TABLE OF CONTENTS Sr.No Section No. Title 1 SECTION-I THE FORM OF THE BID (FB) 2 SECTION-II INSTRUCTION TO BIDDERS (ITB) ANNEDURE 1 TABLE – A CHART OF EVALUATION TABLE – B EVALUATION CRITERIA FOR TECHNCIAL SPECIFICATION 3 SECTION-III GENERAL CONDITIONS OF CONTRACT (GC) 4 SECTION-IV SPECIAL CONDITIONS OF CONTRACT (SC) 5. SECTION - V TECHNICAL SPECIFICATIONS (TSP) 6 SECTION-VI SCHEDULE OF REQUIREMENT / BOQ (SOR) 7 SECTION-VII TECHNICAL SPECIFICATION (TSC) SCHEUDLE TO BID (STB)

Upload: phungque

Post on 30-Jan-2018

228 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

TABLE OF CONTENTS

Sr.No Section No. Title

1 SECTION-I THE FORM OF THE BID (FB)

2 SECTION-II INSTRUCTION TO BIDDERS (ITB)

ANNEDURE 1 TABLE – A CHART OF EVALUATIONTABLE – B EVALUATION CRITERIA FOR TECHNCIAL SPECIFICATION

3 SECTION-III GENERAL CONDITIONS OF CONTRACT (GC)

4 SECTION-IV SPECIAL CONDITIONS OF CONTRACT (SC)

5. SECTION - V TECHNICAL SPECIFICATIONS (TSP)

6 SECTION-VI SCHEDULE OF REQUIREMENT / BOQ (SOR)

7 SECTION-VIITECHNICAL SPECIFICATION (TSC)

8 SECTION -VII SCHEUDLE TO BID (STB)

9 SECTION-IX SAMPLES OF FORMS (SF)

Page 2: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

SECTION-VII

Page 3: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

SECTION IFORM OF BID

S.No. Title Page No.

1 Form of Bid FB 1-5

Page 4: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

SECTION-I

Page 5: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

SECTION - II

INSTRUCTION TO BIDDERS (ITB)Contents

A

IB.1

IB.2

IB.3

IB.4

B.

IB.5

IB.6

IB.7

C

IB.8

IB-9

IB-10

GENERAL

Scope of Bid and Source of Funds

Eligible Bidders

Origin of goods and services

Cost of Bidding

BIDDING DOCUMENTS

Content of Bidding Documents

Clarification of Bidding Documents/ Pre-Bid Meeting

Basis of Bidding Documents, and Addendum

PREPARATION OF BIDS

Language of bid

Documents Comprising the Bid

1

1

2

2

2

3

4

5

6

7

Page 6: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

IB.11

IB.12

IB.13

IB.14

IB.15

IB.16

IB.17

D

IB.18

IB.19

IB.20

IB.21

E

IB.22

IB.23

IB.24

IB.25

IB.26

IB.27

From of Bid and Schedules

Bid Price

Currencies of Bid

Documents Establishing Bidder’s Eligibility and Qualification

Documents Establishing the conformity to Bidding Documents.

Bid security

Extension in the validity of bids security

Format and Signing of bid

SUBMISSION OF BIDS

Sealing and Marking of Bids

Deadline of submission of Bids

Late Bids

Modification, Substitution and withdrawal of Bids

BID OPENING AND EVALUATION

Bid Opening

Clarification to Bids

Preliminary Examination & Determination of Responsiveness of Bids

(a)Preference on Early Delivery of Four Split Hopper Barges,

(b)Conversion to Single Currency

7

10

10

10

12

14

14

15

17

18

18

19

20

21

23

23

28

Page 7: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

IB.28

F

IB.29

IB.30

IB.31

IB.32

IB.33

IB.34

IB.35

IB.36

Detailed Evaluation of bids

Domestic Preference

Process to be confidential

AWARD OF CONTRACT

Post qualification

Award Criteria

Employer’s Right to Vary Quantities at Time of Award

Employer’s Right to Accept Any bid and to reject Any or all Bids

Notification of award

Performance Security

Signing of contract Agreement

Integrity Pact

Appendix – A Evidence of Bidders ‘s Capability

Appendix – B Domestic Goods

Annexure

Table – ATable – B

29

29

30

30

30

30

31

31

31

32

34

11-13

Page 8: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

SECTION - III

GENERAL CONDITIONS OF CONTRACT (GC)Contents

Page 9: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

Definitions

Applications

Country of Origin

Standards

Contract Documents-Confidentiality

Patent Rights

Performance Security

Engineer and Engineer’s Representative

Inspection and Tests

Tests on Completion

Taking Over

Packing

Delivery and Documents

Insurance

Transportation

Incidental Services

Spare Parts

Warranty

Payment

Claims

Prices

GC-1

GC-3

GC-3

GC-4

GC-4

GC-5

GC-5

GC-5

GC-7

GC-8

GC-9

GC-10

GC-10

GC-10

GC-11

GC-11

GC-12

GC-13

Page 10: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

23

24

25

26

27

28

29

30

31

32

33

34

35

36

37

Variation Order

Contract Amendments and annulment

Assignment

Subcontracting

Delays in the Contractor’s Performance

Liquidated damges

Termination for Default

Force Majeure

Termination for insolvency

Termination for Convenience

Resolution Disputes

Governing Language

Applicable Law

Notices

Taxes and Duties

Integrity Pact

GC-14

GC-16

GC-16

GC-16

GC-19

GC-19

GC-19

GC-20

GC-20

GC-21

GC-21

GC-22

GC-22

GC-22

GC-23

Page 11: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

GC-23

GC-23

GC-23

GC-23

SECTION – IV

SPECIAL CONDITIONS OF CONTRACTContents

1

2

3

4

5

6

7

8

Definitions (Clause 1)

Application (Clause 2)

Country of Origin (Clause 3)

Standard (Clause 4)

Use of Contract Documents Information (Clause 5)

Performance Security (Clause 7)

Engineer and Engineer’s Representative (Clause 8)

SC-1

SC-3

SC-3

SC-3

SC-4

SC-4

SC-5

Page 12: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

Delivery and Documents (Clause 13)

Insurance (Clause 14)

Incidental Services (Clause 16)

Spare Parts (Clause 17)

Warranty (Clause 18)

Payment (Clause 19)

Price (Clause 21)

Subcontracting (Clause 25)

Delays in Contractor’s Performance (Clause 26, Progress Reports)

Liquidated damages (Clause 27)

Termination by Default (Clause 28)

Termination – Force Majeure (Clause 29)

Termination for Insolvency (clause 30)

Termination for Convenience (Clause 31)

Resolution of Disputes (Clause 32)

Governing Language (Clause 33)

Notice (Clause 35)

Special Provision (Clause 38)

SC-8

SC-10

SC-12

SC-12

SC-12

SC-13

SC-19

SC-20

SC-20

SC-21

SC-22

SC-23

SC-23SC-23

SC-24

Page 13: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

SC-25

SC-25

SC-26

SC-26

Page 14: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

SECTION – V

TECHNICAL SPECIFICATIONS

Part I- GENERAL SPECIFICATIONContents

1.

2

3

4

5

Brief of the Requirement

1.1 Climatological, Geological Conditions at Karachi Port

I. Temperatures

II. Relative Humidity

III. Precipitation

IV. Wind and Storms

V. Tidal Water levels

VI. Tidal current

VII. Wave Heights

VIII. Corrosion

IX. Earthquakes

General Description of the vessel

Principal characteristics

TSP-1

TSP-2

TSP-2

TSP-3

TSP-3

TSP-3

TSP-3

TSP-4

TSP-4

TSP-4

TSP-4

TSP-4

TSP-6

TSP-7

TSP-7

Page 15: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

6

7

8

9

10

11

12

Tank Capacities (approximately)

Design Standards

Free running Speed

Classification, Rules Regulations and Certificated7.1 Classification

7.2 Ship’s registry and Flag

7.3 Rules, Conventions and regulations

7.4 Certificates

Supervision and inspection

Tests and Trials

9.1 General

9.2 Workshop tests

9.3 Quay Trials

9.4 Preliminary Acceptance Trials

9.5 Confirmatory Trials and Final Acceptance

9.6 Tests and Trials Specifications

Noise & Vibration

10.1 Noise Criteria

10.2 Vibration

Technical Requirements and conditions

11.1 Ambient conditions

Drawing , Calculation , Spare Parts Lists Manuals,

TSP-8

TSP-8TSP-8

TSP-8

TSP-8

TSP-9

TSP-9

TSP-10

TSP-10

TSP-12

TSP-12

TSP-12

TSP-13

TSP-13

TSP-13

TSP-13

TSP-13

TSP-14

TSP-14

TSP-14

TSP-14

Page 16: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

1

2

4

Photos, Patterns and Templates, Model

12.1 General

12.2 Drawings and calculations

12.3 Drawings to be fitted on board

12.4 “As-built” Drawings

12.5 Manufacturer’s instruction, maintenance and spare parts manuals

12.6 Patterns and templates

12.7 Model, photographs and brass plaques

12.8 Inventory

12.9 LPACS

PART II HULL SPECIFICATION

General Arrangement

Hull Construction

2.1 Frames and Webs

2.2 Bottom Strengthening

2.3 Deck Plating

2.4 Bulkheads

Hopper Construction

3.1 Deck hinges and security Combs

TSP-14

TSP-15

TSP-16

TSP-16

TSP-17

TSP-17

TSP-18

TSP-18

TSP-19

TSP-19

TSP-20

TSP-20

TSP-20

TSP-20

TSP-21

TSP-21

TSP-22

TSP-22

TSP-22

Page 17: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

5

1

2

3

4

5

3.2 Recesses for hydraulic cylinders

3.3 Trap Water in the Hopper

Aft & Forward Body Construction

4.1 Stem, Stern and Skeg

4.2 Propeller bosses and shafts brackets

4.3 Rudders

Deckhouse and Funnels

5.1 Deckhouse

5.2 Wheelhouse

5.3 Funnels

PART III MACHINERY SPECIFACTION

Propulsion Maneuvering System

Main Diesel Engineer

Controls of the Propulsion Units

(a)Hydraulic System(b)Barge Splitting System

Primary Ship System

a) Bilge / Ballast/Deck Wash-and Internal Fire Fighting System

b) Fuel System

c) Cooling water System

TSP-22

TSP-22

TSP-23

TSP-23

TSP-23

TSP-24

TSP-24

TSP-25

TSP-25

TSP-25

TSP-25TSP-26

TSP-26

TSP-26

TSP-27

TSP-27

TSP-27

TSP-27

TSP-27

Page 18: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

1

2

3

4

d) Potable Water System

e) Sewage System

f) Filling / sounding and De-aeration System

g) Lubricating Oil System

h) Air-conditioning & Ventilation System

PART – IV ELECTRICAL SPECIFICATION

General

Power Distribution System

Electric Power Generating Plant

3.1 General

3.2 Main Diesel Generators (2)

3.3 Harbour Generator (1)

3.4 Protection, Alarm And monitoring

3.5 Lighting Transformers

3.6 Shore supply

3.7 (24 V) Battery Systems

a) For main and Auxiliary Engines Starting

b) Emergency / Communication / Alarm batteries

c) Radio Equipment

3.8 Test Panel

TSP-27

TSP-28

TSP-29

TSP-29

TSP-29

TSP-29

TSP-30

TSP-30

TSP-31

TSP-31

TSP-31

TSP-31

TSP-31

TSP-31

TSP-32

TSP-32

TSP-32

TSP-32

TSP-32

TSP-33

Page 19: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

5

6

Distribution Equipment

4.1 Main Switchboard

4.1.1 Construction and Installation

4.1.2 Main components

4.1.3 Switchboard layout

4.1.4 Function

4.2 Distribution Boards

4.2.1 Galley equipments distribution board

4.2.2 Lighting distribution boards

Wheelhouse Distribution Board & control console

5.1 Distribution Board

5.2 Navigation light Panel. Signal light Panel and Flashing light Panel

5.3 Main & Auxiliary Engines Control and alarm Panel

5.4 Steering gear control panel

5.5 Emergency stop push buttons

5.6 Splitting hopper hydraulic control unit

5.7 Navigational Equipment

5.8 General alarm system

Lighting System

6.1 Navigation Lights

TSP-33

TSP-34

TSP-34

TSP-34

TSP-34

TSP-35

TSP-35

TSP-35

TSP-35

TSP-35

TSP-36

TSP-36

TSP-36

TSP-36

TSP-36

TSP-36

TSP-36

TSP-36

TSP-37

TSP-37

Page 20: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

7

8

6.2 Anchor Lights

6.3 Not-Under-Command Light, Draft Light and Restricted Manoeuvring Light

6.4 Norse Signal Light

6.5 Portable Daylight signal Light

6.6 Signaling Search Lights

6.7 Flood Lights

6.8 Rounding Lights

6.9 Control Panels

6.9.1 Navigation Light control Panel

6.9.2 Signal Lights Control Panel

6.9.3 Flashing Lights control Panel

6.10 General Lighting

6.10.1 Systems

6.10.2 Switches and Sockets

Navigation Equipment

7.1 Magnetic Compass

7.2 Electronic Compass

7.3 Echo Sounder

7.4 Speed Log

7.5 Radar Plant

7.6 GPS Navigator

TSP-37

TSP-37

TSP-37

TSP-38

TSP-38

TSP-38

TSP-38

TSP-38

TSP-38

TSP-38

TSP-39

TSP-39

TSP-39

TSP-39

TSP-39

TSP-39

TSP-40

TSP-40

TSP-40

TSP-40

TSP-40

Page 21: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

9

10

11

1

2

7.7 Whistle

7.8 Anemometer and anemoscope

7.9 Clear view screen

7.10 Rudder Angle Indicator

7.11 Automatic Identification System (AIS)

Internal Communication

8.1 Sound Power Telephone

8.2 Engine Telegraph

8.3 Revolution Indicator for Main Engines

8.4 Revolution Indicator for Stern Shafts

8.5 Public Address System

8.6 TV Antenna System

8.7 Alarm Systems

8.7.1 Fire Detection, Alarm System

8.7.2 General Alarm System

8.7.3 CO2 Release Alarm System

Radio Communication Equipment

IX.1 VHF Radio Telephone

IX.2 NAVTEX Receiver

IX.3 Satellite E.P.I.R.B. and 9GHz Radar Transponder etc.

TSP-40

TSP-41

TSP-41

TSP-41

TSP-41

TSP-41

TSP-42

TSP-42

TSP-42

TSP-42

TSP-42

TSP-43

TSP-43

TSP-43

TSP-43

TSP-43

TSP-43

TSP-43

TSP-43

TSP-44

TSP-44

Page 22: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

3

4

5

6

7

Electric Cable and Installation

10.1 Cable Application

10.2 Cable Installation

Spare Parts

PART – V OUTFITTEING SPECIFICATION

Lift Saving Appliances

Firefighting Appliances

Alarm Installations

3.1 General Alarm System

3.2 CO2 alarm

3.3 Engine room Alarms

3.4 Splitting Alarm

3.5 Alarm column

Anchor Windlass

Capstan

Steering gears

Accommodation

7.1 General

7.1.1 Complement

7.1.2 Public spaces

TSP-45

TSP-45

TSP-45

TSP-45

TSP-46

TSP-46

TSP-47

TSP-48

TSP-48

TSP-48

TSP-48

TSP-49

TSP-49

TSP-49

TSP-49

TSP-49

TSP-49

TSP-49

TSP-49

TSP-49

Page 23: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

8

9

10

7.1.3 Navigation space

7.1.4 Other spaces

7.2 Insulation

7.2.1 Heat insulation

7.2.2 Sound insulation

7.3 Curtains

7.4 Galley Equipment

7.5 Officer’s mess room

7.6 Crew’s mess room

7.7 Stores & Workshops

Painting and Cathodic protection

8.1 Surface, preparation

8.2 Painting

8.3 Cathodic Protection

Flags and Books

9.1 Distress call, etc

9.2 General

9.3 Spares

Other Requirements / Provisions

PART – VI TEST AND TRIALS

a) GENERAL ARRANGEMENT PLAN

TSP-50

TSP-50

TSP-50

TSP-50

TSP-50

TSP-51

TSP-51

TSP-51

TSP-52

TSP-52

TSP-52

TSP-52

TSP-52

TSP-52

TSP-55

TSP56-58

Page 24: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

b) TESTS AND TRIALS

SECTION VI

SCHEDULE OF REQUIREMENT

Schedule of requirement

Bill of quantity

SOR 1-3

SOR 4-5

Page 25: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

SECTION VII

TECHNICAL SCHEDULE

Technical Schedule TSC 1-22

Page 26: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

SECTION VIII

SCHEDULES TO BID

SCHEDULE A: Specific Work Data

SCHEDULE B: Works to be performed by the Sub-Contractor.

SCHEDULE C: Proposed Program of Work

SCHEDULE D: Deviation from Technical Provision

SCHEDULE F: Deviation from Contractual condition

SCHEDULE F: Method of Performing Works

SCHEDULE G: Proposed Organization

SCHEDULE H: integrity pact

STB-1

STB-2

STB-3

STB-4

STB-5

STB-6

STB-7

STB-8

Page 27: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

SECTION IX

FORMS OF SAMPLE

Form A: Contract Agreement

From B: Performance Security Form

Form C: Advance Payment Guarantee

Form D: Manufacturer’s Authorization Form

Form E: Bid Security Form

Form F: List of Sub-Contractor

Form G: Particulars of Local Associated Firm

SF-1-2

SF-3

SF-4

SF-5

SF-6-7

SF-8

SF-9

Page 28: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX

Page 29: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

SECTION – I(FORM OF BID)

Page 30: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

SECTION –II

(INSTRUCTION TO BIDDERS / TECHNICAL EVAULATION

Page 31: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

SECTION –III(GENERAL CONDITION OF CONTRACT)

Page 32: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in
Page 33: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

SECTION –IV(SPECIAL CONDITION OF CONTRACT)

Page 34: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

SECTION –V(GENERAL SPECIFICATION)

Page 35: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

SECTION –VI(SCHEDULE OF REQUIREMENT)

Page 36: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

SECTION –VII(TECHNICAL SCHEDULE)

Page 37: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

SECTION –VIII(SCHEDULE OF BID)

Page 38: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

SECTION –IX(FORMS OF SAMPLE)

Page 39: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

ANNEXURE -ITABLE A & B

Page 40: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

SECTION - IX

FORM “A”

CONTRACT AGREEMENT

This Agreement made the ……………… day of ………………….2015 between Karachi Port Trust (KPT), Pakistan (hereinafter called “the Purchaser”) of the one part and M/s……………………………… (hereinafter called “the Supplier”) of the other part:

Whereas the Purchaser invited bids for construction and delivery of Four Self Propelled Split Type Hopper Barges and has accepted a bid of the Supplier in the name of …………………. (hereinafter called “the Contract Price”)

NOW THIS AGREEMENT WITNESSETH AS FOLLLWS:

1. In this Agreement words and expressions shall have the same meanings as are respectively assigned to them in the condition of contract referred to.

2. The following documents shall be deemed to form and be read and construed as par of this Agreement, viz.

a. The Bid Formb. Schedule of Requirement and Technical Schedule submitted by the Bidder.

Page 41: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

c. General and Special Condition of Contract.d. The Technical Specificatione. General Arrangement Plan / Drawing No………. dated …….. Code

…………………f. Other correspondence

3. In consideration of the payments to be made by the Purchaser to the Supplier as hereinafter mentioned, the supplier hereby covenants with the Purchaser to provide the Four Self Propelled Split Type Hopper Barges and services and to remedy defects in conformity in all respects with the provision of the Contract.

4. The Purchaser hereby covenants to pay the Supplier in consideration of the provision of the Four Self Propelled Split Type Hopper Barges and services the Contract Price or such other sum as may become payable under the provisions of the Contract at the times and in the manner prescribed by the contract.

IN WITNESS whereof the parties hereto have caused this Agreement to be executed in accordance with the law in force in Pakistan on the day and year first above written.

Signed, sealed and delivered by the

………………………………..

Chairman, Karachi Port Trust

On behalf of the Board of Trustees of

The Port of Karachi.

In the presence of (name of witness)

………………………………..

GENERAL MANAGER (P&D)

KPT

Page 42: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

Trustees of the Board

1. ………………………………(Board’s of Trustees)

2………………………………..

(Board’s of Trustee)

In the presence of ………………………………..

Secretary KPT

Signed by the Supplier Mr………………………(CEO of Firm)

In the presence of (name of witness) Mr……………………………………..

Page 43: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

FORM – “B”

The Chief Accounts Officer

Karachi Port Trust

KPT Head Office Building

Karachi.

PERFORMANCE SECURITY BOND.

To, Karachi Port Trust (name of PURCHASER), WHEREAS ………………………

(name of Builder / Supplier) hereinafter called the Builder / Supplier had undertaken, in pursuance of Contract dated …………for supply of Four Self Propelled Split Type Hoper Barges each of Hopper Capacity 1000 cub.meter hereinafter called “the CONTRACT”

AND WHEREAS it has been stipulated by you in the said CONTRACT that the Builder / Supplier shall furnish you with the Bank Guarantee by a recognized bank for the sum specified therein as security for compliance with the Builder’s performance obligations in accordance with the CONTRACT.

AND WHEREAS we have agreed to give the Builder’s / Supplier’s Guarantee.

THEREFORE we hereby affirm that we are Guarantor and responsible to you, on behalf of the Builder / Supplier, up to a total of ………………………………………

million only) and Guarantee will remain valid for the period for till end of one year Guarantee

Period after delivery of the last vessel as per CONTRACT Clause_____( 18.7) and we undertake to pay you, upon your first written demand declaring the Builder / Supplier to be in default under the contract and without cavil or argument or legalities any sum or sums within the limit (amount of guarantee) aforesaid, without your needing to prove or to show grounds or

Page 44: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

reasons for your demand or the sum specified therein and without questioning the legality of deed.

This guarantee is valid until the ……….. day of ……..months………. year.

Bank Address

……………….

……………….

The Chief Accounts officer , FORM – “C”

Karachi Port Trust,

KPT Head Office Building,

Karachi, Pakistan

ADVANCE PAYMENT GUARANTEE.

Construction and delivery of Four Self Propelled Split Type Hoper Barges each of Hopper Capacity 1000 cub. meter.

WHEREAS the Board of Trustee of the Port of Karachi (hereinafter called the Purchaser) have entered into a CONTRACT with ………… (hereinafter called the BUILDER / SUPPLIER for the above named Four Self Propelled Split Type Hopper Barges.

AND WHEREAS the PURCHASER have agreed to pay the first installment as advance to the

Page 45: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

Builder / Supplier at their request, being an amount of………………………… (………….Million only) to be used by them for the procurement of materials, equipment and outfit for incorporation in and the construction of Hopper Barges.

In the consideration of the KPT making the above installment as advance, we hereby guarantee that the Builder / Supplier M/s…………shall use the amount exclusively for the above purpose, and if they fail or commit default in fulfillment of any of their obligations for which the advance made, we shall be liable to KPT for the payment of the amount in respect of which they have so failed not exceeding the aforementioned sums.

Notice in writing of any default as aforesaid on the part of the BUILDER / SUPPLIER will be given by the PURCHASER and on first demand from the PURCHASER payment shall be made by us for all sums than due from the guarantee without any reference to the BUILDER / SUPPLIER and without questions and legalities whatsoever and that KPT’s verdict in this behalf shall be final and binding on us.

This guarantee shall remain in force till such time the claim for the last installment is lodged by the BUILDER / SUPPLIER and he has furnished the documents for insurance of work in terms of the contract and the advance payment is fully adjusted against the value of the appropriate materials available at the yard of the BUILDER / SUPPLIER exclusively for incorporation in the Four Self Propelled Split Type Hoper Barges each of Hopper Capacity 1000 cub. meter and certified by the Engineer.

In the presence of witness dated this …………of ………. 2015.

Witness: I………………….

Witness II…………………

Bank address

(FORM “D”

MANUFACTURER’S AUTHORIZATION FORM

To………………………………………………………………………………………….

(Name of the Purchaser)

Page 46: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

WHEREAS

……………………………………………………………………………………………

(Name of the Manufacturer/Bidder)

Who are established and reputable manufacturers and are in joint venture with the Bidder / Contractor for Four Self Propelled Split Type Hopper Barges, Karachi Pot Trust – Karachi, ………………………………………………………

(complete Business address of Shipbuilding facility / yard) do hereby undertake and authorize M/s……………………………………………………………

(name and address of Bidder)

to submit a bid, and subsequently negotiate and sign the Contract with you (Purchaser) if their bid is accepted by you for above Four Self Propelled Split Type Hoper Barges each of Hopper Capacity 1000 cub.meter which would be manufactured by us in strict accordance with the Contract Agreement executed between the Purchaser and the Bidder.

We hereby extend our full guarantee and warranty for a period of one year after confirmatory / repeat tests of the Hopper Barges have been carried out in Karachi or as otherwise in accordance with the contract for the machinery, materials, workmanship, design and all other services offered by us.

…………………………………………………………………………………………….

(Name, Designation Stamp and signature on behalf of the Manufacturer / Shipbuilding Yard).

Date:

Place:

Note: This letter of authority should be on the letterhead of the Manufacturer and should be signed by a person competent and having the power of attorney to bind the Manufacturer for his obligations who will also sign the contract between the purchaser (KPT) and supplier / bidder. The Bidder in its bids should include it the above authorization.

Page 47: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

FORM – “E”

The Chief Accounts Officer,

Karachi Port Trust,

KPT Head Office Building,

Karachi - Pakistan

BID SECURITY FORM

Whereas…………. (hereinafter called “the Bidder”) has submitted its bid dated for the supply of Four Self Propelled Split Type Hoper Barges each of Hopper Capacity 1000 cub.meter (hereinafter called “the Bid”).

KNOW ALL MEN BY these presents that

We………… (hereinafter called “the Bank”) having our registered office at …………………………………………………………………………………………….

.are bound unto. The Karachi Port Trust (hereinafter called “the KPT”) in the sum of Pak. Rs.………….for which payment will and truly to be made to the KPT, the Bank binds itself, its successors and assignees by these presents. Sealed with the common seal of the said Bank this …………. Day of …………2015.

Page 48: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

THE CONDITIONS of this obligation are:

After the bid has been opened and if the Bidder:-

a) or his local representative or associate disown his bid or disagree or modifies his Bid by changing the offered specification and terms and conditions as offered in his bid.

b) or his local representative or associate / partner / agent unilaterally contacts KPT during the period of opening of bid till its conclusion or influences the evaluation process in any manner.

c) fails to provide convincingly valid and authenticated documents / evidences for confirmation of claims made therein the bid offer or subsequent commitment.

d) withdraws the bid offer and/or bid security or both before the date of expiry of the bid validity period or extended period.

e) A successful Bidder, fails to:

i) Acknowledge and accept the Letter of Award or refuse to receive the same.

ii) Sign the Contract in accordance with Letter of Award (LOA), / within the stipulated time.

iii) Furnish Performance Security before signing contract agreement, in accordance with the stipulations.

iv) Extend the validity of bid and bid security (if required), after accepting the Letter of Award and its terms and conditions.

Page 49: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

We ………………………………………………………………………………………..

(Name of the Bank)

undertake to pay to the KPT without recourse to the bidder and without questioning the legality of demand, up to the above amount upon receipt of its first written demand, without the KPT having to substantiate its demand, provided that in its demand the KPT will note that the amount claimed by it is due to it owing to the occurrence of one or more of the conditions, specifying the occurred condition or conditions.

This guarantee will remain in force up to seven (07) days more than ……..(date to be mentioned) after the period of bid validity (including the extended period, if any), and any demand in respect thereof should reach the Bank not later than the above date.

……………………….

Seal of the Bank 1. Signature of the Bank’s

official with name and designation.

………………………..

2. Signature of the Bank’s

official with name and

designations

Date:

Page 50: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

FORM – “F”

LIST OF SUB-CONTRACTORS

Following is the list of Sub-Contractors which the Bidder intends to or may employ for items / part of the contract work as mentioned against each for a value limiting to US$ (Pak Rs………………….) SUB-CONTRACTOR complete name and address.

Sub-Contractor(complete name and address)

FIELD OF WORK

Page 51: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

FORM – “G”

PARTICULARS OF LOCAL ASSOCIATED FIRM

Name:

Page 52: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

Address:

Detail of Contract and Authorization available with the Local Firm

SECTION – I

FORM OF BID

Reference No.__________

To,

Page 53: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

The Chairman,

Karachi Port Trust

K.P.T. Head Office Building,

KARACHI – PAKISTAN

SUB:- BID FOR THE CONSTRUCTION AND SUPPLY OF FOUR SELF PROPELLED SPLIT TYPE HOPPER BARGES EACH OF HOPPER CAPACITY OF 1000 M 3

NOTE:- Bidders are requested to fill all the blank space in this Form of Bid and the accompanying Schedule of requirements / BOQ, Appendices etc. included in the set of these documents. Duly filled in, each page signed and stamped Form of Bid shall be integral part of both the Technical and Financial offers. All blank spaces for rates or cost / amount shall remain unfilled in the Technical proposal only.

Dear Sir,

1. Having studied these bid document and checked all local conditions affecting the use of purpose of Four Self Propelled Split Type Hopper Barges and also having carefully studied and examined the contents of the Bidding Documents including the Instructions to Bidders, Conditions of Contract, Specification, Schedule of Requirements, Bills of Quantity and method for the construction and delivery of the above mentioned Four Self Propelled Split Type Hopper Barges, we the undersigned being a company doing business under the name of and address ________________________________________________________________and being duly incorporated under the laws of Pakistan hereby offer to construct, complete, delivery at Karachi to the Karachi Port Trust and guarantee the said Four Self Propelled Split Type Hopper Barges in accordance with the terms and conditions of these bidding documents at (in figures) CIF + Custom duty, Sales Tax and other import charges) – Karachi ………………………….(not to be filled in Technical offer but to be filled in Financial offer only) and (in words) ……………………………………………………………………………………………. and enclose with our bid the bank guarantee / pay order as bid security amounting to US$ 500,000/- in equivalent Pak Rupees in the name of Chief Accounts Officer – KPT.

2. We accept all the above Bidding Documents, including the Schedules attached hereto, as valid and binding, also those parts not countersigned in full by us, but have been submitted with our bid.

Page 54: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

3. We acknowledge that we have satisfied ourselves about these bidding documents the local conditions affecting the design and subsequent operation of the Four Self Propelled Split Type Hopper Barges among others winds, waves, currents. Tidal conditions, environmental & climatic conditions, corrosion conditions, navigational and weather requirements in the areas of Karachi Harbour and adjacent areas, or any other condition(s) which may influence the function of Four Self Propelled Split Type Hopper Barges in these areas and that we cannot raise any claim for not knowing them or else, or due to any inaccuracies in the Bidding Documents or any of them, or any statements made therein or any information given therein or in the subsequent documents and we understand that our bid may be rejected for not knowing the above requirements and use of purpose of the Four Self Propelled Split Type Hopper Barges and to guarantee for one year’s smooth use by rectifying the warranty defects etc.

4. We undertake to carryout such alterations, additions or omissions of the Four Self Propelled Split Type Hopper Barges associated services and provisions as may from time to time be determined and ordered generally at the rates and prices entered by us against each items in the Bill of Quantities / Schedule of requirements and after mutual consent to modify the terms and conditions of contract without change in the contract value and contractual delivery period.

5. We confirm that the rates and prices which we have entered in the Bill of Quantities / Schedules and all information and data attached with our Bids are complete and without implications. They have been duly checked, finalized, and are correct in every respect and are prohibited for future enhancement, till completion of work.

6. We do hereby declare that the Bid is made without any collusion, comparison of figures or arrangement with any other person or persons making a Bid for the Works.

7. We confirm, if our Bid is accepted, that all partners of the joint venture shall be liable jointly and severally for the execution of the Contract and the composition or the constitution of the joint venture shall not be altered without the prior consent of the Employer. (Please delete in case of Bid from a single firm).

8. We confirm that the rates and prices which we have entered in the Bill of Quantities are fixed, unchangeable and firm. Claims for extra payments will be not raised by us till completion of work for variations in wage rates, prices of materials, machinery and equipments, Government‘s Award, decree, imposition of customs duties, taxes (if any) and the like, whatsoever and also due to change by us in the origin / makes / model / material and capacity of any part of the work quoted in our bid.

9. We attach herewith as Bid Security the Bank Guarantee / Pay Order No…………………………… conforming to the Instruction to Bidders, amounting to US$

Page 55: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

500,000/- or equivalent Pakistani Rupees from a Schedule Bank in Pakistan, located in Karachi, except United Bank Ltd. in favour of the Karachi Port Trust, which is valid for a period of seven (07) days beyond the period of validity of Bid. We agree to keep the bid security valid for 127 days and are bound to extend the validity of Pay order we have furnished as our bid security, necessarily before the completion of 127 days starting from the date of opening of Bids, otherwise our bid will be rejected.

10. A certificate attesting the name, signatures and designation of the person who will represent our company and shall correspond on all matters related with this bid and subsequent contract, is enclosed.

11. We further agree to take as binding on us and to abide by this Bid for a period of 120 days from the date of opening of the Bid and it shall remain binding upon us and may be accepted at any time before the expiration of that period.

12. If our bid is accepted by the Employer, we undertake, to furnish Performance Bank Guarantee (as per contract conditions) before signing the Agreement of Contract, within fourteen (14) calendar days after receipt of the written notification of award LOA for accepting our Bid. We further undertake to commence preparatory works, within further twenty eight (28) days after the Letter of Credit has been opened or first payment received, which ever is earlier, and thereafter to expeditiously construct, complete and make ready for two shipments (of Two Self Propelled Split Type Hopper Barges each) to Karachi Port as per contract terms within 21 and 24 months respectively, calculated from the date Employer release the first payment in our favour (for foreign bidders) and to expeditiously construct, complete and make ready for delivery two sets of barges in all respect to the Employer as per contract terms, consisting of Two Self Propelled Split Type Hopper Barge, within 24 & 27 months respectively, calculated from the date the Employer releases the first payment in our favour (for local bidders).

13. We guarantee the trouble free operation of supplied of Four Self Propelled Split Type Hopper Barges for one year after final tests by the Employer in Karachi. We shall depute one each Operation/Nautical Master, Chief Engineer and Maintenance Engineer’s /Technician at each two barges for warranty matters and Training of Employer’s operating crew and maintainers, in a manner that at least 03 persons would be present all time during one year warranty period of all the Four Barges, to complete 54 months for this purpose. We have furnished details of training to be given to the Employer’s personnel and the modus operandi for attending the warranty repairs via ourselves and Karachi based agent / representative.

14. We understand that as soon the validity period of our bid security or bid expires, our bid shall be liable for rejection

15. We also understand that non-compliance to any of the clause(s) of Technical Specification or of any nature to any / or all clauses of these documents shall provide basis to declare our bid as non-responsive.

Page 56: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

16. We accept that the Employer has full right to accept any bid or reject any or all bids without assigning reasons thereof and to annul this bidding process at any stage without any liability. We understand that you are not bound to accept the lowest bid.

17. If our Tender is accepted and the Letter of Award / Intent is issued to us, we agree to pay all costs towards the preparation and submission of 06 sets of Court stamped and legally acceptable contract agreement documents for execution.

18. Unless a formal Contract Agreement is prepared and signed, the Bid submitted by us together with your written acceptance (LOA) thereof, shall constitute a binding contract between us and Employer.

19. We fully understand and agree that you are not bound to accept the lowest or any Bid that you may receive and that the bidding documents constitute equal opportunity, transparency of process and fairly exposed criteria for evaluation of bids, therefore following to the Employer’s evaluation of bids, we shall have no claim of any nature subsequent to the Employer’s decision for Award of work or rejection of bid(s).

Dated this, ………………. Day of ………… 2015

Signature(s) …………………………………………………………………………….(by the person(s) who have signed the pre-qualification application request)

In the capacity of ………………………………………………….……………………….Duly authorized to sign Bid for and on behalf of

……………………………………………………………………… ……………………..(Name and Designation of the Bidder in block capitals)

Address with telephone, fax, and e.mail nos.

Seal …………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………

Tel. No………………..

Fax No………………..

E.mail No…………….

In the presence of:

Witness ……………………………………………………………………………………

Page 57: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

Address:………………………………………………………………………………………………………………………………………………………………………………….

Occupation ………………………………………………………………………………..

