Page 1: K-20 Edge Router Installation Training April 9, 2015

K-20 Edge Router Installation TrainingApril 9, 2015

Page 2: K-20 Edge Router Installation Training April 9, 2015

Introductions

Who am I? Name Location Experience

2

Page 3: K-20 Edge Router Installation Training April 9, 2015

Agenda

Pre-Installation ET K-20-101 Laptop configuration ET K-20-102 Vendor site access ET K-20-103 Maintenance window scheduling ET K-20-104 Know location of K-20 router, modem and UPS ET K-20-105 Know location of vendor equipment and demarc

Day of Installation ET K-20-106 Prep work, tools and consumables ET K-20-107 Router installation ET K-20-108 Card Installation ET K-20-109 Optics Installation ET K-20-110 Cable Installation ET K-20-111 Modem Installation

Evaluation ET K-20-112 Evaluation / documentation

3

Page 4: K-20 Edge Router Installation Training April 9, 2015

Pre-Installation

4

Page 5: K-20 Edge Router Installation Training April 9, 2015

Laptop configuration

Laptop requirements: Windows OS with RDP enabled K-20 test account (k20test)

Username: k20test Password: <to be communicated to NOC>

Iperf.exe installed This allows for testing the circuit bandwidth

Firewall settings allow RDP and IPERF (defaults) TCP: 3389, 5001 UDP: 3389, 5001 Wireless connectivity disabled

5

Page 6: K-20 Edge Router Installation Training April 9, 2015

Vendor site access

The Edge Technician will work with K-20 Network Provisioning to coordinate dates and times for testing and transitions.

K-20 Network Provisioning [email protected]

6

Page 7: K-20 Edge Router Installation Training April 9, 2015

Maintenance window scheduling

When maintenance is needed, the Edge Technician will contact the K-20 NOC to coordinate maintenance time.

The Edge Technician will coordinate directly with local site contact prior to performing maintenance so they are informed of pending work and have access granted if needed.

K-20 NOC +1 (888) 934-5551 [email protected]

7

Page 8: K-20 Edge Router Installation Training April 9, 2015

Know location of K-20 router and modem

The Edge Technician will verify with the local site contact:

UPS location (if applicable)Router locationModem location

8

Page 9: K-20 Edge Router Installation Training April 9, 2015

Know location of vendor equipment and demarc

The Edge Technician will verify with the local site contact:

POTS line (plain old telephone service), demarc and extension, if extendedVendor equipment, service delivery point and extension, if extended

9

Page 10: K-20 Edge Router Installation Training April 9, 2015

Pre-Installation Questions

Pre-Installation Questions?

10

Page 11: K-20 Edge Router Installation Training April 9, 2015

Day of Installation

11

Page 12: K-20 Edge Router Installation Training April 9, 2015

PreparationOn the day of installation, confirm the following:

Work to be performed onsiteWho your site contact is and their contact informationVerify if you will need a visitor badge, telco room keys or other items for access to perform requested workIf necessary to contact the site ahead of arrival, call to notify site contact you are en routeArrive at site with required equipment for installationBring necessary tools to complete the requested work

12

Page 13: K-20 Edge Router Installation Training April 9, 2015

Tools and consumables

Tools and consumables you may need:

Electrostatic Discharge (ESD) Wrist StrapFlat head screwdriver (assortment)Phillips screwdrivers (#2, #6, #8)Torx screwdriver (T15)Wire crimper Green (AWG 6) wire for grounding connections Ring terminal ¼” inner diameter (5-7mm)Screws (including specific to your rack)

13

Page 14: K-20 Edge Router Installation Training April 9, 2015

Tools and consumables cont'd

Tools and consumables you may need:

Console cable (and USB serial port)Fiber cleanerSinglemode LC patch cableMultimode LC patch cableCategory 5 cablesRJ45 CouplerEthernet loopback cable

14

Page 15: K-20 Edge Router Installation Training April 9, 2015

Electrostatic Discharge (ESD) Wrist Strap

Before performing any work on K-20 routers, switches or modems, you should be wearing a properly grounded ESD wrist strap.

15

The ESD wrist strap should be worn on the wrist with contact to bare skin and should be connected to a grounded object such as a rack or cabinet.

Page 16: K-20 Edge Router Installation Training April 9, 2015

Router install

To install the router, follow the steps below:

Unpack router from box, verifying contentsAttach mounting bracketsMount in rack or cabinetGround the chassisPlug in powerInsert cardsInsert opticsConnect cables

16

Page 17: K-20 Edge Router Installation Training April 9, 2015

Router install – Unpack router

While wearing the grounded ESD wrist strap, unpack the router and verify the contents, it should contain:

RouterMounting bracketsMounting bracket screwsPower cable(s)

If replacing router, package old router wrapped in plastic bag, power cable(s), brackets and screws in sturdy cardboard box with proper packaging materials (bubble wrap, packing paper, packing peanuts).

