jupiter bar chart
TRANSCRIPT
Sl. no Activity
W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1
1.0 Civil work
1.1 Footings
1.2 Plinth beam
1.3 1 st slab to 5th slab
1.4 Brick work
1.5 Internal celling&wall plastering
1.6 External plasting
1.7 Scaffolding work
1.8 Railings fitting
1.9 Wood frames making
1.10 Doors and windows fittings
2 Electrical work
2.1 Groove cutting and conduit laying
2.2 Wiring work
2.3 Board fitting (switch board)
3 Plumbing work
3.1 Groove cutting and conduit laying
3.2 Wash basin and comord fixing
3.3
External water supply & drainage
work
4 Tiling work
4.1 Toilets wall tiling
4.2 Floor tiling
4.3
Common area marble tiles all floors
& staircase
4.4 External wall cladding
5 Paint work
5.1
walls and Doors putty 1st coat
painting
5.2
2nd coat painting wall, doors and
grills
5.3 External texture and paint work
6 Other works
6.1 compound wall
6.2 septic tank
6.3 gates fixins
6.4 basement flooring
6.5 DG
6.6 Transformer
6.7 Panel board
6.8 solar6.9 R O water plant
6.1 Rain water harvesting system
6.2 Jogging track
6.3 plants&garden work
6.4 Lift work
May-15 Jun-15 Jul-15 Aug-15 Oct-12 Nov-12Feb-15 Mar-15 Apr-15
Site: Jupiter ( Area - 43560 Sq Ft)
BAR CHART
Aug-14 Sep-14 Oct-14 Nov-14 Dec-14 Jan-15Jul-14Jun-14
W2 W3 W4 W1 W2 W3 W4
Dec-12Nov-12
Week 33
Dates37 Columns for 3rd Phase leaving 8 columns at
Tank area.
11th Digging and laying PCC for Plinths.
12th Marking for Plint
13th Rod Bending
13th and 14th Centring
15th Concrete
16th Mud Filling in Room Areas
17th Watering in Room areas
18th Mud Levelling in Room areas
19th PCC in Room Areas and Setbacks
20th Survey
21st Column Concrete
22nd Column Concrete Completion
24th Bottoms Raising Start for Flats (21,22,23,24)
14th Start of Bottom Slab for Four Flats
5,18,19,20
Sl. no Activity
W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4
1 Civil work
1.1 Footings
1.2 Plinth beem
1.3 Ground Slab (Raising Bottoms till Slab)
1st Slab
2nd Slab
3rd Slab
4th Slab
1.4 Brick work
1st Floor
2nd Floor
3rd Floor
4th Floor
1.5 Internal celling&wall plastering
1.6 External plasting
1.7 Scaffolding work
1.8 Railings fitting
1.9 Wood frames making
1.1 Doors and windows Fittings
2 Electrical work
2.1
Groove cutting and conduit
laying
BAR CHART
Site : Jupiter - Panathur
1-Jun-14 1-Jul-14 1-Aug-14
2.2 Wiring work
2.3 Board fitting (switch board)
3 Plumbing work
3.1
Groove cutting and conduit
laying
3.2 Wash basin and comord fixing
3.3
External water supply &
drainage work
4 Tiling work
4.1 Toilets wall tiling
4.2 Floor tiling
4.3
Common area marble tiles
all floors & staircase
4.4 External wall cladding
5 Paint work
5.1
walls and Doors putty 1st
coat painting
5.2
2nd coat painting wall,
doors and grills
5.3 External texture and paint work
6 Other works
6.1 compound wall
6.2 septic tank
6.3 gates fixins
6.4 basement flooring
6.5 DG
6.6 Transformer
6.7 Panel board
6.8 solar
6.9 R O water plant
6.1 Rain water harvesting system
6.2 Jogging track
6.3 plants&garden work
6.4 Lift work
W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2
BAR CHART
Site : Jupiter - Panathur
1-Sep-14 1-Oct-14 1-Nov-14 1-Dec-14 1-Jan-15
W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4
BAR CHART
Site : Jupiter - Panathur
1-Jan-15 1-Feb-15 1-Mar-15 1-Apr-15 1-May-15
W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4
1-Aug-15 1-Sep-151-Jun-15 1-Jul-15