Date:………………………………………………………………………………………

SECTION III

GENERAL CONDITIONS OF CONTRACT(G.C)

1. Definitions:

1.1. In the contract (as hereinafter defined) the following words and expression shall have the meanings hereby assigned to them except where the context the requires otherwise:

1.1.1 "Commencement Date" means whichever is the latest of:

Page 58: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

(a) the date specified in the contract as the date the contract comes into effect or the date for commencement of the Works or the date when the Contractor receives:

(b) such payment in advance of the commencement of the Works as may be specified in the terms of payment, or

(c) notice of the issue of any import license necessary for commencing performance of the Contract, or

(d) notice that any legal requirements necessary for the Contract to enter into force have been fulfilled, or

(e) notice that any necessary financial or administrative requirements specified in Section-IV as conditions precedent to commencement have been fulfilled.

1.1.2 “Conditions" means the terms and Conditions of Contract.

1.1.3 “The Contract" means the agreement entered into between the Employer and the Contractor, as recorded in the Contract Form signed by the parties, including all attachments and appendices thereto and all documents incorporated by references therein;

1.1.4 "Contractor" means the person / firm whose tender has been accepted by the Employer and the legal successors in title to the Contractor but not (except with the consent of the employer) any assignee of the Contractor.

1.1.5 "The Contract Price" means the price indicated in the Employer’s Letter of Award placed on for the full and proper performance of Contractor’s contractual obligations for supply of goods and service.

Page 59: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

1.1.6 "Contractor's Drawings' means all drawings, samples, patterns, models and operation and maintenance manuals to be submitted by the Contractor.

1.1.7 "Employer" means the Organization purchasing the Goods; in this case the Board of Trustees of Karachi Port Trust (KPT) is the Employer. General Manager of Planning and Development Division – KPT shall represent the Employer for all correspondence with the Contractor.

1.1.8 "Engineer” means a supervision firm or person(s) appointed by the Employer within the scope of this Contract or their successors to act in that capacity.

1.1.9 "Foreign Currency" means a currency of a country other than that in which Plant is to be employed.

1.1.10 “Goods” means all of the equipment, machinery, and/or other materials which the Contractor is required to supply to the Employer under the Contract.

1.1.11 "Letter of Award" means the formal acceptance by the Employer of the bid incorporating any adjustments or variations to the bid agreed between the Employer and the Contractor.

1.1.12 "Performance Security" means the security to be provided by the Contractor for the due performance of the Contract.

1.1.13 "Schedule of Prices" means the item wise price filled in the Schedule of Prices, or any part or individual schedule thereof, submitted by the Contractor with his bid and forming a part of the Contract documents.

1.1.14 "Services" means services ancillary to the supply of the Goods, such as transportation and insurance, registration and any other incidental services, such as warranty obligation, commissioning, provision or technical assistance, training

Page 60: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

and other such obligations of the Contractor covered under the Contract.

1.1.15 "Specification" means the specification of the Works included in the Contract and any modification thereof made in accordance with Clause IB.23.

1.1.16 “Sub Contractor" means any person (other than the Contractor) named in the Contract for any part of the Works, or any person to whom any part of the Contract has been subcontracted with the consent of the Employer / Engineer, and the Sub Contractor's legal successors in title but not any assignee of the Sub Contractor.

1.1.17 "Time for Completion" means the time stated in the contract for completing the Works or any Section thereof and passing the Tests on Completion calculated from the Commencement Date unless extended.

1.1.18 "Variation Order" means any written order, identified as such issued to the Contractor by the Engineer under Clause 22.

2. Application:

These General Conditions shall apply to the extent that provisions in other part of the Contract do not supersede them.

2.1 Headings and Titles:

The headings and titles in these Conditions shall not be deemed part thereof or be taken into consideration in the interpretation or construction of the Contract.

2.2 Interpretation:

Page 61: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

Words importing persons or parties shall include firms and corporations and any organization having legal capacity.

Words importing the singular only also include the plural and vice versa where the context requires.

2.3 Written Communications:

Wherever in the contract provision is made for a communication to be "written" or "in writing” this means any hand-written, type-written or printed communication, including telex, cable and facsimile transmission.

2.4 Notices, Consents and Approvals:

Wherever in the Contract provision is made for the giving of notice, consent or approval by any person, such consent or approval shall not be unreasonably withheld. Unless otherwise specified, such notice, consent or approval shall be in writing and the word "notify" shall be construed accordingly.

2.5 Costs, Overhead Charges and Profit:

Whenever by these Conditions the Contractor is entitled to be paid cost, such cost shall be properly incurred and shall include any overhead charges properly allocable thereto but not profit unless so stated.

2.6 Periods:

In these Conditions "days" means calendar day and "year" means 365 days.

Page 62: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

3. Country of Origin:

3.1 All Goods and Services supplied under the Contract shall have their origin in the acceptable countries.

3.2 For purposes of this Clause "origin" means the place where the Goods were mined, grown or produced, or from which the Services are supplied. Goods are produced, through manufacturing, processing or and major assembling of components a commercially recognized new product results that is substantially different in basic characteristics or in purpose or utility from its components.

3.3 The origin of Goods and Services is distinct from the nationality of the Contractor.

4. Standards:

4.1 The Goods and service supplied under this Contract shall conform to the standards mentioned in the Instructions to Bidders and Technical Specifications and, when no applicable standard is mentioned, to the authoritative standard appropriate to the Good’s country of origin and such standards shall be the latest issued by the concerned institution / the classification society and accepted by the Engineer.

5. Contract Documents-Confidentiality:

5.1 The Contractor shall not, without the Employer's prior written consent, disclose the Contract, or any provision thereof, or any specification, plan, drawing, pattern, sample or information furnished by or on behalf of the Employer in connection therewith, to any person other than a person employed by the

Page 63: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

Contractor in the performance of the Contract. Disclosure to any such employed person shall be made in confidence and shall extend only so far as may be necessary for purposes of such performance.

5.2 The Contractor shall not, without the Employer's prior written consent, make use of any document or information enumerated in para 5.1 except for purposes of performing the Contract.

5.3 Any document, other than the Contract itself, enumerated in para 5.1 shall remain the property of the Employer and shall be returned (in all copies) to the Employer on completion of the Contractor's performance under the Contract if so required by the Employer.

6. Patent Rights:

6.1 The Contractor shall indemnify the Employer against all third-party claims of infringement of patent, trademark or industrial design rights arising from use of the Goods or any part thereof in Pakistan and shall be taking care of all issues related with patent rights of all goods, components, material design etc used in the Four Split Hopper Bares supplied by the Contractor to Employer.

7. Performance Security:

7.1After the written notification of award has been placed by the Employer on Contractor, the Contractor shall furnish Performance Security to the Employer in

Page 64: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

the amount equivalent to 10% of contract price mentioned in the above notification of award within 14 days and necessarily before signing the Contract Agreement.

7.2The proceeds of the performance security shall be payable for full value or part thereof to the Employer as against the Contractor's failure to the agreed terms or to perform in accordance with the contract.

7.3The performance security shall be in the currency of the Employer’s country (Pak. Rupees) and shall be in the form of a bank guarantee provided in the Bidding Documents (Form-B), issued by a + A1 ranking / first class scheduled bank located in Karachi – Pakistan except United Bank Ltd.

7.4The performance security will be discharged by the Employer and returned to the Contractor not later than 07 days after the date of completion of the one year guarantee period of Four Split Hopper Barges.

8. Engineer and Engineer's Representative:

8.1 Engineer's Duties:

The Engineer shall carry out the duties specified in the Contract.

If the Engineer is required, under the terms of his appointment by the Employer, to obtain the specific approval of the Employer before carrying out any of these duties, full particulars of such requirements shall be set out in Section-IV Special Conditions of Contract.

Except as expressly stated in the Contract the Engineer shall have no authority to relieve the Contractor of any of his obligations under the Contract.

8.2 Engineer's Representative:

Page 65: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

The Engineer's Representative shall be appointed by and be responsible to the Engineer and shall only carry out such duties and exercise such authority as may be delegated to him by the Engineer under Sub-Clause 8.3.

8.3 Engineer's Power to Delegate:

The Engineer may from time to time delegate to the Engineer's Representative any of the duties vested in the Engineer and may at any time revoke such delegation.

Any such delegation or revocation shall be in writing and shall not take effect until a copy thereof has been delivered to the Contractor and the Employer.

Any decision, instruction or approval given by the Engineer's Representative to the Contractor in accordance with such delegation shall have the same effect as though it had been given by the Engineer. However:

(a) any failure of the Engineer's Representative to disapprove any Plant or workmanship shall not prejudice the right of the Engineer to disapprove such Plant or workmanship and to give instructions for the rectification thereof;

(b) if the Contractor questions any decision or instruction of the Engineer's Representative he may refer the matter to the Engineer who shall confirm, reverse or vary such decision or instruction.

8.4 Engineer to Act Impartially:

Wherever under the Contract the Engineer is required to exercise his discretion by:

Page 66: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

(a) giving his decision, opinion or consent. or

(b) expressing his satisfaction or approval, or

(c) determining value, or

(d) otherwise taking action which may affect the rights and obligations of the Employer or the Contractor, he shall exercise such discretion impartially within the terms of the Contract and having regard to all the circumstances.

8.5 Engineer's Decisions and Instructions:

The Contractor shall proceed with the decisions and instructions given by the Engineer in accordance with these Conditions.

8.6 Confirmation in Writing:

The Contractor may require the Engineer to confirm in writing any decision or instruction of the Engineer which is not in writing. The Contractor shall notify the Engineer of such requirement without undue delay. Such a decision or instruction shall not be effective until written confirmation thereof has been received by the Contractor.

8.7 Disputing Engineer's Decisions and Instructions:

If the Contractor disputes or questions any decision or instruction under Clause 8.5 or a written confirmation under Clause 8.6, he shall give notice to the Engineer within 28 days after receipt thereof, giving his reasons.

Page 67: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

The Engineer shall within a further period of 28 days by notice to the Contractor and the Employer with reasons, confirm, reverse or vary such decision.

9 Inspections and Tests:

9.1 The Employer or the Engineer or their representative shall have the access and right to inspect and to test the materials / Goods to confirm their conformity to the Contract / acceptable standard and to his approval. The Conditions of Contract and/or the Technical Specifications shall specify what inspections and tests the Engineer / Employer requires and where they are to be conducted. Depending upon the stages of construction and progress of work similar instructions for tests / repeat tests may also be issued by the Engineer / Employer. During the time period starting from the commencement of work till such time the Four Split Hopper Barges are ready to sail (for foreign bidders) or ready for delivery (for local bidder). The Employer shall notify the Contractor in writing of the identity of representatives retained for these purposes.

9.2 The preliminary inspections and tests may be conducted on the premises of the Contractor or its sub-contractor(s). at point of delivery and / or at the Good’s final destination. All reasonable facilities and assistance including access to drawing and production data shall be furnished by the Contractor to the inspectors at no charge to the Employer or his representative.

9.3 Should any inspected or tested Goods fail to conform to the Specifications / Engineer’s approval, the Engineer / Employer may reject them and the Contractor shall either replace the rejected Goods or make all alterations necessary to meet specification requirements free of cost, after approval by the inspector.

9.4 The Employer's right to inspect, test and, where necessary, reject the Goods after the Good's arrival in Pakistan shall in no way be limited or waived till such time the Employer issues the “Certificate of Due Performance” in terms of clause 9.1 and by reason of the Goods having previously been inspected, tested and

Page 68: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

passed by the Employer or its representative prior to the Goods' shipment from the country of origin.

9.5 Nothing in under this Clause shall in no way release the Contractor from any warranty or other obligations under this Contract. All cost incurred in carrying out the inspections, tests and trials including repeated inspection, test and trials and all cost for boarding, lodging and travel etc. of the inspector(s) and other representatives of Employer shall be for the account of Contractor..

10. Tests on Completion:

10.1 Notice of Tests

The Employer shall give to the Engineer 21 day's notice of the date after which he will be ready to make the Tests on Completion (the Tests). Unless otherwise agreed, the Tests shall take place within 14 days after the said date on such day or days as the Engineer shall notify the Contractor.

10.2 Time for Tests:

If the Engineer fails to appoint a time after having been asked to do so, or does not attend at the time and place appointed, the Contractor shall be entitled to proceed with the Test in his absence. The Test shall then be deemed to have been made in the presence of the Engineer and the results of the Tests shall be accepted as accurate.

10.3 Delayed Test:

If the Tests are being unduly delayed by the Contractor the Engineer may by notice require the Contractor to make the Tests within 21 days after the receipt of such notice. The Contractor shall make the Tests on such days within that period

Page 69: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

as the Contractor may fix and of which he shall give notice to the Engineer.

10.4 Retesting:

If the Works or any Section fails to pass the Tests, the Engineer or the Contractor may require such Tests to be repeated on the same terms and conditions, until proven satisfactory.

10.5 Consequences of Failure to Pass Tests on Completion.

If the Works or any section fails to pass the Tests on the repetition thereof as above, the Engineer, after due consultation with the Employer and the Engineer, after due consultation with the Employer and the Contractor, shall be entitled to:

a) Order one further repetition of the Tests under the conditions of Sub-clause 10.4, or

b) Reject the Works or section, or

c) Issue as Taking-Over Certificate, if the Employer so wishes, notwithstanding that the Works are not complete. The Contract Price shall then be reduced by such amount as may be agreed by the Employer and the contactor.

10.6 Test Certificate:

As soon as the Works or any Section thereof has passed the Tests, the Engineer shall issue a Certificate to the Contractor and the Employer to that effect.

11. Taking Over

Page 70: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

11.1 Taking over :

The Works shall be taken over by the Employer when they have been completed in accordance with the Contract, except in minor respects that do not affect the use of the Works for their intended purpose, have passed the Tests on Completion and a Taking-Over Certificate has been issued or deemed to have been issued.

11.2 Taking-Over Certificate:

The Contractor may apply by notice to the Engineer for a Taking-Over Certificate not earlier than 14 days before the Works will in the Contractor's opinion be complete and ready for taking over.

The Engineer shall within 28 days after the receipt of the Contractor's application either:

(a) issue the Taking-Over Certificate to the Contractor with a copy to the Employer stating the date on which the Works were complete and ready for taking over, or

(b) reject the application giving his reasons and specifying the work required to be done by the Contractor to enable the taking over certificate to be issued.

If the Engineer fails either to issue the Taking Over Certificate or to reject the Contractor’s application within the period of 28 days he shall be deemed to have issued the Taking Over Certificate on the last day of that period.

11.3 Further Test on completion:

Page 71: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

If the replacement or renewals are such that they may affect the performance of the Works the Engineer / Employer may request that Tests on Completion be repeated to the extent necessary. The request shall be made by notice within 28 days after the replacement or renewal. The Tests shall be carried out.

12 Packing:

12.1 The Contractor shall provide such packing of the Goods as is required to prevent their damage or deterioration during transit to their final destination as indicated in the Contract. The packing shall be sufficient to withstand, without limitation, rough handling during transit and exposure transit and exposure to extreme temperatures, salt and precipitation during transit and open storage. Packing case size and weights shall take into consideration, where appropriate, the remoteness of the Goods' final destination and the absence of heavy handling facilities at all points in transit. Employer shall retain all packing accessories.

13. Delivery and Documents:

13.1 Delivery of the Goods shall be made by the Contractor in accordance with the terms specified by the Employer in its Schedule of Requirements and the Special Conditions of Contract and delivery of documents, drawings, manuals etc. pursuant to clause 8.10 of Special Condition of Contract, in numbers or sets as may be specified by the Employer (but not more than six) shall be supplied by the Contractor.

13.2 For purposes of the Contract, “FOB” "C&F.", “CIF” and other trade terms used to describe the obligations of the parties shall have the meanings assigned to them by the current edition of the International Rules for the Interpretation of the Trade Terms published by the International Chamber of Commerce, Paris, and commonly referred to as INCOTERMS.

14. Insurance:

Page 72: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

14.1 Consolidated insurance for all contracted goods i.e Four Self Propelled Type Hopper Barges and accessories is mandatory. The insurance for full cover shall be effective for a period starting from the date of loading claim for 2 nd payment till such time the claim for the last payment is Lodged by the Foreign Contractor and by the Local Contractor till such time the one year warranty period of last delivered Barge is started. The Insurance shall be for the ‘Insurance of Work of construction and supply of Four Self Propelled Type Hopper Barges. All premiums shall be for the Contractor’s account. Insurance Policy shall be in joint names of Employer, and Contractor.

15. Transportation:

15.1 The Contractor is required to deliver all the Goods at the Karachi Port. Therefore, putting the Goods on board the vessels at specified port of loading to make the arrangements for safe transportation of offer of Four Self Propelled Type Hopper Barges and accessories shall be responsibility of Contractor. Accordingly, he shall arrange all clearances and compliance of Rules including voyage insurance fee and other charges etc. for safe transportation of Four Self Propelled Type Hopper Barges and accessories to Karachi. All cost thereof shall be included in the Contract Price / DDP cost (with separate mention of freight cost). Such prices shall include all marine transportation cost including ocean freight, the Voyage insurance and other charges etc. The transportation of Four Self Propelled Type Hopper Barges shall not be under self propulsion

15.2 The Contractor shall arrange on behalf of the Employer for ocean transportation via national flag carriers of Pakistan. The Contractor may arrange for such transportation on alternative carriers if the Pakistani flag carriers are not available to transport the Goods within the time period specified in the Contract and necessary no objection from Pakistani flag carriers / company has been obtained by the Contractor, if so required.

16. Incidental Services:

16.1 The Contractor shall provide the following services:

Page 73: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

(a) Performance and supervision of on site assembly, conductance of all functional tests and trials at Builder’s works and in Karachi and demonstration of specified performance of Four Split Hopper Barges.

(b) Furnishing of tools required for assembly and maintenance of the supplied Goods and touch up paints;

(c) Furnishing of a detailed operations and maintenance manual and spare parts catalogues with code number for each part of each appropriate unit of the supplied Goods and relevant documents comprising as built drawing, certificates, guarantees, inspection and test reports, undertakings etc as specified in the special condition of contract or other relevant documents pertaining to the supplied goods, as required by Employer during the contract execution period.

(d) To comply the guarantee obligations for the purpose of operational continuity of the Four Split Hopper Barges during the one year guarantee period the Contractor may acquire the services for repairs including docking if so required / parts from within the local resources or agents of manufacturer’s of installed equipment by allocating sufficient provision all inclusive in the bid price.

(e) Performance for guarantee obligations by providing guarantee master, guarantee engineer and technician and on the job training to Employer’s staff for guidance of operation and maintenance, one bottom inspection or survey by Class approved diver of each barge till the end of guarantee period on the extended period of guarantee of the last barge, if any.

16.2 Prices charged by the Contractor for the preceding incidental services and provisions taking care during the period Four Split Hopper Barges has arrived in Karachi or ready for ex-yard delivery by local bidder till completion of one year warranty period shall be included in the Bid Price (fixed CIF Cost by foreign bidder and fixed ex-yard cost by local bidder).

17. Spare Parts:

Page 74: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

17.1 As specified in the schedule of requirements, the Contractor shall provide and put on board Four Split Hopper Barges for delivery at Karachi Port with the following spare parts and tools along with the list of each. The cost shall be included in the bid price,

(a) Spare Parts received from the Original Equipment Manufacturers (OEMs) for all the Machinery(s) / equipment free of cost.

(b) Spare Parts as may be recommended by the Classification Society under whose Rules the Four Split Hopper Barges have been constructed, free of cost.

(c) Manufacturer’s supplied Tools, accessories and gauges etc and “special tools for all machinery / equipment and the same to be according to the manuals to be supplied free of cost.

(d) Spare parts to be supplied as under:-

i. “Spare parts for two top end overhauls and one major overhaul (list with item wise price to be providing for each) of:

a) Two Main Engines

b) Two Auxiliary Engines (Main Generator)

c) One Harbour Engine.

ii. Spare parts for hydraulic installation including splitting cylinders for 4500 splitting operations (list with item wise price to be provided).

iii. Hopper Seals sufficient for Two complete renewal (list with item wise price to be provided).

Page 75: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

iv. Spare parts for other auxiliary machinery (i.e pumps, purifiers etc) in Engine room, steering gear, air-conditioning and deck machinery for one complete Overhaul.

(e) Consumable spare such as Filters, Gaskets, Fuses, Seals, Packing, O’ rings, washers, belts, hoses, ICs etc. or any other consumable spare the Contractor may consider necessary to be put on board, each sufficient for one year operation of Four Split Hopper Barges.

Note: All lists under (d) and (e) require approval of OEM.

18. Warranty:

18.1 The Contractor warrants that the goods supplied under the contract are new, unused, of the most recent or current models and incorporate all recent improvements in design and materials unless provided otherwise in the Contract. The contractor further warrants that the goods supplied under this contract shall have no defect arising from design, materials and workmanship or from any act or omission of the Contractor that may develop under normal use of the supplied goods in the environmental and operational conditions prevailing in Karachi Harbour.

18.2 The warranty shall remain valid for 12 months respectively for each barge after the date of conducting the Acceptance / repeat trials in Karachi for all the Goods, or any portion thereof as the case may be. The warranty shall be for any defect arising due to omission in design or bad / faulty materials or due to bad workmanship during manufacturing or due to short supply of component of system / units for its consolidated working, will be rectified by the bidder / Contractor at its own cost provided the defect has been reported to the Contractor within 72 hours of its occurrence and has not developed as a result of wrong handling of Four Split Hopper Barges or its components or use/operation of the same by unqualified/inexperienced operators or due to mishap or non adherence to the OEM’s recommended / Planned Maintenance Schedule of the

Page 76: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

installed units/sub-assemblies or systems etc. Defects due to Mishandling by the Contractor’s personnel on board shall be remedied as warranty. In case of dispute the Engineer’s opinion shall be final and binding on both parties. In this event the consultancy cost shall be for the account of the Bidder / Contractor.

18.3 The Employer shall not later than 72 hours notify the Contractor in writing of any claims arising under this warranty.

18.4 Upon receipt of such notice, the Contractor shall, with all reasonable speed, repair or replace the defective parts / units/sub-assemblies or Goods etc thereof, without costs (other than the local charges for Custom Clearance, for foreign bidder and not local bidder) to the Employer ensuring to retrieve the operational / workability status of Four Split Hopper Barges.

18.5 After the Contractor, having been notified of warranty defect, fails to undertake the remedial action of the defect(s), the Employer after a reasonable period of 144 hrs. To take such remedial action as may be necessary to retrieve the operational / workability status of Four Split Hopper Barges at the Contractor's risk and expense which would be compensated from any dues payable to the Contractor or from Performance Guarantee.

19. Payment:

19..1 The method and conditions of payment to be made to the Contractor under the Contract shall be specified in the Special Conditions of Contract.

19.2 Unless otherwise specified in Special Conditions of Contract, applications by the Contractor for payment shall be made to the Engineer as follows:-

(a) The Contractor’s request(s) for payment shall be made to the Employer through Engineer in writing, accompanied by an invoice describing completion of all obligations for the stage payment, as appropriate, supported by certificates and other documents, submitted pursuant to Clause 13 of Special Condition of Contract and upon fulfillment of other obligations stipulated in the contract.

Page 77: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

(b) In respect of Plant shipped and en route to destination, identifying the plant concerned and accompanied by each evidence of shipment and payment of freight and insurance and by such other documents as the Engineer may require, and

(c) For additional payment claim to be made in accordance with Clause 20.

(d) Any other application for payment shall state the amounts claimed and the detailed particulars in respect of which the application is made.

19.3 Payments shall be made promptly by the Employer within thirty (30) days, after submission of an orderly / acceptable invoice / claim by the Contractor.

19.4 Payment will be made only in local currency (Pak Rupees).

19.5 Issue of Certificate of Payment:

Within 14 days after receiving an application for payment which the Contractor was entitled to make the Engineer shall issue a certificate of payment to the Employer showing the amount due, with a copy to the Contractor.

A certificate of payment, other than the Final Certificate of Payment, shall not be withheld on account of:

a) defects of a minor character which are not such as to affect the use of the Works, or

b) any part of the payment applied for being disputed. In such case a certificate of payment for the undisputed amount shall be issued.

19.6 Corrections to Certificates of Payment:

Page 78: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

The Engineer may in any certificate of payment make any correction or modification that should properly be made in respect of any previous certificate.

19.7 Application for Final Certificate of Payment:

The application for the Final Certificate of Payment shall be accompanied by a final account prepared by the Contractor. The final account shall give full details of the valued of all plant supplied and work done under the contract together with:

(a) such additions to or deductions from the Contract Price as have been agreed, and

(b) all claims for additional payment to which the Contractor may consider himself entitled.

19.8 Final Certificate of Payment Conclusive:

A Final Certificate of Payment shall conclusive evidence of the value of the Works, that the Works are in accordance with the Contract and that the Contractor has performed all his obligations under the contract.

Payment of the amount certified in the Final Certificate of Payment shall be conclusive evidence that the Employer has performed all his obligations under the contract.

A Final Certificate of Payment or payment shall not be conclusive.

(a) to the extent that fraud or dishonesty relates to or affects any matter dealt with in the certificate, or

Page 79: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

(b) if any arbitration or court proceedings under the Contract have commenced by either party before the expiry of 84 days after the issue of the Final Certificate of Payment.

20. Claims :

20.1 Procedure

In any case where under these conditions there are circumstances which the contractor considers himself entitled to claim additional payment, the contractor shall:

(a) If he intends to make any claim for additional payment shall give to the Engineer notice within 28 days of his intention to make such claim after the said circumstances became known to the contractor stating the reasons for his claim, and

(b) As soon as reasonably practical after the date of such notice submit to the Engineer full and detailed particulars of his claim but not later than 182 days after such notice unless otherwise agree by the Engineer. In any event such particulars shall be submitted no later than the application for the Final Certificate of Payment. The Contractor shall thereafter promptly submit such further particulars as the Engineer may reasonably require to assess the validity of the claim.

21. Prices:

Page 80: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

21.1 Prices charged by the Contractor for Goods delivered and Services performed under the Contract shall not, with the exception of any price adjustments authorized by the Special Conditions of Contract, vary from the prices quoted by the Contractor in its bid.

22. Variations Order:

22.1 The Employer may at any time during the period of commencement of work till start of the one year warranty period, by a written order(s) of value limiting to the 15% of the contract price, given to the Contractor make changes for alteration, addition and/or omission in the general scope of the work under the Contract and the Contractor shall un-necessarily not decline for modification for:

(a) The Goods to be supplied, Specifications and Accessories, Provisions and Services etc.

(b) Method of shipment etc.

22.2 If any such change causes an increase or decrease in the cost of, or the time required for, the Contractor's performance of any part of the work under the Contract, whether changed or not changed by the order and for unforeseen reasons, an equitable adjustment shall be made in the Contract Price for additions, omissions by either party and consequent adjustment in the Delivery schedule, subject to the approvals by the Employer.

22.3 The Employer shall not be liable to any extra cost on account of following:-

(a) The Contractor shall ensure availability of equipment (of the makes, model, size, capacity etc) / service / provisions according to the terms and conditions and specification which the contractor has offered in his bid or before signing the contract and shall bear the entire excess amount etc. if any, in case of his subsequent request due to his limitations and reasons beyond his control for any changes, alterations, additions, omissions and modifications in the offer / contractor’s bid (Technical offer only) provided the proposed change for compatible and / or equivalent provision and

Page 81: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

reasons thereof are accepted by the Engineer / Employer and the same is un-necessarily not delayed or refused.

(b) The Employer shall not bear any expenses which the contractor may ask in addition to the contract price imposed on him due to decree, interruptions in the execution of contract due to internal / local / domestic reasons (excluding force majeure) such as labour / industrial unrest, discontinuation of power supply, etc.

(c) The Employer shall not ask Contractor for his service beyond the contract provision without cost and time adjustments if so necessary and without placing of Variation Order as per terms of these documents. The Contractor shall have full right to withdraw the extra / left over materials than the contractual requirement, consumable or other items, loose or compact materials, tools, spares etc. from For split Hopper Barges) after the start of warranty period. The Employer if so intend to or utilizes the left over materials shall pay to the Contractor the cost as per vouchers to be furnished by the Contractor.

22.4 Variation Order Procedure:

(a) The Engineer may by Variation Order to the Contractor at any time before the Works are taken over, instruct the Contractor to alter, amend, omit, add to or otherwise vary as explained above.

(c) The Contractor shall not vary or alter any of the Works, except in accordance with a Variation Order from the Engineer. The Contractor may, however, at any time propose variations of the Works to the Engineer.

© After having received Variation Order the Contractor shall submit to the Engineer.

(I) a description of work, if any, to be performed and a program for its execution, and

Page 82: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

(II) the Contractor's proposals for any necessary modifications in the schedule of construction or to any of the Contractor’s obligations under the Contract, and

(III) the Contractor's proposals for adjustment to the Contract Price.

22.5 Following the receipt of the Contractor's submission the Engineer shall, after due consultation with the Employer and the Contractor, decide as soon as possible whether or not the variation shall be carried out.

22.6 If the Engineer decides that the variation shall be carried out, he shall issue a Variation Order clearly identified as such in accordance with the Contractor's submission or as modified by agreement. If the Engineer and the Contractor are unable to agree the adjustment of the Contract Price, the provisions of following Clause shall apply

22.7 Disagreement on Adjustment of the Contract Price:

If the Contractor and the Engineer are unable to agree on the adjustment of the Contract Price, the adjustment shall be determined in accordance with the rates specified in the Schedule of Prices.

If the rates contained in the Schedule of Price are not directly applicable to the specific work in question, suitable rates shall be established by the Engineer reflecting the level of pricing in the Schedule of Prices

Where rates are not contained in the said Schedule, the amount greed shall be based on documentary evidence.. Due account shall be taken of any overheads by the Contractor in consequence of the variation.

The Contractor shall also be entitled to be paid.

Page 83: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

(a) the cost of any partial execution of the Works rendered useless by any such variation, and

(b) the cost of making necessary alterations to Plant already manufactured / or any work done that has to be altered in consequence of such a variation, and

(c) any additional costs incurred by the Contractor by the disruption of the progress of the Works as detailed in the program, and

(d) the net effect of the Contractor's finance costs, including interest, caused by the variation.

The Engineer shall on this basis determine the rates or prices to enable on-account payment to be included in certificates of payment.

22.8 Contractor to Proceed:

On receipt of a Variation Order, the Contractor shall forthwith proceed to carry out the variation and be bound to these Conditions in so doing as if such variation was stated in the Contract.

The work shall not be delayed pending the granting of an extension of the Time for Completion or an adjustment to the Contract Price

22.9 Record of Costs:

In any case where the Contractor is instructed to proceed with variation prior to the determination of the adjustment to the Contract Price in respect thereof the Contractor shall keep records of the cost of undertaking the variation and of time

Page 84: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

spent thereon. Such records shall be open to inspection by the Engineer at all reasonable times.

23. Contract Amendments and annulment: :

23.1 Subject to Clause 22, no variation in or modification of the terms of the Contract shall be made except by written amendment by the Employer / Engineer. 19.2

23.2 The contract between the Contractor and the Employer shall be considered ineffective for all purpose and provisions 14 days after the one year warranty period of delivered vessels has been completed.

24. Assignment:

24.1 The Contractor shall not assign, in whole or in part, it’s obligations to perform under the contract, except with the Engineer’s / Employer’s prior written consent.

25. Sub-Contracting:

25.1 The contractor shall not sub-contract whole of the works.

25.2 The contractor shall notify the Engineer / Employer in writing of all sub-contracts awarded under the contract if not already specified in his bid. Such notification, in his original bid or later, shall not relieve the contractor from any liability or obligation under the contract for supply of tendered item complete in all respect in accordance with the general requirement and Rules etc. to ensure use of purpose of the tendered items.

Page 85: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

25.3 The contractor shall however, not require such consent for purchases of materials or to place contracts for minor details or for any part of the works of which the manufacturer or contractor is named in the contract.

25.4 Sub-contractors must comply with the provisions of all clauses and will be bound to perform in a manner the Contractor had to perform and will not authorize to raise claim of their performance with the Employer.

26. Delays in the Contractor’s Performance:

26.1 Delivery of the Goods and performance of Services shall be made by the Contractor in accordance with Conditions of Contract and Schedule of Requirement.

26.2 An unexcused delay by the contractor in the performance of its delivery obligations shall render the contractor liable to any or all of the following, sanctions, forfeiture of its performance security, imposition of liquidated damages, holding up of due payment and / or termination of the contract for default.

26.3 If any time during performance of the contract, the contractor or its sub-contractor(s) should encounter conditions impeding timely delivery of the Goods and performance of services, the Contractor shall promptly notify the Employer in writing of the fact of the delay, it’s likely duration, its cause(s) and methodology for removal of causes, as soon as practicable. After receipt of the Contractor’s notice, the Employer shall evaluate the situation and may extend the contractor’s time for performance.

27. Liquidated Damages:

27.1 If the Contractor fails to deliver any or all of the Goods or perform the Services within the time period specified in the Contract, the Employer shall, without

Page 86: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

prejudice to its other remedies under the Contract, deduct from the Contract Price, as liquidated damages, a sum as specified in the Special Conditions of Contract. Once the delays accrue to build the maximum of liquidated damages, the Employer may invoke forfeiture or termination of the Contract or may consider limited extension etc.

Liquidated damages may also be imposed in the event of non-performance or non-compliance of the clauses of contract, up to a reasonable sum calculated by the Engineer and accepted by the Contractor in whole or in part (it would be supported with relevant evidences and rationales).

28. Termination for Default :

28.1 The Employer may, without prejudice to any other remedy for breach of contract, by written notice of default sent to the Contractor, terminate the Contract in whole or in part:

(a) if the Contractor fails to deliver any or all of the Goods within the time period specified in the Contract, or any extension thereof granted by the Employer pursuant to Clause 26 or

(b) if the Contractor fails to perform any other obligation(s) under the Contract.

28.2 In the event the Employer terminates the Contract in whole or in part, pursuant to para 28.1, the Employer at the risk and cost of Contractor may procure, such

Page 87: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

terms and in such manner, as it deems appropriate, Goods and services similar to those undelivered, and the Contractor shall be liable to compensate the Employer for any excess costs for such similar Goods and service. However, the Contractor shall continue performance of the Contract to the extent not terminated.

29. Force Majeure :

29.1 The Contractor shall not be liable for forfeiture of Contractor’s performance security /other dues, imposition of liquidated damages or termination for default, if and to the extent that, its delay in performance or other failure to perform its obligations under the Contract as a result of an event of Force Majeure. As a result of an event of Force Majeure in the city of Karachi-Pakistan or Karachi Harbour, it would be equally applicable to Employer for his obligations/performance under the contract provisions.

29.2 For purposes of this clause, "Force Majeure" means an act of the Good and an event beyond the control of the Contractor and Employer and not involving the Contractor's or Employer’s fault or negligence and not foreseeable. Such events of extreme hindrances may include, but are not restricted to, acts either in its sovereign or contractual capacity, wars or revolutions, fires, floods, epidemics, quarantine, earth-quakes, storms, extremely bad weather, erupted disease, restrictions and freight embargoes.

29.3 If a Force Majeure situation arises, the Contractor shall promptly notify within seven (7) days to the Employer in writing of such condition and the cause thereof, otherwise a Force Majeure claim by the Contractor shall not be acceptable to the Employer. Unless otherwise directed by the Employer in writing, the Contractor shall continue to perform its obligations under the Contract as far as is reasonably practical, and shall seek all reasonable alternative means for performance not prevented by the Force Majeure event.

30. Termination for Insolvency:

Page 88: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

30.1 The Employer, may at any time terminate the Contract by giving written notice to the Contractor, without compensation to the Contractor, if the Contractor becomes bankrupt or otherwise insolvent, provided that such termination will not prejudice or affect any right of action or remedy which has accrued or will accrue thereafter to the employer. In the event of termination for insolvency all materials, goods etc. and completed work lying at Contractor’s yard or custody, shall become the sole property of Employer, all monies due and securities shall be forfeited and the Employer shall not be liable for performance of his obligation.

31. Termination for Convenience:

31.1 The Employer, may by written notice sent to the Contractor, terminate the Contract, in whole or in part, at any time for its convenience. The notice of termination shall specify that termination is for the Employer's convenience, the extent to which performance of work under the Contract is terminated, and the date upon which such termination becomes effective:-

The Goods that are complete and have been booked for shipment within 15 days after the Contractor's receipt of notice of termination shall be purchased by the Employer at the Contract terms and prices. For the remaining Goods, the Employer may elect:

(a) to have any portion completed and delivered at the Contract terms and prices; and/or

(b) to cancel the remainder and pay to the Contractor an agreed amount for partially completed Goods and for materials and parts previously procured by the Contractor.

32. Resolution of Disputes:

Page 89: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

32.1 The Employer and the Contractor shall make every effort to amicably resolve by direct informal negotiation any disagreement or dispute arising between them under or in connection with the Contract including the notice for termination, if any, for their withdrawal after an understanding, to be recorded.

