K. Long, 18 April 2023
MICE Muon Beam
Beam line and decay solenoid: Pressure reducing valves:
Fitted to Q7—9; To be fitted to Q4—6
Upstream MLI: Plan to fit as presented at review; Cool down scheduled to take place over Easter:
Clear instructions to baby sitters: Shutdown and make safe if there are issues that can not be
resolved without presence of expert
Volunteers required! LC has plan (see later), but manpower is short (usual
‘suspects’!)
Target: Production of jugs etc. has started:
Welding and grinding jigs: AC @ RAL
Production of parts has started: Bearing blanks: RH @ IC
Test welding/test grinding: Hope for:
Welding this week; Send to grinders next week