17

Page 18: K-20 Edge Router Installation Training April 9, 2015

Familiarization with Cisco 2921 Front

Front:Power Supply 0Power Supply 1Note: No ports to connect to on the front, only the power supplies.

18

Page 19: K-20 Edge Router Installation Training April 9, 2015

Familiarization with Cisco 2921 Back

Back:HWIC SlotsConsole PortDMZ PortUplink PortManagement Ethernet PortGrounding Point

19

Page 20: K-20 Edge Router Installation Training April 9, 2015

Familiarization with Juniper MX5 Front

Front:PowerMIC Slot 0DMZ PortUplink PortConsole PortManagement Ethernet PortMIC Slot1

20

Page 21: K-20 Edge Router Installation Training April 9, 2015

Familiarization with Juniper MX5 Back

Back:MIC Slot 0Clock PortSync PortGrounding PointNote: only the grounding port should be utilized on the back of the Juniper MX5, MX10.

21

Page 22: K-20 Edge Router Installation Training April 9, 2015

Router install – Cisco mounting brackets

Once unpacked and familiarized with the Cisco router, attach the mounting brackets to the router:

Attach either the 19” or 23” mounting brackets as necessary on the appropriate side (front or back mount) and location (flush mount or center mount):

22

Page 23: K-20 Edge Router Installation Training April 9, 2015

Router install – Juniper mounting brackets

Once unpacked and familiarized with the Juniper router, attach the mounting brackets to the router:

Attach either the 19” or 23” mounting brackets as necessary on the appropriate side (front or back mount) and location (flush mount or center mount):

23

Page 24: K-20 Edge Router Installation Training April 9, 2015

Router install – Mount in rack

Once the mounting brackets are installed, mount in the rack or cabinet:

Depending on mounting constraints, either flush mount or center mount the router to the cabinet or rack (respectively) utilizing screws appropriate for enclosure:

24

Page 25: K-20 Edge Router Installation Training April 9, 2015

Router install – Ground the router

Once the router is mounted securely in the enclosure, ground the chassis:

Utilizing green AWG 6 cable and the supplied lugs attach a grounding cable to the router chassis in appropriate location:

25

Cisco

Juniper

Page 26: K-20 Edge Router Installation Training April 9, 2015

Router install – Ground the router cont'd

Once the router has it's grounding connection established, attach to grounded source. The enclosure where the router is mounted should have a grounding bar or a nearby earth ground noted. Verify with site contact where this is.

26

Page 27: K-20 Edge Router Installation Training April 9, 2015

Router install – Power install

Once the router is mounted inside the enclosure and is properly grounded, plug the supplied power cable into the router power supply 0 and turn on:

CiscoPower Supply 0Power Supply 1 (if applicable)

JuniperPower Supply 0Power Supply 1 (if applicable) 27

Page 28: K-20 Edge Router Installation Training April 9, 2015

Router install – Card install

While wearing the grounded ESD wrist strap, unpack the card and verify the contents:

If a card installation or swap is required, the K-20 Engineer will ship the required card to the Edge Technician in advance of the site appointment.

If replacing card, package old card wrapped in plastic bag in a sturdy cardboard box with proper packaging materials (bubble wrap, packing paper, packing peanuts).

28

Page 29: K-20 Edge Router Installation Training April 9, 2015

Router install – Card install, identify slot

Verify the slot you will be using for the installation or swap with the K-20 Engineer you are working with. Below is a listing of slots.

CiscoHWIC 3

HWIC 2

HWIC 1

HWIC 0

JuniperMIC 0MIC 1

29

Page 30: K-20 Edge Router Installation Training April 9, 2015

Router install – Card install, remove card

Once the slot to be used has been verified, remove the existing card.

CiscoUses phillips and torx screws in different models.

Determine appropriate type then remove screws

and utilize appropriate type for installation

of card.

JuniperUses a pull tab mechanism for disengaging the

Card. Pull the tab above the slot to disengage

the card then insert the new card and ensure

the pull tab reengages.