32.2 If, after forty five (45) days from the commencement of such informal negotiations, the Employer and the Contractor have been unable to resolve amicably a Contract dispute, either party may require that the dispute be referred for resolution to the formal mechanisms specified in the Special Conditions of Contract. These mechanisms may include, but are not restricted to, conciliation mediated by a third party. The mechanism shall be specified in the Special Conditions of Contract.

33. Governing Language:

33.1 The bid and Contract shall be written in English language. All correspondence and other documents pertaining to the Bid/Contract that are exchanged by the parties shall be written and accepted only in English language.

34. Applicable Law:

34.1 The Contract shall be interpreted / executed in accordance only with the prevailing laws of Pakistan and relevant / SRO’s.

35. Notices:

35.1 Any notice given by one party to the other pursuant to the Contract shall be sent in writing or by fax and confirmed / acknowledged in writing to the address specified for that purpose.

35.2 A notice shall be effective when delivered or on the notice's effective date, whichever is later.

Page 90: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

36. Taxes and Duties:

36.1 Contractor shall be responsible for all taxes, stamp duties, license fees, etc. and other such levies imposed outside and within Pakistan (except port dues in Karachi, for which waiver may be considered on request of Contractor) incurred for the supply of the contracted Goods and service to the Employer.

36.2 Domestic Contractor shall bear all expenses in respect of Four Split Hopper Barges, its accessories and belongings as may be required for berthing, warehousing, ship handling, shifting, docking etc. within the country till completion of one year guarantee period of offer of Four Split Hopper Barges.

37. Integrity Pack:

37. If the Contractor, or any of his Sub-Contractors, agents or servants is found to have violated or involved in violation of the Integrity Pack signed by the Contractor as Schedule-H to his Bid, then the Employer shall be entitled to:

(a) Recover from the Contractor an amount equivalent to ten times the sum any commission, gratification, bribe, finder’s fee or kickback given by the Contractor or any of his sub-contractors, agent or servants.

(b) Terminate the contract, and

(c) Recover from the Contractor any loss or damage to the Employer as a result of such termination or of any other corrupt business practices of the contractor or any of his sub-contractors, agents or servants.

37.2 On termination of the contract under Sub-Para 37.1 (b) of this sub-clause, the contractor shall demobilize from the site leaving behind contractor’s Equipment which the Employer instructs, in the termination notice, to be used for the completion of the works at the risk and cost of the contractor. Payment upon such termination shall be made under clause 30, in accordance with sub-para (c) thereof, after having deduct the amounts due to the Employer under Sub-para (a) and (c) of Sub-Clause 37.1.

Page 91: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

SECTION II

INSTRUCTIONS TO BIDDERS (ITB)

A. GENERAL

IB.1 Scope of Bid and Source of Funds:

1.1 Scope of Bid:

The Employer”) wishes to receive bids:

“Construction and Supply of Four Self Propelled Split Type Hopper Barges”

Bidders must quote for the complete scope of work. Any bid covering partial scope of work will be rejected as non-responsive, pursuant to Clause IB.24.

1.2 Source of Funds:

The project being a self financed one, shall be funded from within Employer’s own resources. The payments shall be payable directly by Employer under banker’s cheque.

IB.2 Eligible Bidders:

2.1 The bid would be eligible for the stage examination for the Bidders who:-

(a) Submit a fixed price bid (to be confirmed in the cover letter and Clause by Clause Commentary without mentioning the quoted cost).

Page 92: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

(b) Have not been black listed by Employer.

(c) Submit irrevocable bid valid for 120 days along with acceptable Bid Security valid for 07 days more than validity of bid, pursuant to Clause 15.3 of ITB.

2.2 Only the bids which are established eligible in terms of clause 2.1 shall be

considered for further evaluation i.e. for examination of Technical Proposal.

IB.3 Origin of Goods and Services:

3.1 For purposes of this Clause, “origin” means the place where the Four Self Propelled Split Type Hopper Barges are produced or from where the ancillary services / equipment are supplied through manufacturing process. The preferable origin of the main and auxiliary machinery, hydraulic system, communication, navigation and deck equipment and other materials are U.K., Western European countries, Japan and USA.

3.2 The origin of Four Self Propelled Split Type Hopper Barges distinct from the nationality of the Bidder.

IB.4 Cost of Bidding:

The Bidder shall bear all costs associated with the preparation and submission of his Bid, and the Employer, will in no case be responsible or liable for any of those costs which may be incurred for preparation, submission of bid, till its conclusion, regardless of the conduct or outcome of the bidding process.

B. BIDDING DOCUMENTS

Page 93: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

IB.5 Content of Bidding Documents:

5.1 To acquire Four Self Propelled Split Type Hopper Barges the required, bidding procedure and contract terms are prescribed in the Bidding Documents comprising following parts and should be read in conjunction with any Addendum issued in accordance with Sub-Clause IB 7.1.

Section I Form of Bid (FB)

Section II Instructions to Bidders (ITB)

Appendix A Evidence of Bidder Capability

Appendix B Domestic Goods (value added in Pakistan)

Annexure I Table – A Chart of Evaluation

Table – B Evaluation Criteria for Technical Specification

Section III General Conditions of Contract (GC)

Section IV Special Conditions of Contract (SC)

Section V Technical Specification (TSP) & Bid Drawings

Section VI Schedule of Requirement (SOR), Bill of Quantities (BOQ)

Section VII Technical Schedule (TSC)

Section VIII Schedules to Bid (STB)

Page 94: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

Schedule A Specific Works Data

Schedule B Work to be performed by Sub-contractors.

Schedule C Proposed Program of works

Schedule D Deviations from Technical Provisions

Schedule E Deviations from Contractual Conditions

Schedule F Method of Performing Works

Schedule G Proposed Organization

Schedule H Integrity Pact

Section IX Forms (Samples) (SF)

Form A Contract Form

Form B Performance Security Form

Form C Advance Payment Guarantee

Form D Manufacturer’s Authorization Form

Form E Bid Security Form

Form F List of Sub-Contractor(s)

Form G Particular of Local Associated Firm(s)

5.2. The Bidder is expected to examine all instructions, forms, annexure, addendums (if any) terms and specifications in the Bidding Documents. Failure to furnish all information required by the Bidding Documents or submission of a Bid not valid for 120 days and not responsive to the Bidding Documents in every respect will be at the Bidder’s risk and may result in the rejection of his Bid.

IB.6 Clarification of Bidding Documents / Pre-Bid Meeting:

6.1Prospective Bidder requiring any clarification of the Bidding Documents may notify the Engineer / Employer in writing or by fax at the Employer’s / Engineer’s

Page 95: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

mailing address indicated in Sub-Clause 19.1. Engineer / Employer will examine the request for clarification of the Bidding Documents which it receives not later than twenty (28) days prior to the deadline for the submission of bids. The Employer will respond in writing to any request for clarification of the Bidding Documents, which it receives on or before the date of pre-bid meeting, which shall be conducted at a date 15 days before the date of receiving bids (The exact date is 15-01-2015). Written copies of the Engineer’s / Employer’s response (including an explanation of the query but without identifying the source of inquiry) will be sent to all prospective Bidders who have received the Bidding Documents.

6.2Pre-Bid Meeting:

The aim of pre-bid meeting is to provide necessary clarification for the clear understanding of the Bidders to the bid documents. The purpose of the period available with the Bidders to prepare the bid and the extended period if any and of Pre-Bid meeting is to receive from the interested Bidders, a complete and clear bid that may be conforming to the bid documents avoiding the requirement of clarification from the Bidders. The pre-bid meeting will be conducted between the Employer and the Bidders, on a date 15 days before the date of receiving the bids at the address given in the Invitation for bid. The purpose of the meeting will be to provide clarification to the queries on the Bidding Documents received from those participating in the meeting and those which have been received by Employer in writing by that time. The minutes of the meeting shall be circulated by Employer via fax, to all the bidders and shall be the part of the bid to be submitted by the bidder(s). After the date of pre-bid meeting queries received if any regarding clarification to the bid documents shall not be responded by Employer.

IB.7 Basis of Bidding Documents, and Addendum:

7.1 At any time prior to the deadline for submission of Bids, the Employer may for any reason, whether at its own initiative or in response to a clarification requested by a prospective Bidder, modify the Bidding Documents by issuing addendum.

Page 96: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

7.2 Any addendum thus issued shall be part of the Bidding Documents pursuant to Sub- Clause 7.1 hereof, and shall be communicated in writing to all purchasers of the Bidding Documents. Prospective Bidders shall acknowledge receipt of each addendum in writing to the Employer. The bidder shall also confirm in the Form of Bid that the information contained in such addendum have been considered in preparing his bid.

7.3 In order to afford prospective Bidders reasonable time in which to take the addendum into account in preparing their bids etc. the Employer may, at the request of prospective bidders or at its own discretion, may extend the deadline for the submission of bids in accordance with Clause IB.19.

7.4 Basis of this bidding procedure is the “Single Stage – Two envelope bidding procedure” as defined in Clause 36 (b) of the PPRA Rules 2004. PPRA website www.ppra.org.pk may be visited. The clause is as under:-

b) Single Stage – two envelope procedure:-

(i) The bid shall comprise a single package containing two separate envelopes. Each envelope shall contain separately the financial proposal and the technical proposal;

(ii) The envelopes shall be marked as “FINANCIAL PROPOSAL” and “TECHNCIAL PROPOSAL” in bold and legible letters to avoid confusion;

(iii) Initially, only the envelope marked “TECHNICAL PROPOSAL” shall be opened;

(iv) The envelope marked as “FINANCIAL PROPOSAL” shall be retained in the custody of the procuring agency without being opened;

Page 97: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

(v) The procuring agency shall evaluate the technical proposal in a manner prescribed in advance, without reference to the price and reject any proposal which does not conform to the specified requirements;

(vi) During the technical evaluation no amendments in the technical proposal shall be permitted;

(vii) The financial proposals of bids shall be opened publicly at a time, date and venue announced and communicated to the Bidders in advance;

(viii) After the evaluation and approval of the technical proposal the procuring agency, shall at a time within the bid validity period, publicly open the financial proposals of the technically accepted bids only. The financial proposal of bids found technically non-responsive shall be returned un-opened to the respective Bidders; and

(ix) The bid found to be the lowest evaluated bid shall be accepted.

C. PREPARATION OF BIDS

IB.8 Language of Bid:

The Bid prepared by the Bidder and all correspondence and documents relating to the Bid exchanged by the Bidder and the Employer shall be written in the English language, provided that any printed or other literature furnished by the Bidder may be written in another language so long as accompanied by an English translation of its pertinent passages in which case, for purposes of interpretation of the Bid, the English translation shall govern.

IB.9 Documents Comprising the Bid:

Page 98: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

9.1 The Bid prepared by the Bidder shall be considered by Employer for processing provided the same essentially comprises the following components:

(a) Covering Letter.

(b) A Bid Form / “Form of Tender” and the Technical Schedule and Price Schedule / BOQ completed in accordance with the relevant instruction / clauses and blanks have been filled in, sealed and signed.

(c) Power of Attorney authorizing the signatory of the bidder to act for and on behalf of the Bidder according to Sub-Clause 17.5 provided.

(d) Documentary evidence established in accordance with that the Bidder is eligible to Bid and is qualified to perform the contract if its Bid is accepted.

(e) G.A. Plan complete Technical Specification, Technical Schedule and other Documentary evidence establishing the proposed Four Self Propelled Split Type Hopper Barges and ancillary services to be supplied by the Bidder conforms to the Bidding Documents.

(f) Bid security furnished in strict accordance with tender condition.

(g) Joint Venture Agreement (if applicable) provided.

(h) Complete name and address of the authorized local partner(s), if any, and extent of collaboration. Copy of the memorandum, if any, between the principals and authorized local partners / representative to be submitted.

(i) All Forms and Schedules and blank spaces given in the bid documents are duly filled-in.

(j) Clause by Clause commentary to the Bid Documents and list of deviation (if any) has been furnished in order to demonstrate the substantial responsiveness to Technical details of proposed Four Self Propelled Split Type Hopper Barges and all its structure and machinery for safe and

Page 99: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

efficient functioning and compliance of all other obligations as depicted in the conditions of contract and specification.

(k) The bid document supplied by Employer is returned in original duly signed and stamped (each page) as token or awareness and also the additional documents, if any. .

(l) Bidders applying for eligibility for domestic preference in bid evaluation shall supply all information and evidence to establish the claim for domestic preference required to satisfy the criteria for eligibility as described in Clause IB.27. The particulars of Domestic Goods prescribed in Appendix B to these Instructions shall also be filled in to substantiate claim for domestic preference.

(m) Any other documents prescribed in Special Conditions of the Contract for Technical Provisions to be submitted with the Bid.

9.2 Sufficiency of Bid: Each bidder shall satisfy himself before Bidding as to the correctness and sufficiency of his Bid and of the rates and prices entered in the Schedule of Prices, which rates and prices shall except in so far as it is otherwise expressly provided in the Contract, cover all his obligations under the Contract and all matters and things necessary for the proper completion of the Works.

9.3 The bidder is advised to obtain for himself at his own cost and responsibility all information that may be necessary for preparing the bid and entering into a Contract for execution of the Works.

IB.10 Form of Bid and Schedules:

The Bidder shall complete, sign and seal the Form of Bid, Schedules (A to H, or as modified) to Bid and Schedule of Prices furnished in the Bidding Documents, and shall also enclose other information as detailed in Clause IB.9.

IB.11 Bid Prices:

Page 100: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

11.1 The Bidder shall indicate on the appropriate Price Schedule attached to these documents the unit prices and total Bid Price of Four Self Propelled Split Type Hopper Barges it proposes to supply under the Contract.

(a) Bid Price – for Four Self Propelled Split Type Hopper Barges offered from within Pakistan. The price of the vessels quoted ex-yard shall be fixed including

(i) All cost of design, construction, supply, provisions, services, accessories etc. as may be required for complete fulfillment of the terms and conditions of the tender documents including those indicated in the schedule of requirement and out side the schedule of requirement but in the tender documents and all duties and taxes/charges payable by decree in the of origin – Pakistan during the currency of the contract.

(ii) All import duties, sales tax and any other taxes / duties / charges already paid or payable towards manufacture and supply of Four Self Propelled Split Type Hopper Barges for their design, machinery, equipment, raw material to be used in the manufacturing or assembly of the vessels, quoted ex-yard. All taxes payable in Pakistan including GST, income tax, royalties etc. if the contract is awarded to a domestic bidder are to be included.

(iii) All incidental costs including cost of surveys by Classification and / or local Maritime agency / MMD and Environmental Agencies, etc. that for berthing / docking of four Split Hopper Barges (as and when required) till completion of one year warranty period and for registration of Four Self Propelled Split Type Hopper Barges with Pakistan Flag Authority MMD, and Insurance of work till start of one year warranty period and / or other levies on account of Government Directives / Labour Awards / revision of SRO’s, Port Charges etc. The consolidated ex-yard fixed cost is to be quoted for (i) through (iii).

(b) Bid Price - for Four Split Hopper Barges offered from abroad:

Page 101: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

(i) All cost of design, construction, supply, provisions, services, accessories of Four Split Hopper Barges as may be required for complete fulfillment of the terms and conditions of the tender documents including those indicated in the schedule of requirement and out side the schedule of requirement but in the tender documents all duties and charges/taxes and import charges payable in the country of origin and all other places in and outside Pakistan (except Custom Clearance and Flag authority registration in Pakistan).

(ii) The cost of transportation of vessel to Karachi, including voyage insurance.

(iii) All incidental costs, charges, paid or payable to various agencies if any, including cost of surveys by Class and / or local Maritime agency (other than registration) till end of one year warranty period and any other cost including the costs under decree which may be incurred till such time the one year warranty period starts.

(iv) Spare parts, tools etc as per General Condition’s Clause 17.1 (d)

(v) Provision of bottom Survey by approved diver of each Hopper Barges at Karachi and Guarantee Engineer, Guarantee Master and Technician for 54 man months spread over one year warranty period, to look after the warranty claims and to give training to KPT’s operating crew and instructions to repairers. The fixed DDP (CIF + Customs,, duty, Sales Tax and other import charges) price is to be quoted for (i) through (v)

The freight cost and voyage insurance cost to be indicated separately.

Mode of Payment of freight cost may be:

(i) By Employer to Seller.

(ii) By Employer to the National Flag carrier. In this event freight will not be paid to Seller and value of contract may be reduced for freight cost.

Page 102: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

(iii) By Seller to the National Flag carrier or others, in this event above (a) shall prevail.

11.2 The comparable consolidated quoted cost shall be arrived at after adding the financial implication as may be applicable in terms of these documents to the consolidated ex-yard fixed cost quoted by the local bidder for the four Split Hopper Barges offered from within Pakistan in accordance with Sub-Clause 11.1 (a) and the fixed DDP (CIF + Custom duty, Sales Tax and other Import charges) cost quoted by the foreign bidder for the four Split Hopper Barges offered from outside Pakistan in accordance with Sub-Clause 11.1(b)

11.3 The time for complete delivery at Karachi is 24 and 27 months for 1st and 2nd set of two Split Hopper Barges respectively by local bidders from within Pakistan and time for arrival at Karachi is 24 and 27 months for 1st and 2nd set of Two Split Hopper Barges respectively by foreign bidders from outside Pakistan.

11.4 Unless otherwise stipulated in the Conditions of Contract, prices quoted by the Bidder shall remain fixed during the Bidder’s performance of the Contract and not subject to variation on any account. When the Bidders are required to quote only fixed price(s) a bid submitted with an adjustable price quotation will be treated as non-responsive and rejected, pursuant to Clause IB.24.

11.5 Any discount offered shall be valid for at least the period of validity of the bid. A discount valid for lesser period shall be considered null and void.

IB.12 Currencies of Bid:

12.1 Employer shall make payments in equivalent local currency (Pak. Rupee) only. Prices may be quoted in the following manner:

(a) The bidders from the country of origin (Pakistan) may quote the prices in single currency i.e. Pakistani Rupee or in two currencies i.e. one foreign currency and local currency (Pakistani Rupee). The exchange rate and the corresponding amount of quoted foreign currency have to be necessarily indicated in local currency.

Page 103: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

(b) The bidders from the country of origin (outside Pakistan) may quote the prices in one foreign currency or in two currencies i.e one foreign currency and local currency Pakistani Rupee.

(c) In each case, the foreign currency component has to be expressed in Pak. Rupees along with the exchange rate, where applicable.

IB.13 Documents Establishing Bidder’s Eligibility and Qualification:

13.1 Pursuant to Clause IB.9, the Bidder shall furnish, as part of its Bid, documents establishing the Bidder's eligibility to bid and its qualification for further evaluation,

13.2 The Bidder / Manufacturer must process and provide evidence of its capability and the experience as stipulated in Bidding Data and the Qualification Criteria stipulated in the Bidding Documents.

13.3 The bidder to qualify for consideration of his bid is required to submit following documents as part of their bids in addition to those described in IB.9.

(a) Agreement between the bidder and ship builder, if applicable. (b) Manufacturer’s authorization to bid if the bidder shall not manufacture the

tendered item.

IB.14 Documents Establishing the Four Split Hopper Barges Eligibility and Conformity to Bidding Documents:

14.1 The documentary evidence of the Four Split Hopper Barges conformity to the Bidding Documents may be in the form of literature, drawings/plans, certificates, tests and trial protocol, performance record and other relevant data.

Page 104: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

(a) A detailed description of the of the proposed vessel and its essential technical parameters and characteristics viz a viz the tender specification/broad parameters.

(b) A list giving full particulars including available sources / origin of all machinery/sub-assemblies, materials/components. Provisions for the guarantee master guarantee engineer and training of Employer’s staff visits, inspection, tests and trials etc.

(c) In addition to Clause by Clause Commentary pursuant to Clause 9.1 a statement of deviations. If any, and exceptions to the provisions of the General and Special Terms and Technical Specifications.

(d) Follow up of local and international maritime rules and regulations during, construction, transportation and one year warranty period of Four Split Hopper Barges. The proposed Four Split Hopper Barges shall be fully equipped as per rules and requirements of:-

- Classification Society from within those which are acceptable to Pakistan Flag Authority i.e Mercantile Marine Department (MMD) - Government of Pakistan

- IMO

- MARPOLE

- SOLAS &

- International Tonnage Measurement.

- International Load line Regulations.

- International Collision at sea Regulation &

- MMD (Mercantile Marine Department - Pakistan) Rules..

- Insurance of work and any other rule of Marine, Maritime or domestic sector as may be applicable towards fulfillment of the contract.

Page 105: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

(e) Committed to design and to submit with his bid the proposed General Arrangement and other Plans, if so preferred. Taking all Specification as Guidance only, the design shall be for the maximum conformity of the broad parameters as given in the specifications.

(f) Committed to construct the Four Split Hopper Barges ensuring all provisions, whether or not mentioned in the specifications/ bid documents, for the safest use of purpose, sea- worthiness and to comply the relevant conditions of the International and Local Maritime Authorities/Institutions for the safest use in the Karachi Harbour / Pakistani Coast.

(g) To confirm that the construction of Four Split Hopper Barges shall be sturdy and robust using the world wide known makes and origin of equipment and exercising the highest standard of quality and workman ship for the finished goods and systems therein ensuring the quickest maneuverability and reliability of all operation by proposed Four Split Hopper Barges.

14.2 For purposes of the commentary to be furnished, the Bidder shall note that standards for workmanship, material and equipment, and references to brand names or catalogue numbers designated by the Employer in its Technical Specifications are intended to be descriptive only and not restrictive. The Bidder may substitute alternative standards brand names and/or catalogue numbers in its Bid, provided that the substitutions demonstrates for substantially equivalent or superior to those designated in the Technical Specifications etc.

IB.15 Bid Security:

15.1 Pursuant to Clause 9 the Bidder shall furnish, as part of its Bid, Bid Security in the Form Bank Guarantee or Pay order for a fixed amount of US$ 500,000 (United States Dollars Five Hundred Thousand) in equivalent Pak Rupees (converted at buying rate of exchange on the day 15 days before the date of Tender submission) for Four Self Propelled Split Hopper Barges in the manner described in these documents.

Page 106: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

15.2 The Bid Security is required to protect the Employer against the risk of Bidder's conduct, which would warrant the security's forfeiture, pursuant to following Paras of these documents.

15.3 Mode of Bid Security and Validity:

The Bid security shall be furnished in the local or foreign currency (Pak Rupees) and shall be in the form of a Bank Guarantee or Pay order issued by a bank with +A1 rating / authorized, first Class scheduled bank located in Karachi except United Bank Ltd. The Bank guarantee for the Bid Security shall be valid for period 07 days more than the days beyond the validity of the Bid, which would be valid for 120 days.

15.4 Bid Rejection for no Bid Security:

Any bid not accompanied the original documents for the Bid Security or Bid Security not in accordance with the terms of these documents expressed under this Clause of ITB will be rejected as non responsive

15.5 Return of Bid Security:

Page 107: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

(a) The Financial Proposal and Bid Security will be returned to the bidders who are evaluated as technically disqualified, after opening Financial Proposals of technically qualified bidders.

(b) The bid security of the Technically Qualified Bidders would be returned, after the Contract has been signed with the Successful Bidder.

(c) The bid security of the successful Bidder would be returned, after the accepted Performance Bond pursuant to Clause 34 has been furnished by the successful Bidder.

(d) The bid security of the Bidders would be returned at appropriate time to all the Bidders, in the event of discharge of tender.

15.6 Forfeiture of the Bid Security:

The Bid security may be forfeited and / or the bid may be liable for rejection if:

(a) After the bid has been opened and if a Bidder or his local representative or associate disown his bid or part thereof or disagree or the Bidder or his associates at his own or as a result of query placed on him for clarification modifies his Bid by changing the specification and terms and conditions as offered in his bid.

(b) After the bid has been opened and if a Bidder or his local representative or associate / partner / agent unilaterally contacts Employer in regard with his bid during the period of opening of bid till its conclusion (Signing of contract with the successful Bidder or discharge of tenders) or influences the evaluation process in any manner except as per provision of Clause 23.

(c) After the bid has been opened and if a Bidder fails to provide convincingly valid and authentic and/or original documents / evidences for confirmation of claims / statements made therein the bid Proposal.

(d) After the bid has been opened and if a Bidder withdraws the bid Proposal and /or bid security or both before the date of expiry of the bid validity period or extended period.

(e) A successful Bidder, fails to:

Page 108: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

(i) Acknowledge and accept the Letter of Award or refuse to receive the same.

(ii) Sign the Contract in accordance with Letter of Award (LOA) within the stipulated time.

(iii) Furnish Performance Security, in accordance with the stipulations.(iv) Extend the validity of bid and bid security (if required), after accepting

the Letter of Award and its terms and conditions.

IB.16 Extension in the validity of bid security:

16.1 In exceptional circumstances, the Employer may solicit the Bidder’s consent to an extension of the period of validity of bid and bid security. The request and the responses thereto shall be made in writing. A bidder may refuse the request. Bidders’ disagreement to extend the validities will in no case be a reason for the forfeiture of the bid security. A bidder granting the request will be without modifying its Bid and Bid Security in manner.

IB.17 Format and Signing of Bid:

17.1 Bidders are particularly directed that the amount entered on the Form of Bid shall be for performing the Contract strictly in accordance with the Bidding documents.

17.2 All Schedules to Bid are to be properly completed and signed.

17.3 No alteration is to be made in the Form of Bid nor in the Schedules thereto except in filling up the blanks as directed. If any alteration be made or if these instructions be not fully complied with, the bid may be rejected.

17.4 Each Bidder shall prepare one (1) Original and one (1) Copy, of the documents comprising the bid as described in Clause IB.9 and clearly mark them “ORIGINAL” and “COPY” as appropriate. In the event of discrepancy between them, the original shall prevail.

Page 109: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

17.5 The original and all copies of the bid shall be typed or written in indelible ink and shall be signed by the Bidder (a person who have signed the “ Form of Bid”), and shall stamp and initial all pages of bid, except for un-amended printed literature and he shall be the dealing person on all matters from the Bidder’s side till signing of contract. This shall be indicated by submitting a written Power of Attorney authorizing the signatory of the Bidder to act for and on behalf of the Bidder. The Bidder may however, in their cover letter provide the name(s), designation and specimen signature of the alternative persons who may sign

correspondence in regard with his bid, with Employer.

17.6 The bid shall contain no alterations, omissions, erasures, overwriting or additions, except to comply with instructions issued by the Employer, or as are necessary to correct errors made by the Bidder. The person or persons making corrections shall cut by single horizontal line, in which case such corrections shall be initialed and affixed stamp.

17.7 Bidders shall indicate in the space provided in the Form of Bid their full and proper addresses at which notices may be legally served on them and to which all correspondence in connection with their bids and the Contract is to be sent.

17.8 Bidders should retain a copy of the Bidding Documents as their file copy.

D. SUBMISSION OF BIDS

IB.18 Sealing and Marking of Bids:

18.1 “Single Stage – Two envelop Bidding Procedure” has been adopted as explained in detail in clause 7.4

Page 110: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

18.2 One Envelope, addressed to the Employer at the address given in Clause 19.1 containing separate sealed envelopes for Technical and Financial Proposals shall be submitted.

18.3 Each envelope has to indicate the Title of envelope i.e. “Tender for Four Self Propelled Split Type Hopper Barges“ Technical Proposal” or “Financial Proposal” and Name and complete address of the Bidder.

18.4 ORIGINAL and each COPY of the Bid shall be separately sealed and put in separate envelopes and marked as such.

18.5 The Bid shall be delivered in person or sent by registered mail at the address to Employer as given in Sub-Clause 19.1 heretofore.

18.6 If the outer envelope is not sealed and marked as above, the Employer will assume no responsibility for Bids misplacement, or premature opening of the bid.

18.7 Each Technical and Financial Proposal shall be opened in the presence of bidders or their representatives (from within those who have obtained the bidding documents), who may so wish.

(a). Each bid shall be accompanied by a cover letter from the Bidder, (at the Bidder Company’s letter head) and will be placed on top of respective envelopes.

(b). The letter shall be signed by the same person who has signed the Form of Bid.

(c). The letter shall clearly define the content of envelopes over which it is placed and indicate details of the Bank Guarantee or Pay Order for bid security.

Page 111: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

(d). The bid security may be placed in an un-sealed envelops along with the covering letter, annexed with the envelope containing “Technical Proposal”.

(e). The sealed envelopes for Technical Proposal shall be opened only if the Bank Guarantee or Pay Order for bid security has been furnished in accordance with these documents..

18.8 The envelope marked “Technical Proposal” shall be opened first and contain:-

.

(a). Complete set of the issued Tender Documents duly signed and stamped each page.

(b). Bidder’s Technical Proposal, including Technical schedule, Clause by Clause commentary to all parts of the issued Bid documents including Instruction to Bidders, General & Special conditions of contract, Technical Specification, etc.

(c). Technical Specification and other associated details with all blank spaces properly filled in and drawing / proposed G.A. plan shall be furnished along with list of deviations, if any

(d). Form of Tender filled in, except for cost.

(e). Clause by Clause commentary to all the parts of issued tender documents depicting deviations (if any) to the clauses.

(f). Documents to comply all other requirement of bidding documents.

(g). Plan / methodology for providing training for the operators and maintainers of Employer and attending the warranty repairs during initial one year and local set up/assistance for the purpose of prompt rectification of defects under warranty.

(h). Any other additional documents which the Bidder may consider to submit for evaluation of his technical Proposal.

Page 112: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

18.9 Already opened or tempered or damaged envelopes received via mail or in person shall not be accepted and returned. Employer shall not assume any responsibility of damaged envelopes or of late arrival of the tender / bid Proposal at receiving desk of Employer.

18.10 Envelope marked ‘Financial Proposal’ shall accompany a cover letter on top with indication of:-

(a). Acceptance of the stage payments as per Special Conditions of Contract.(b). Confirmation of bid to be fixed priced, otherwise pursuant to clause 11.4 the

bid shall be non-responsive and rejected and the Financial Proposal shall be returned un- opened.

The envelope marked ‘Financial Proposal’ shall contain:-

(a) The priced bill of quantities, with separate indication of freight charges

(b) Form of Tender duly filled in for price.

(c) Time period for the completed delivery of 1st and 2nd set of two barges in 24 & 27 months (starting from the date furnishing Performance Security) by the Local Bidder offering Four Split Hopper Barges from within Pakistan and time period for the arrival of 1st and 2nd set of two barges in 24 & 27 months in Karachi, by the Foreign Bidder offering Four Split Hopper Barges from outside Pakistan.

(d) List of deviations with the contract clauses for price, payment and delivery time.

(e) Any other cost factor outside the purview of the supplied bid documents.

IB.19 Deadline for Submission of Bids:

19.1 Bids delivered in person or sent by registered / courier mail must be received by the Employer at the address given below up to or before

Page 113: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

1100 hrs. Pakistan Standard Time on the 06-02-2015 after which no bid will be received. The bids arrived by other means (except in person or international mail/courier service) will not be considered.

GENERAL MANAGER (P&D)Planning and Development DivisionKARACHI PORT TRUSTEdulji Dinshaw Road,Karachi-74000, Pakistan

Tel : 92-21-9214530 -40 Ext: 2230 & 2232, 2459, 99214312, 99214376Fax : 92-21-9214329-30E-mail : [email protected]

19.2 The Bidder may obtain a receipt for submission of their bid and produce the same on demand. The Employer may, at its discretion, extend the deadline for the submission and opening of bids by amending the Bidding Documents in accordance with Clause IB.7, in which case all rights and obligations of the Employer and Bidders, subject to the previous deadline will thereafter be subject to the deadline as extended.

IB.20 Late Bids:

20.1 Any Bid received by the Employer after the deadline for submission of bids prescribed by the Employer, pursuant to Clause 19, will be rejected and returned unopened to the Bidder.

20.2 Delays in the mail, delays of person in transit, or delivery of a bid to the wrongoffice shall not be accepted as an excuse for failure to deliver a bid at the proper place and time. It shall be the Bidder’s responsibility to determine

the manner in which timely delivery of his bid will be accomplished either in person, by messenger or by mail.

IB.21 Modification, Substitution and Withdrawal of Bids:

Page 114: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

IB.21 The Bidder may modify or withdraw its Bid after the Bid's submission, provided that written notice (delivered in the manner as the bid to be submitted) of the modification or withdrawal is received by the Employer up to half hour (30 minutes) prior to the deadline prescribed for submission of bids.

21.2The Bidder's modification, substitution or notice for withdrawal shall be prepared, sealed, marked and delivered in accordance with Clause IB.19 with the outer and inner envelops additionally marked “MODIFICATION”, “SUBSTITUTION or “WITHDRAWAL”, as appropriate. It should be received by KPT not later than half hour (30 minutes) before the time and deadline for submission of bids. Bidder’s modification in the bid or withdrawal of his bid at a time half hour (30 minutes) earlier than the time for submission of bids will not constitute forfeiture of Bid Security of respective Bidder.

21.3At any stage after the time for receiving the bids has been arrived, no Bid may be modified by the Bidder in any manner. Except pursuant to Clause 23.1 the Bidder has suggested in writing (not by e-mail) as clarification to his bid for a query by the Employer, sent to Bidder via fax or courier mail but not e-mail. The Bidder clarification, if any, via exchange or correspondence shall be without financial impact to Employer and time over run and ensures better than the offered technical specification, in terms of reliability, robustness, asking low economical maintenance, easy and efficient operation and use of purpose.

21.4 No Bid may be withdrawn or modified during the interval between the deadline for submission of bids and end of the period of Bid validity specified by the Bidder on the Bid Form or the extended period of validity. Withdrawal or modification of a Bid and / or Bid Security during this interval may result in the forfeiture of Bidder's Bid security, pursuant to Clause 15.6 and rejection of bid.

E. BID OPENING AND EVALUATION

IB.22 Bid Opening

22.1 Bids will be opened same day at the date and at the address as given in the Clause 19, half hour (30 minutes) after the dead line for submission of bids.

Page 115: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

A committee consisting of nominated members by the Employer and by the Engineer will open the bids, including withdrawals, substitution and modifications made pursuant to Clause IB.21, in the presence of Bidders’ representatives who choose to attend, at the time, date and location stipulated in the Invitation for Bids.

The Bidders’ representatives who are present shall sign in a register evidencing their attendance.

22.2 Envelopes marked “MODIFICATION”, “SUBSTITUTION” or “WITHDRAWAL” shall be opened and read out first and the name of the Bidder shall be read out. Bids for which an acceptable notice of withdrawal has been submitted pursuant to Clause IB.21 shall not be opened.

22.3 The Bidders' names, Bid modification, substitution and withdrawals, the presence or absence of requisite Bid Security and other details may be announced at the time of opening the bids.

The Employer will prepare minutes of the Bid opening for both the openings of Technical Proposals and Financial Proposals (to be opened later), and the Bidders’ and Employer’s representatives who are present shall sign the statement of attendance & announcement (if any) as to confirm the correctness of the announcement made if any by Employer.

IB.23 Clarification to Bids

23.1 Considering, the Bidders are provided with:

(i) the period for preparation of bid

Page 116: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

(ii) Opportunity of obtaining clarification to the clause(s) of bid

documents and

(iii) Participation in the pre-bid meeting

Employer foresees of receiving a comprehensive, clear and complete bids from each participating Bidder. Yet for clear understanding and confirmation to comply the conditions & specifications etc, Employer / Engineer may ask in writing the Bidders to provide clarification to section(s) of his bid. The asking clarification may be for the parts of bids excluding following, where complete compliance is necessary:-.

(a) Financial Proposal.

(b) Form of Bid.

(c) Instruction to Bidders.

(d) Bid security.

23.2 The clarification sought if any by the Employer may be generally for the unavailable / “Missing information” in the terms and conditions and technical Proposal of a received bid and may be for a clear understanding of the already provided Technical and other information. The query and Bidder’s clarification to a query by Employer shall be in writing and without change / modification of the following:-

(i) Quoted bid price.(ii) Delivery period./ completion time(iii) Substance of the bid(iv)Technical Specification (v) The already provided information in the bid except for better than the offered

technical specification and improvement only.(vi)Liability of then Employer in any meanings

23.3 Prior to finalization of the evaluation of bids, Employer’s evaluation Committee, Board and/or the Government if needed, may ask the Bidder(s) to provide

Page 117: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

detailed clarification via presentation on any or all technical, financial, contractual, managerial, legal and other aspects of his bid to asses/ascertain the production and financial capability and credibility/competency of the Bidder / construction yard and supplier(s). To authenticate the prequalification of Bidder, Employer may also seek physical inspection of generally the pre-qualified and in particular of the eligible and evaluated responsive Bidder’s resources, work facilities / site etc. at the cost of the Bidder.

