IBN RUSHD ARABIAN INDUSTRIAL FIBERS COMPANY
IR – II U&O DBN PROJECTJOB SAFETY ANALYSIS (JSA)
Company Task to be carried out
Pipe Tie-In
General Work Permit MSDS
Date Special Work permit Lock-out Tag
Supervisor Confined Space Entry Emergency Response Plan
Work Area Hole/Fire Watch
Work Description Crafts Involved Basic Job Steps Risk S.R. Recommended Safe Job Procedure
Civil Preparation of spools in
workshop
*Cause fire incident
*Cutting cause hand injury
*Correct using Firefighting
equipment.
*Proper PPE require for activity
Electrical
Equipment Installation
Excavations Loading fabricated spools
using crane to trailer
*Spools fall down due to improper
rigging practice.
* Crane trip over due to overloading
or improper position of crane.
*Qualified rigger and operator
shall be assigned for lifting
activity.
* Load chart and pre-lifting
checklist shall be followed. Crane
position shall be on firm ground
with fully extend outrigger.
Chemicals
Instrumentation
Insulation Transportation of
fabricated spools to work
area
*spools slips from trailer
*property damage due to car
accident
*trailer hits pipe rack
*All spools shall be secured by
competent person.
*Traffic route shall be planned.
*Flagman shall be provided with
vehicle.
*Goal post shall be equipped with
pipe rack elevation .
Lifts
Piping
Rigging Unloading fabricated
spools using crane to
jobsite
*Spools fall down due to improper
rigging practice.
* Crane trip over due to overloading
or improper position of crane.
*fire case due to unloading in
*Qualified rigger and operator
shall be assigned for lifting
activity.
* Load chart and pre-lifting
checklist shall be followed. Crane
Scaffolding
Welding
IBN RUSHD ARABIAN INDUSTRIAL FIBERS COMPANY
IR – II U&O DBN PROJECTJOB SAFETY ANALYSIS (JSA)
restricted area. position shall be on firm ground
with fully extend outrigger.\
*IR work permit shall be followed.
Toolbox meeting shall be
conducted prior starting activity.
Required Personal Protective Equipment Erection scaffolding *Scaffolding collapsed and fall
down.
*Worker fall down
*Tools and material fall down
*Scaffolding tubes touch living line
causes electrical shock
*Competent person shall erect
scaffolding platform.
*100% tie up policy shall be
followed.
*Tools and material shall be
secured while working at height.
*Safe distance shall be kept
between living line and
scaffolding.
Hard Hat Fall Protection
Safety Glasses Gloves
Ear Protection Safety Shoes Cutting, grinding and
wielding
*Fire case
*Human burned
*Existing pipe shall be properly
flushed and inspected before
starting any activity.
*Cool cutting will be carried out.
*Fire protection such as fire
blanket, fire hydrant and fire
extinguisher shall be available on
the spot.
Sniffer Air Packs
NDT & UT *Radiation injury and environment
pollution
*Proper tight tie or support X-ray
unit at position, good insulation
condition of x ray power cables,
sockets plug.
*Assign watch man to make sure
Severity Rating (S.R.)
IBN RUSHD ARABIAN INDUSTRIAL FIBERS COMPANY
IR – II U&O DBN PROJECTJOB SAFETY ANALYSIS (JSA)
person not entering to barricade
area.
Hydro Test *Cap remove on high pressure
condition cause person injury
*Trip and electrical shock due to
hydro test water overflow.
*Cap shall be fitted properly
according to specification.
*Proper disposal hydro test water.
1 First Aid/Property Damage-Not Probable
WE CAN GO BACK AND DO THE WORK AGAIN, BUT WE CANNOT UNDO ANY DAMAGE AND OR INJURY
2 First Aid/Property Damage
3 Recordable Accident/Property Damage
4 Lost time Accident/Major Property Damage
5 Catastrophic Accident