
tool is to use an accurate dynamic model to calculate the bound-
aries. In preliminary engineering, a design engineer often usessteady-state simulators (or other correlations based on low-pres-
sure, small-diameter, air/water laboratory data). These relation-ships should be used with caution. In one case that we encountered
while working on a subsea pipeline, transient-model predictions
for the pipeline pressure drops were 30% greater than the steady-
state-model predictions (with similar differences in predicted liq-uid holdups). On the basis of the transient-model results, the line
size was reduced by 2 in. from the size initially recommended on
the basis of steady-state-model results. Field data subsequently
confirmed that the transient-model predictions were within 8% of
the actual values. If the larger line size had been installed, thepipeline would have been in the terrain-slugging region under nor-
mal flowing conditions, creating substantial operational problems.
LINE PACK/UNPACK
Gas is difficult to store in large quantities unless converted to liq-
uefied products. Therefore, offshore gas production typically is reg-
ulated to match onshore demand. Because of the storage (com-pressibility) and resistive properties (friction loss) of the pipeline, a
time lag occurs between changes in the gas flow rate into the
pipeline and corresponding changes in the gas flow rate out of the
pipeline. To maintain deliveries during short offshore shutdowns,
the pipeline may be operated in a packed condition. Packed inthis sense refers to the additional gas that can be stored in the
pipeline by increasing operating pressures. These operating pres-
sures are higher than the driving force required simply to transport
the gas to shore given the minimum allowable arrival pressure.Moreover, an oversized line has been used in some cases to providethe line packing necessary to ensure uninterrupted onshore deliv-
ery during temporary offshore shutdowns. In multiphase systems,
this issue becomes more complicated because the liquid reduces
the volume available for gas compression. Furthermore, increasesin flow rate can produce the intended gas volumes but may also
yield problematic quantities of liquid.
Beyond design considerations, commercial and operations peo-
ple need to know the delivery capacity of the system throughout the
day. On-line models have been developed to provide an accurateassessment of potential performance. For example, an operator
knows that the compressor offshore will be down for 4 hours in the
afternoon for planned maintenance activities. The on-line modeltakes the current state of the pipeline (continuously calculated from
Copyright 1999 Society of Petroleum Engineers
This is paper SPE 52757. Distinguished Author Series articles are general, descriptive repre-sentations that summarize the state of the art in an area of technology by describing recentdevelopments for readers who are not specialists in the topics discussed. Written by individu-als recognized as experts in the area, these articles provide key references to more definitivework and present specific details only to illustrate the technology. Purpose:to inform the gen-
eral readership of recent advances in various areas of petroleum engineering. A softboundanthology, SPE Distinguished Author Series: Dec. 1981Dec. 1983, is available from SPEsCustomer Service Dept.
-
8/2/2019 JPT1999 04 DA Series
2/4
APRIL 1999 85
production data) and the current gas-nomination profile and fore-
casts the size of the shortfall (or surplus) that may be expected in
the contract period. In addition, if the operator wants to sell gas onthe spot market, the on-line model can forecast the volume of sur-
plus gas currently available as line pack (and any ramp-up limita-tions governed by liquid holdup in the line). Similarly, if production
is increased offshore, the amount of gas that can be made available
at the sales point can be forecast as a function of time.
SAFETY-SYSTEM ANALYSIS
There are several applications for transient-multiphase-flow tech-
nology in the area of safety-system analysis. These include high-
integrity pressure-shutdown systems, pressure-relief systems, lineruptures, surge analysis, and leak detection. Again, the presence of
two phases substantially affects the flow transients and the dynam-
ics of pressure buildup or bleed-down. The following example
illustrates a typical type of analysis.
A live (volatile) -condensate pipeline was simulated to determineacceptable closure times for a shutdown valve, which protects a
pipeline in case of line breaks. Simulations showed that, without a
fast-closing shutdown valve in place, more than half the pipeline
inventory would leave the pipeline. Gas is formed as the pressure inthe pipeline falls, thereby pushing additional liquid out of the
pipeline. This type of failure is the worst case of all the fire scenar-
ios because condensate density is much higher than gas density.