IB.24 Preliminary Examination & Determination of Responsiveness of Bids

24.1 Prior to the detailed evaluation of bids, pursuant to Clause IB.26,

(a) the Employer will examine the Bids to determine whether; (i) the Bid is complete and does not deviate from the scope,

(ii) any computational errors have been made,

(iii) required sureties have been furnished,

(iv) the documents have been properly signed, stamped, filled in and returned,

(v) the Bid is valid till required period,

(vi) the Bid prices are firm during currency of contract.

(vii) completion period offered is within specified limits,

(viii) the Bidder/Manufacturer is eligible to Bid.

(ix) the Bid does not deviate from basic technical requirements and

(x) the Bids are generally in order.

(b) A bid is likely not to be considered, if;

(i) it is unsigned,(ii) its validity is less than specified,(iii) it is submitted for incomplete scope of work,(iv) it indicates completion period later than specified,(v) it indicates that Works and materials to be supplied do not meet

eligibility requirements,

Page 118: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

(c) A bid will not be considered, if;

(i) it is not accompanied with Bid security,

(ii) it is submitted by a Bidder who has participated in more than one bid,

(iii) it is received after the deadline for submission of bids,

(iv) it is submitted through fax, telex, telegram or email,

(v) it indicates that prices quoted are not firm during currency of the contract

(vi) the Bidder refuses to accept arithmetic correction,

(vii) it is materially and substantially different from the Conditions/Specifications of the Bidding Documents.

22.2 Arithmetical errors will be rectified on the following basis:

If there is a discrepancy between the unit price and the total price that is obtained by multiplying the unit price and quantity, the unit price shall prevail and the total price shall be corrected. If there is a discrepancy between words and figures, the amount in words will prevail. If there is a discrepancy between the total Bid price entered in Form of Bid and the total shown in Price Schedule / BOQ Summary, the amount stated in the Form of Bid will be corrected by the Employer/Engineer in accordance with the Corrected Price Schedule.

If the Supplier does not accept the correction of the errors, its Bid will be rejected and his Bid Security will be forfeited.

24.3 Prior to the detailed evaluation, pursuant to Clause IB.26 the Employer/Engineer will determine the substantial responsiveness of each Bid to the Bidding Documents. For purpose of these Clauses, a substantially responsive Bid is one which conforms to all the terms and conditions of the Bidding Documents without material deviations.

A material deviation or reservation is one:

Page 119: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

(i) Which affects in any substantial way the scope, technical specification, quality or performance of the Works.

(ii) which limits in any substantial way, inconsistent with the Bidding Documents, the Employer’s rights or the Bidder’s obligations under the Contract; or

(iii) Whose rectification/adoption would affect unfairly the competitive position of other Bidders presenting substantially responsive bids.

The Employer’s / Engineer determination of a Bid’s responsiveness will be based on the contents of the Bid itself and inspection (at Bidder’s cost) of the Bidder’s work facility and capability, by Employer’s representative(s), if any without recourse to extrinsic evidence.

24.4 A bid determined as not eligible and/or not substantially responsive will be rejected at respective stage and will not subsequently be made responsive by the Bidder by correction of the nonconformity(s).

24.5 The Employer may waive any minor informality or non-conformity or irregularity in a bid that does not constitute a material deviation, provided such waiver does not prejudice or affect the relative ranking of any Bidder.

24.6 Employer shall not be bound to accept the lowest or any other tender and reject the same without mentioning grounds.

24.7 The conditional bids and bids with adjustable price, bid submitted without filling up of the blank spaces or without the required documents and information, shall be rejected as non-responsive.

24.8 Employer shall not be responsible to reimburse the cost incurred by the Bidder for preparation and submission of his bid, contract agreement and payment of stamp duty for the contract or any other expenses by decree and any liability in regard with submission of bid by the Bidder.

Page 120: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

IB.25.(a) Preference on Early Delivery of Hopper Barges

(b) Conversion to Single Currency:

25.1 The construction and ex-yard delivery period for 1st set of 2 Self Propelled Split Type Hopper Barges is estimated at 21 months and for the second set of 02 Self Propelled Split Type Hopper Barges by foreign bidders 24 months. The period for transportation to Karachi is estimated as 03 months. During the financial evaluation of bids for comparison purpose US$ 100,000.00 per month shall be added in the offered bid price against longer delivery than 24 and 27 months by local bidder and for arrival of Hopper Barges in Karachi by foreign bidders.

25.2 To facilitate evaluation and comparison pursuant to clauses of these documents the Employer will convert all Bid prices if expressed in various currencies to the single currency (Pakistan Rupee) at the selling exchange rate established by the National Bank / State Bank of Pakistan, for similar transactions, on the date of bid opening.

IB.26 Detailed Evaluation of Bids:

26.1 The Employer / Engineer will evaluate and compare only the bids previously determined to be substantially responsive pursuant to Clause IB.24 ‘Preliminary Examination & Determination of Responsiveness of Bids’ as per requirements given hereunder:

.

The bids have been received in two separate envelops, containing “Technical Proposal” and “Financial Proposal” at the due date and time. Envelopes for Technical Proposals will be opened and will be examined in the following order to assess their eligibility for further consideration:-

(a). Those Two Inner envelopes marked “Technical Proposal” and “Financial Proposal” and covering letter with each envelope indicating the contents of envelopes have been submitted.

(b). The bid security and it’s amount and validity viz a viz the clauses of Instruction to Bidder is in order.

Page 121: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

(c). Check contents of the envelopes marked “Technical Proposal”

(d). Examination of bidder’s response for all the documents of his bid contained in the envelope marked “Technical Proposal”

.

(e). Examination of the Bidder’s response to the sections (I through VI) of the bid documents i.e. Form of Tender, Instruction to Bidders, General Conditions, Special Conditions, Technical specifications and G.A. Plan, Technical Schedule and other requirements, Clause by Clause Commentary, list of deviation (if any).etc. for substantial responsiveness and no material deviation.

(f). The detailed evaluation of Technical Proposal shall be carried out as per following clause 26.2. Only the technically qualified Bidders shall be eligible for further consideration of opening their financial Proposal.

(g). The retained, unopened envelopes for Financial Proposal of only the technically qualified Bidders shall be opened publicly as per venue to be announced later and examination of the same shall be carried out in accordance with the clauses of ITB for evaluation of the “consolidated cost for comparison” and the lowest cost Bidder shall be recommended for award.

(h). The disqualification at any stage during examination for technical qualification and examination of Financial Proposals shall be conveyed in writing to the respective Bidders and their bid securities shall be returned pursuant to clause 15 of ITB.

26.2 Evaluation and Comparison of Bids:

After the bids have been received and opened (only technical Proposals) examination shall be carried out in the following manner:-

(a). Technical Proposals and subsequently provided clarification, if any shall be evaluated to assess the responsiveness and level of compliance to the set of issued bid documents. The Bidder will have to fill in the blank spaces for

Page 122: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

Technical Details and may additionally provide the details if not asked for. Information for all the proposed machinery, equipment and materials for their make, capacity, size and origin be essentially given, non-compliance of any of the essential technical parameter and terms and conditions of the bid documents, instructions to Bidders shall provide basis for technical disqualification of a bid.

(b). For fair Technical Evaluation of Bidders of different status, capability and experience and offered four Split Hopper Barges built to different specifications, Table A “CHART FOR EVALUATION” has been drawn with minimum 70% compliance to the requirements mentioned therein. Evaluation Criteria for Technical Specifications has been drawn at Table B “EVALUATION CRITERIA FOR TECHNICAL SPECIFICATION OF FOUR SPLIT HOPPER BARGES” with minimum 70% compliance to the specifications mentioned therein. Both tables A & B have been placed in Annexure-I.

(c). After completion of examination of all received Bids for Technical Evaluation of the Bids, Financial Proposals of only the technically qualified bidders, who have scored minimum 70% qualifying marks and who have already furnished the accepted and valid Bid Security and their Financial Proposal in the manner as described in Sub-Clause 18.10, shall be opened publicly at a date and time to be announced later.

(d). Retained un-opened Financial Proposals of bidders, evaluated “technically dis-qualified” for opening of Financial Proposals shall be returned pursuant to Clause 15.

(e). Bids with any allowance or conditions requiring price adjustment during the period of execution of the Contract shall not be considered for financial evaluation and rejected being not the fixed priced. Additional provision offered if any, over and above the condition of contract / technical specification shall not be taken into account during the financial evaluation of bids.

26.3 Evaluated Bid Price:

Employer evaluation of Bids will take into account the bid price for the supply of Four Self Propelled Split Type Hopper Barges along with all accessories, provisions, services, warranty and training etc. in strict accordance with the terms

Page 123: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

of the bidding documents.

Generally the bid price to be quoted in their bid by each of the foreign and local Bidder shall generally be for the following:-

Foreign Bidder: All cost for the design, construction and supply of Four Self Propelled Split Hopper Barges at Karachi along with all accessories, provisions, services, warranty and training etc. in strict accordance with the terms of the bidding documents. Transportation cost (including Freight and voyage insurance) all duties and taxes in and out side Pakistan etc. other than Custom Clearance and Registration in Karachi which would be arranged by Employer. Insurance of work till star of warranty period of the delivered Four Self Propelled Split Hopper Barges shall also be to bidder’s account.

Local Bidder: All cost for supply of Four Self Propelled Split Hopper Barges along with all accessories, provisions, services warranty and training etc. in strict accordance with the terms of the bidding documents shall be included in the bid price. All duties and taxes in and outside Pakistan during the entire period of contract and registration of Four Self Propelled Split Type Hopper Barges and Insurance of work till start of warranty period of delivered Four Self Propelled Split Type Hopper Barges shall also be to bidder’s account.

26.4 The Employer's evaluation of Bids will take into account, the following factors, in the manner and to the extent for arriving at the consolidated cost for comparison:

(a) Delivery schedule offered in the Bid:

After the first payment has been released by the Employer in favour of successful foreign or local bidder, Four Self Propelled Split Hopper Barges is required to be made ready for ex-yard delivery or subsequent shipment for arrival at Karachi Port complete, consolidated as given in the pertinent Clauses of these documents in a period such that:

- Two sets of two Split Hopper Barges each by Foreign Bidder from outside Pakistan shall arrive at Karachi Port in 24 and 27 months

Page 124: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

respectively, classed by Classification Society (B.V, or Lloyd’s), insured and will be delivered to the Employer after repeat acceptance tests and trials at Karachi have been carried out during a fortnight after clearance by the Employer.

- Two sets of two Split Hopper Barges each by Local Bidder from within Pakistan have been registered with Pakistan Flag Authority, classed by Classification Society (B.V, or Lloyd’s), insured and all tests and trials have carried out thereafter delivered completely in all respects to the Employer in 24 and 27 months .

- Delays for each day over and above the date of arrival of Four Self Propelled Split Hopper Barges at Karachi by Foreign Bidder in 24 and 27 months and date of completed delivery by local bidder in 24 and 27 months shall be accounted for by adding to the offered cost for evaluating the consolidated cost for comparison only, as against the longer delivery @ US$ 100,000 per day per month.

-

(b) Deviations in payment schedule, from that specified in the Special Conditions of Contract;

The Special Conditions of Contract indicate the payment schedule in Clause 19.10 offered by the Employer. If a Bid deviates from the payment schedule and if such deviation is considered acceptable to the Employer and the bid is not rejected for deviation on this account then, the Bid will be evaluated by calculating interest earned for any earlier payments involved in the terms outlined in the Bid as compared to those stipulated in this invitation, at a rate of 16% per annum and adding it to the offered cost.

(c) Cost of Spare Parts (refer to clause 17 of GC)

Page 125: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

The cost of one year consumable spare parts, Class recommended spare parts and manufacturer’s supplied spare parts and tools (Bidder shall provide the list for each) shall be inclusive in the offered cost. Other spare parts listed in GC Clause 17.1 (d) are to be included in bid price as per Price schedule

(d) Performance and Productivity of the Equipment:

Performance, productivity and other factors, as in the Bid, will be assessed and evaluated in accordance with Technical Specifications for a quality product conforming to the announced specification, use of purpose and the Bidder’s commitment for providing training and to abide one year guarantee for prompt rectification of defects.

(e) The cost effect of the Bidders non-compliance(s) to the Technical Specification / Technical Schedule and terms and conditions where applicable shall be added to the quoted fixed cost for arriving at the consolidated cost for comparison.

Commitment of local bidder, during the period one year guarantee is completed local bidder shall be committed to bear all cost for:-

i. Berthing / un-berthing, Docking / un-docking of Four Self Propelled Split Hopper Barges at their yard as per requirement.

ii. Warehousing of all items pertaining to the Four Split Hopper Barges.

iii. Registration of Four Self Propelled Split Hopper Barges with Mercantile Marine Department and

iv. Maintenance of Classification.

Page 126: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

v.

IB.27 Domestic Preference:

27.1 The bidders offering vessels from within Pakistan, Provided the Bidder shall have established to the Satisfaction of the Employer that the manufacturing cost of such vessels includes a domestic value addition equal to at least 20% of ex-Yard Bid price of such vessels. Bidder applying for domestic preference shall fill in Appendix B of these instructions to substantiate their claim for Domestic preference in accordance with the PPRA Rules – 24(2). The entitlement and extent of presence shall be in accordance with the policies of the Federal Government and /or as described in the SRO 827(1)/2001 dated 03 rd Dec 2001 for the Engineering Goods listed in Custom General Order 07 of 1998.

27.2 The comparison shall be Ex-factory price of vessels to be offered from within Pakistan (such prices to include all costs as well as custom duties and taxes paid or payable on KoM and components incorporated or to be incorporated in the construction of the vessel and the DDP (CIF + Customs duty, sales tax and others import charges) Pakistan seaport price of the vessel to be offered from outside Pakistan.

27.3 The lowest evaluated bid of each group shall first be determined by comparing all evaluated bids in following groups among themselves taking into account:

a) In the case of Goods manufactured in Pakistan, sales tax. Local body charges and other similar taxes which will be payable on the finished Goods in Pakistan.

b) In Case of Goods of foreign origin offered from abroad, customs duties, sales tax and others import charges which will be payable on finished Goods in Pakistan.

c) In the case of Goods of foreign origin already located in Pakistan, customs duty, sales tax and import charges on CIF prices as applicable for sub-clause 27.3(b) here above.

27.4 The price preference to Group (a)bids will be:

Page 127: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

I. 15% of the ex-factory bids price, if the value addition through indigenous manufacturing is at least 20%.

II. 20%of the ex-factory bid price, if the value addition through indigenous manufacturing is over 20% and upto 30% and

III. 25% of the ex-factory bid price, if the value addition through indigenous manufacturing is over 30%.

27.5 The applicable price preference i.e. as per Sub-Clause 27.4 here above will be applied to Group (a) Bid by reducing the ex-factory bid price. The bid evaluated as technically qualified and the lowest in cost shall be recommended for award of Work.

IB.28 Process to be Confidential:

28. 1 Subject to Clause 23 heretofore, no Bidder or his representative(s)/ associates at his own shall not contact Employer / Engineer on any matter relating to its Bid from the time of the Bid opening to the time the bid evaluation result is announced by the Employer. The evaluation result shall be announced at least ten (10) days prior to award of Contract.

The announcement to all bidders will include table(s) comprising read out prices, discounted prices, price adjustments made, final evaluated prices and recommendations against all the bids evaluated.

28.2 Any effort by a Bidder to influence Employer/ Engineer in the Bid evaluation, Bid comparison or Contract Award decisions may result in the

rejection of his Bid.

28.3 Whereas, any bidder feeling aggrieved may lodge a written complaint not later than ten (10) days after the announcement of the bid evaluation result, however, mere fact of lodging a complaint shall not warrant suspension of procurement process.

Page 128: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

F. AWARD OF CONTRACT

IB.29 Post Qualification:

29.1 The Employer, at any stage of the bid evaluation, having credible reasons for or prima facie evidence of any defect in supplier’s or contractor’s capacities, may require the suppliers or contractors to provide information concerning their professional, technical, financial, legal or managerial competence whether already pre-qualified or not:

Provided that such qualification shall only be laid down after recording reasons thereof in writing. They shall form part of the records of the bid evaluation report.

29.2 The determination will take into account the Bidder’s financial, technical and production capabilities. It will be based upon an examination of the documentary evidence of the Bidder’s qualification submitted under Prequalification Documents, as well as such other information as required under the Bidding Documents. In pursuance of clause 23.3 the Employer may carry out physical examination of Bidder’s facilities / production capabilities and product performance etc. for his post qualification.

29.3 An affirmative determination will be a pre-requisite for award of the Contract to the lowest evaluated Bidder. A negative determination will result in rejection of that Bidder’s bid in which event, Employer will proceed to undertake a similar determination of the next lowest evaluated Bidder's capabilities to perform the Contract satisfactorily.

IB.30 Award Criteria:

Subject to Clause IB.32, the Employer will place the “Letter of Award” on the successful Bidder whose Bid has been evaluated to be substantially responsive during the technical evaluation of bids and for price comparison has been

Page 129: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

evaluated as the financially lowest cost Bid, provided that such Bidder has been determined to be qualified to satisfactorily perform the Contract in accordance with the provisions of Clause IB.29.

IB.31 Employer’s Right to Vary Quantities at Time of Award:

The Employer reserve the right at the time of award of Contract to increase or decrease the quantity of work components and other provisions etc. of the Four Split Hopper Barges up to fifteen (15%) without any change in the quoted unit rate and terms and conditions of the bidding documents, or as subsequently modified, if any.

IB.32 Employer’s Right to Accept Any Bid and to Reject any or all Bids:

32.1 Not withstanding Clause IB.30 the Employer reserves the right to accept or reject any or all Bids, and to annul the bidding process at any time prior to award of Contract, without incurring any liability to the affected Bidder or Bidders or any obligation to inform the affected Bidder or Bidders of the grounds for the Employer’s action.

32.2 No negotiations with the Bidder having been evaluated as lowest responsive or any other Bidder shall be permitted. However, the Employer may have clarification meeting(s) to get clarify any item(s) in the bid evaluation report.

IB.33 Notification of Award:

33.1 Prior to the expiration of the period of Bid validity, the Employer may notify the successful Bidder in writing (“Letter of Award”) by registered letter or by fax, that his Bid has been accepted. This letter shall name the sum which the Employer will pay the Contractor in consideration of the execution and completion of the Works by the Contractor as prescribed by the Contract (hereinafter and in the Conditions of Contract called the “Contract Price”).

Page 130: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

33.2 The “Letter of Award” and its acceptance by the Bidder will constitute the formation of the Contract, binding the Employer and the Bidder till signing of the formal Contract Agreement.

33.3 Upon the successful Bidder's furnishing an affirmative response to the “Letter of Award” pursuant to clause 33.1 and formal contract has been entered into, the Employer will promptly notify each unsuccessful Bidder and will discharge their Bid security, pursuant to Clause 15.

IB.34 Performance Security:

34.1 Within 14 days of the receipt “Letter of Award” from the Employer, the successful Bidder shall furnish the performance security in the form of acceptable Bank Guarantee, issued by a scheduled bank in Karachi-Pakistan except Unite Bank Ltd. of value 10 % of the contract price or as entered in the “Letter of Award”, in accordance with the Conditions of Contract and the Performance Security Form & Integrity Pact provided by Employer or as conveyed by Employer

34.2 Failure of the successful Bidder to comply with the requirement of furnishing the Performance Security and Integrity Pact in accordance with sub clause 34.1 or clause IB.35 or clause IB.36 shall constitute sufficient grounds for the with-drawl of the Letter of Award and forfeiture of the Bid security of the successful Bidder

IB.35 Signing of Contract Agreement:

35.1 Within fourteen (14) days from the date of furnishing of acceptable Performance Security and Integrity Pact under the Conditions of Contract, Bidder shall prepare and present to Employer for signature, 06 sets of Contract Agreement after the same have been court stamped (each page) followed by the payment of stamp duty at prescribed rate by the contractor to the concerned revenue earning department, without recourse to Employer and to furnish to Employer the receipt

Page 131: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

for the payment made by the Successful Bidder towards Court Stamping of the contract.

35.2 The formal Agreement between the Employer and the successful Bidder shall be executed within fourteen (14) days of the receipt of such Form of Contract Agreement by the successful Bidder from the Employer.

IB.36 Integrity Pact:

The Bidder shall sign and stamp the Integrity Pact provided at Schedule-H to Bid in the Bidding Document for all procurement contracts exceeding Rupees ten million. Failure to provide such Integrity Pact shall make the bid non-responsive

Appendix – A to

Instructions to Bidders

EVIDENCE OF BIDDER’S CAPABILITY

[Note: Bidders to provide the following information with the bid separately and indicate herein its references where this information is available.

S No. Information o to be supplied Bid References1

2

Name of bidder, business address and country of incorporation.

Type of firm whether individually owned, partnership, corporation of joint venture and the names of its owners or partners.

Page 132: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

3

4

5

6

7

8

9

10

11

The annual reports of qualification statements giving general des description of the firm, sort of business carried out, balance sheets, profit and loss statements, turn over and business done by the firm, duly authenticated, for the last three (3) years. Audited Balance Sheets for the preceding 3 years and project assets and liabilities for the next 2 years shall be provided.

Location and address of manufacturing facilities.

Full description of factories owned and the annual manufacturing capacities of various items made therein..

Details of the factory of factories where the offered equipment is proposed to be manufactured. This description should include the facilities and capacities of the particular factories including testing facilities and the processes used in manufacturing and testing. Where parts of components are purchased from outside, the details of equipment purchased and the names and experienced record of the suppliers.

Detailed description of the quality control testing and research facilities. If the equipment is manufactured under license, the name of the licenser and details of the licensing arrangements, such as the duration of the license, the facilities provided to the bidder by the licenser and whether future improvements are available or not etc. A copy of the license agreement may be attached.

Names, qualifications and experience of the key technical personnel.

The time since the manufacturer has been in this business and the time since he has been doing work of similar nature.

The time since the particular equipment offered has been manufactured and the time for which it has been in service. The manufacturer shall have the following experience.

(List of the equipment and experience required)

Reference lists of similar works done by the bidder in its country and abroad indicating the name of customer, description and quantity of product, year of supply and the approximate value.

Page 133: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

12

13

14

Details of projects under execution and future contractual commitments (for each partner, in case of a joint venture).

Banking reference, names of banks and addresses may be given to whom reference regarding financial capability of the bidder may be made, with authority to make inquiries from the bidder’s bankers and clients regarding any financial and technical aspects (for each partner, incase of a joint venture).

Information on any litigation or arbitration resulting from contracts completed or under execution by bidder over the last ten (10) years. The information shall indicate the parties concerned, the matter of dispute, the disputed amounts and the result thereof (for each partner, in case of a joint venture).

Page 134: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

Appendix – B to

Instructions to Bidders

Domestic Goods (Value added in Pakistan)

[Bidder claiming eligibility for domestic preference should fill in for supply items only all columns hereunder and provide necessary documentation to substantiate their claim]

Sr No

Description of indigenous Goods

Unit Qty Total Price of Goods Ex- Factory (Pak Rs.)

Domestic value added in the manufacturing cost as percentage 0 Ex-factory Price

Amount of value addition (Pak Rs.)

1 2 3 4 5 6 7

Total in Column 5 & 6

Computations:

Page 135: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

A. Total amount of Value Addition (from Col.7)Rs._____________________

B. Total Ex-factory Price of Indigenous Goods (from col.5) Rs._____________________

C. Total DDP Price of imported supply items Eqv. Rs.._________________

D. Total Price of supply items [B+C] Eqv. Rs_________________

E. % of value addition =[(A/D)x100] ___________________%

F. domestic Preference = (15,20 or 25)% of B Rs._____________________

SECTION – IV

SPECIAL CONDITIONS OF CONTRACT (SC).

The following Special Conditions of Contract in continuation of the General Condition of the Contract and Instructions to Bidders are specific terms of the bidding documents namely “The Standard Form of Bidding Documents for Procurement of Works” available at Pakistan Engineering Council’s web site www.pec.org.pk which document is an integral part of this set of bidding documents.

The Clauses of Special Conditions of Contract shall be addition to the General Conditions of Contract for being specific. The corresponding clause number of the General Conditions is indicated in parentheses.

At any time during currency of the contract the Engineer is not available or announced by Employer the General Manager of Planning and Development Division of Employer will act in that capacity.

1. Definitions (Clause 1):

(a) "The Employer” is the KPT (The Board of Trustees of the Karachi Port) as defined

Page 136: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

hereafter.

(b) "The Chairman" means the Chairman of the KPT or such person as may be acting in that capacity. The Chairman is also the Chairman of the Board of Trustees- KPT and issues instructions on behalf of the Board.

(c) “The Contractor” is (Name of Contractor/Bidder who enters into a contract Agreement with the Employer/KPT for tender work).

(d) “The Contract” means the agreement entered into between the Employer and Contractor, as recorded in the Contract Form signed by the parties, including all attachments and appendices thereto and all documents incorporated by references therein;

(e) “The Engineer” means a consulting firm / person(s) appointed by Employer within the scopes of this Contract or their successors of others persons appointed by the Employer to act in that capacity. Engineer further means the authorized representative(s) of the Employer and / or aforesaid consulting firm approved by the Employer.

(f) “The Government means” the Government of the Islamic Republic of Pakistan.(g) “The Goods” means, “the Marine Crafts along with all accessories, provisions and

services intended to be procured by the Employer” as defined thereafter.

(h) “The Marine Crafts” means the Four self Propelled Split Type Hopper Bares Works or services along with all required installations, to be constructed, tested, delivered at Karachi Port and guaranteed all under the terms of this contract.

(i) Day, Week, Month and Year in the Contract means, except where the Contract otherwise requires, calendar-day calendar-week, calendar-month and calendar-year according to the Gregorian calendar.

(j) “The Specifications” means the relevant technical documents, included in the contract and as interpreted by the Engineer / Employer.

(k) “The Bid Drawings” means the drawings (if any) included in the Bidding Documents.

(l) “Approved” means written approval by the Employer or Engineer as indicated in this Contract. Any document, data or drawings submitted with the Bid are only then deemed as approved, when expressly so fixed in the contract.

Page 137: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

(m) “Approval” means written approval including the aforementioned.

(n) “The Site” means the actual place where the Marine crafts are to be constructed by the Contractor under the contract and places involved in the manufacture, assembly, test and trials before handing over of the contracted goods.

(o) “Pak. Rupees or Rs.” means Pakistan Rupee.

(p) “The Foreign Currency” means the currency, other than Pakistani Rupees, named in the Bid Form by the Contractor.

(q) “The Works” means the construction, testing, delivering at the site(s) / Karachi Port and the guarantee of the Contracted Goods as described in the contract.

(r) “Services” means services ancillary to the supply of the Goods, such as transportation and insurance, registration and any other incidental services, such as warranty obligation, commissioning, provision or technical assistance, training and other such obligations of the Contractor covered under the contract.

1.1 Words used only in the singular, also include the plural and vice versa where required by the context.

1.2 Words used for persons shall include firms and corporations.

1.3 The marginal heading and notes of these Conditions of Contract do not represent a part of these Conditions and have no influence on the construction or interpretation of the Contract.

2. Application (Clause 2):

2.7 The Contract comprises the construction, storage, supply, shipment, provisions, services, completion, delivery, handing over and guarantee of the Four Self Propelled Split Type Hopper Barges and in so far as not otherwise specified in the Contract, provision of all labour, materials, , constructional plant, temporary works and everything whatsoever whether of a permanent or temporary nature required to comply with

Page 138: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

provision as specified in the contact or is to be reasonably inferred from the contract.

2.8 The Employer shall not be liable to the Contractor for any matter or thing arising out of or in connection with the Contract unless the Contractor shall have made a claim in writing as provided under the Contract in respect thereof before the issue of the acceptance/ completion Certificate under this Clause, and the basis and amount of any such claim have been examined and approved by the Engineer / Employer if justified.

3. Country of Origin (Clause 3):

3.4 All countries accepted by the Government of Pakistan for the purpose.

4. Standard (Clause 4):

4.2 The Four Self Propelled Split Type Hopper Barges shall be built under survey and to the requirement of the Classification Society, preferably the LRS or B.V. as accepted by Mercantile Marine Department-Government of Pakistan (MMD).

4.3 As far as the execution of the Works has not been minutely laid down in any regulation and/or Specifications this shall be affected to the best of the Contractor’s knowledge and experience and the workmanship and materials used shall be of highest quality to the approval of Engineer all conforming to the standard of classification society and other Maritime Standards / Regulation.

4.4 Classification, survey and testing charges relating to the Contractor's obligations and items of supply under this Contract shall be for account of the Contractor. Testing and issuing of the corresponding certificates of parts which are not officially subject to Classification survey, can be required by the Engineer / Employer and all costs shall be borne by the Contractor.

4.5 On Technical matters the decisions of the Classification Society (LRS or B.V) shall be final and binding on both parties for the design, construction and tests and trials of Four Self Propelled Split Type Hopper Barges.

Page 139: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

During the supply and tests and trials of Four Self Propelled Split Type Hopper Barges all rules of Marine / Maritime organizations shall be followed to produce the sea worthy and standardized Four Self Propelled Split Type Hopper Barges complete with all provisions and facilities, Safety, Nautical, Communication, Deck and Propulsion equipment, Fixed Machinery / items etc whether mentioned or not mentioned in the Technical Specification or other parts of the bidding documents.

4.6 Since the Four Self Propelled Split Type Hopper Barges shall be registered in Pakistan therefore, during construction the rules of the Pakistani Flag Authority – MMD shall be followed where applicable. In this regard the Classification Society (L.R. or B.V) shall obtain necessary authorization from Pakistan Flag Authority (MMD). The contractor shall assist by providing all certificates, documents and drawings, surveys, inspection in connection with registration of the Four Self Propelled Split Type Hopper Barges local bidder shall deliver the Four Split Type Hopper Barges duly registered with MMD.

5. Use of Contract Documents Information (Clause 5):

5.4 The various documents forming the Contract shall be viewed as mutually explanatory. In the event of any ambiguity or contradiction, which are found in these documents, the Contractor shall immediately bring them to the notice of the Engineer who, after due consideration, shall thereupon issue instructions to the Contractor directing in which manner the works shall be executed.

6. Performance Security (Clause 7):

7.5 The Performance Security shall be in the form of Bank Guarantee issued by a first class + A1 rating bank located in Karachi except United Bank Ltd. and in the local currency (Pak. Rupees) for an amount of 10% of the fixed Price finally accepted by the Employer and entered in the Letter of Acceptance. Availability with the Employer of a valid and accepted performance bank guarantee in the prescribed format and amount from the date of signing contract till the date of completion of warranty period of Four Split Type Hopper Barges is necessary for clearance of the Contractor’s claim(s) / dues of any nature and for contractual payments etc.

Page 140: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

7.6 Full or part thereof the amount of the Performance Bank Guarantee shall be forfeited by Employer if the Contractor fails to perform in accordance with the Contract. Provided an extension in the validity of Performance Bank Guarantee is required the Contractor shall arrange the same within three days before the date of expiry otherwise the Employer shall proceed to cash the guarantee sum before its expiry. The Performance Bank Guarantee shall be released three days after completion of warranty period of the Four Self Propelled Split Type Hopper Barges.

7. Engineer and Engineer’s Representative (clause 8)

8.8 The duties of the Engineer shall be to monitor and supervise the construction, supply, testing, trials safe transportation etc. delivering and handing over of Four Self Propelled Split Type Hopper Barges as well as to check and examine all drawings and design, materials, workmanship, machinery and equipment etc. to be used and all performances and deliveries required in connection with the Contract (between Employer and Contractor), including follow up of the Rules of Classification, IMO, MARPOLE, SOLAS and Pakistan Flag Authority (MMD) as may be applicable, checking and examining the guarantee obligations. He is not authorized to relieve the Contractor of any of his duties or obligations under the Contract or, if not expressly foreseen in the following or elsewhere in the Contract and approved by the Employer, to order any work which could result in major additional payment on the part of the Employer, or to approve any major change with regard to the delivery period of Four Self Propelled Split Type Hopper Barges.

8.9 Any formal Approval of the Engineer in no case releases the Contractor from his sole responsibility and liability for the supply of Four Self Propelled Split Type Hopper Barges and its parts in accordance with the Contract.

8.10 The Contractor is obliged to supply all drawings, calculations, documents (separately for each machinery/sub-assembly the Instruction for Operation, Maintenance and Catalogue with Code Number of each spare part for future procurement of Spare parts etc.), as determined by Employer, Contractor and/or the Engineer, that are necessary for the supply of Four Self Propelled Split Type Hopper Barges. These shall include, but not necessarily be limited to those mentioned in the Specifications.

8.9 Any formal approval of the Engineer in no case release the Contractor from his sol

Page 141: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

responsibility and liability for the Supply of Four Self Propelled Split Type Hopper Barges and its parts in accordance with the contract.

8.10 The contractor is obliged to supply all drawings, calculations, documents (separately for each machinery / sub-assembly the Instruction for Operation, Maintenance and catalogues with code number of each spare part for future procurement of spare parts etc.) as determined by Employer, Contractor and / or the Engineer, that are necessary for the construction of the Four Self Propelled Split Type Hopper Barges. These shall include, but not necessarily be limited to those mentioned in the Specifications.

8.11 All drawings and calculations prepared by the Contractor shall be submitted to the Engineer for checking and approval allowing sufficient time for the Engineer to make his required investigations and checks but, in any case not less than twenty one (21) working days prior to the time required for approval. The purpose of such checks is to assist the Contractor in the interpretation and use of the Specifications, Technical and Special Conditions of Contract and other provisions of the Contract, and hence no claim whatsoever from the contractor shall be entertained for delays in the performance of the contract on this account.

8.12 Copies of drawings for preliminary check shall be submitted in quadruplicate each to Head Office of the Engineer. After conclusion of the preliminary check, 1 (one) copy each shall be sent to the Contractor for incorporating the corrections and supplementation, one copy of the Site office of the Engineer and one copy to the Employer for record.

8.13 The Contractor shall furnish to the Engineer three copies of all mill, test, or other certificates obtained by the Contractor evidencing quality or fitness of materials and workmanship etc.

8.14 Tests and trials shall be carried out to the Contractor’s program as conveyed to the Engineer by the Contractor. They shall be performed in the presence of nominated representatives of the Employer and the Engineer and shall be at the expense and risk of the Contractor including all repeated actions, if any and all visit cost for the Employer’s representatives.

8.15 Repeat Tests and Trials of the imported Four Self propelled Split Type Hopper Barges

Page 142: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

shall be conducted following arrival at Karachi. The test shall be a repeat exercise of the previously carried out tests in the country of origin at the builder’s yard and would be to demonstrate that the imported Four Split Hopper Barges are not ill-affected during transportation. The repeat / confirmatory Tests at Karachi shall be at the risk and cost of contractor and the contractor shall immediately carry out the remedy of deficiency(s) observed if any during above repeat test.

8.16 In the event of defects or omissions for which the Contractor is liable under the provisions of the Contract, being revealed by the test-trials and / or resulting from inspections, the Contractor shall remedy the same and if the Engineer considers necessary, new tests shall be made at the Contractor's expense and risk, to establish that the Four Self Propelled Split Type Hopper Barges are complete in all respects according to the Contract.

8.17. On the completion of the technical and other trials near the yard (and prior to the transport to Pakistan) the machinery and equipment shall be inspected by the Engineer and Employer and if such shall be deemed necessary, engines top or any other equipment shall be opened and any deficiencies shall be remedied.

8.18 As soon as, in the opinion of the Engineer, the Four Self Propelled Split Type Hopper Barges have been completed and have satisfactorily passed the repeat tests and trials at Karachi and as may be required towards assurance on use of purpose and to meet the maritime rules/regulations and provided the Four Self Propelled Split Type Hopper Barges have been fully registered with MMD (For local bidders only) and are in good working order, finished perfectly as per contract by putting thereon all loose inventory, consumable and spare parts carefully stored on board, and Employer has received a written undertaking from the Contractor to finish any outstanding work during the first 15 days after the Four Self Propelled Split Type Hopper Barge(s) have arrived in Karachi and Custom Cleared, the one year guarantee period shall start thereon.

8.19 The Four Self Propelled Split Type Hopper Barges shall be transported at the Karachi Port, with proper approved marine insurance (inclusive of Piracy clause) and all other clearances.

8.20 The bottom inspection of Four Self Propelled Split Type Hopper Barges on arrival in Karachi may be carried out on the means of transport or a Classification approved diver’s report for bottom inspection may be considered as to be inspection in dry dock

Page 143: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

provided the surveyors of MMD and / or Classification may accept the above inspection on means of transport or the diver’s report, as bottom inspection, as was to be carried out in dry dock. The bottom inspection shall also be applicable in the same manner to the Four Self Propelled Split Type Hopper Barges constructed in Pakistan.