30

Page 31: K-20 Edge Router Installation Training April 9, 2015

Router install – Optic install

The K-20 routers may need to have fiber optic transceivers installed to operate correctly. These may be any of the following types:

31

SFP/SFP+SFPs are 1GbESFP+ are 10GbE, usually backward compatibleLC Connector

SFP/SFP+ BiDiSame speed as SFP/SFP+ but only uses one fiber optic cableLC Connector

XFP10GbE, older form factor not used as oftenLC Connector

*Always clean transceivers after installation*

Page 32: K-20 Edge Router Installation Training April 9, 2015

Router install – Optic install

Insert the appropriate optic transceiver into the indicated slot on the device or card. Ensure that the module is plugged in firmly and has a good connection to the backplane:

CiscoThe SFP will be inserted into the port

that is a combo port for either a SFP

or copper connection

JuniperThe SFP/SFP+/XFP will be inserted into

the port on the card in either MIC0 or

MIC132

Page 33: K-20 Edge Router Installation Training April 9, 2015

Router install – Fiber optic cleaning

It may be necessary to clean the fiber optic cable and/or the transceiver to resolve an issue, in order to do so:Clean the inside of the SFP/SFP+/XFP

by inserting the single-fiber port cleaner into the port and pumping the cleaner once.

Clean the outside of the connector/single fiber by attaching the adapter and inserting the fiber cable into the adapter and pumping once.

33

Page 34: K-20 Edge Router Installation Training April 9, 2015

Router install – Fiber optic handling tips

From time to time issues may arise that involve handling the fiber optic cables. Please keep the following in mind when dealing with fiber cables:

When inserting fiber cables, make sure the connector “clicks” to ensure a tight fitDo not bend the fiber optic cable, this will cause it to break and not effectively transmit lightAlways clean the fiber optic connections when working with themDo not look into the laser, it can burn your cornea, this can occur from the transceiver as well as from the cableAlways cap fiber optic transceivers when not in use

34

Page 35: K-20 Edge Router Installation Training April 9, 2015

Cable installation

35

For the Juniper router remove the rubber safety plug from the cable connector. Insert connector into 1/MIC 0, port 1/0/0 this connects to the DMZ and fiber is left dangling. Port 1/1/0 connects to vendor switch.

Modem DB25 connects to the console port.

Test laptop needs a mini convertor switch. Ask site to use theirs for testing.

For the Cisco router, insert the RJ45 connector into the GE 0/0 port until the latch is securely in place, connect the other end of cable to test laptop.

Modem DB25 cable connects to console port.

The telco circuit connects to GE 0/1

Page 36: K-20 Edge Router Installation Training April 9, 2015

Modem install

Once the router is mounted securely in the enclosure and grounded, install the modem. Below is the typical modem supplied by K-20. It will need to be connected to the site supplied POTS (Plain Old Telephone Service) phone line.

36

Page 37: K-20 Edge Router Installation Training April 9, 2015

Modem install – Unpack modem

While wearing the grounded ESD wrist strap, unpack the modem and verify the contents. It should contain:

ModemPower cableDB25 to RJ45 Console CableTelephone line cable

If replacing modem, package old modem wrapped in plastic bag, console cable and power cable(s) in a sturdy cardboard box with proper packaging materials (bubble wrap, packing paper, packing peanuts).

37

Page 38: K-20 Edge Router Installation Training April 9, 2015

Familiarization with Modem front

Front:Power Button

38

Page 39: K-20 Edge Router Installation Training April 9, 2015

Familiarization with Modem back

Back:Reset ButtonPower outletPOTS LineSerial Port

39

Page 40: K-20 Edge Router Installation Training April 9, 2015

Modem install – Connect power and line

Connect the modem to power and to the POTS line. The power should be plugged into the UPS, if available, or site power. The POTS line should be plugged into the line port on the modem.

40

Page 41: K-20 Edge Router Installation Training April 9, 2015

Modem installation – Connect console

Connect the modem to the console port of router. In order to do so you will need to have the modem and the DB25 to RJ45 cable that came with the modem:

Connect DB25 end of cable to Serial port of modem

Connect RJ45 to Console port of router

41

Page 42: K-20 Edge Router Installation Training April 9, 2015

Console Connection

It may be necessary to connect the laptop to the console port of router. In order to do so you will need to have the laptop, the USB Serial cable and the DB9 to RJ45 cable:

Connect USB Serial cable to computer. Verify which COM port it is connected to.COM Settings should be:

Baud: 9600 Parity: N Data bits: 8 Stop bits: 1 Flow control: None

Connect DB9 to RJ45 cable to SUB Serial cable and console port on router. 42

Page 43: K-20 Edge Router Installation Training April 9, 2015

Testing

If the site visit is a prescheduled testing appointment, the Edge Technician will call the K-20 NOC @ 888-934-5551, 30 minutes before arriving at site to allow the NOC to set up for testing.