Consequently, fast-closing valves were required. Multiphase-flow
simulations then were used to determine whether the valve seatscould handle the surge stress imposed by the rapid valve closure.
SLUG-CATCHER SIZING
One problem with multiphase flow is that increasing the distance
between the separator and the multiphase-flow source increases thelikelihood that liquid will arrive at a variable rate. For this reason,large separators, called slug catchers, are located at the end of
multiphase flowlines. The required slug-catcher size depends on the
liquid-handling or drawdown rate, frequency with which the
pipeline is to be pigged, and range of swing in anticipated flow rates.
In gas/condensate pipelines, the primary cause of slug-catcherflooding is ramp-up slugs. Ramp-up slugs are not true slugs but
waves of liquid caused by the increase in gas flow rate (which
sweeps liquid out of the pipeline). These ramp-up liquid slugs are
a problem because of their potential to fill (flood) the slug catcher,
causing a costly system shutdown. Ramp-up slugs are particularlyharmful because they occur when the flow rate is increasing and
the gas is in high demand. The following procedure is used to sizea slug catcher for this type of service.
First, steady-state simulations are run at a number of flow rates.
Next, the flow rate is ramped up from these initial states and theliquid flow rate leaving the pipeline recorded. This information is
sent to a slug-catcher model, which calculates the maximum
required slug-catcher size for a range of assumed liquid-handlingrates. Fig. 3 shows this information for several cases. Once theslug-catcher/liquid-handling rate is selected, a curve can be gener-
ated that shows how high the flow rate can be ramped up for a
given initial steady-state flow rate. Because many systems achieve
steady-state infrequently, on-line models have been developed2 to
predict accurately how fast the flow rate can be increased given the
current pipeline condition (on the basis of historical field data).
The on-line model then controls the flow rate by controlling thechoke position of each well in the field.
Sizing a slug catcher for a pipeline that is pigged regularly is rel-
atively straightforward. First, a graph (Fig. 4) is generated with
information from approximately 50 transient-multiphase-flow sim-
ulations. Fig. 4 shows slug sizes for various pigging intervals asfunctions of flow rate. A cost/benefit analysis is then performed to
balance pigging frequency with slug-catcher size. The transient
pigging analyses used in design work usually are based on steady-
state starting conditions (liquid holdups). On-line models can be
used in field operations to predict pigging requirements accuratelyon the basis of a current assessment of the state of the pipeline
(which may be far from steady state).
In oil systems, terrain and hydrodynamic slugs dominate liquid
arrival rates and are the design basis for slug-catcher sizing. Terrain
Fig. 1Wet-gas gathering and transmission. Fig. 2Envelope of operability.
Fig. 3Ramp-up slugging behavior in a 14-in. North Sea flow-line at 265 psia.
-
8/2/2019 JPT1999 04 DA Series
3/4
86 APRIL 1999
slugs typically can be controlled by means of gas lift, control valves
at the top of the riser, or line-size selection. Fig. 2 shows that the
envelope of operability expands when gas lift is used. Field obser-
vations have shown that the multiphase-flow simulations of these
strategies accurately predict this behavior. For example, slug-con-trol valves work best when they control pipeline backpressure and
a large reset time constant is used to dampen the dynamics of thecontrol moves.
For hydrodynamic slugging, a model capable of tracking indi-vidual slugs is used. The output from the slug-tracking model is fed
into the slug-catcher model to determine whether the slug catcher
floods. An additional twist with hydrodynamic slugs is that slug
sizes are not uniform but follow a frequency distribution. Slug size
also is affected by fluctuations in boundary conditions. Therefore,under these conditions, slug-catcher sizing requires some proba-
bilistic information, such as typical variance in slug-catcher pres-
sure and the design-slug basis. The design-slug basis is defined as
the maximum slug size the system must handle (e.g., the 1 in 1,000
slug or the 1 in 1,000,000 slug). Slug-catcher size is selected so that
its cost is balanced with the cost of a slug-induced shutdown.