8. Delivery and Documents (Clause 13):

13.3 Upon shipment of the imported Four Self Propelled Split Type Hopper Barges, the Contractor shall notify the Employer by fax or courier and electronic mail the full details of the shipment including contact number, description, quantity, the bill of lading number and date, port of loading, date of shipment, port of discharge, etc. The Contractor shall mail the following documents to the Employer’s bankers, with a copy to the Insurance Company:

(i) 6 Copies of the Contractor's invoice showing the Four Self Propelled Split Type Hopper Barges description, quantity, unit price, total amount and Packing list.

(ii) Original and 6 copies of the negotiable, clean, on-board bill of lading marked freight prepaid and 12 copies of non negotiable bill of lading;

(iii) The complete vessel with all accessories provisions, martial all as (iv) indicated in the contract or subsequently ordered by the Employer, shall be referred

as to one package and copies of packing list identifying contents of each packets / boxes.

(iv) Insurance Certificate;

(v) Manufacturer's Contractor's guarantee certificate;

(vi) Inspection Certificate as issued by the Engineer and Insurer.

(vii) Certificate of Origin.

(viii)Free from Lien Certificate.

(ix) Builder Certificate

(x) Any other certificate / official document related with the export of contracted goods and as may be required by the Employer.

The above documents along with any other document required in addition to above shall

Page 144: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

be received by the Employer’s bankers which will be retired by Employer for further processing. , If the shipping documents are not received, the Contractor shall be responsible for any delays / expenses and related consequences etc.

13.4. After the repeat test at Karachi has been carried out and in pursuance of General Conditions clause 9.1 one year warranty period has started, every responsibility for the operation, maintenance, safety and generally for the condition of the contracted goods shall be transferred to the Employer and thereafter all responsibility on the part of the Contractor shall cease with the exception of the guarantee and training obligations and services provided for in these Conditions of Contract.

13.5 The Contractor shall provide at the time of delivery in Karachi in six sets of each of the following (as may be applicable) i.e. consumable and standard spares, material, goods, tools documents, drawings etc.

a. Drawing and Plans (06 sets):

- Set of “as built” drawings.

- General arrangement plan.

- Deck Machinery Plans

- Machinery installation plan

- Electrical installation plan

- Outfitting installation plan

- Docking plan.

- Coloured Layouts for piping and cables for all systems.

- Sounding charts.

b. Certificates and Measurement Records and Lists:

- Workshop test certificates.

Page 145: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

- Harbour acceptance / quayside test record.

- Sea acceptance / functional test record.

- List of inventory and tools.

- Class certificate for all surveys under the purview of Classification.

- Load line certificate.

- Safety certificate.

- Tonnage measurement certificate.

- Rat proof certificate.

- LSA, FFA certificates.

- Marpole certificate.

- Certificates by Class and local maritime / Flag authority for sea worthiness.

- Builder certificate.

- Ownership / lien / mortgage certificate / documents for de-registration (if applicable).

- List of Consumable items such as filters, hoses, fuses, ICs etc. grease, lubricants.

- Certificate of no lien.

- Any other similar document required by Employer.

- MMD Registration certificates (by local bidders only).

- Putting up of Four Self Propelled Split Type Hopper Barges under Class (LR or BV) up to the end of warranty period of delivered Four Self Propelled Split Type Hopper Barges.

c. Booklets / Instruction Manuals / Brochures (06 sets each):

- Stability booklet for inclination tests result and calculation thereof duly approved by Classification Society.

Page 146: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

- Catalogues for operation and maintenance of each machinery, instrument and system.

- Instruction for daily and periodical maintenance

- Maintenance procedure as recommended by the OEM (Original Equipment Manufacturers) for each sub-assembly.

- Complete description of machinery and materials used.

- List of recommended Spare Parts with complete description (Part Number, Drawing Number,) of each spares, unit price.

- Spare Parts catalogs with OEM’s Description for Part Number, Drawing Number, Unit Price. etc. and any other useful information as may be required at the time of future procurement of spares of main machinery (Propulsion system, Aux. engines, Hyd. system etc.).

- List of names and addresses of the designers, sub-contractors, manufacturers/Contractors of each sub-assembly, unit ,spare parts etc.

- All PLC / ELC software (including operational and trouble shooting) to be supplied in CD.

- Any other documentary information related with technical matters of the supplied Four Self Propelled Split Type Hopper Barges

d. Others:

- Photographs, installed /fixed and loose to be provided in frames.

- Two Model (as per scale of 1:50 ).

- Six numbers Souvenir Brass Plaques mounted on wooden base size 230 x 150 mm for each Barge with sketch of Split Hopper Barge, its particulars, engraved sketch, Year of Built, Builders Name, Employers data, etc.

- One large Brass Plate with above data to be fixed at prominent place of each Split Hopper Barge.

- Set of maintenance tools for main machinery and Propulsion systems etc. and other accessories.

- Touch-up Paints.

- Any other drawing, plan, certificate, booklet, document (related with the scope of

Page 147: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

contract work) as may be required by the Employer.

- Hard and Soft copies of the above drawings & documents be provided, as possible, except of the OEM’s printed material i.e. literature, brochures, leaflets for operation, maintenance and Spare parts manuals for main machinery etc.

9. Insurance (Clause 14):

14.2 The insurance of the contracted goods shall be for the full cover and in an amount equal to 110% of the Contract value of the goods from "warehouse to warehouse" (Construction yard to Karachi Port) on "All Risks" (except war risk and inclusive of piracy clause) basis and Employer shall all the time be entitled / beneficiary to an extent 10% more then it’s investment and for direct refunding of Insurance claim/s, if any.

14.3 The insurance shall be in the joint names of the Employer and the Contractor and shall be effective from the date after the advance payment has been fully utilized or a date before lodging claim for second contractual payment by the Contractor.

14.4 All premiums shall be for the Contractor’s account as to be under the Insurance cover for all the raw and finished materials, floating structures or parts thereof pertaining to this contract lying within the premises or control of the Contractor berthed or warehoused by him, within the period starting from the date of effectiveness of the Contract till start of one year guarantee period of Four Self Propelled Split Type Hopper Barges shall be taken care by the contractor for the safest custody and for the subsequent handing over to the Employer, without any charge.

14.5 All materials / goods shall be insured against all risks in the shipbuilding industry, including trials and transport to Karachi, for an amount equal to the Contract Price plus ten percent (10%), and further for any loss or damage occasioned by the Contractor in the course of any operation carried out by him for the purposes of complying with his obligations under various Clauses of the Contract.

14.6 The Contractor shall be obliged to produce to the Engineer and the Employer, the policies of insurance and the receipt for payment of the insurance premiums. The policies for insurance shall neither be altered nor terminated without the consent of the Employer.

Page 148: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

14.7 The Contractor shall indemnify and keep indemnified the Employer and the Engineer against all losses and claims for injuries or damage to any property whatsoever, which may arise out of or in consequence of the construction and delivery of the Four Self Propelled Split Type Hopper Barges and against all claims, demands, proceedings, damages, costs, charges and expenses whatsoever in respect of or in relation thereto.

14.8 Duly approved and all time valid and effective insurance(s) starting from a date before lodging second contractual claim by the Contractor till start of the one year warranty period of the Four Self Propelled Split Type Hopper Barges is mandatory requirement. If the Contractor fails to effect and keep in force the insurances referred to above, which he may be required to effect under the terms of the Contract, then and in any such case, the Employer may effect and keep in force the insurance and pay such premium as may be necessary for the purpose, and from time to time shall deduct the amounts, along with 20% mark-up, from any monies due or which may become due to the Contractor or recover the same as a debt due from the Contractor.

10. Incidental Services (Clause 16):

16.3 For the purpose of attending the warranty defects the contractor may acquire necessary technical support from local repairing agency(s)/workshop and would be firmly committed for prompt attendance on warranty issues for remedy of defects under warranty. The DDP (CIF + Customs duly, sales tax and other import charges) cost quoted by foreign bidder and ex-yard cost quoted by local bidder shall be inclusive of expense for removal of warranty defects and providing training to Employer personnel.

11. Spare Parts (Clause 17):

17.2 The Contractor shall furnish a list of spare parts which he may consider a requirement for initial three years maintenance (optional item) indicating quantity, complete nomenclature, Part No., Drawing No., Category / Sub-category etc. and the unit and total price for each item. The contractor shall provide detailed information to replenish and ordering of spare parts from the OEMs. The above list may be provided at a time before start of the warranty period of the Four Self Propelled Split Hopper Barges.

Page 149: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

12. Warranty (Clause 18) / Deductions from Performance Bank Guarantee or any other sum:

18.6 The Contractor shall guarantee that all goods, materials, machinery, equipment, outfit and workmanship are of standard shipbuilding quality and comply with the relevant provisions of the Contract and Specifications and the instructions of the Engineer. They shall be subjected to such tests from time to time, as the Engineer may direct at the place(s) of manufacture or fabrication at the site, or at all or any of such places, to facilitate such inspection and testing.

18.7 Warranty: The Contractor shall remedy at his own expense any defect due to bad workmanship, use of defective materials or faulty design, defective plant, machinery, equipment and installations, not discoverable until the start of warranty period but which becomes apparent during the period of 12 months from the start of warranty period and such defects have not aroused due to mishandling or operation by in-experienced and unqualified/uncertified operators (Nautical Captain / Master and his sub-ordinate staff on Board), mishap or improper maintenance or maintenance not in accordance with the manufacturer’s recommendations or the operation/maintenance of the main and other machinery by in-experienced and un-qualified/uncertified engineers.

Training: During the Guarantee period of twelve months of Four Split Hopper Barges the Contractor shall depute Guarantee Master, Guarantee Engineer and Technician on each Two Split Hopper Bares in a manner that at least three persons are present all time during the warranty period and 54 man months are completed. Preferable six persons may be deputed during initial six months and three persons for last six months.

The Contractor’s shall take care of all warranty issues for each of Four Self Propelled Split Type Hopper Barges during warranty period and will ensure after sale support to fully look after the warranty issues by themselves or via outside support.

The contractor’s personnel present on Four Self Propelled Split Type Hopper Barges shall provide necessary instructions / tainting to Employer’s crew for the operations and maintenance of the installed equipment / systems / machinery supplied under the contract for safe and efficient handling of the Four Self Propelled Split Type Hopper

Page 150: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

Barges for the proposed use.

18.8 During initial one year warranty period the Employer shall lodge the warranty claim(s) within 72 hours after discovery of a defect aroused due to warranty failures. The Contractor having accepted the claim shall necessarily undertake the rectification of defects by himself or by a local firm duly approved by the Contractor for the specified purpose for a settlement of the claim. In the event the warranty claim is not accepted the Contractor shall convincingly revert within 72 hours.

Discontinuation of the operational availability/function-ability of Four Self Propelled Split Type Hopper Barges for more than 14 days on account of the warranty defects would be subject to compensation by means of extending the validity of respective Performance Bank Guarantee or by making deductions from the Guarantee sum for an amount as per clause for imposition of LD for late delivery or by additional provisions/service, necessarily restricted to the function-ability of Four Self Propelled Split Type Hopper Barges or its components only. This would however not relieve the Contractor from his responsibility of removing the cause(s) of operational unavailability of Four Self Propelled Split Type Hopper Barges requiring removal of warranty defects.

13. Payment (Clause 19)

19.9 a) The date of release of advance payment by Employer shall be the date of effectiveness of contract.

b) Contractor may lodge claims for the part payments and furnish refund guarantees in accordance with the following Clause 19.10 of contract for not less than two barges.

19.10 Payment of the contract price shall be made by the Employer to the Contractor by installments as follows:-

In case of Foreign Bidders:

(1) 20% of the Contract Price. As advance payment, against a Bank

Page 151: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

Guarantee for equivalent amount in Pak. Rupees. The Bank Guarantee to be issued by Class – 1 Bank of rating + A1 / Schedule Bank approved by State Bank of Pakistan and operating in Karachi except United Bank Ltd.

(2) 20% of the Contract Price Not before Two (2) months following the date of release of advance / first payment provided that the first sections of the Four Split Hopper Barges have been placed and firm order for Steel, main Machinery, propulsion and auxiliaries sets have been placed with Sub-contractors and Engineer has issued the keel laying certificate(s)

(3) 25% of the Contract Price The launching of the last split Hopper Barges has been carried out and the main engines, propulsion machinery and Hyd. Equipment have been placed / fixed in position and all structural and fitting work has been completed up to or above the main deck level and Engineer has issued the launching certificate(s).

(4) 15% of the Contract Price After the quay side functional tests for idle running and full load running of all the equipment for Harbour and Sea Acceptance tests has been carried out at builder’s yard and the Engineer has verified separately for each Barge the conductance of above tests and results to conform the specifications and the split Hopper Bares have started sailing to Karachi.

(5) 17.5% of the Contract Price After all the contracted goods(i.e. 04 X Split Hopper Barges, Spares, Documentation, etc) completed as one package and has safely arrived in the Port of Karachi and shipping documents have been retired duly endorsed by the issuing bank in Karachi.

(6) 2.5% of the Contract Price After repeat tests have been completed in Karachi, compliance to all the clauses of contract for supply have been satisfactorily made or undertaking given for left over provision etc. and pursuant to clause 18 the warranty period has started.

Page 152: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

In case of Local Bidders:

(1) 20% of the Contract Price. As advance payment, against a Bank Guarantee for equivalent amount in Pak. Rupees. The Bank Guarantee to be issued by Class – 1 Bank of rating + A1 / Schedule Bank approved by State Bank of Pakistan and operating in Karachi except United Bank Ltd.

(2) 20% of the Contract Price Not before Two (2) months following the date of release of advance / first payment provided that the first sections of the Four Split Hopper Barges have been placed and firm order for Steel, main Machinery, propulsion and auxiliaries sets have been placed with Sub-contractors and Engineer

Page 153: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

has issued the keel laying certificate(s)

(3) 10% of the Contract Price The launching of the First set (02 in number) of split Hopper Barges has been carried out and the main engines, propulsion machinery and Hyd. Equipment have been placed / fixed in position and all structural and fitting work has been completed up to or above the main deck level and Engineer has issued the launching certificate(s).

(4) 10% of the Contract Price The launching of the Second set (02 in number) of split Hopper Barges has been carried out and the main engines, propulsion machinery and Hyd. Equipment have been placed / fixed in position and all structural and fitting work has been completed up to or above the main deck level and Engineer has issue the launching certificate(s).

5) 20% of the Contract Price After the quay side functional tests for idle running and full load running of all the equipment for Harbour and Sea Acceptance tests have been carried out at builder’s yard and the Engineer has verified separately for each Barge the conductance of above tests and results to conform the specifications as per the provisions of contract.

(6) 20% of the Contract Price After all the contracted goods (i.e. 04 x Split Hopper Barges, Spares, Documentation, etc) completed as one package and compliance to all the clauses of contract for supply have been satisfactorily made or undertaking given for left over provision etc. and pursuant to clause 18 the warranty period has started.

Eligibility for Payment

Except for first payment all other payment invoices of the contractor shall become eligible for processing only after the contractor has completed all obligations for the stage payment as per provision of the contract and furnished the documents which may be liable to be provided by him or as may be required by the Engineer, including the acceptable and valid Performance Bank Guarantee, comprehensive Insurance in the manner and stipulated sum and Engineer’s certificates etc. at the time of submitting the respective invoices.

Page 154: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

19.11 As a guarantee that the Contractor will use the advance payment of the accepted bid Price for the procurement of materials, equipment and out fit for the construction of the Four Self Propelled Split Hopper Barges, the Contractor shall at his own expense provide to the Employer with a Bank Guarantee for the advance payment in accordance with the Form –“C”. This guarantee shall remain in force until the Four Self Propelled Split Hopper Barges supplied by the Foreign bidders have arrived in Karachi and until start of one year warranty period of the locally manufactured Four Self Propelled Split Hopper Barges.

19.12 The Bank Guarantee for advance payment shall be in the local currency

(Pak.Rs) for an equivalent sum calculated at the selling rate of exchange of the day of effectiveness of the guarantee.

19.13 Property: After Employer has released the first installment of due the payment out of the Contract Price, every part thereof and all equipment, components and materials required or ordered by the contractor intending to use for the construction the Four Self Propelled Split Type Hopper Barges as a compliance to the contract, as soon as it or part thereof arrives in any of Contractor’s premises or Contractor’s yard shall deemed to have become Employer’s property without any argument. No mortgages or liens shall be registered or admissible against the contract goods, thereafter.

19.14 Except for the first installment, the contractor shall notify the Employer and Engineer at least 14 days in advance of estimated dates of sending his invoices along with the evidence for utilization of previously released sum, to prove that part of the works, which was invoiced, had been accomplished completely and in conformity, in all respects, with the contract, whereupon the Engineer shall confirm the same to the Employer. Similarly the Bank Guarantees shall be revalidated, if deemed necessary or asked by the Employer aleast two days before the date of expiry.

19.15 The amounts due for modifications under the terms of the contract shall be paid or credited in proportions corresponding with installments due at the date of the written approval for modifications and / or additions by the Engineer.

19.16 The amounts of liquidated damages due to delay in delivery of the Four Self Propelled Split Hopper Barges vide Clause 27.4, shall be calculated and determined by the Engineer on bi-monthly basis and shall be deducted from payments due to the Contractor or to become due. The finalized or balance (if any) amount of liquidated

Page 155: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

damages or else due to be deducted from the payable sums shall be deducted from the

last two invoices of the Contractor and / or performance bond. The Contractor may opt to compensate the Employer by making payments for the loss(es) sustained by him due to non-performance of Contractor, as to keep the Performance Bond intact.

19.17 Deductions: All costs of damages / non-performance or expenses disbursed by the Employer, for which the Contractor is responsible under this contract, may be deducted by the Employer from last two payments due to the Contractor or any other dues, and for the damages, non-compliance during the one year warranty period from the performance bond.

19.18 The Employer may withhold the whole or a part of any payment requested by the Contractor if it is necessary, in the opinion of the Employer, to protect itself against losses on account of defective work / service (as against the warranty), not rectified and delay in delivery of the goods. After the reasons for withholding of payments have been eliminated to the satisfaction of the Employer and / or Engineer, payments to the Contractor shall be released by the Employer without delay.

19.19 The Contractor shall submit all the accessories, provisions, service and documents and other essential things related to the Four Split Hopper Barges and may be required for their function / use, to the Employer as demanded and / or prescribed under the contract before claiming the final payment in respect of each Barge. After release of the final payment by Employer, the Contractor’s obligations under the contract shall cease except for the warranty matters and training, the Contractor shall have the right to lodge claim for his service / provisions etc. during warranty period, extended by him, if any, outside the contract provision.

19.20 Frustration: In the event of the Contract being frustrated, i.e. if the performance of the Contractor becomes physically and/or legally impossible, whether by war or otherwise, the Employer is not bound to pay any money to the Contractor in respect of the Work executed and the Contractor shall refund to the Employer within thirty (30) days after the date the frustration becomes apparent, the total amount of installments and all monies received by the Contractor from Employer, until the date of frustration and the property of the Four Split Hopper Barges and parts thereof, according to the conditions of Contract, will re-pass to the Contractor, after repayment has been made to Employer. The date of frustration shall be decided by the Engineer, who shall inform the Contractor about his decision in this respect by a registered letter.

Page 156: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

14. Prices (Clause 21):

21.2 The value of the Contract is for fixed-price. Hence, no price adjustment whatsoever shall be admissible in the Contract Price; except against specific provisions / services under variation order only pursuant to clause 22 of General Condition of Contract.

15. Subcontracting (Clause 25):

25.5 The Contractor remains fully responsible for the actions, defaults and neglects of any Sub-Contractor, or their representatives, staff and workers, just as for the actions defaults and neglects of his own representatives, staff and workers and obligations under the contract provision till such period that the one year guarantee time of the last delivered Barge has been completed.

16. Delays in Contractor’s Performance(Clause 26, Progress Reports):

26.4 In case of Force Majeure, the Contractor is entitled to an extension of time limit for delivery of the Four Split Hopper Barges as applicable only after the Contractor’s request has been supported by the Engineer and accepted by the Employer.

26.5 Based on the proposed Time Schedule submitted with the Bid, the Contractor must submit within twenty eight (28) days after the signing of the Contract, preliminary detailed time schedules, and construction program for the construction and delivery of contracted goods, to the Engineer for checking and approval. The Contractor shall subsequently submitting the revised schedules to the Engineer at appropriate intervals with the indication of delays, if any, Catch up plan, target dates of mile stones etc. The submittal to and approval by the Engineer of such schedules or the furnishing of such particulars shall not relieve the Contractor of any of his duties or responsibilities under the Contract.

26.6 The Contractor shall submit to the Engineer, monthly progress reports giving full information on all other facts and events of importance to the progress of the construction of Four Hopper Self propelled Split Type Hopper Barges, together with

Page 157: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

possible reasons for delay, if any. The reports, along with the photographs, shall be to the formats approved by the Engineer and the Employer.

26.7 Time is one of the essences of the Contract Four Split Self Propelled Split Type Hopper Barges shall be constructed, tested and completed within the time stated in these documents or such extended time as may be allowed under the Contract. After the date of release of first payment by the Employer the time for ex-yard completion is 21 and 24 months for 1st and 2nd set of Two Self Propelled Split Type Hopper Barges each for foreign builders and 24 and 27 months for local builders. The ex-yard completion for foreign builders means the date of shipment or start of voyage of Barges for Karachi. This period includes the tests and trials to be carried out in the Contractor’s country. The Contractor shall then transport / deliver the Barges in accordance with the schedule depicted at Clause 26.4 (a) of Instruction to Bidder.

17. Liquidated Damages(Clause 27):

The obligations of the Contractor in regard to the bollard pull speed, draught and late delivery of the Barges is defined as follows:

27.2 Speed:

For the purpose of determining the actual speed, sea trials of the Four Split Hopper Barges shall be carried in the country of origin and / or in Karachi as prescribed by the Engineer/Employer. If the actual trial speed at full load of, so computed shall be less than the minimum specified 10 knots at 90% MCR, the contractor shall pay to the Employer as liquidated damages the following percentages on prorate basis of the contract price of the respective Barge.

Actual less speed in knots, Barge Percentage of the Contract Price

0.10 – 0.25 1.00

0.26 - 0.50 2.00

0.51 – 1.0 3.00

Page 158: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

Should the deficiency in the speed be more than 1.0 knot, then the Employer will have the right to refuse accepting the respective. The Contractor shall remedy the deficiency and repeat the trials on his account, until it is proven that the speed deficiency after the remedy is not more than 1.0 knot in which case the above mentioned liquidated damages stipulated in this paragraph shall be applicable.

27.3 Draught:

Should the actual draught (Distance between the water line to the deepest point of keel) of the Four Split Hopper Barges exceed the prescribed maximum limit of 5.50 (meters) then the Contractor shall pay to Employer as liquidated damages an amount equal to 0.25% of the ¼ of the Contract Price per Barge for each 0.05 meter excess draught.

Should the draught of the Barge (s) exceed than the acceptable limit of 5.50 (m) by 0.10 meter Employer may refuse accepting the respective barge. The contractor shall remedy the deficiency until the draught is within acceptable limit, in which case the above mentioned liquidated damages shall still be applicable.

27.4 Late Delivery:

If the Contractor shall fail to deliver of Four Split Hopper Barges within the time prescribed in the clause 11.3 of Instruction to Bidder or within the extended time, he shall pay to the Employer as liquidated damage amounting to a sum for every calendar day which shall elapse between the time prescribed or the extended time as the case may be and the respective dates of completion of each Barge, equivalent to 0.10 percent of the 1/4th of the Contract Price per barge for each calendar day upto a maximum of 10% of the Contract Price per barge for each calendar day up to a maximum of 10% of the Contract Price per barge in addition to other liquidated damages as specified in the Contract. In the event the maximum limit of LD has been reached, all sums and dues to be payable by the Employer shall be forfeited and the securities to be returned shall be cashed and all raw material and finished work in possession of the Contractor shall

Page 159: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

become the Employer’s property as his contractual right.

In case the maximum limit is not reached the Employer may without prejudice to any other method of recovery, deduct the amount of liquidated damages; from his obligations to complete and deliver Four Split Hopper Barges or from any other due sums of his obligations and liabilities under the Contract. if any, which shall not relieve the Contractor from his contractual obligations.

18. Termination by Default(Clause 28):

28.3 If the Contractor shall assign the Contract without the written consent of the Employer first obtained, or if the Engineer shall certify in writing to the Employer that in his established opinion, the Contractor is at default in executing the Contract, then the Employer may, after giving 14 days notice in writing to the Contractor cancel the Contract without further notice or formality and without previous judicial interposition. The Employer can then redeem the Performance Bond. In case of such cancellation of the Contract the Contractor’s Performance Bond will be forfeited to the Employer. The full amount of payments made by the Employer shall be refunded by the Contractor to the Employer within 30 days after cancellation and the property of the Four Split Hopper Barges or parts thereof shall re-pass to the Contractor after repayment.

28.4 The forfeiture of the Contract becomes invalid if the Contractor, within 14 days after receipt of the notice of forfeiture, eliminates the causes which have evoked the forfeiture and the Engineer confirms the removal of such cause(s). In this case, the Contractor may continue the construction of Four Split Hopper Barges after approval of the Engineer / Employer.

19. Termination - Force Majeure(Clause 29):

29.4 If during the currency of the Contract there shall be an outbreak of war (whether war is declared or not) or of civil war, rebellion, revolution, insurrection or usurped power in the Contractor‘s country (hereinafter referred to as “the said outbreak”) and if offer of Four Split Hopper Barges have not been completed and finally delivered as aforesaid, the Employer shall be entitled to terminate the Contract (as to save the rights of the parties

Page 160: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

under Contract). If the Contract shall be terminated as aforesaid, the Contractor shall refund to the Employer within thirty (30) days after termination of the Contract all monies and installment paid by the Employer until that date.

20. Termination for Insolvency(Clause 30):

30.2 If the Contractor shall become bankrupt or becomes unable to perform the Contract or have a receiving order made against him or shall present his petition in bankruptcy, or shall make an arrangement with or assignment in favour of his creditors, or shall agree to carry out the Contract under a committee of inspection of his creditors, or (being a corporation) shall go into liquidation (other than a voluntary liquidation for the purpose of amalgamation) or reconstruction shall have an execution levied on his goods, then the Employer may, after giving 14 days notice in writing to the Contractor cancel the Contract without further notice or formality and without previous judicial interposition.

21. Termination for Convenience(Clause 31):

31.2 The Employer shall in addition to any other power enabling it to terminate the Contract and whether or not the Contractor is in default, shall have the power to terminate the Contract at any time by giving notice in writing to the Contractor and the Contract shall (with the exception of relevant Clauses of the Contract) forthwith terminate. In the event of the Contract being terminated under the provisions of this clause, the Contractor shall with all reasonable dispatch comply with the directions of the Engineer as follows:

a) Immediately discontinue work.b) Place no further orders on sub-contractors.c) Assist in the maintenance, protection and position of the property physically acquired

and transferred by the Employer under the contract.d) Execute any other work or services in respect of any matter arising out of the Contract

with regard to which the Engineer decides that directions are necessary or expedient.

Upon any such termination, the Contractor agrees to waive any claim for damages including loss of anticipated profit on account thereof but as the sole right and remedy of the contractor and the Employer, the employer shall pay the contractor (without duplication of any item) a sum limited to:

Page 161: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

a) The amounts payable in respect of any preliminary items so far as the work or service comprised therein has been carried out or performed at the site, and a proper proportion as certified by the Engineer or any such items, the work or service comprised in which has been partially carried out or performed at the site.

b) The cost of materials or goods reasonably ordered for the works or temporary works which have been delivered to the Site or of the those which the contractor is legally liable to accept delivery, provided that such materials or goods will actually arrive safely at site. All such materials or goods become the property of the Employer upon such payment being made by it.

c) A sum to be certified by the Engineer, being the amount of any expenditure reasonably incurred by the Contractor at the site in the expectation of completing the whole of the works, insofar as such expenditure shall not have been covered by the payments in this paragraph before mentioned.

The total sum payable by the Employer as referred to above shall be reduced by the total of the amount of installments paid by the Employer until the date of termination. Upon all such payments, the Four Split Hopper Barges along with all materials and installations specifically procured for this work, can be removed by the Employer from the contractor’s yard, if they so desire, and the contractor is obliged to provide all possible help and facilities as may be required by Employer for the satisfactory accomplishment of the above purpose.

Alternatively, the contractor can in mutual agreement with Employer take over Four Split Hopper Barges as so far constructed, along with all materials and installation procured for the Four Split Hopper Barges after payment of an amount equal to all monies received by the Contractor from the Employer under this contract.

31.3 In case of forfeiture, the contractor has no claim to indemnification for any loss of profits or any other losses.

22. Resolution of Disputes (Clause 32):

32.3 If any dispute or difference of any kind whatsoever shall arise between the Employer and

Page 162: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

the Contractor in connection with or arising out of the Contract, it shall in the first place be referred to and settled by the Engineer, who within a period of 90 days after being requested to do so, shall give written notice of his decision to the Contractor. If the Engineer has given written notice of his decision to the Contractor and no claim to arbitration has been communicated to him by the Contractor within a period of 90 days from receipt of such notice, the said decision shall remain final and binding upon the Contractor.

32.4 If the Engineer shall fail to give notice of his decision as aforesaid within a period of 90 days after being requested as aforesaid, or if the Contractor should be dissatisfied with any such decision, then the Contractor may within 90 days after receiving notice of such decision, or within 90 days (as the case may be) require that the matters in dispute be referred to arbitration as hereinafter provide.

32.5 The court of arbitration shall be carried out according to the Arbitration Act 1940. It shall be held in Karachi in any case. The point at issue shall thereby be submitted to three arbitrators, of whom one shall be nominated by the Employer, the other by the Contractor, and the third shall be named by the aforesaid two arbitrators. The decision of the arbitrators by majority shall be final and binding for both parties, the Employer and the Contractor.

32.6 Work under this Contract, which has nothing do with such dispute, question or difference, shall be continued without any delay during the court of arbitration. The same is valid for the disputed portion of the works, insofar as the dispute does not extend to essential questions of the technical solution to be selected.

23. Governing Language (Clause 33):

33.2 All markings on equipment, recording devices, nameplates, drawings, documents, lists, certificates and other objects shall also be in legible English. The Contractor is obligated to replace any markings on objects in any other language than English, without additional cost. Any thing in language other than English shall not be accepted towards completion of work.

24. Notices (Clause 35):

Page 163: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

35.3 For the purpose of all notices, the following shall be the addresses of the Employer and Contractor:

(a) Employer

GENERAL MANAGER (P&D),

KARACHI PORT TRUST,

HEAD OFFICE,

EDULJI DINSHAW ROAD, P.O. BOX 4725,

KARACHI-74000, PAKISTAN

FAX NO. (92-21) 9214329,30

TEL. NO. (92 – 21) 9214312

(b) Contractor (To be filled in at the time of submitting the bid))

_______________________________________________________________

35.4 Any notice to be given to the Contractor under the terms of the Contract shall be served, by sending the same to the Contractor's head office by registered air mail or courier service or to leave it at the head office and the local Site office.

Any notice to be given to the Employer by the Contractor under the terms of the Contract is to be sent to him by post as above, or to be left at the office of the Employer against a receipt. The office of the Engineer shall receive a copy of the notice.

25. Special Provision (Clause 38):

Page 164: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

38.1 The Contractor shall notify the Employer and Engineer and arrange progress review meetings, which will be conducted at site at every three months after the date of signing contract. The contractor shall furnish the hard copies in descriptive and graphic form of the materials used and progress achieved. The contractor shall also indicate the reasons for delay, if any, and the proposed plan to recover the time loss. The contractor shall confirm the minutes of the each progress review meeting previously conducted. The contractor shall inform the Engineer and Employer’s representatives of his plan and level of achievements earmarked up to the next meeting to review the progress. The meetings shall be witnessed by at least one representatives of each Employer and Engineer. The contractor shall inform 30 days before the date of progress review meeting, the schedule / program / duration of meeting and arrange all expenses for traveling, boarding, lodging, visa requests etc and provide all assistance as may be required for specified purpose.

The contractor shall invite the Employer’s official(s) at the time of carrying out the mile stone activities such as keel laying, launching, and commencement of functional tests and trials at the builder’s site and departure of Four Split Hopper Barges etc. All costs incurred in such visits shall be for the contractor’s account.

38.2 The Contractor shall arrange to provide to the engineer the work facilities / aids, including compact unit / office, computer, coloured printer, internet connection, and communication equipment etc. as may be indicated by the Engineer, with the permission of Employer. Such provisions supplied to the Engineer at site or at final destination in Karachi shall be taken over by the Employer before start of one year warranty period, as the Employer’s property. The contractor shall arrange Engineer, Class and Flag Authority’s Surveyors (as per need) for witnessing the repeat tests and trials of Four Split Hopper Barges carried out in Karachi and to make remedy of the observations made by the Surveyor, Engineer or Employer, if any.

38.3 Guarantee Master, Guarantee Engineer and Technician and Ship Crew:

The Guarantee Engineer and Guarantee Master shall be English spoken and shall receive instructions from Employer. The Guarantee Master and Engineer shall be responsible for following:-

- To provide necessary training and guidance to on board Employer’s officers and staff for operation of Hopper Barges and maintenance for duration and in the manner described at clause 18.7 of this section of bid documents.

Page 165: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

- To provide instructions to maintain and up-keep the Hopper Barges for function-ability, physical state etc. to match the day one condition.

- To ensure function-ability of all equipment and removal of errors and calibration of all indications, alarms and measuring instruments / devices and maintain all records in writing on the logbooks for machinery functions, special and normal events, utilization of consumable from within those put on board Four Split Hopper Barges for one year as per clause 17,of General Conditions of Contract recording the data of periodical checks of systems and machinery function.

- To furnish to Employer a quarterly report of the Four Split Hopper Barges performance, consumptions, problems and remedial action for warranty items/claims, inventory level and status of the Four Split Hopper Barges condition along with suggestions if any.

38.4 Alteration / Modification / Change in the contract clause / conditions:

During the period of the date of effectiveness of the contract and delivery of Four Split Hopper Barges any condition / clause of the contract may be modified after the written confirmation of both parties to agree to do so, provided such modification does not change the substance or quality or standard (but equivalent or better) and is without an effect to the agreed / contractual cost and delivery time.

38.5 Ownership of Four Split Hopper Barges / Insurance refund:

With effect from the date of release of 2nd installment by Employer, the right of ownership of the Four Split Hopper Barges shall fully pass on to Employer. All material, machinery and belongings of the Four Split Hopper Barges arrived in the Contractor’s yard and the material already ordered or to be ordered etc. till final delivery of the Four Split Hopper Barges in Karachi to Employer (for foreign bidder) shall be deemed to be the Employer’s property and at any stage till annulment of the contract contractor shall have no claim on Employer for demurrage / warehouse charges / mooring / berthing etc. of such material / machinery / equipment lying at the contractor’s yard or in his custody at other places.

Page 166: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

38.6 Security of Contractor’s crew / personnel on board:

Employer shall not be responsible for the security and insurance of contractor’s personnel on board as operating crew and guarantee engineer and guarantee master, technician or engineer etc. during the period of start of voyage to Karachi till completion of one year guarantee period of delivered Four Split Hopper Barges or extended period.

Page 167: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

SECTION – VI

SCHEDULE OF REQUIREMENTS

Item Description Unit Quantity Unit Rate

Local Pak

Rs.

Foreign, Expressed in Pak.Rs.

Total

Pak.Rs.

1 2 3 4 5 6 7

1.

a. Tender Items:

Ex-yard Cost

Construction and supply of Four Self Propelled Split Type Hopper Barges as per contract conditions and specifications for the perfect and safe use of purpose and sea worthiness, built in accordance with IMO and Class Rules and Rules of local maritime agency / Flag Authority and to be made available with all accessories, out fittings and provisions as per international requirements for a Hoper Barges of this size. The Hopper Barges to be delivered at Karachi Port finished. Complete, with all other installation / fittings, weather or not mentioned in the contract or specification. Hopper Barges shall be built to the highest quality of workmanship, material and performance and shall be sturdy and of robust condition along with all standard and special tools and inventory as integrated component of supplies. Hoper Barges transported not under self propulsion, and delivered complete, after satisfactory execution of Harbour and Sea Acceptance tests of Hopper Barges and all necessary / prescribed

Page 168: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

2.

3.

workshop and quay side functional tests and trials at the yard and repeat tests in Karachi.

Duties and Taxes:

Custom duty and Sales tax and other import charges payable in Pakistan.