Once all connections are made, call the K-20 NOC and advise site is ready for testing.

The K-20 NOC will then test to see if they can reach the equipment at the site to perform remote testing.

The Edge Technician must remain onsite until the K-20 NOC has confirmed they have connectivity and can proceed with testing.  

Once connectivity is confirmed, the K-20 NOC will advise the Edge Technician they are cleared to leave the site.

43

Page 44: K-20 Edge Router Installation Training April 9, 2015

Testing

44

Page 45: K-20 Edge Router Installation Training April 9, 2015

Transition

After K-20 NOC has completed testing the transition will occur.

At the time of Transition the Edge Technician will return to the K-20 site and remove the testing equipment and connect the K-20 equipment. 

The Edge Technician will work with K-20 Provisioning (Core) during the transition.

The Edge Technician will move cable connections from the test equipment to the K-20 router and modem.

The Edge Technician will remove the test router and the test laptop from the site.

45

Page 46: K-20 Edge Router Installation Training April 9, 2015

Transition

46

Page 47: K-20 Edge Router Installation Training April 9, 2015

Quick Installation Sheet

Verify work to be completed. Prep site for installation. Verify all equipment is correct and available. Locate customer demarc.

47

Page 48: K-20 Edge Router Installation Training April 9, 2015

Quick Installation Sheet, cont’d

For new site installation or equipment/port upgrade (K-20 router will be connected to telco vendor equipment and K-20 modem at the time of Transition):Unpack router.Attach mounting brackets.Install router into rack.Attach green grounding wire.Connect power cord.Install any required cards.Install any required SFP/XFP’s.

48

Page 49: K-20 Edge Router Installation Training April 9, 2015

Quick Installation Sheet, cont’d

Connect test equipment:Connect cables from telco vendor equipment to test router.Connect test router to modem.Connect modem to UPS if applicable.Connect test laptop.Contact K-20 NOC for testing or to notify that site is ready for remote testing. 888-934-5551Wait until K-20 NOC verifies they can access the equipment remotely to test and clear Edge Technician to leave the site.Sign out and return access badges to site if applicable.

49

Page 50: K-20 Edge Router Installation Training April 9, 2015

Quick Installation Sheet, cont’d

At Transition:Disconnect the test laptop.Move cable connection between test router and telco vendor jack/port to the K-20 router port.Move cable connection between test router and K-20 modem to the K-20 router port.Remove test laptop and test router from site.Sign out and return access badges to site if applicable.Document work done at site on Evaluating/Documenting Vendor Installations at End Sites form and return form to K-20 Provisioning at [email protected]

50

Page 51: K-20 Edge Router Installation Training April 9, 2015

Coordination

If in doubt of who to contact for coordination efforts, contact the K-20 Provisioning department:

K-20 Provisioning [email protected]

For issues relating to performance and testing, contact the K-20 NOC:

K-20 NOC +1 (888) 934-5551 [email protected] 51

Page 52: K-20 Edge Router Installation Training April 9, 2015

Day of Installation Questions

Installation Questions?

52

Page 53: K-20 Edge Router Installation Training April 9, 2015

Evaluation

53

Page 54: K-20 Edge Router Installation Training April 9, 2015

Evaluating/Documenting Vendor Install

After installation, testing and transition are complete, K-20 Network Provisioning asks that the following be documented:Verify UPS is installed.Verify cabling installation. The path of the cable should not obstructing anything, at risk of being caught on anything or being crushed. Insure cabling is properly tied back. Is cabling installed correctly?Is vendor cable terminated correctly?Was the vendor equipment installed into a rack?

If no, what is the location of the vendor equipment?Is the modem on top of the router?

If no, what is the location of the modem?

54

Page 55: K-20 Edge Router Installation Training April 9, 2015

Evaluating/Documenting Vendor Install

If possible, please verify modem line phone number and document it.

Document demarc and location of the equipment: RM or /Suite number, location in the room (back wall, etc.), in rack or alternate location, and port number. Examples: (Seattle K12, Main building, telco closet, floor 1, vendor equipment pos 2, K-20 equip mounted in top position of rack, port 1, modem placed on top of router) or (Seattle K12, Main building, attendance office, back left corner of room on shelf, vendor equip on bottom shelf, K-20 Equip port 1, modem on top of router).

Please take a photo of the installed equipment. Email photo and demarc information K-20 Network

Provisioning office at [email protected].

55

Page 56: K-20 Edge Router Installation Training April 9, 2015

Conclusion and Questions

This concludes the K-20 Edge Router Installation Training.

At this time we will take questions that were not addressed or answered during the training modules.

56