CORROSION-INHIBITOR TRANSPORT
Most operators prefer to use carbon-steel pipelines because of thelower material cost compared with pipes made of special alloys. In
multiphase service, however, the danger of internal corrosion
always exists. Corrosion inhibitors typically are added at levelsbetween 10 and 1,000 ppm. For a corrosion inhibitor to function
properly, it must cover the entire surface of the pipeline at the cor-rect concentration. Multiphase-flow simulation aids the corrosion
engineer by estimating the concentration of the inhibitor at various
locations along the pipeline length.3 One problem is that corrosion
inhibitor is carried in the bulk phase. At some locations, conden-
sation occurs that dilutes the inhibitor concentration. Under cer-tain flow conditions, liquid flow is stagnant in some locations and
solids (sand) can deposit. The corrosion potential is higher in these
locations. Multiphase modeling can determine whether the solids
can be re-entrained or whether the pipeline should be pigged to
facilitate solids removal.
HYDRATE/PARAFFIN CONTROL
At low temperatures, hydrate and paraffin formation is possible.
Both of these solids have the potential to plug a flowline. Typically,
any subsea well or flowline at shut-in conditions may be in the
hydrate-formation region.4
Pipelines often are buried and/or insulated to lower heat lossesand keep temperatures elevated. However, this does not cure start-
up and shutdown problems. To study these problems, a transient,
soil-heat-conduction model was developed.5 For a subsea pipeline,
the model showed that the pipeline cools down to hydrate-forma-
tion temperature in approximately 24 hours (previous simplifiedmodels predicted cooldown times of 4 hours). To prevent hydrate
formation after this period, the pipeline is depressurized; however,if the depressurization is too rapid, the temperature drops because
of Joule-Thompson cooling. Therefore, the depressurization
process is modeled to examine minimum fluid and well tempera-tures along the length of the pipeline.
Long lag times also are seen for warmups. It may take days or
weeks to raise temperatures to steady-state values in buried
pipelines. The problem from a hydrate perspective is that the pres-
sure builds up in a matter of minutes. High pressures and low tem-peratures increase hydrate-formation potential. In some cases,
operating procedures can be developed to keep the fluids out of
the hydrate region. In other cases, methanol injection is required
during startup.
Heated bundles also may be used to provide protection.6 Bundlesoften are considered when it is impossible to maintain the steadytemperatureabove the hydrate- or wax- formation temperature and
chemical inhibitors are not cost-effective. Bundles are simply large
heat exchangers. However, they are much more difficult to design
than standard heat exchangers because of the significant external
heat losses. If the flow rate for the heating medium is chosen incor-rectly and the flow is countercurrent, the temperature in the bun-
dle reaches a minimum. This minimum can be close to the ambi-
ent temperature even when temperatures at the inlet and outlet of
the pipeline remain high. With an incorrect design, hydrates can
then form at the middle of the pipeline, the least desirable locationbecause of the difficulty in removing the plug. To improve perfor-
mance, the return line may be insulated; however, performancedrops if too much insulation is used.
Fig. 4Pigging intervals with line pack.
-
8/2/2019 JPT1999 04 DA Series
4/4
PIPELINE STRESS
In multiphase flowlines, the volume andmass rate of liquid in a given pipeline sec-
tion changes with time. As a result, the
dynamic load on the pipeline changes. If a
multiphase pipeline is not anchored down,it can move. Normally, the structural engi-
neer designs the riser and piping supports
using the sum of the individual phase den-
sities multiplied by the effective phase
velocities. In the past, when informationwas not available, loads would be calculat-
ed with the liquid density multiplied by the
maximum gas velocity. For most pipelines
(especially gas/condensate pipelines), this
practice yielded predicted stresses that weretwo to five times too high. Consequently,
more piping support was added than was
required. Conversely, if phase densities and
velocities are used and slugging events arenot accounted for accurately, insufficient
support and excessive vibration, or even
failure, can occur.