Transportation:

All costs, whatsoever for the proper and safe sea transportation of the Four Self Propelled Split Type Hopper Barges along with all inventory consumable spares, tools and other provisions and accessories, fitting as per contract, as one package Hopper Barges, with all arrangement duly approved by the Engineer to his entire satisfaction, from the Supplier’s shipyard / Port of discharge to Port of Karachi, including arrangements of certificates and no objections to comply all international navigation, transportation and other requirements of comprehensive marine and all other insurances etc. and transit harbour / canal dues, complete in all respects, including all heavy duty seaworthy preservation for safe sea transport of Four Self Propelled Split Type Hopper Barges for its arrival at Karachi Port.

Marine Insurance

Marine Insurance for voyage to Karachi.

Incidental service:

Incidental services including bottom inspection and local

Page 169: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

4

5.

6

/ domestic and misc. requirements for the operational up keep of Four Self Propelled Split Type Hopper Barges during one year guarantee / warranty period (including consumable spare such as filters, gaskets, plugs, fuses, seals, packing, O’rings, washers, belts, hoses, PLCs, ICs, etc. or any other consumable spare the Contractor may consider necessary to be put on board, each sufficient for one year operation of each vessel.

Guarantee Engineer and Master:

Provision of Training and Warranty by Guarantee Engineer, Guarantee Master and Technician during 12 months guarantee period for 54 man-months.

Spare Parts:

i. Spare parts for two top end overhauls and one major overhaul (list with item wise price to be provided for each) of:

a) Two Main Engines.b) Two Auxiliary Engines (Main Generator)c) One Harbour Engine.

ii. Spare parts for hydraulic installation including Splitting Cylinders for 4500 splitting operations (list with item wise price to be provided).

iii. Hopper Seals sufficient for two complete renewals (list with item wise price to be provided).

iv Spare parts for other auxiliary machinery (i.e

pumps,purifiers etc) in Engine room,

Page 170: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

7

steering

gear, air-conditioning and deck machinery for one

complete Overhaul.

Total for construction and supply of Four Self Propelled Split Type Hopper Barges as per tender terms and conditions:-

a) Consolidated fixed ex-yard cost by Local Bidder.

b) Consolidated fixed DDP (CIF + Custom duty, Sales Tax and other Import charges) cost by Foreign Bidder expressed in equivalent Pak Rupees with rate of exchange.

Name and official address of Bidding firm and date

Designation and Signature of the Bidder with stamp of. the firm and date.

SUMMARY OF THE SCHEDULE OF REQUIREMENTS /BILL OF QUANTITIES (B.O.Q)

Note: Unit rates, Quantity and Total are to be mentioned in figures and words, in case of conflict words shall prevail.

Page 171: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

Item Description Unit Quantity Unit Rate

Local Pak

Rs.

Foreign, Expressed in Pak.Rs.

Total

Pak.Rs.

1 2 3 4 5 6 7

1.

2.

3.

4

5.

Design, Construction and ex-yard completion of Four self Propelled Split Type Hopper Barges, complete as per description of the Tender Documents and Schedule of requirements, for the delivery to Karachi Port.

Custom duty and Sales tax and other import charges payable in Pakistan.

Transportation of Hopper Barges from Port of discharge to Karachi Port, not under self propulsion, complete as per description of the Bidding Documents ready for the delivery to Karachi Port, for the Foreign Bidders only.

Marine Insurance for voyage to Karachi.

Incidental services and any other misc. work for the maintenance of operational status of Hopper Barges during one year guarantee / warranty period, (including consumable spare such as filters, gaskets, plugs, fuses, seals, packing, O’rings, washers, belts, hoses, PLCs, ICs etc. or any other consumable spare the Contractor may consider necessary to be put on board, each sufficient for one year operation of Hopper Barges.

Provision of Bottom Survey by approved diver of each Hopper Barges at Karachi and Guarantee Engineer, Guarantee Master and Technician for 54 man-months

Page 172: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

6

7

spread over one year warranty period, to look after the warranty claims and to give training to KPT’s operating crew and instruction to repairers.

i. Spare parts for two top end overhauls and one major overhaul (list with item wise price to be provided for each) of:

a) Two Main Engines.

b) Two Auxiliary Engines (Main Generator)

c) One Harbour Engine.

ii. Spare parts for hydraulic installation including Splitting Cylinders for 4500 splitting operations (list with item wise price to be provided).

iii. Hopper Seals sufficient for two complete renewals (list with item wise price to be provided).

iv. Spare parts for other auxiliary machinery (i.e pumps, purifiers etc) in Engine room, steering gear, air- conditioning and deck machinery for one complete Overhaul.

Total for construction and supply of Four Self Propelled Split Type Hopper Barges as per tender terms and conditions:-

a) Consolidated fixed ex-yard cost by Local Bidder.

b) Consolidated fixed DDP (CIF + Custom duty, Sales Tax and other Import charges) cost by Foreign Bidder expressed in equivalent Pak Rupees with rate of exchange.

Page 173: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

Name and official address of Bidding firm and date

Designation and Signature of the Bidder with stamp of. the firm and date.

SCHEDULE – A TO BID

SPECIFIC WORKS DATA

(Proforma for Specific Data to be prepared and filled in by the Bidders)

Page 174: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

SCHEDULE – B TO BID

Page 175: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

WORK TO BE PERFORMED BY SUB-CONTRACTORS

The bidder will do the work with his own forces except the work listed below which he intends to sub-contract.

Item of Work Name and address of Statement of similar

To be Sub-Contracted Sub-Contractor works previously

Executed (attach

Evidence)

Page 176: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

Note:

1. No change of sub-contractor shall be made by the bidder without prior approval of the Employer.

2. The truthfulness and accuracy of the statement as to the experience of sub-contractors is guaranteed by the bidder. The Employer’s judgment shall be final as to the evaluation of the experience of sub-contractors submitted by the bidder.

3. Statement of similar works shall include description, location and value of work, year completed and name and address of the clients.

SCHEDULE – C TO BID

PROPOSED PROGRAMME OF WORK

Bidder shall provide a program in a bar-chart/CPM/PERT form showing the sequence of work items by which he propose to complete the work of the entire contract. The program should indicate the sequence of work items and the period of time during which he proposes to complete the works including the activities like designing, schedule of submittal of drawings, ordering and procurement of materials, manufacturing, delivering,

Page 177: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

construction of Four Self Propelled Split Type Hopper Barges, commissioning, testing and handing over of works to be supplied under the contract.

Page 178: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

SCHEDULE – D TO BID

DEVIATIONS

FROM

TECHNCIAL PROVISIONS

It is presumed that the bidder shall not take any deviations. However, if he intends to take deviations to the specified terms, those must be listed in the space provided below:

S.No.. Clause No / Section No. Deviations / Clarification

Page 179: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

Note: [Attached additional sheet, if necessary]

SCHEDULE – E TO BID

DEVIATIONS

FROM

CONTRACTUAL CONDITIONS

Page 180: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

It is presumed that the bidder shall not take any deviations. However, if he intends to take deviations to the specified Contractual / Commercial Conditions, those must be listed in the space provided below:

S.No.. Clause No / Section No. Deviations / Clarification

Page 181: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

Note: [Attached additional sheets, if necessary]

SCHEDULE – F TO BID

METHOD OF PERFORMING WORKS

The bidder is required to submit a narrative outlining the method of performing the works. The narrative should indicate in detail and include but not be limited to:

The sequence and method in which he proposes to carry out the work, including the number of shifts per day and hours per shift, he expects to work.

A list of all major items of constructional and erection plant, tools and vehicles proposed to be used in carrying out the Works at Site, including number of each kind, make, type, capacity of all equipment, working condition, which shall be deployed by him. Testing and commissioning of the Works, in sufficient detail to demonstrate fully that the equipment will meet all the requirements of the Technical Provisions.

The procedure for construction of Four Self Propelled Split Type Hopper Barges, installation of equipment, tests and trials and transportation to Karachi Port in case of foreign bidder only and handing over after satisfactory compliance of the contract.

Organization chart indicating head office and field office personnel involved in management, supervision and engineering of the Works to be done under the contract.

Page 182: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

SCHEDULE – G TO BID

PROPOSED ORGANIZATION

The bidder shall list in this schedule the key personnel he will employ from Head Office and from Site Office to direct and execute the Works, together with their names, qualification, experience, positions held and their nationalities.

Page 183: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

Designation Name of Summary of QualificationExperience, PresentPosition andNationality

Head Office:

- Site Office:Contractor’s Representative

Site Superintendent

Supervision Engineer

Plant Erectors

Construction Supervisors

Other Key Staff

Page 184: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

SCHEDULE H – TO BID

INTEGRITY PACTDECLARATION OF FEES, COMMISSION AND BROKERAGE, ETC. PAYABLE BY THE BIDDER FOR CONSTRUCTION AND SUPPLY OF FOUR SELF PROPELLED SPLIT TYPE HOPPER BARGES

Contract No. ___________________ Dated_______________Contract Value _________________Contract Title __________________

…………………………..(name of Bidder) hereby declares it has not obtain or induce the procurement of any contract, right, interest, privilege or other obligation or benefit from Government of Pakistan or (Gip) any administrative subdivision or agency thereof or any other entity owned or controlled by (GoP) through any corrupt business practice.

Without limiting the generality of the foregoing, name of Bidder)……………………. represents and warrants that it has fully declared the brokerage, commission, fees etc. paid or payable to anyone and not given or agreed to give and shall not give or agree to give to anyone within or outside Pakistan either directly or indirectly through any natural or juridical person, including its affiliate, agent, associate, broker, consultant, director, promoter, shareholder, sponsor or subsidiary, any commission, gratification, bribe, finder’s fee or kickback, whether described as consultation fee or otherwise, with the object of obtaining or inducing the procurement of a contract, right, interest, privilege or other obligation or benefit in whatsoever form from GoP, except that which has been expressly declared pursuant hereto.

(name of Bidder) …………………….certificates that it has made and will make full disclosure of all agreements and arrangements with all persons in respect of or related to the transaction with GoP and has not taken any action or will not take any action to circumvent the above declaration, representation or warranty

(name of Bidder ) ……………………………. accepts full responsibility and strict liability for making any false declaration, not making full disclosure, misrepresenting facts or taking any action likely to defeat the purpose of this declaration, representation and warranty. It agrees that any contract, right, interest, privilege or other

Page 185: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

obligation or benefit obtained or procured as aforesaid shall, without prejudice to any other right and remedies available to GoP under any law, contract or other instrument, be voidable at the option of GoP.

Notwithstanding any rights and remedies exercised by Gop in this regard, (name of Bidder) ………………….. agrees to indemnify GoP for any loss or damage incurred by it on account of its corrupt business practices and further pay compensation to GoP in an amount equivalent to ten time the sum of any commission, gratification, bribe, finder’s fee or kickback given by (name of Bidder) …………………… as aforesaid for the purpose of obtaining or inducing the procurement of any contract, right, interest, privilege or other obligation or benefit in whatsoever form from GoP.

Name of Buyer …………………. Name of Bidder ………………………….Signature ……………………… Signature ………………………….

[Seal] [Seal]TABLE – A EVALUATION CRITERIA OF FIRM FOR CONSTRUCTION OF 1000 M 3 SPLITY TYPE HOPPER BARGES.

S.No. REQUIRMENTS

1 Status of Firm

a. Public limited/ Multinational/ Joint Venture (JV)

b. Private Limited

c. Private Owner

Note: Both b and c will have low priority

2 Certifications

a. ISO 9001

b. ISO 14001

c. OHSAS 18001

Note: All are mandatory

Page 186: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

3

Total Age of Building Yard (at least over 15 years)

4 No.of 1000 M3 Split Hopper Barges built for international clients (at least 04 in number said Barges)

5 Total number of harbour crafts built so far (minimum number should be above 25)

6 Financial Capability of the Bidder for Supply of Split Hopper Barges:

Net worth

Over US$ 300 million

Over US$ 200 million

Over US$ 100 million

Note: Minimum Qualification criteria would be 70% of the compliance to the above mentioned requirements.

TABLE – B EVALUATION CRITERIA FOR THE CONSTRUCTION OF 1000 M 3 SPLIT TYPE HOPPER BARGES AGAINST THE GIVEN TECHNICAL SPECIFICATIONS The Bidders are required to provide the following information pertaining to essential parameters, about their offered 1000 M3 split Hopper Barges in their submitted Technical Proposal with relevant documentary evidence (as and where applicable).

S.No SPECIFICATION / DETAILS OF SPLIT / HOPPER BARGES

1 The main characteristics of the barge should remain within following parameters:

a. Dimensions(1) Hopper capacity 1000 M3

(2) Overall Length Commensurate with displacement but within range of 56-62 m

Page 187: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

(3) Breadth Mouled 11-14m or i.a.w displacement

(4) Draught Minimum possible w.r.t hopper capacity but not more than 4.0-5.0m

(5) Dead Weight 1600 Tons

(6) Accommodation Spaces: As per complement of the barges, with a single and attached bath room for 02 officers, separate accommodation and bath rooms for 12 crew members.b. Availability of the Platform Barge shall be available for minimum of 80% of the time throughout its designed life of 20 years and all maintenances and refits shall be designed to allow such availability.c. Speed

(1) Maximum Speed – around 12 Kts.(2) Full Load Speed – 10 Kts @ 90% MCR.

d. Endurance

(1) Store and spares capacity – 05 Days(2) Victualling store capacity

(a) Fresh provisions - 03 Days(b) Dry provisions -03 Days(c) Frozen provisions-03 Days

e. Fluid Tanks(1) Fresh epoxy painted fuel tanks with total capacity in the range of 75-80 Mfuel.(2) Fresh painted tanks for 12-15 M3 fresh water to meet Loyds’s/BV or equivalent criteria of safe drinking water.

Page 188: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

(3) Sewage tank with a total capacity of 5M3 or as per endurance/ role.(4) Other tanks for POLs, as required.

f. Environment

(1) The barge and its equipment/ machinery/ systems should be able to operate in Arabian Sea upto Sea State 6 bf under following environmental conditions:

(a) Ambient temperature - upto 45OC (b) Relative Humidity - 95 %

(c) Sea water temperature - upto 32oC

(2) Moreover all machinery/ equipment/ systems shall comply with Environment Protection Rules in vogue, such as Marine Pollution Rules (MARPOL) and IMO regulations

g. Stability

(1) Stability standards for the design, construction and operation of vessel should be in accordance with Lloyd’s/BV Rules (or equivalent). Supplier will provide a certificate of conformance for captioned standards.

(2) The vessel should conform to International/ SOLAS standards for survivability against fire and under water damage.

h. Maneuvering Barge is to be classified in accordance with Lloyd’s/BV Maneuvering Assessment or equivalent.

j. Hull Barge’s hull structure should be designed to accommodate the mechanism for releasing material (consisting of mud, sand, stone clay and trash). Moreover, following aspects may also be catered for:

(1) Capable to bear weight of dumping material/ internal loading.

(2) Steel hull and super structure i.a.w Lloyd’s / BV Rule of this type / class of vessel or equivalent.

k. Hull Protection Following be complied for the protection of the barge’s hull:

Page 189: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

(1) Paint scheme of International Paints (IP) to be applied throughout the barge confirming to latest War Paints issue.

(2) Underwater paint scheme as per Lloyd’s / BV Rules or Equivalent International Paint scheme acceptable to KPT, having a minimum of 5 years satisfactory performance.

(3) Sacrificial anodes to provide protection against galvanic corrosion on underwater hull, sea chests and rudders etc with anode life of minimum months.

(4) 5 years warranty for entire paint system.

l. Noise Criteria

(1) Wheel House 75 dB (A)(2) Accommodation 70 dB

2 PROPULSION MACHINERY

Propulsion, Shafting and Propellers. Propulsion of the barge should be designed as per Lloyd’s/BV Rules or Equivalent acceptable to KPT, having the following features:

a. Diesel propulsion system being most common and economical to operate with 02 X main engines of Make/Model: Wartsila/Cummins/Caterpillar/MAN manufactured at West European/ USA or Equivalent. Electrical start system with adequate battery backup along with charging system for Main Engines.

b. Make/Model of Bow Thrusters shall be Rolls Royce/ Wartsila of West European, USA origin or Equivalent.

c. Opening angle of Hopper 35o to 40o.

d. FPPs (Fixed Pitch Propellers).

e. Maximum fuel economy.

Page 190: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

f. Ease and economy of maintenance & repairs.

g. 2 x Shafts for redundancy in operation and better maneuverability.

h. Make/Model of Gear Boxes, Propeller Shafts, Stern tube seals, Propellers, Rudder Bearings, Steering gear, Compressors, Pumps, etc shall be from Western Europe, USA or Japanese origin.

J. Make/Model of Hydraulic Eq. shall be Rexroth Vickers or Equivalent. See details at Clause 4 of TSP 25.

3 Auxiliary Machinery

a. Power Generation and Distribution (PG & D). The PG & D system is to be designed as per Lloyd’s/BV Rules or Equivalent acceptable to KPT keeping in view the following features:

(1) Make/Model of 02 X Main Diesel Engines shall be MAN / Caterpillar/ Volvo of West European, USA origin or Equivalent. Single DG load capacity should be 40 % above the maximum demand with 100% redundancy.

(2) Make/Model of 01 X Harbour Gen Engines shall be MAN / Caterpillar / Volvo of West European, USA origin or Equivalent. DG load capacity should be 40 % above the maximum Harbour load.

(3) Make/Model of Alternators shall be Stamford/Leroy Somer/Siemens or Equivalent.

(4) Electrical distribution system with complete redundancy for critical main machinery, and equipment.

(5) Electrical start system with adequate battery backup along with charging system for DGs.

(6) Battery backup (UPS) for communication equipment and navigation aids along with charging facility.

(a) Shore supply connection boxes with shore supply cable.

(b) Appropriate lighting arrangements on upper decks.

Page 191: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

b. Air-conditioning & Ventilation System. Commercial type air conditioners of sufficient capacity to maintain good habitability in the Wheel House and accommodation spaces. Ventilation and exhaust/ recirculation system for Machinery compartment & wastage storage tanks as per Lloyd’s/BV Rules or Equivalent, acceptable to KPT suitable for Extreme Tropical Conditions. Ozone friendly gases are to be used. Air-conditioning system be designed to cater following environment condition:

(1) Ambient temperature - 45oC(2) Ambient relative humidity – upto 95%(3) Sea water temperature – upto 320C.(4) Temp within living spaces – 22o-24oC.(5) Temp within Wheel House – 20oC

c. Sea Water System. The system is required for Fire fighting, flushing, emergency main and auxiliary cooling etc. The sea water systems piping should be made of Stainless Steel or any other suitable contemporary material having equivalent or better anticorrosion properties.

d. Portable / Fresh Water System Fresh water system for drinking, domestic use and machinery cooling circuit. Fresh water pumps capable of continuous running with 100% redundancy. See Details at Clause 5c&d of TSP 27.

4 DC & FF AND DE-FLOODING ARRANGEMENTS

Damage Control System. The barge is to be divided in water tight compartments and damage control zones in accordance with Lloyd’s/BV Rules of equivalent. Barge is to have adequate fire fighting, damage control, electric repair and communication outfit at suitable locations.

5 GENERAL ALARM SYSTEM. As per Clause 3 of TSP 45.

a. Bilge/ flood Alarm System. The bilge alarm system as part of the general alarm system, safety and warning system for flooding in main engine room, auxiliary machinery room and other compartments where accumulation of water may occur.

Page 192: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

b. Fire Detection & Alarm System. Fire Detection and Alarm System is to be provided as per Lloyd’s Rules/BV or equivalent. The fire detection control unit is to be located at Wheelhouse. Fire detection indicating panels are to indicate the section in which a detector has operated along with a distinguishable audible fire alarm.

6 Fire Fighting System.Fire fighting arrangements of both fixed and portable types are to be provided as per Lloyd’sBV Rules or equivalent. DC & FF personnel gear should be in accordance with fire Safety Systems Code of SOLAS (International Convention for the Safety of Life at Sea). Following are the minimum requirements:

a. Fire main pumps in separate zones with redundancy to cater for barge’s DC & FF requirements.

b. Portable fire fighting extinguishers at appropriate locations for all types of fire.

c. Fixed fire fighting system (CO2) for machinery spaces with remote operating facility.

d. Automatic fire fighting arrangements (AFFF system) for fire risk in the machinery spaces compartments and all inflammable stores.

e. Foam inductor connections with sea water line for machinery spaces.

f. Heat, smoke and fire alarms with remotely/ locally monitoring facility.

g. Fire hydrants alongwith hoses and nozzles.

h. 2 x Standard shore connection (NATO Standards) for the fire main on each side of the vessel.

j. Ozone friendly gasses are to be used.

7 De-flooding Arrangements. Adequate number of fixed and portable educators and pumps are to be provided for de-flooding.

Page 193: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

8 SEAMANSHIP All essential seamanship gear in accordance with Lloyds/BV Rules for Ships or equivalent including replenishment, fuelling, towing, shackles, links, thimbles, ropes, deck fittings, purchases and tackles, deck eyes, sheer legs, swivel and other boatwain’s gear should be available on board. In addition, following should also be provided:

a. Anchors Windless – 2 with anchor cables & Cable lockersb. Capstan – 2c. Life Rafts – 02 for 15 persons each.d. 01 X GRP man overboard boat (with 25 HP Yamaha/Honda outboard engine).e. Jumping Ladders - 1f, Life saving & Survival gear for 15 persons - As per SOLAS.g. Towing gear - 1

9 STORES & WORKSHOPS

Store Rooms. Following store rooms/ lockers for onboard stocking:

a. Bos’n seamanship and Replenishment gear store.b. Paint/ Chemical store.c. Mechanical Engineering store.d. General store for any additional requirement of stowage.

10 Navigation. The barge should have the following navigation equipment of West Europe, USA and Japan origin. See details at Clause 7 of TSP 39:

a. Navigational radarb. GPS.c. Echo sounderd. HF Radio Telephones.e. Navtex Receiver.f. AIS

11 Training. As per Clause 18.7 of SC-13.

Page 194: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

12 Documentation. As per Clause 12 of TSP 14.

13 Spares. As per Clause 17 of GC 12.

14 Communication Equipment. Following communication equipment should become the part of communication suite (Frequencies of external equipment is to be set, as per KPT requirements):

a. External Communication Equipment As per Clause 9 of TSP 43.

(1) VHF Radio Telephone.(2) Navtex Receiver.(3) Satellite E.P.I.R.B and 9GHz Radar Transponder etc.

b. Internal Communication Equipment Integrated internal communication for the following operational functions should be available as per Clause 8 of TSP 41:

(1) Machinery Control.(2) Damage Control.(3) Intercom.(4) Sound power telephone system should be provided to establish emergency communication between important Compartments/ locations such as Wheelhouse, aft steering position, machinery spaces, DC & FF lockers etc.

15 Guarantee.

a. The barge as a whole and all its machinery/ equipment/ system shall have the guarantee for a period not less than one year from date of acceptance of the platform.

b. Guarantee for availability of spares for next 10/15 years.

16 DESIGN STANDARDS.

a. Design of the said Barge shall be proven and proof to this effect is required to be submitted.

Page 195: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

b. Complete design, construction and test and trials of the barges are to be in accordance with latest addition of Lloyds/BV Classification Society Requirements or equivalent, except where explicitly mentioned in this document or accepted by KPT.

CLASS NOTATION: “ + 100A1 Split Hopper Barge, Extended Protected Water Service from the port of Karachi + LMC ”.

Note: Minimum Qualification criteria would be 70% of the compliance to the above mentioned specifications.

SECTION VII

TECHNICAL SCHEDULE

Bidders are required to carefully fill in the following Technical schedule,

Vessel’s Principal Characteristics

The principal characteristics of the Four Hopper Barges will be:

Length overall

Length B. Prep.

Breadth moulded

Depth moulded (at ½ L)

Design Draught in sea water with specific gravity (1.025 ton / m3)

Deadweight all told at design draught

Maximum working draught at no load and full load.

Maximum freeboard and free board at full load.

Hopper capacity at max. overflow level

Trial speed at design draught

Trial speed at full load in the hopper, (load in the hopper to be indicated in Tons and speed in knots.

Volume of trap water in the empty hopper

…………………….. meters

……………………. meters

……………………. meters

……………………. meters

…………………….. meters

................ ................. ton

................ & ........... meters

................... & ...........meters

................... m3............ tons

................ ............ ....knots

.....................knots..... tons

................ m3 ............ Tons

Page 196: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

Light Weight Specification

Steel hull

Outfit and equipment.

Machinery installations.

Electrical installations.

Splitting equipment.

Water and oil in system

Victual and spare parts (usually on board)

Total light weight.

………………………………………tons

………………………………………tons

………………………………………tons

………………………………………tons

………………………………………tons

………………………………………tons

………………………………………tons

………………………………………meters

TRIM AND INITIAL STABILITY

a. “Light ship” with 50% normal stores and water in hopper equal to outboard level (hopper closed)

Total light weight

Stores on board: Fuel oil

Fresh water

Lubricating oil

Victuals

………………………………………tons

………………………………………tons

………………………………………tons

……..……………………………….tons

………………………………………tons

Page 197: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

Crew and luggage

Displacement

Water in hopper compartment

Displacement

Draught aft.

Draught forward

Mean draught

Met centric height

Free surface effect (to be deducted)

……………………………………. tons

…………………………………… .tons

…………………………………… .tons

…………………………………… .tons

……………………………………tons

………………………………………meters

………………………………………Meters

………………………………………Meters

………………………………………Meters

b. “Light Ship” with 50% normal and hopper fully opened.

Total light weight.

Stores on board: Fuel oil

Fresh water

Lubricating oil

Victuals

Crew and luggage

Water in hopper compartment

Displacement Draft aft

Draught forward

Main draught

Meta centric heighty

Free surface effect (to be deducted)

……………………. …………….. tons

……………………. ……………. tons

………………………………… ..tons

…………………………………. . tons

......................................................tons

…………………………………,..tons

…………………………………..tons

…………………………………meters

……………………………….. .meters

………………………………..meters

………………………………..meters

………………………………..meters

Page 198: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

c. Ship loaded to design draught with 50% normal stores and hopper filled homogeneously to maximum overflow level to maximum draught.

Total light weight.

Stores on board: Fuel oil

Fresh water

Lubricating oil

Victuals

Crew and luggage

Spoil in hopper (s.w…….)

Displacement

Draft aft

Draught forward

Mean draught

Meta centric height

Free surface effect (to be deducted)

……………………. …………….. tons

……………………. ……………. tons

………………………………… ..tons

…………………………………. . tons

......................................................tons

…………………………………,..tons

…………………………………..tons

…………………………………meters

……………………………….. .meters

………………………………..meters

………………………………..meters

………………………………..meters

………………………………..meters

d. Ship loaded to draught with 50% normal stores and hopper filled homogeneously to minimum overflow level to maximum draught.

Total light weight.

Stores on board: Fuel oil

Fresh water

Lubricating oil

Victuals

Crew and luggage

Spoil in hopper (s.w…….)

……………………. …………….. tons

……………………. ……………. tons

………………………………… ..tons

…………………………………. . tons

......................................................tons

…………………………………,..tons

…………………………………..tons

Page 199: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

Displacement

Draft aft

Draught forward

Mean draught

Met centric height

Free surface effect (to be deducted)

…………………………………meters

……………………………….. .meters

………………………………..meters

………………………………..meters

………………………………..meters

………………………………..meters

e. Ship loaded with 50% normal stores and hopper filled to maximum overflow level with water.

Total light weight.

Stores on board: Fuel oil

Fresh water

Lubricating oil

Victuals

Crew and luggage

Spoil in hopper (s.w…….)

Displacement

Draft aft

Draught forward

Mean draught

Meta centric height

Free surface effect (to be deducted)

……………………. …………….. tons

……………………. ……………. tons

………………………………… ..tons

…………………………………. . tons

......................................................tons

…………………………………,..tons

…………………………………..tons

…………………………………meters

……………………………….. .meters

………………………………..meters

………………………………..meters

………………………………..meters

………………………………..meters

ENGINE ROOM FANS (2)

Make

Type

Capacity

……………………. ……………..

……………………. …………….

………………………………… ..

…………………………………. .

Page 200: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

Motor power

Speed

Country of origin

......................................................

…………………………………,

ACCOMMODATION FAN(S)

Make

Type

Capacity

Motor power

Speed

Country of origin

……………………. ……………..

……………………. …………….

………………………………… ..

…………………………………. .

......................................................

…………………………………,

EXHAUST FAN(S) SANITARY SPACES

Make

Type

Capacity

Motor power

Speed

Country of origin

……………………. ……………..

……………………. …………….

………………………………… ..

…………………………………. .

......................................................

…………………………………,

PAINTS

Make and description

Country of origin

……………………. ……………..

……………………. …………….

Page 201: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

ANCHOR WINCHES (2)

Make

Type RPM

Motor power

Country of origin

……………………. ……………..

……………………. …………….

………………………………… ..

…………………………………. .

CAPSTAN

Make RPM

Type RPM

Motor power

Country of origin

……………………. ……………..

……………………. …………….

………………………………… ..

…………………………………. .

FENDERS

Make

Type / size

Country of origin

……………………. ……………..

……………………. …………….

………………………………… ..

HYDRAULIC PLANT

Make

Pump Type

Pump Capacity

……………………. ……………..

……………………. …………….

………………………………… ..

Page 202: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

System pressure

Country of origin

…………………………………. .

......................................................

MAIN ENGINES (2)

Make

Type

RPM

Direction of rotation

Fuel consumption

Country of origin

……………………. ……………..

……………………. …………….

………………………………… ..

…………………………………. .

......................................................

…………………………………,,

REVERSE REDUCTION GEAR BOXES (2)

Make

Type

Radio

Motor power

Country of origin

……………………. ……………..

……………………. …………….

………………………………… ..

…………………………………. .

......................................................

SHAFT SEALS (4)

Make

Inboard Type

Outboard type

Country of origin

……………………. ……………..

……………………. …………….

………………………………… ..

…………………………………..

Page 203: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

PROPELLERS (2)

Make

Type

Number of blades and material

Country of origin

……………………. ……………..

……………………. …………….

………………………………… ..

…………………………………..

AUXILIARY ENGINES (03)

Make

Type

Continuous tropical output

RPM & Load generating capacity

Country of origin

……………………. ……………..

……………………. …………….

………………………………… ..

…………………………………. .

......................................................

MAIN ENGINE SILENCERS WITH SPARK ARESTORS

Make

Type

Country of origin

……………………. ……………..

……………………. …………….

………………………………… ..

AIR CONDITIONERS (2)

Make

Type

Capacity

Pressure

Country of origin

……………………. ……………..

……………………. …………….

………………………………… ..

…………………………………. .

......................................................

AIR DRYERS (2)

Page 204: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

Make

Type

Capacity

Country of origin

……………………. ……………..

……………………. …………….

………………………………… ..

…………………………………. .

FUEL OIL TRANSFER PUMP (1)

Make

Type

Capacity

Head

Country of origin

……………………. ……………..

……………………. …………….

………………………………… ..

…………………………………. .

……………………………………

FUEL OIL PURIFIER (1)

Make

Type

Capacity

Country of origin

……………………. ……………..

……………………. …………….

………………………………… ..

…………………………………. .

FUEL OIL TRANSFER PUMP (2)

Page 205: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

Make

Type

Capacity

Head

Country of origin

……………………. ……………..

……………………. …………….

………………………………… ..

…………………………………. .

......................................................

STANDBY FUEL OIL BOOSTER PUMPS M.E. (2)

Make

Type

Capacity

Head

Country of origin

……………………. ……………..

……………………. …………….

…………………………………

……………………. …………….

…………………………………

STANDBY L.O. PUMPS MAIN ENGINES (2)

Make

Type

Capacity

Head

Country of origin

……………………. ……………..

……………………. …………….

………………………………… ..

…………………………………. .

......................................................

STANDBY L.O. PUMPS GEAR BOXES (2)

Make ……………………. ……………..

Page 206: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

Type

Capacity

Head

Country of origin

……………………. …………….

………………………………… ..

…………………………………. .

…………………………………. .

DIRTY OIL PUMPS (2)

Make

Type

Capacity

Head

Country of origin

……………………. ……………..

……………………. …………….

………………………………… ..

………………………………….

………………………………….

SLUDGE PUMPS (2)

Make

Type

Capacity

Head

Country of origin

……………………. ……………..

……………………. …………….

………………………………… ..

…………………………………. .

...................................................

BOX COOLERS (2)

Make

Type

……………………. ……………..

……………………. …………….

Page 207: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

Country of origin ………………………………… ..

STAND BY FRESH WATER COOLING PUMPS (2)

Make

Type

Capacity

Head

Country of origin

……………………. ……………..

……………………. …………….

………………………………… ..

…………………………………. .

......................................................

GENERAL SERVICE PUMP AND TROLLEY MOUNTED PORTABLE PUMP (2)

Make

Type

Capacity

Head

Country of origin

……………………. ……………..

……………………. …………….

………………………………… ..

…………………………………. .

......................................................

BILGE BALLAST PUMP (1)

Make

Type

Capacity

……………………. ……………..

……………………. …………….

………………………………… ..

Page 208: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

Head

Country of origin

…………………………………. .

......................................................

HYDROPHORE PUMPS (3)

Make

Type

Capacity

Head

Country of origin

……………………. ……………..

……………………. …………….

………………………………… ..

…………………………………. .

......................................................

SEWAGE TREATMENT PLANT (1)

Make

Type

Capacity

Head

Country of origin

……………………. ……………..

……………………. …………….

………………………………… ..

…………………………………. .

......................................................

CO2 INSTALLATION

Make

Type

Capacity

Head

……………………. ……………..

……………………. …………….

…………………………………..

……………………. …………….

Page 209: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

Country of origin …………………………………..

OILY WATER SEPRATOR

Make

Type

Capacity

Head

Country of origin

……………………. ……………..

……………………. …………….

………………………………… ..

…………………………………. .

......................................................

ALTERNATORS (3)

Make

Type

Capacity

Head

Country of origin

……………………. ……………..

……………………. …………….

………………………………… ..

…………………………………. .

......................................................

MAIN SWITCH BOARD AND PANELS

Make

Type

Country of origin

……………………. ……………..

……………………. …………….

………………………………… ..

ENGINE ROOM AND BRIDGE CONTROL / ALARM INSTALLATION

Page 210: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

Make

Type

Number of Alarm points

Country of origin

……………………. ……………..

……………………. …………….

………………………………… ..

......................................................

BATTERY CHARGER (1)

Make

Type

Capacity

Country of origin

……………………. ……………..

……………………. …………….

………………………………… ..

…………………………………. .

TRANSFORMERS (4)

Make

Type

Country of origin

……………………. ……………..

……………………. …………….

………………………………… ..

GYRO COMPASS (1)

Make

Type

Country of origin

……………………. ……………..

……………………. …………….

…………………………………..

ECHO SOUNDER AND TRANSDUCERS

Page 211: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

Make

Type

Country of origin

……………………. ……………..

……………………. …………….

………………………………… .

VHF - INSTALLATIONS

Make

Type

Power

Number of Channels

Country of origin

……………………. ……………..

……………………. …………….

………………………………… ..

…………………………………. .

…………………………………. .

TELEPHONE SYSTEM (1)

Make

Type

Country of origin

……………………. ……………..

……………………. …………….

………………………………….

TALK BACK INSTALLATION

Make

Type

……………………. ……………..

……………………. …………….

Page 212: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

Output

Country of origin

………………………………….

………………………………….

PORTOPHONES (3 SETS)

Make

Type

Out put

Country of origin

……………………. ……………..

……………………. …………….

………………………………….

………………………………….

NAVIGATION LIGHT UNIT

Make

Type

Country of origin

……………………. ……………..

……………………. …………….

…………………………………..

RADAR

Make

Type

Country of origin

……………………. ……………..

……………………. …………….

…………………………………..

GPS

Make

Type

Country of origin

……………………. ……………..

……………………. …………….

…………………………………..

Page 213: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

Name and official address of Bidders……………………………………………………………………………………………..…………………………………………….

Date…………………………………….

Designation and Signature of the Tender with stamp of firm

IMO

SOLAS

CLASSIFICATION

LOCAL MARITIME AGENCY(S)ANY OTHER

SECTION – V

PART I – GENERAL SPECIFICATION

Brief of the requirement:

The broad based Technical Specification shall follow. Before these specifications following aspects are to be taken into consideration which shall prevail over the specification.

Page 214: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

Opening condition of the Barge

Classification

Class notation

Fuel Capacity

Frame Space

Hydraulic pipes and fittings

Opening angle of hopper

Scantling

Quantity of trap water in emptied hopper

Hyd. Cylinder for opening hopper

2 x Diesel generator sets

Main engine starting

Main engine make and origin

Control console at Wheel House

Speed @ 90% MCR

Sea state 6 bf

LR or BV

Equivalent to “+ 100 A1 Split Hipper Barge Extended Protected Water Service +L MC”

Approx 80 m3

400 – 500 mm

All seamless in Stainless Steel

35o – 40 o

10% more than Class recommendation

Approx 100 m3

To be at max. height preferably above sea water. All accessories with hyd. Cylinder and pipes must be above sea water after closing hopper.

Each DG load capacity should be 40 % above the maximum demand.

Electric

Preferably from within Cummins, Caterpillar, MAN, Wartsila of the country origin i.e. Western Eurpeon, USA.

To facilitate all operation and monitoring of main and auxiliary engines, hydraulic system and navigation and communication equipment (as necessary)

Not less than 10 knot (speed test at full load in sea condition bf 2-3)

Not less than 1.60 ton / m 3

Page 215: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

17

Density of dredged materialand

Load capacity of Hopper

1 X Harbour Diesel generator

1,600.00 tons

DG load capacity should be 40 % above the maximum Harbour load.

18.Hopper sealing “D” cross section Rubber all along the hopper length, fixed in thicker steel flat bars. 02 hopper seals (complete) to be supplied as spare with each barge.

19.Special tools for all machinery / equipment is required with each craft same to be supplied according to the manuals.

20.All PLC / ELC Software (including operational and trouble shooting) to be supplied in CD.

21.Ball / Roller / Spherical bearings to be fitted in the deck hinges under the superstructure bottom plate to maintain level during splitting of the hopper barge.

22.High pressure water jet machine and welding plant units and Gas cutting equipment to be supplied with each hopper barge.

1.1 Climatological, Geological Conditions at Karachi Port.

i. Temperatures

The extreme maximum temperature of 48o C and minimum temperature of 39oC were observed in Karachi city area over the period of last 80 years. However, the extreme temperatures near sea-side as recorded at Manora observatory were maximum 36 o C and minimum 10oC F. The mean monthly temperature variations at sea-side during summer months are between 32 o C and 24 o C and during winter months are between 24 o C and 16 o C .

Page 216: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

ii. Relative Humidity

The relative humidity regularly remains higher in the mornings than in the evenings. The observations at 8.00 AM gave values between 63% in January and 90% in August,, and at 5.00 PM, humidity varies between 44% in January and 77% in August.

iii. Precipitation

Karachi belongs to the dry zone of Pakistan. The mean annual rainfall is only 7.70” of this, approx. 3.20” alone fall during the rainy months of July & August. The average number of rainy days in the years with precipitation of over 0.10” or more is 10, of which 3 are to be expected in July. Substantial deviations from the above mean values are also possible through extraordinary meteorological condition. Accordingly, because of excessive rains during the months of March, July and August of 1967, the annual precipitation of about 38” was recorded for the full year of 1967.

iv. Wind and Storms

The prevalent wind direction in the months of April to October is south-west to west. In other months, it fluctuates between northwest and north-east. The predominant wind force is in the range 4-7 Beaufort scale, which if observed during the months of May to August, with average wind velocity of upto16 Kots. Individual wind force in the Beaufort scale 8 had also been observed during these months. Cyclonic storms with forces of Beaufort 10 and more have also been observed, but their frequency is one in two years.

v. Tidal Water levels

The following tidal water levels in relation to Karachi Port datum, are valid for the Port of Karachi.

Page 217: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

Mean higher high water +8.8ft

Mean lower high water +7.2ft

Mean sea level +5.4ft

Mean higher low water +3.6ft

Mean lower low water +1.4ft

Highest high water spring +9.4ft

Lowest low water springs -0.7ft

Highest astronomical tide +10.4ft

Lowest astronomical tide -1.4ft

Highest high water +12.2ft (Recorded on 23.5.1959)

Lowest low water +2.4ft (Recorded on 25.12.1953)

Springs near solstices

The highest tidal water level of + 14.3 ft. KPD was recorded during a cyclonic storm in June 1902.

vi. Tidal current

The following tidal currents were recorded in front of Oil Piers.

Flood current 1.02 knot or 1.73 ft. per second

Ebb current 1.30 knot or 2.20 ft. per second

The maximum tidal currents are not likely to exceed a velocity of 2 knots or 3.38 ft, per second at extreme spring tides in the lower Harbour of the navigable channel.

vii. Wave Heights

Page 218: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

No appreciable wave heights in front of the existing oil pier facilities have been registered till now. The wave measurements recorded over past several Years, at 30 ft. depth contour in open sea opposite the Manora peninsula near the entrance to Karachi Harbour, indicated maximum significant wave height of 7.0 ft. during monsoon months of May till September, and about 1.0 ft, in December with wave period ranging from 6 to 12 seconds.

Viii. Corrosion

Corrosion manifestations below the level of + 8.0 ft. KPD are tolerable. However, they heavily increase at + 10.0 ft. KPD level, and appear in an extraordinarily sever form above this lever, where the corrosion rate has been observed at about 0.06” per Year, and necessitate adequate corrosion protection system.

ix. Earthquake

The entire coastal strip of Pakistan belongs to an active seismic zone, which extends inland towards the north, via Lasbela, Jacobabad and Kalat. The epicenters in most cases, lay in the north and in the western portion are expected. For this reason, a horizontal mass acceleration of 1/10 to 1/20, with a mean of 1/15 of the vertical acceleration due to gravity is taken for Karachi area.

2. General Description of the Vessel

The vessel is a Self-Propelled Split Hopper Barge with hopper of volume of 1000 M3

suitable for coastal service near the port in Karachi, Pakistan, to work in conjunction with Bucket Dredger, Back Hoe, and Grab Dredger etc during all seasons including monsoon and rough weather. The purpose of Split Hipper Barge is to receive dredged spoil from stationary type dredgers, in its hopper, to carry the dredged material load to dumping site (s) and to discharge the same efficiently by splitting the barge and its hopper.

Page 219: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

These specifications are general and are for guidance of prospective bidders. The bidders are, however, required to submit along with their bid the detailed complete specification and General Arrangement Plan of the barges offered by them. The detailed specification should be in standard form drawn in professional manner so as cover all components, sections of the barge specifying their sizes/capacity and material configuration, technical details, ratings etc. Any change, addition, alteration, modification in these specifications so as to ensure improvement in the purpose of use, efficiency and economy, durability, maintenance, supported with complete design and drawings may be proposed by the bidder.

The Vessel to be built in two port and stbd identical halves, and the midship to be the hopper. The two halved to be connected by the deck hinges fixed on the seats above the upper deck hatchway coamings and below the coamings of raised quarter – deck at aft and forward ends of the hopper. Hopper to be opened and closed by two hydraulic cylinders fitted inside compartments at ech end of the hopper. Cylinders to be of suitable size and capacity to operate the hopper efficiently during monsoon waves of height upto 4 meter. Cylinder compartments to be watertight for ease of maintenance. The vessel to be an aft engine rooms ship with twin propulsion engines, twin propellers, twin rudders, single upper deck, transom stern and stern.

Two tiers deck house shall be rested on main deck of two half bodies of the aft hull through hinges with self adjusting spherical bearings, grease lubricated, so as to remain leveled during splitting of the barge. Wheelhouse shall be well designed with enough height above main deck with large windows to obtain an unobstructed all round visibility. On the aft deck two engine room entrances, one for each port and stbd engine room, with funnels shall to accommodate exhaust lines and dampers of the main engines, generator engines, the mechanical supply ventilation ducts and fans. Funnels are shall be designed in such a way so as to provide unobstructed all around view from the wheel house. On outer sides of the funnels, KPT’s insignia, constructed of steel plating with oven baked enamel colours, shall be fitted, away from funnel plating, which could be easily removed when required.

A steel superstructure, placed on the aft deck is to be provided with day accommodation for the crew consisting of 12 crew and 02 officers.

Page 220: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

The Self Propelled Split Type Hopper Barges shall have diesel engines and a reduction assembly gears driving a propeller at each halve hull.

The Split Type Hopper Barges shall have single bottom structure except the area of cylinder compartment aft and cylinder compartment forward and has fore raised quarter-deck, aft raised quarter-deck and two-tiers deckhouses at the stern. Machinery space, Accommodation and Navigation space to be located aft.

Watertight transverse bulkheads divide the ship into one hopper, Engine Rooms, Ballast tanks, Forepeak and Aft peak tanks and so on. The void tanks to beat the both sides and the bottom for producing buoyancy. Freshwater tanks to be arranged at the double bottom of fore cylinder room, fuel tanks to be arranged in both sides of aft cylinder room or in the engine rooms. Aft peak could be used to ballast tank.

3. Principal Characteristics

The broad based parameters of the Hopper Barges would be as under:-

Length overall = Approx. 56-62 meters

Length b.pp = Approx. 54 – 58 meters (or accordingly)

Breadth molded = Approx. 11-14 meters

Depth molded = Approx. 04-05 meters

Draft loaded = Approx 3.8-4.0 meters

Dead weight = Approx. 1600 ton (or accordingly)

Hopper capacity = Approx 1000 m3 &not less than 1600 ton

Max Speed = Approx 12 knots

Full Load Speed = 10 knots @ 90% MCR

Deck house = Hinge mounted, with Ball,Roller or Spherical

Page 221: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

Bearings.

Main engine = 2 x diesel engines, water cooled, Electric start engine of Western European, American origin with fixed pitch in the line propulsion system.

Split system = To be of robust construction, capable of being operated safely / efficiently at 7-8 beaufor scale up to 4 meter wave height.

Ambient condition = Outside Temperature 45 o C with 95% Relative Humidity .

Sea Water temperature max. 32o C.

Atmospheric pressure 760 mm Hg.

Engine room temperature 50 o C

Endurance = Store and spares capacity – 05 Days

Victualling store capacityFresh provisions - 03 DaysDry provisions -03 Days Frozen provisions-03 Days

4. Tank Capacities (approximately)

- Fuel Oil approx. 80 M3

- Fresh Water approx. 15 M3

- Lubrication Oil approx. 3 M3

- Dirty Oil / Sludge approx. 3 M3

- Sewage approx. 5 M3

Page 222: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

- Water ballast approx. 100 M3 or as required.

(This may have arrangement for filling

discharge of fresh water also)

5 Design Standards

5.1 Design of the said Barge shall be proven and proof to this effect is required to be submitted.

5.2 Complete design, construction and test and trials of the barges are to be in accordance with latest addition of Lloyds/BV Classification Society requirements or equivalent, except where explicitly mentioned in this document or accepted by KPT with notation equivalent to:

“100A1, Split Hopper Barges, Extended protected waters service from the port of Karachi, + LMC”

5.3 Availability of the Platform Barge shall be available for minimum of 80% of the time throughout its designed life of 20 years and all maintenances and refits shall be designed to allow such availability.

5.4 Stability

a) Stability standards for the design, construction and operation of vessel should be in accordance with Lloyd’s/BV Rules (or equivalent). Supplier will provide a certificate of conformance for captioned standards.

Page 223: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

b) The vessel should conform to International/ SOLAS standards for survivability against fire and under water damage.

5.5 Maneuvering Barge is to be classified in accordance with Lloyd’s/BV Maneuvering Assessment or equivalent.

6 Free Running Speed

The trial speed of the vessel, fully loaded at a draught of 3.80m to 4.0 m at even keel, while both engines are running at 90% MCR, should not to less than 10.0 knots in smooth and sufficiently deep sea water. This speed will be maintained in smooth, sufficiently deep sea water at a maximum wind fore of 7 to 8 Beaufort Scale (up to 4 meter waves).

7 Classification, Rules, Regulations and Certificates.

7.1 Classification

The hull, machine, equipment, outfit to be in accordance with Classification rules and regulation and built under inspection of Class surveyor.

7.2 Ship’s registry and Flag: Government of Pakistan

Page 224: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

7.3 Rules, conventions and Regulations

The vessel is to comply with the rules, IMO conventions and regulations of the following rules (including amendments forced at the time of signing the Contract.):

a) Rules and Regulations for the Classification of ships of LR or BV (2013). b) International convention for the Safety of Life at Sea 1974 and its Protocol of

1978, and latest Amendments.

c) Regulation for the Prevention of Pollution 1973 of IMO, and its protocol of 1978 and amendments (Annex I, IV,V)

d) International Convention on Load Lines 1966 and its protocol of 1988, and MSC77 Amendments.

e) International Convention for the Prevention of collision at sea1972 with its Amendments.

f) International Telecommunication/Radio Regulation 1985, and amendments.

g) International Convention on Tonnage Measurement of Ship, 1969.

7.4 Certificates

The following certificates or provisional certificates are to be furnished to the Owner at the delivery of the vessel:

a) Classification Certificate for hull issued by classification society 1. Safety construction certificate for SOLAS 2. Safety equipment certificate

Page 225: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

3. Safety radio certificate for SOLAS

b) Classification Certificate for Machinery issued by classification society.c) International oil pollution prevention certificate issued by classification

society, authorized by Government of Pakistan d) International load line certificate-issued by classification society,

authorized by Government of Pakistane) Certificate for tests of anchors, chain cables and mooring ropes – issued

by classification society.f) International tonnage certificate—issued by classification society,

authorized by Government of Pakistan.g) Dead weight certificate – issued by Builders for and approved by

classification society.h) Test reports for cast pieces and forging pieces – issued by manufactory

and to be approved by classification society.i) Certificate for fire fighting equipment – issued by classification society,

authorized by Government of Pakistan.j) Certificate for life saving appliance – issued by classification society,

authorized by Government of Pakistan.k) Certificate for signal registry – issued by classification society.l) Certificate for ship’s lights – issued by Competent Authority of

Government of Pakistan.m) Certificate for compass adjustment – issued by Competent Authority.n) Builder’s certificate – issued by Builders.o) De-ratting exemption certificate – issued by Competent Authority.

8 Supervision and Inspection

The complete Split Hopper Barges including its machinery, equipment, all installations and outfit shall be built under the inspection of Purchaser’s nominated Engineer. The steel hull, steel superstructure, the machinery installations and the electrical installations, shall also be under the inspection of Class.

The Engineer has full power to inspect the work at any stage, at all times, and to satisfy himself by every means, inclusive testing of materials, trials at manufacturer’s test-beds, x-raying and ultrasonic-testing of welds and similar tests, as he may deem fit, that the materials and workmanship employed are of highest standards and according to the requirement of the specification.

The Engineer is entitled to reject or refuse materials, machinery or its components, equipment and outfit where they are considered not to comply with the standard of

Page 226: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

goods workmanship. The Supplier shall repair or replace at his own cost the rejected parts, work, materials, etc. to the satisfaction of the Engineer.

The Engineer/Employer’s representative shall at any time have free access to the Split Hopper Barges, to the Supplier and to the workshops of the Supplier and of his Sub-Contractors. The Supplier and Sub-Contractors shall give full co-operation in order to enable the Engineer to carry out the intended inspections efficiently. In addition the Supplier shall include in the Contract Price all the costs related with inspection-visits of representative of the Engineer/Employer, viz.a viz) to the factories: 2 man-trip to Model Test 2 man-trips to main engines bed test, 2 man-tips to auxiliary engine bed test and 10 man-trips to the builder’s Yard.

The Supplier shall put at the disposal of the Engineer office room with 4 chairs, 2 writing desk, a personal computer with printer, telephone, internet, Photostat machine, light, heating/air-conditioning, refrigerator, lockers for drawings and clothes, toilet facilities, etc. The Suppliers shall also provide transport to the Engineer.

Furthermore, the supplier will provide following facilities / equipment for use of Employer’s personnel (Planning and Development Division of Karachi Port Trust) for supervision of construction 04 self propelled split type hopper barges.

a) Two Laptop latest version along with one computer operator.

b) One Photo copier along with scanner.

The above facilities/equipment shall remain in use of Employer’s personnel till expiry of one year warranty period and the same shall be return to the supplier.

9 Tests and Trials

Page 227: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

9.2 General

Of those materials for which no Classification Certificate is required, the Engineer shall have the power to require tensile, bend and/or other mechanical tests and chemical analysis for plates, sections, castings, forging as the case any be, in such number as may be considered to represent fairly the lot of articles and materials to be used.

All the specified tests and trials, including the repeated tests and trials, shall be carried out and checked by the Supplier and shall be their full responsibility,. The Supplier shall bear all costs including costs for the crew, fuel oil, lubricating oil, etc during the trials.

Welds shall be tested by taking x-ray photographs and / or ultrasonic testing to the satisfaction of the Engineer and Or the Class.

The Supplier shall submit to the Engineer and the Class for approval a complete program and time schedule of all the specified tests and trials, along with the test-procedures, the test-methods and the test-protocol forms, at least four weeks before the commencement of the proposed test & trials. All tests and trials shall be conducted to establish the vessel’s compatibility to accomplish the assigned tasks effectively to the entire satisfaction of the Employer. Engineers/ Class Surveyors. The tests shall include speed, endurance and maneuverability trials, which are common for any vessel of this type.

An inclining test shall be carried out with the fully equipped the Split Hopper Barges. All final calculations regarding the stability for which this test is a base, shall be submitted to the Engineer for approval within two weeks after the completion of the inclining tests.

All instruments required for the tests, such as torsion meters, tachometers, ammeters, duly calibrated, shall be provided by the Supplier free of cost. Results shall be measured and recorded, estimates shall not be acceptable.

Page 228: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

All gear / equipment required for conducting trials should be available on board and confirmation to this effect is to be give by the Supplier prior to commencement of the vessel’s trials.

The Engineer shall have the right to decide whether the proposed trial areas and water depths are suitable to carry out the specified trials. If under the tests and trials any part of the works or machinery/equipment fails to fulfill adequately the specified requirements, the faulty part of works shall be repaired, renewed or replaced and the test shall be repeated at the Supplier’s expense, to the satisfaction of the Engineer and/or the Class.

Tests and trials which are declared unsatisfactory by the Engineer shall be repeated at the Supplier’s expense until they are successfully carried out and approved by the Engineer.

All the recorded protocols of workshop tests, quay, sea and other trials shall be in well tabulated form and on approved format, signed/ countersigned by representatives of the Supplier, Engineer and the Employer respectively, filed in durable bindings and supplied in six-fold before delivery of the Split Hopper Barges to the Employer.

After all the trials have been carried out satisfactorily, the Split Hopper Barges shall be neatly finished, dried, cleaned, oiled, etc., all paint and varnish shall be brought in a good condition, all defects and failings shall be repaired and all spare parts and inventories shall be put on board. The imported Split Hopper Barges shall be made ready for transport to and for Confirmatory Trials in Karachi and thereafter final delivery to the Employer at Karachi Port.

9.3 Workshop tests

All machinery, equipment, articles, materials etc. shall be tested in the manufacturer’s workshops and test-beds before dispatch to the Supplier to ensure proper functioning and operation. Engineer / Employer shall be given sufficient advance information of important workshop tests such as main engines, auxiliary engines, switch board etc. so that they may attend these tests if they so desire.

Page 229: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

Complete set of these tests records to be submitted to the Engineer for approval and three sets of approved record to be supplied with the Split Hopper Barges.

9.4 Quay Trials

Well in advance before the relevant trials are carried out, the Supplier shall carry out the quay trials of the complete machinery installations, the auxiliaries, the piping systems, the electric installation, including running of the generator sets on load, the deck machinery, the mechanical ventilation system, the controls and all other instruments etc. to ascertain its good working and its durability separately as well as in possible conjunction with other installations, to the entire satisfaction of the Engineer and where applicable of the Class.

9.5 Preliminary Acceptance Trials

The Split Hopper Barges shall be subject to “Preliminary Acceptance Trials (PAT)” which shall be to the satisfaction of the Engineer and the Class and shall comprise all the tests which are necessary to verify, check and confirm the performance requirements of the Split Hopper Barges and its installed machinery, equipment and material, as determined and specified by the Engineer. The PAT shall include continuous endurance trials and splitting of the Split Hopper Barges, without any mishap, mal-operation or defects. In case of imported split Hopper Bares only, PAT shall be carried out prior to their shipment to the Karachi Port

After successful completion and acceptance of the PAT by the Employer and the Engineer, a Preliminary Acceptance Certificate for Split Hopper Barges shall be issued to the Supplier by the Employer, based on the recommendations of the Engineer.

9.6 Confirmatory Trials and Final Acceptance

After arrival in Karachi, Confirmatory Trials shall be carried out (in case of imported Split Hopper Barges only) during normal working hours for a period of continuous two days prior to final acceptance at Karachi Port. Furthermore, these trials shall

Page 230: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

additionally include the running tests of all machinery and equipment as may be considered necessary by the Engineer, which shall be conducted to demonstrate that the Split Hopper Barges and its components have not been ill-affected during the delivery voyage to Karachi. The schedule and details of the Confirmatory Trials shall be mutually agreed with the Engineer.

The supplier shall bear all costs whatsoever, including costs for the crew, fuel oil, lubricating oil etc. necessary for the Confirmatory Trials.

After successful completion and acceptance of the Confirmatory Trials by the Engineer and the Employer, and on final completion of all the technical and contractual requirements, a Final Acceptance Certificate for Split Hopper Barges shall be issued to the Supplier by the Employer, based on recommendations of the Engineer.

9.7 Tests and Trials Specifications

Tests and Trials requirements of the Split Hopper Barges are detailed in Part VI, herein, which shall be fulfilled to the satisfaction of the Engineer / Employer.

10 Noise and Vibration

10.2 Noise Criteria

The sound level on board for following spaces, when sailing with engine running at 90% of the rated speed light wind and all systems in operation, shall comply to following requirements

Wheelhouse 75 dB (A)

Accommodation 70 dB(A)

Page 231: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

Good and reliable acoustic insulation shall be carried out for the above spaces / areas with the prior approval of the engineer.

10.3 Vibration

The Supplier shall be responsible to take all practical steps to minimize vibrations particularly in the accommodation and wheelhouse. Any excessive vibration defects discovered during trials are to be rectified by the Supplier at his own cost.

11 Technical Requirements and conditions

11.1 Ambient Conditions/ Environment

a) The Split Hopper Barge and its equipment/ machinery/ systems should be able to operate in Arabian Sea upto Sea State 6 under following environmental conditions:

i) Ambient temperature - upto 45OC

ii) Relative Humidity - 95 %

iii) Sea water temperature - upto 32oC

iv) Engine room temperature – upto 50 o C

b) Moreover all machinery/ equipment/ systems shall comply with Environment Protection Rules in vogue, such as Marine Pollution Rules (MARPOL) and IMO regulations

12. Drawings, Calculations, Spare Parts Lists, Manuals, Photos, Patterns and Templates, Model.

Page 232: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

12.1 General

Before starting the construction, the drawings and calculations, descriptions and brochures and other details shall be sent to the Engineer for approval as specified in the contract.

12.2 Drawings and Calculations

At least the following fully detailed drawings and detailed calculations shall be sent to the Engineer for approval.

1. General Arrangement Plan, showing the total arrangement of the Split Hopper Barges, completely and clearly. This drawing shall be kept up-to-date during the whole building period.

2. Midship section with specified cross sections and the construction of the frames and webs.

3. General construction plan of hull and construction of the oil tight and watertight bulkheads and tanks.

4. Construction of Hopper and void spaces.5. Calculation of Hopper capacity with Diagram

6. Construction of the maindeck7. Shell expansion8. Construction of Ship ends with stern, stern and skeg.9. Construction of the deckhouse, casings, funnels and masts.10.Construction of the foundations of the main engines and auxiliaries in the engine

room.11.Construction of hawse pipe and chain locker.12.Construction of the foundation of windlass and deck auxiliaries.13.Layout and construction of deck, machinery and equipment.14.Construction of hatches, trunks, skylights, etc.15.Construction of bulkwark, railings, stairs, ladders etc.16.General Arrangement Plan of the engine room.17.Construction of engine Girders.18.Layout of engine room floors and gratings.19.Diagrams of all pipeline systems, etc.20.Arrangement of hoisting gear in engine room.21.Plans with details of the paneling, linings, ceilings, floor covering and

arrangement of the accommodation, stores, etc.22.Plans with details of natural ventilation.23.Plans with details of the mechanical ventilation.

Page 233: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

24.Body plan with appendices.25.Hydro static and cross curve diagrams and calculations.26.Curves of tank capacities with centers of gravity.27.Weight and strength calculations.28.Trim and stability calculations.29.Tank testing plan.30.Docking plan31.Safety and fire fighting plan32.Electrical single line diagrams, general layout, main switch board diagram,

distribution diagrams, wiring connecting diagrams, construction and installation drawings etc.

33.All other detailed drawings, diagrams, calculations, etc. which shall be considered necessary by the Engineer.

Approved by the Engineers of all the drawings shall in no way exonerate the Builder from his responsibility for the possible consequences caused by errors in the approved drawings.

.

12.3 Drawings to be fitted on board

The following drawings, in light proof and plasticized execution, shall be framed and fitted on board in consultation with the Engineer.

General Arrangement plan Engine room arrangement Bilge scheme Safety and fire fighting plan Electrical key diagram (Single Line General Arrangement)

Number and places of fitting shall be settled in consultation and agreement with the Engineer / Employer.

12.4 “As-built” drawings

Page 234: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

One week prior to issue of the Preliminary Acceptance Certificate of the Split Hopper Barges, six sets of as built drawings shall be supplied. In addition, one CD set of as-built drawings shall be supplied. These as-built drawings shall comprise the design drawings, the principal construction drawings of hull and equipment, including drives, windlass, stability calculations, tank capacity curves, docking plan, engine room arrangement plan, the principal arrangement drawings of the diesel-engine, propulsion equipment, generators, pipelines auxiliaries, switchboards, the principal electric schemes and the arrangement drawings, and the equipment on deck. These drawings shall be numbered and shall be put on a list. This list, together with the drawings, shall be supplied to the Engineer / Employer.

12.5 Manufacturer’s instruction, maintenance and spare parts manuals.

The Builder shall be required to obtain six (6) folds of all Maker’s detailed instruction, operation and maintenance manuals, including spare parts catalogues for each item of machinery / equipment which the Supplier shall procure for the Split Hopper Barges.

The above mentioned documents, which shall be required for the preparation of “Plant Operation Manual” and “Planned Maintenance Manual”, shall form also an integrated part of these Manuals.

“Plant Operation Manual” - & “Planned Maintenance Manual”

(a) General:

The Supplier shall be required to prepare and deliver along with drawings of the Split Hopper Barges, six (6) original copies of “Plant Operation Manuals” and “Planned Maintenance Manuals” for the Split Hopper Barges, for all technical installation.

Page 235: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

The set-up of both Manuals shall be according to an industrial documentation system and, additionally, affiliating all the requirement as specified particularly by the Class, and to the approval of the Engineer.

(b) Plan Operation Manual

In the “Plant Operation Manual”, the industrial documentation system has to provide an easy and better understanding of the Split Hopper Barges, their operation and its supporting documentation, in order to serve as an aid to:

fast and accurate trouble shooting fast breaking-in of new personnel Implementation of essential and preventive maintenance

The “Plant Operation Manual” shall first be submitted in draft for approval by the Engineer and finally, shall be supplied in completely plasticized execution.

© Planned Maintenance Manual

The purpose of the “Planned Maintenance Manual” is to serve as a guide to maintain the Split Hopper Barges in optimum condition.

The Planned Maintenance Manual shall first be submitted for approval to the Engineer and, finally, shall be supplied in completely plasticized execution.

(d) Daily routine check cards.

Along with the “Plant Operation Manual” and “Planned Maintenance Manual”, a separate daily routine check cards shall be prepared, indicating and describing all the daily routine maintenance jobs, e.g. usual inspections, greasing, etc.

Page 236: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

12.6 Patterns and templates

On instructions of the Engineer, all specially made patterns and templates used for the construction and / or manufacture of the non-standard machinery or its components shall be delivered, packed and stowed on board of the Split Hopper Barges, as per the directives of the Engineer, prior to their shipment to Karachi.

12.7 Model, photographs and brass plaques

For placing in the board-room of the KPT main office, two numbers accurately made detailed, high quality models of the Split Hopper Barges, scale 1:50, shall be delivered. The models shall be placed on a teak wooden under a transparent cover.

Photographs of the Split Hopper Barges during construction and trials shall be supplied as required by the Engineer, in A4 size, max. 50 No. in two copies, in albums.

For each hoper barges six Brass Plaques 200 x 250 mm mounted on wooden base made to the approval of owner with owners name, insignia, vessels name and sketch, year of built, its particulars’, names of KPT’s concerned officials, Engineers etc. shall be supplied with each split hopper barge. A large Plaque (600 x 750mm) with same information shall be fixed at prominent place near wheelhouse.

12.8 Inventory

Each crafts shall be equipped with standard general tools for all level of maintenance (Mechanical/Electrical/Deck) and stores.

12.9 LPACS

- L.P. Air Compressor for Pneumatic tools / clearing etc.- Portable Pumps 02 Nos.

Page 237: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

- Emergency Lights- Recommended spare from OEM- Special Tools for all machinery- Submersible Pumps (02 Nos) complete in all respect to clear water from hopper

spares in1.30 min.

Page 238: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

PART I I – HULL SPECIFICATION

1. General Arrangement:

The Barge has a single deck, raised beyond the fore and aft end of the hopper.

Both watertight hull halves are each subdivided by transverse bulkheads into a number of watertight compartments.

aft peak with steering gear room engine room with ballast tank recess for hydraulic cylinder the buoyancy compartment into at least three compartments of which one

with fuel bunker and ballast tank in one half and fresh water tank ballast tank in the second half recess for hydraulic cylinder store and chain locker forepeak as ballast tank

2. Hull Construction

Barge’s hull structure should be designed to accommodate the mechanism for releasing material (consisting of mud, sand, stone clay and trash). Moreover, following aspects may also be catered for:

a) Capable to bear weight of dumping material/ internal loading.

Page 239: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

b) Steel hull and super structure i.a.w Lloyd’s / BV Rule of this type / class of vessel or equivalent.

The hull shall be hard chine form, with transom stern and tapered bow:

The hull shall consist of two halves, hinging at top coaming level.

Each hull half shall be of all welded construction and be subdivided into watertight and / or oil tight compartments, in accordance with the relevant rules and regulations of Class, as per general / introduction herein above.

The hull, the scantling of which shall base on the above indicated loaded draught, to be strengthened by a combined transverse and longitudinal frame system – 10% in excess of class requirement.

Thickness of all hull plating, including centre line bulkheads, shall be 10% in excess of minimum requirements of Classification Society.

Bottom plating in fore and aft ship from bilge to bilge to have a wear allowance of 2 mm in excess of class requirement instead of 10% increase in plate thickness. Side plating in way hopper and cylinder recess to be 4 mm in excess of Class requirement.

Any discontinuity of strength in way of hull openings such as sea inlets and overflow openings in the side, to be compensated by inserted thicker plates. All openings to have corners of ample radius.

The bilge shall be double hard chine type.

2.1 Frames and Webs

Page 240: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

The longitudinal frame system to be supported by transverse web frames or wash bulkheads.

In the engine rooms and stores web frames to be positioned every forth frame. Plate thickness and main scantlings generally 10% in excess of Classification requirements.

2.2 Bottom Strengthening

In the engine rooms a double bottom to be provided where required for arrangement of storage for lub. Oil, dirty oil and sludge. Remaining space to be supported by open floors and longitudinal girder. Thickness of floors / longitudinal shall be 10% in excess of Class requirements.

2.3 Deck Plating

The deck in way of the hopper, the aft deck house and the fore deck to have a camber of at least 50 mm per 2500 mm.

Thickness of deck plating in way of hopper shall be 2 mm in excess of Class requirements.

Heavy inserted plates in way of the hinges and at corners of the hopper.

2.4 Bulkheads

Page 241: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

Watertight and / or oil tight bulkheads to be provided to achieve the subdivision described in 6.1

Scantling of bulkheads to be 10% in excess of Class requirements. The lower boundary of the bulkheads to be at least with a plate thickness of 9 mm

3. Hopper Construction.

The vertical hopper plating shall have a thickness of 16 mm, while the inclined plating is 20 mm or as required scantling for hopper seals to have reinforcement for strength.

The longitudinal frame spacing in hopper region shall be 400mm. The spacing of the web frames in this region shall be 2600 mm

The raised hopper coaming is a hopper ends extended by brackets sufficiently tapered to the deck level for continuation of the longitudinal strength elements.

The hopper on spoil side to be flush and plain. The thickness of the plating 4 mm in excess of Class requirements. The capacity of the hopper to be nett 1000 cubic meters, calculated in level 0.5 m under the top of the coaming a midships. The lower slope of the hopper to be not less than 25”. The opening angle of the hopper at least 2 x 17.5”.

3.1 Deck hinges and security combs.

The two halves of the barge to be connected by two hinges, fitted about 0.6 m above the raised deck.

Page 242: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

The hinges to be of cast steel. Eye plate and fork plate construction integrated in the deck and cylinder recess construction.

The hinge pins to be made of steel C 35 to be provided with a self-aligning spherical bearings. The pins to be secured by watertight sealed covers. The spherical bearing to be sealed by two V-rings, oil and seawater resistant. The space between the eye plate and fork, as well as the pin bearing surface to be grease lubricated.

Longitudinal movement of closed barge’s halves in relation to each other to be prevented by heavy steel security combs on the forward and aft end of the hopper.

The clearance and fitting to be of high accuracy to assure correct functioning of bottom catchers and top combs.

3.2 Recess for hydraulic cylinders

The recess on forward and aft end of the hopper accommodates the hydraulic cylinders for split movement. The recesses are to be of a strong and heavy construction with integrated heavy eye plates, in the washer bulkhead, one on each side, for fitting of the fork construction of bottom and rod end of the cylinder. The structural members in line with the eye plates in line with a deck hinge plates to be carried forward into the buoyancy compartments to transfer the resulting forces into the Barge’s structure. All work to be carried out to extremely high quality for perfect fitting.

Page 243: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

The trimmed condition with water level inside the hopper equal to outside the recess can be opened enabling inspection of hydraulic cylinders, hoses etc., as well as to facilitate repair.

The recess to be designed such that mounting / dismounting of the cylinder in closed position of the hopper is possible via a hatch in the deck.

The opening of hopper / splitting of barge shall be backed up with installation of a standby hydraulic ram is optional. The cost to be indicated separately.

Around the hull thicker steel flat bars for holding rubber D type fenders are to be fitted.

3.2 Trap water in the Hopper

For removing of trap water, the Piston Pump / self prime pump with 4” suction dia to be fitted with all accessories and flexible pipes.

4. Aft and Forward Body Construction

4.1 Stem, Stern and Skeg

The stem constructed of steel plate with cylindrical section to be strengthened by brackets. The openings between the two stem plates to be not more than 60mm

The stern of each ship halve to be fitted with a skeg. Each skeg about 400 mm wide.

4.2 Propeller bosses and shat brackets

Page 244: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

The propeller bosses to be connected to the hull by shaft brackets, and connected to the forward bearing by means of a thick walled seamless pipe, forming the stern tube.

Shall brackets of fabricated mild steel to be of a streamlined cross section, welded to the boss and suitably connected to the structural members of aft ship’s hull and skeg.

4.3 Rudders

The two rudders to have streamlined cross section, and of free hanging type. The area of each rudder to be about 1.25% of the lateral area. Rudders to be coated inside. Rudders to be provided with lifting lugs. Also adequate attachments to be provided on the hull.

Each rudderstock to be supported in two bearings.

The lower support mounted in a tabular support with wearing bush and sealing of a double V-type rings. The upper bearing to be incorporated in the steering gear machine.

An automatic and continuous grease lubrication system to be provided for each rudder stock.

5. Deckhouse and Funnels

5.1 Deckhouse

The deckhouse is a self supporting construction, mounted on four points by means of hinges with Roller, Ball, Spherical Bearings in such a way that it remains almost horizontal during splitting movement of the barge.

Page 245: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

At one side the two supports each to consist of a single hinge. At the other side each support to consist of a double or link type hinge. Hinges to be provided with self adjusting spherical bearings, grease lubricated . Bearings to be sealed with oil and seawater resistant V-rings. Pins to be locked up by the watertight covers.

The deckhouse to be of fully welded construction, and adequately stiffened. Decks are to be without sheer and camber. Longitudinal stiffeners to be supported by web frames. Minimum thickness of deck plating to be 7 mm, lower beam of side walls of 8 mm, and upper tier of 7 mm.

The deckhouse arrangement to suit the necessary spaces of the two tiers as shown in General Arrangement. Plate thickness of boundary bulkheads of web spaces, provision, galley and technical room to be of 6 mm steel. Deck heights to be 2600 mm minimum. Height of technical room to be 1500 mm to provide adequate view from the wheelhouse.

5.2 Wheelhouse

The wheelhouse is to be of steel plate construction, well designed with large windows to obtain an unobstructed all around visibility and adequately and stiffened in way of doors and windows. The walls to be titled about 10” outwards. Plate thickness of deck and bulkheads to be not less than 7 mm. In way of the standard compass over an area as required by the regulations, see ISO R694-1968, the wheelhouse to be constructed of antimagnetic material under the wheelhouse.