SYSTEM MONITORING AND
OPTIMIZATION
Multiphase flow technology is now beingapplied to system monitoring and opti-
mization.2,7 On-line modeling provides
information about pressures, temperatures,
densities, liquid holdup (volume fraction),
and mass rates throughout the pipeline.With these data, continuous forecasting
provides the operator with information
about allowable ramp-up rates (slugging
dangers), pigging requirements, gas-com-
position tracking, and paraffin-/hydrate-formation potential. Moreover, control
algorithms can be used to regulate individ-
ual well flows, riser control volumes, and
compressor speed. Properly designed con-trol algorithms can prevent well sandout or
liquid loadup, excessive erosion in valves
and manifold piping, and problematic liq-
uid slugging in gathering flowlines and
pipelines. These same techniques can beused to optimize blending and gas-com-
pression requirements and to evaluate gas
deliverability on the day while considering
system performance and planned or
unplanned shutdowns.
CONCLUSIONS
During the last 10 years, explosive growth
has occurred in the application of multi-
phase-flow technology for design, operation,
and optimization of offshoreproduction sys-tems. Increasing utilization of the technolo-
gy has allowed operators to save capital costs
and reduce life-cycle operating and overhead
costs. Moreover, recent use of this technolo-
gy in on-line monitoring and control sys-tems is allowing operators to push existing
systems further, thereby achieving addition-al profits and/or cost savings.
REFERENCES
1. Erickson, D. and Danielson, T.: A
Comparison of ConOlga with Field Data from
a Gas Condensate Pipeline, Proc., Eighth Intl.
Conference Multiphase Flow, Cannes, France
(1997) 19.
2. Erickson, D. and Twaite, D.: A Pipeline
Integrity Monitoring System for Leak
Detection, Control, and Optimization for Wet-
Gas Pipelines, paper SPE 36607 presented at
the 1996 SPE Annual Technical Conference
and Exhibition, Denver, Colorado, 69
October.
3. Erickson, D., Buck, E., and Kolts, J.:
Corrosion Inhibitor Transport in Wet-Gas
Pipelines, J. Materials Performance
(September 1993) 32, 49.
4. Erickson, D. and Brown, T.: Occurrence of
Hydrates in Multiphase Flowlines, Proc.,
New York Academy of Sciences Intl.
Conference on Natural Gas Hydrates, New
York City (April 1994) 715, 40.
5. Erickson, D. and Mai, M.: A Transient
Multiphase Temperature-Prediction Program,
paper SPE 24790 presented at the 1992 SPE
Annual Technical Conference and Exhibition,
Washington, DC, 47 October.
6. Brown, T. et al.: Application of a Transient-
Heat-Transfer Model for Bundled Multiphase
Pipelines, paper SPE 36610 presented at the
1996 SPE Annual Technical Conference and
Exhibition, Denver, Colorado, 69 October.
7. Lamey, M.F. and Wasden, F.: Dynamic
Simulation Model Aids Mensa Development,
Oil & Gas J. (10 August 1998) 96, 72.
SI METRICCONVERSION FACTORS
bbl1.589 873 E01=m3
ft32.831 685 E02=m3
Dale D. Erickson is a principal consul-
tant with Multiphase Solutions Inc. in
Houston, where he has developed real-
time, transient-multiphase flow simula-
tors and control/optimization software
for multiphase pipelines. He has con-
ducted technical studies on transient
multiphase flow worldwide. Erickson
holds BS and MS degrees from theColorado School of Mines and a PhD
degree from Rice U., all in chemical
engineering. Michael C. Maiis a princi-
pal consultant with Multiphase Solutions
Inc. in Houston where he has developed
on-line, forecasting, and optimization
software for pipelines and related
process equipment. He has conducted
technical studies worldwide on transient
multiphase flow in oil and gas systems.
Mai holds a BS degree from the U. of
Notre Dame and MS and PhD degrees
from the U. of Texas at Austin, all inchemical engineering.
APRIL 1999 87