5.3 Funnels

On the aft deck two engine room entrance with funnels to be fitted, to accommodate exhaust lines and dampers of the main engines, generator engine, harbour generator engines, the mechanical supply ventilation ducts and fans. The funnels serve partly for the natural exhaust of engine room. Scantlings of plates and structural parts is the same as for the deckhouse.

Page 246: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

Funnels to be closed at topside. Ladders for access where practicable to be fitted inside the funnels.

The funnels to be designed in such a way which provide unobstructed all round view from the wheelhouse.

On outer sides of the funnels, Owner’s mark constructed of steel plating with oven baked enameled colours, shall be fitted, free from the funnel plating, which cold easily be removed when required.

Page 247: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

PART III – MACHINERY SPECIFICATION

1. Propulsion and Maneuvering System.

The vessel shall provided with two fixed bladed propeller (in line propulsion system) each driven by a marine diesel engine via a reduction gearbox.

Starting / Stopping of the main engines is to be from engine room and also from the wheelhouse.

The generating sets to be provided with capacity as per installed consumers power plus 40%.

The main and auxiliary diesel engines shall be water cooled and electric started.

The design and layout shall be in accordance with the relevant rules of Classification.

2. Main Diesel Engine

Main Diesel Engines shall be marine type water cooled, electric start, of origin Western Europe / America Preferably, M.A.N. Caterpillar, Cummins or Wartsila.

3. Controls of the Propulsion Units

Page 248: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

The wheelhouse shall be provided with a min control desk, containing the respective control and / or monitoring devices of the propulsion units and generating sets. Make Western Europe.

4. (a) Hydraulic System

Hydraulic Equipments shall be Western Europe America or Japan make.

The hydraulic pumps shall be of plunger type.

The pumps shall be flexibly coupled to the respective prime movers. Pump unit shall be built together with belonging circulation tanks and valve panels to be complete modules ready for resilient mounting on the ships foundation.

The complete pump unit to be provided with a drip tray. All pipe connections with pump and motors shall be with metal strengthened flexible joints.

Pumps in open system will have their own suction connection equipped coarse filters. Fine filter shall be fitted in the pressure or return lines. All filters shall be of the full-flow type with fouling indications and alarm contacts.

The pressure gauge shall be in stainless steel execution with a needle valve.

The vessel shall be provided with the following hydraulic system.

4. (b) Barge Splitting System

System shall consist of two splitting cylinders.

For the above system, one electric hydraulic pump set and one back up pump set shall be installed (location shall be appropriate for easy access as per design requirement also maintenance work on main cylinders can be carried out in afloat condition). All hydraulic Pipes materials shall be of Stainless Steel.

Page 249: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

Proper ventilation system especially for enclosed area to be provided.

One stainless steel hydraulic oil tank with built-on solenoid valves, etc. shall be fitted.

Hydraulic system can be remotely operated fro the wheelhouse.

Make of Hydraulic system – Rexroth or Vickers.

Both Splitting Hydraulic ram and hydraulic pipes must be above sea water level of ease of repair / maintenance work.

5. Primary Ship System

a. Bilge / Ballast / Deck Wash and Internal Fire Fighting System.

All piping shall be made out of stainless steel, the valves to be of bronze. Valves shall be applied as far as possible.

This system shall be complete with two electric driven bilge / general service pump sets, each with capacity according to class requirements. Make Western Europe.

Pumps shall be centrifugal / plunger type, with corrosion resistant casing, bronze impeller and stainless steel shaft. Make Western Europe.

The (internal) fire fighting system shall be in accordance with the relevantly rules for this type of vessel.

One portable engine driven fire fighting pump with flexible suction and discharge hoses to be provided.

b. Fuel System

Page 250: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

Steel piping and bronze valves shall be used.

Both fuel bunkers shall be located inside the aft cylinder compartment.

Two – day tanks shall be mounted in the forward section of engine room.

A electric driven fuel transfer pump shall be supplying fuel to each day tank. A second transfer pump shall be fitted as stand-by.

c. Cooling Water System

All diesel engines shall be water cooled. The cooling water of the main engines shall be cooled via Box or Tube cooler.

The generating sets and hydraulic pumps shall be cooled by means of a sea-chest cooler.

d. Potable Water System

The main distribution line shall be made out of galvanized steel piping. The water lines in the accommodation shall be copper. The vessel should have a pressurized potable water system with two pump units, one of which to serve as stand-by (Hydrosphere).

e. Sewage System

All sewage water shall be collected into the sewage tank, which should be provided with an electrically driven sewage pump, having a hose connection on main deck level. System should be according to IMO Standards for environment.

f. Filling / Sounding and De-aeration system

Page 251: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

All piping shall be made out of steel, galvanized where appropriate. Ventilation caps are in accordance with the requirements of the class.

g. Lubricating Oil system

All piping shall be of steel and valves of cast steel. One lubricating oil transfer pump shall be installed in each engine room.

Priming pumps for main engine.

Clean lubricating oil shall be gravity supplied to diesel engines from an elevated oil tank with pipe line.

Dirty oil to be collected in a separate tank, located at the bottom of the vessel. The content can be pumped to a connection on deck level by means of above mentioned pump.

with additional stand-by split type air conditioning for the wheelhouse

h. Air-conditioning & Ventilation System. Commercial type air conditioners of sufficient capacity to maintain good habitability in the wheelhouse and accommodation spaces with additional stand-by split type air conditioning for the wheelhouse. Ventilation and exhaust/ recirculation system for Machinery compartment, sanitary space & wastage storage tanks as per Lloyd’s/BV Rules or Equivalent, acceptable to KPT suitable for Extreme Tropical Conditions. Ozone friendly gases are to be used. Air-conditioning system be designed to cater following environment condition:

Ambient temperature - 45oC

Ambient relative humidity – upto 95%

Sea water temperature – upto 320C.

Page 252: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

Temp within living spaces – 22o-24oC.

Temp within Wheel House – 20oC

PART IV – ELECTRICAL SPECIFICATIONI

1. General

1.1 The whole electric works on the vessel are to be carried out in accordance with the L.R. Classification Society rules and relevant standard requirement

1.2 Origin of electrical equipments shall be German/UK/Reputable European Make.

Page 253: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

1.3 Equipment and materials are to be in accordance with ISO, IEC Standard, manufacturer’s standard and to meet relevant rules, regulation

1.4 Drawings for electric, electronic and automation plants shall be submitted to the owner for approval according to SPECIFICATION of this vessel.

2. Power Distribution System

Generator AC 400 V, 50 Hz, 3 phase 3 wire insulated system.

Motor AC 380 V, 50 Hz, 3 phase 3 wire insulated system

General lighting feeder AC 220 V, 50 Hz, 3 phase 3 wire insulated system

Lighting branch circuit AC 220 V, 50 Hz, single phase 2 wire insulated

system

Interior communication AC 220 V, 50 Hz, single phase 2 wire insulated and /

or DC 24V system

Navigationa equipment AC 220 V, 50 Hz, single phase 2 wire insulated and /

or DC 24V system

Radio equipment AC 220 V, 50 Hz, single phase 2 wire insulated and /

or DC 24V system

Emergency lighting DC 24V system

3. Electric Power Generating Plant

3.1 General

The electric power generating plant with preferred alternators makes, Stamford, Siemens, AVK or Leroy Somers, shall be installed as follows:

Page 254: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

Main Generators: Two (2) diesel generator (440V, 3 Ph, 50Hz)

Harbour Generator: One (1) harbour generator (400V, 3 Ph, 50 Hz)

The number of running generators for each operating condition shall be designed as follows:

Condition Running

Normal sea going condition 1 main Generator set loaded under 75%

Maneouvering 1 main Generator set loaded under 75%

Filing Hopper and discharging 1 main Generator set loaded under 75%

Harbour Harbour Generator set loaded under 75%

The running alternator set(s) for each condition and its (their) rating(s) shall be confirmed by an electric load analysis prepared by the Designer in advance and submitted for Employer approval before selecting generators.

3.2 Main Diesel Generators (2)

Two (2) main diesel generators shall be installed in the starboard engine room. M.A.N. / Caterpillar / Volvo or Equivalent diesel engine of Western European/USA origin.

To avoid black out while load transfer, the parallel running of diesel generators should be possible for a short time via synchronizing device or manual switch.

Page 255: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

Generators

Make Stamford, Leroy Somer, Siemens

Rated output Single DG load capacity should be 40 % above the maximum demand.

Rated Voltage AC 400V

Frequency 50Hz

Type Self excited, brushless

Insulation Class “F”

Enclosure IP23

Space heater AC 220V

3.3 Harbour Generator (1)

One (1) harbour diesel generator shall be installed in the Port engine room. M.A.N. / Caterpillar / Volvo or Equivalent diesel engine of Western European/USA origin.

Generator

Make Stamford, Leroy Somer, Siemens

Rated output DG load capacity should be 40 % above the maximum Harbour load.

Rated Voltage AC 400V

Frequency 50H

Number of phase 3 phase

Type Self excited, brushless

Insulation Class “F”

Page 256: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

Enclosure IP22

Space heater AC 220V

3.4 Protection, Alarm and monitoring

Protection, Alarm and monitoring shall be in accordance with the relevant requirements for this type and size of vessel. Important shut down facilities / circuit breakers shall be provided.

3.5 Lighting transformer

Two Lighting transformers (one standby) shall be 3-phase rating 400/230 volts, 50Hz.

3.6 Shore Supply

The vessel shall have shore connection provision with sufficient capacity, with phase sequence indicator, single phase protection, short circuit protection, voltmeter, amp meter, indication lamps etc. and provision of required cable (150 meter) socket connections on both port and stbd sides of the Barge.

3.7 (24 V) Battery Systems

(a) For main and Auxiliary Engines starting

An individual 24 V-battery, each of 200AH, shall be installed for starting of each diesel engine. These batteries will be charged by dynamos mounted on diesel engines via rectifiers.

Page 257: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

(b) Emergency / communication / alarm Batteries.

Duplicate emergency battery sets of 24V of sufficient capacity shall also be provided. Charging method shall be the one-charging, and the other one discharging type with manual voltage adjusted.

The panel shall be supplied from the AC 220V from main switchboard.

The silicon rectifier shall be as follows:

Max. output current 40 (A)

Max. output voltage 36(V)

The following outgoing circuits to be fed from the bus-bar moulded case circuit breakers:

- emergency lights- Interior communication equipment- Alarm device (general, fire and engines) etc.

In case of man power supply failure, the temporary emergency lights shall be automatically switched on.

(c) Radio equipment

One (1) set of battery charger and one DC 24V distribution unit for radio equipment shall be located in charger room.

Page 258: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

The radio battery charger shall be supplied from AC220V distribution unit in wheelhouse control console.

The following outgoing circuits of DC24V to be fed via moulded case circuit breakers:

- Radar- Echosounder- GPF- VHF radio telephones- Electric log- NAVTEX receiver- Public address system.

3.8 Test Panel

One (1) set of wall mounting type test panel shall be installed in the port engine room and provided with the following device.

1 – Set of terminals for testing AC 380V up to 10 A three phase apparatus

1 – Set of terminals for testing AC 220V up to 10 A single phase apparatus

1 – Set of terminals for testing AC 24V up to 5A apparatus

1- Fuse checker

1 – Set of test sockets for each kind of incandescent and fluorescent lamps

1 – Volt meter for AC

1 – Volt meter for DC

1 – Circuit breaker

1 – Source pilot lamp

4. Distribution Equipment

Page 259: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

4.1 Main Switch-boar

4.1.1 Construction and Installation

The Switch board shall be of drip-proof, dead-front, self-supporting, sheet steel frame construction with ventilation louvers and a drip-over over the top. On both sides of the switchboard and between the difference voltage panels shall be protected by sheet steel plates Non-conducting rails at the front and rear of the switchboard shall be provided. The No. 1 main switchboard to be installed in the stbd. engine room. The No. 2 main switchboard to be installed in the port engine room.

4.1.2 Main components

All switch, circuit breaker and fuses to be approved type. The main generator’s circuit breaker shall be of Siemens or equivalent, electrically operated. In addition, a manual operating handle shall be provided.

The harbour generator’s circuit breaker shall be of Siemens or equivalent, electrically operated. In addition, a manual operating handle shall be provided.

All circuit breakers shall have an over current trip device for long time and short time inverse action and shall have magnetic coils for instantaneous trip and under voltage trip.

The feeder circuits of the switchboard shall be protected by moulded case circuit breaker, but the steering gear motor and transformers feeders, which shall be protected against short circuit only.

Moulded case circuit breaker shall be equipped with thermal cover current and magnetic instantaneous trip device.

4.1.3 Switchboard layout

Page 260: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

The No. 1 main switchboard be consisting of the following panels:

1 – Generator panels

2 – AC 400V and AC220V feeder panel

The generator panel with volt, ampere, frequency with phase selector, change over switches, synchronizing, indication lamps, governor control switches, voltage regulators etc. shall be provided on the upper part. The air circuit breaker of generator shall be provided on the lower part. The moulded case circuit breaker equipped with thermal over current and magnetic instantaneous trip device shall be provided in the feeder panel.

The No.2 main switchboard shall be consisting of one panel with two partitions. The meters and its change over switches, Insulation level meter with earth indicating lamp, indication lamps, air circuit breakers, voltage regulators etc. shall be provided on the upper part. The moulded case circuit breaker equipped with thermal over current and magnetic instantaneous trip device shall be provided on the lower part. The 220V feeder panel shall be fed via one of two transformers.

4.1.4 Function

To avoid blackout while load transferring, the main generator can be run in parallel for a short time.

The stand-by diesel generator shall be started automatically in the Bus in no voltage conditions, and is to be automatically connected to the Bus within 30 seconds. The electrical interlocks between the main generator circuit breakers and the harbour generator circuit breaker shall be provided to prevent the main generators from running with the harbour generator in parallel.

Page 261: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

The shore connection box connected via permanent cable to the main bus bar of NO.1 main switchboard by a contactor in switchboard. Interlocks between the shore power supply and the generators shall be provide.

Air condition, ventilation fans, oil pumps, shall provided with stop push buttons in the wheelhouse and engine room entrance.

4.2 Distribution Boards

Generally, distribution boards shall be constructed by sheet steel with front door, and in general, shall be of drip-proof Type.

The distribution boards shall be provided with moulded case circuit breakers with thermal over current trip device and magnetic instantaneous trip device.

All distribution boards shall have about 10% reserve circuits for future consumers.

4.2.1 Galley equipments distribution board

One (1) set AC220V PD6 type Galey equipments distribution board shall be located in Galley, served for galley equipments and laundry equipment.

4.2.2 Lighting distribution boards

Lighting distribution boards shall be fitted in each the port and starboard engine room, for lighting in the engine room, steering gear room and other spaces.

Page 262: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

One(1) Set lighting distribution board fitted for lighting in the officer and platform decks. Distribution boards mentioned above are fed from the No. 1 main switchboard.

5 Wheelhouse Distribution Board & control console

5.1 Distribution Board

The wheelhouse Distribution Board shall be sheet steel construction, floor mounting, and provided with the following circuits:

Moulded case circuit breakers (feeder circuit) Moulded case circuit breaker, which is provided with thermal over current trip

device and magnetic instantaneous trip device is to be arranged inside the wheelhouse Distribution Board for supply of the following consumers:

Normal lighting in the navigation deck and the weather deck (AC220V) 1 Floodlight in the weather deck (AC220V) Communication and navigation equipment (AC220V & DC24V) Radio equipments (AC220V & DC24V)

5.2 Navigation light panel, Signal light panel and Flashing light panel

The power supply shall be feed from the No. 1 main switchboard of AC 220V panel and 24 V charging and discharging board via an inverter. Two –way power supply with a automation change-over switch shall be provided.

5.3 Main & auxiliary engines control and alarm panel

The main engine control and alarm panel shall be including the main engine remote clutching and speed controller, main engine starting supply air control, main engine emergency stop push button with protection cover to prevent maloperation, audible and

Page 263: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

visual alarm for main engine emergency stop, main engine L.O. low pressure alarm/stop, cooling water high temperature alarm/stop, over speed stop alarm, gear box L.O low pressure alarm, generators L.O low pressure and cooling water high temperature alarm etc, also the push button for buzzer stop and lamp test.

The electric instrument shall be provided for engine: M/E revolution and propeller shaft revolution indicator, etc.

5.4 Steering gear control panel

This panel shall be include star and stop push buttons for oil pumps, indicating lamp, steering wheel, over load and single phase alarm for steering gear motors, power failure alarm, hydraulic oil tank low level alarm, filter blocking alarm, etc,

5.5 Emergency stop push buttonsEmergency stop push buttons for fans/oil pumps/air conditioner, and remote start/stop push button for fuel pumps.

5.6 Splitting hopper hydraulic control unit

Split hopper hydraulic control unit shall be provided on wheel house control desk.

5.7 Navigational Equipment

Global Positioning System, Radar, Echo sounder, VHF Radio Telephone, radar display, NAVTEX receiver, public address master, sound powered telephone, engine telegraph, fire alarm control panel, air whistle controller, switch panel of clear view screen, etc. Shall be located o wheel House desk.

5.8 General alarm system

Page 264: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

The general alarm system shall be fed from the AC220V of the wheelhouse control console and the DC24V of the charging and discharging board. The alarm signal shall be transferable to the air whistle controller. The general alarm system shall be capable of releasing emergency alarm via bell and whistle under the state of emergency.

6 Lighting System

6.1 Navigation Lights

Navigation light to be water tight and provided with double bulbs (AC220) / 65W each) as follows:

1 - Masthead light, foremast

1 – Masthead light, radar mast

1 – Stern light

1 – Port side light

1 – Starboard side light

6.2 Anchor Lights

Two (2) Sets of AC220 V 65W double layer anchor light shall be provided, one on the foremast and another on the stern mast, and shall be controlled from navigation lights control panel.

6.3 Not-Under-Command Light, Draft Light and Restricted Maneuvering Light

Following AC220V 60W single lamp shall be provided for not-under command (NUC) light, constrained draft light and restricted manoeuvring light.

Page 265: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

5 – Red lights: On radar mast

4 – Green lights On radar mast

1 – White light On radar mast

These lights shall be controlled on signal control panel on the W/H control console.

6.4 Morse Signal Light

One (1) set of AC220V 25W Morse signal light shall be provided as follows:

1 – Morse signal light on the radar mast

1 – Key on each bridge wing

6.5 Portable Daylight Signal Light

One (1) set of DC24V 60W portable daylight signal light of water-proof type with chargeable battery in carry case shall be provided and stored in the wheelhouse.

One (1) set of DC24V sockets shall be provided on each bridge wing, fed from the general charging and discharging board.

6.6 Signaling Search Lights

Two (2) sets of AC220V 1000W, incandescent type signaling search light shall be installed on compass deck.

6.7 Flood Lights

Page 266: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

Five (5) sets of AC220V 500W flood lights shall be provided on navigation deck, foremast and stern of platform deck, for operation on the main deck. Two (2) sets of DC24V 1000W flood light shall be provided on aft of platform deck, fed from the general charging and discharging board.

6.8 Rounding Light

Two (2) Sets of AC220V 60W rounding lights (one red light and another green light) shall be provided on compass deck.

Each light shall be controlled from the flashing light control panel.

6.9 Control Panels

6.9.1 Navigation Light Control Panel

One (1) set of navigation lights control panel with mimic diagram shall be installed on the wheelhouse console and shall have a control switch for each navigation light. The warning of lamp or circuit failure shall be provided.

The navigation lights control panels shall be fed from the AC220V main supply and the DC24V charging and discharging board via one of inverter with a chang-over switch.

6.9.2 Signal Lights Control Panel .

One (1) set of signal lights control panel with mimic diagram for control all signal lights shall be installed beside the navigation light control panel. It shall be fed from the AC220V of the wheelhouse control console and the DC24V charging and discharging board via one of inverter.

Page 267: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

6.9.3 Flashing Lights Control Panel

One (1) set of Flashing Light Control Panel shall be installed near by the signal lights control panel. It shall be fed from signal lights control panel.

6.10 General Lighting

6.10.1 Systems

The generally illumination system shall be consisted as follows:

- AC220V Normal Lighting System

The normal lighting shall be fed from the No.1 main switchboard via a normal lighting distribution panel.

- DC24V Emergency Lighting System

The emergency lighting shall be fed from the general charging and discharging board.

6.10.2 Switches and Sockets

Flush mounting type plastic switches and sockets are to be used in the accommodation and watertight Nylon switches and sockets are to be introduced in engine room and other machinery and W.T. compartments, stores etc. AC220V/AC24V W.T. receptacle to be provided in engine room, wheelhouse, steering gear room, for AC220V maintenance tool and DC24V portable lamp. An adequate number of AC220V sockets to be provided in accommodation, wheelhouse, galley, mess room, for portable equipment.

Page 268: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

7. Navigation Equipment

7.1 Magnetic Compass

One (1) set of standard magnetic compass shall be installed on the top of the wheelhouse. One (1) set of steering magnetic compass shall be installed on the wheelhouse control console. DC24V for compass illumination shall be fed from distribution panel built in wheelhouse control console.

7.2 Electronic Compass

One (1) set of Electronic Compass shall be provided. The electronic compass can be interfaced with Radar and AIS, switch need ship’s own azimuth can be feed by electronic compass. The equipment shall be fed from the DC24V feeder of the wheelhouse control console distribution panel.

7.3 Echo Sounder

One (1) set of each sounder shall be installed as follows:

1 – Recorder with recording paper.

1 – Transducer

The equipment shall be fed from the AC220V and DC24V feeders inside the wheelhouse control console.

7.4 Speed Log

Page 269: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

One (1) set of magnetic speed log shall be installed as follows:

1 – Main unit with speed and distance display in chart area

1 – Transducer with shutoff valve in echo sounder and speed log trunk

The system shall be fed from the AC220V feeder of the wheelhouse control console.

7.5 Radar Plant

One (1) set of X band radar with auto plotter, 10 display, antenna, interconnecting cables and accessories shall be provided. The equipment shall be fed from the DC24V feeder inside the wheelhouse control console.

7.6 GPS Navigator

One (1) set of GPS navigator shall be provided. The navigator shall be interfaced with the radar plant, VHF radio telephone and other relevant equipment. The navigator shall be fed from the DC24V feeder inside the wheelhouse control console.

7.7 Whistle

One (1) set sound pressure level 130db and frequency 315Hz of electric air whistle shall be fitted on the compass deck, one set fog light shall be fitted on compass deck, One set fog light shall be fitted on wheel house control console. (1) set of push button shall be fitted at port and starboard bridge wings. The equipment shall be fed from the AC 220V feeder inside the wheelhouse control console.

7.8 Anemometer and anemoscope

Page 270: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

One (1) set of wind speed and direction indicator shall be installed in wheelhouse. Transmitter shall be installed on the radar mast. The equipment shall be fed from the AC220V feeder inside the wheelhouse control console.

7.9 Clear View Screen

Two (2) sets clear with Ф=350mm of clear view screen with heaters to be fitted for wheelhouse front windows. Two (2) set switch panel shall be installed on wheelhouse control console. The equipment shall fed from the AC220V feeder inside the wheelhouse control console.

7.10 Rudder Angle Indicator

One (1) set Rudder angle transmitter shall be installed in steering ger room

One (1) set Rudder angle indicator shall be installed on steering gear control panel on the wheelhouse control console. The equipment shall be fed from the DC24V feeder inside the wheelhouse control console.

7.11 Automatic Identification System (AIS)

One (1) set automatic identification system (AIS) shall be provided. The transponder unit shall be interfaced with the radar plant, electronic compass, GPS navigator, and shall be installed on wheelhouse control console. Antenna shall be installed on compass deck The equipment shall be fed from the DC24V feeder of the wheelhouse control console distribution panel.

8. Internal Communication

Page 271: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

8.1 Sound Power Telephone

Three (3) sets of sound power telephone shall be provided as follows:

Wheelhouse control console – Main engine side of port engine room.

Wheelhouse control console – Main engine side of stbd engine room.

Wheelhouse control console – Emergency control position in steering gear room.

The telephone on Wheelhouse control console shall be flush mounted type.

The telephone at main engine side and in the steering gear room shall be headset type.

The equipment shall be fed from the DC24V feeder inside the wheelhouse control panel.

8.2 Engine Telegraph

One (1) set of engine telegraph for both main engine shall be provided, and it is to consist of

1. Transmitter with receiver, buzzer in the wheelhouse2. Receiver at main engine side

The equipment shall be fed from the AC220V and DC24V feeder inside the wheelhouse control console.

8.3 Revolution Indicator for Main Engines

Two (2) sets of revolution indicator for main engines shall be provided by main engine maker as follows:

Page 272: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

- Revolution transmitter on the main engine- Flush mounting type revolution indicators with dimmer on the wheelhouse

control console.

8.4 Revolution Indicator for Stern Shafts

Two (2) sets of revolution pickup system for propulsion shaft shall be provided as follows:

- Signal unit and revolution transmitter on the each stern shaft.- Flush mounted type revolution indicator for each shaft with dimmer on the wheel

house control console.

The equipment shall be fed from the AC220V feeder inside the wheelhouse control console.

8.5 Public Address System

Public address system rated output to be 50W. Flush mounting type main unit shall be installed on the wheelhouse control console. Two (2) output circuits shall be provided for speakers. The systems shall be fed by AC220V from feeder inside wheelhouse control console and DC24V from the radio charging and discharging board.

8.6 TV Anteena System

One (1) set of omni-directional type antenna for TV shall be provided. The equipment shall be fed from the AC220V feeder inside the wheelhouse control console.

8.7 Alarm Systems

8.7.1 Fire Detection, Alarm System

Page 273: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

The fire detection systems covering machinery spaces and passage areas in the accommodation including stairways shall be installed. The control panel shall be located on the wheelhouse control console. One set the fire alarm repeater shall be installed in the captain’s room. The system shall consist of combinations of detectors and manually operated call points. Detectors shall be operated by heat, smoke depending on the regulation. Audible fire alarm signal shall be given on the ship’s “general emergency alarm system “as a continuous signal. The system shall be fed from the No. 1 main switchboard of AC220V panel and charging and discharging board of DC24V

8.7.2 General Alarm System

An general alarm system consisting of bells and buzzer as appropriate, control panel shall be provided. The control panel shall be located on the wheelhouse control console. The system shall be used for sounding fire and general emergency alarm signal. The 20cm bells should be arranged engine room, steering gear room, gallery and air conditioner room. The buzzer should be arrange in cabin, messes, CO2 room, toilet & shower and in inner passage of accommodation. The general alarm system may be manually operated, spring loaded call points installed at the control panel. The general alarm system shall be interfaced with the air whistle, the air whistle cam be give out alarm sounding while the general emergency alarm initiated. The system shall be fed from the No. 1 main switchboard of AC 220 V panel and the general charging and discharging board.

8.7.3 CO2 Release alarm system Alarm system for the engine room CO2 release shall be provided. The system shall be fed from the general charging and discharging board. The system can be give out audible and visual alarm in engine room via electronic alarm unit 20 seconds before CO2 release, which is activated by switch of the release control box. Ventilating fans oil pumps in the E/R shall be stopped in case of CO2 release. One (1) Alarm panel shall be located on the wheelhouse control console. Alarm panel shall be give out audible and visual alarm in case of electric power failure and CO2 leakage.

Page 274: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

9. Radio communication Equipment

The radio system shall comply with GMDSS requirements for sea area AI and be based on the duplication of equipment and shore based maintenance for ensuring availability.

9.1 VHF Radio Telephone

One (1) VHF radio telephone with DSC controller and watch receiver for ch.70. The equipment shall be fed from the AC220V radio supply system and DC24V.

9.2 NAVTEX ReceiverOne (1) set of NAVTEX receiver for 518 KHz with printer. The equipment shall be fed from the DC24V radio supply system.

9.3 Satellite E.P.I.R.B. and 9GHz Radar transponder etc.

One (1) satellite E.P.I.R.B. and two (2) 9GHz radar transponder shall be provided. Six (6) sets portable two way VHF radio with rechargeable batteries shall be provided.

10. Electric Cable and installation

10.1 Cable Application

All cables shall be fire retardant and complied with rules. The cables shall be of EPR (ethylene propylene rubber) insulated PCP type sheathed and copper wire or steel wire braided cables. In addition, if the cable shall be located in wet space or exposed to the weather, PVC cover shall be applied. Ethylene propylene rubber insulated PCP sheathed and copper wire braided cables shall be used for in the radio system to reduce the interference disturbance. For portable appliances, PCP sheathed flexible cable shall be used. Fire resistant cable and complied with rules will be used in

Page 275: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

necessary circuit according to requirement of the Rule. (e.g. general Alarm System, Fire Detection System, Temporary Emergency Lighting System, etc.)

10.2 Cable Installation

Cable shall be located so as to avoid spaces where excessive heat, water condensation or harmful vapour may present. Cable on weather deck, under engine room floor shall be drawn in galvanized pipes or flexible conduit, Cable exposed to mechanical damage shall be protected by suitable means. The fire resistant compounds to be used for the fire resistant bulkheads, deck in order to prevent air circulation in case of fire. Where cables pass through water tight, gas-tight bulkhead or to exposed weather deck, the type approved cable penetration or compound to be used, Where cables penetrate through fire protection division, method approved by the Classification society shall be applied. Cables in the accommodation, where paneling is applied over the hull structures, shall be concealed but approachable as far as possible, the cables shall not be embedded in structural insulation. In general, the cables in the engine room, stores, etc. shall be exposed.

11. Spare Parts

All electrical spare parts shall be supplied according to rules applicable and the manufacturer’s standard.

Page 276: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

PART V – OUTFITTING SPECIFICATION

1. Life Saving Appliances

All life saving equipment shall be provided as per requirement of SOLAS.

- Two life raft for 15 persons each shall be located at port and starboard side of the wheelhouse.

- One G.R.P. man overboard boat (with removable 25 HP outboard motor) complete with electric davits on the aft ship. Sufficient lashing to be provided.

Page 277: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

- Lifejackets shall be provided for 15 persons with proper stowing lockers.

- Lifebuoys, line throwing apparatus, parachutes etc. shall be provided as per rules.

2. Firefighting Appliances

At least the following firefighting out fit or approved make and type to be provided and stored / placed in appropriate stowage.

- One breathing apparatus - Two safety lamps - One lifeline - Two fire axes- Three fire hoses in teakwood or GRP box on main deck and accommodation,

length 20m, 21/2 “ diameter - Two fire hoses on reels, one in each engine room, length 15m, 21/2 “ diameter - Portable extinguishers as required under rule- One safety helmet - One fire resistant suit

3. Alarm Installations

3.1 General Alarm System

A general alarm system powered by 24VDC shall be installed. The control switches with three positions (one-off with spring return to off) to be installed in the wheelhouse. Red coloured bells to be placed in the accommodation).An audible and visual alarm to be provided in each engine room.

3.2 CO2 Alarm

Page 278: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

The CO2 alarm systems in the engine rooms have to be actioned at opening of the concerning door for control of the CO2 system. An audible and visible alarm in the engine room. The Ventilation has to be stopped at activating of the gas release system.

3.3 Engine Room Alarms

This alarm installation approved make by Engineer, according to the closed circuit principle with as much as possible plug-in type solid state units built into a panel in each engine room. The installation to be split-up into many systems, each monitoring maximal 8 points, each with a protection and power available light. Alarms of non-running engines have to be suppressed. An alarm situation shall actuate an audible and a visual alarm in each engine room. After pressing as accept button, the flashing light will change into a steady light and the audible signal will stop. Further more, the panels to be equipped with a lamp test arrangement.

A Panel to be installed in each engine room with the alarm units for equipment installed in the same engine room. However, the alarms have also to be signalized in the other engine room. Acceptance of the alarm in both engine rooms. A number of alarm will be displayed in the wheelhouse too. This can be a resulting alarm of a group of alarm or a repeat of a single alarm.

At least the following alarms have to be installed in the engine rooms for each propulsion diesel engine:

a) Lub Oil low pressure b) Turbo charger oil pressure c) Cooling water high temperature d) Lub Oil filter e) H.P fuel leakagef) Lub Oil low pressure stopg) Cooling water high temperature stop h) Over speed stop i) Alarm as required by the manufacturer.

Page 279: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

For each propulsion Gearbox:

a) Lub Oil pressure b) Lub Oil temperature c) Lub Oil filter d) Alarms as required by the manufacturer.

For each Aux. Diesel Engine:

a) Lub Oil low pressure b) Lub Oil level

c) Cooling Water high temperatured) Cooling water level e) H.P fuel leakagef) Lub Oil low pressure stop g) Cooling water high temperature stop h) Over speed stop i) Alarms as required by the manufacturer

For the hydraulic installation:

a) Hydraulic pressure splitting system LP and HPb) Hydraulic Oil filtersc) Too low pressure hydraulic cylindersd) Low level hydraulic tank

For miscellaneous installations:

a) Fuel oil day tanks low and high levelb) Overflow fuel oil tanks high levelc) Stern tubes header tanks leveld) Steering gearse) Dirty Oil tanks level f) Sewage tank level g) Sludge tanks leverh) Battery chargeri) Fuel Oil purifierj) Alternators temperature k) Bilge levels l) Low pressure CO2m) 3 spare alarms, fully equipped

Further more resulting alarm has to be installed in the wheelhouse of:

Page 280: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

a) Each propulsion

b) Bilge level in several parts

c) The remaining alarms

d) Steering gears as required by the Classification

3.4 Splitting Alarm

Before splitting of the hopper barge an audible alarm has to be given on deck, as audible and visual alarm in the engine rooms and in the steering gear rooms. The pulsating audible alarm will start before the split movement will be activated (adjustable time). The time lapse between the automatic start of the audible alarm and the split movement to be easily adjustable between two to five minutes.

3.4 Alarm Column

To install in each engine room signal light column with a signal light for:

- Telephone- General alarm- Engine room alarm- Splitting

The signal lights are to be provided with pictographs indication the type of alarm. For the splitting alarm all the alarm signal lights will be bright. Furthermore, one siren and orange rotating light will be for all the alarms.

4. Anchor Windlass

Page 281: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

Two horizontal electro hydraulic unilateral anchor windlasses with (1) gypsy wheel, two (2) warping heads, shall be provided on fore raised quarter – deck of both halves. The gypsy wheel and warping heads with a clutch and a manual stopper, to be operated solely when the gypsy wheel comes away the warping heads. The anchor windlass to have side controlling.

5. Capstan

An electric capstan shall be installed on aft raised quarter-deck of left half and mooring fiber ropes to be stored at rope reel. Capstan to be of a clutch and a manual stopper.

6. Steering gears

Electro-hydraulic reciprocating oil cylinder with double cylinders and double pistons, rived by one set of electro-hydraulic system, one oil tank and two sets of pump groups, to be installed in one half body and each system shall include one axial piston pump and one electro motor, pipes, valves etc.

Steering gears to be derived by either pump or both pump at one time, Hand wheel steering shall be from the wheel house, and the manual lash-up steering to be installed in steering gear compartment.

Steering gear turn from 35 degrees on either side to 30 degrees on the other side in 28/20 seconds when sailing at max. draft and max. speed.

Rudder angle indicators to be installed in the wheel house and sensors in the steering gear compartment.

Page 282: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

Stopping rudder limit switch and mechanical rudder stopper to be installed in the steering gear compartment. Steering gear to meet the requirement of Class rules and international convention of IMO.

7. Accommodation

7.1 General

The material used in accommodation to meet requirement of rules and convention for dry cargo ship, IC method of SOLAS to use of th fire division and joinery structure, and noncombustible materials to be used at paneling, ceilings of living space, service space and control stations.

Day accommodation arrangement shall be generally as showed on General Arrangement Plan:

7.1.1 ComplementOfficer 2 Nos

Crews 12 Nos

7.1.2 Public spaces

Officer’s mess, TV room

Crews mess, TV room

Office

Galley (Electrical fully equipped)

Dry Provision Store

Officers Toilet (Western WC, showers, Wash basin)

Crews Toilet (Asian WCs, Showers, Wash Basin)

Page 283: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

7.1.3 Navigation space Wheel house (including chart space)

7.1.4 Other spaces Fire space: CO2room

Working space: AC room, battery charge room

7.2 Insulation

7.2.1 Heat insulation Heat insulation to be provided on all exposed bulkheads and ceiling finished with paneling and ceiling.

7.2.2 Sound insulation

Sound insulation to be provided in living space to obtain required noise level.

7.3 Curtains

Curtains and blinds to be provided on all windows in accommodation.

7.4 Galley Equipment

1- Gallery range (with 4-hot plates cooking range)

1- Electric pan (220V, 2000W)

1- Electric rice cooker

1-Stainless steel Sink

1- Stainless steel Dresser

1- Stainless steel working table

Page 284: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

1-Cup board

1-Chopping block &rack

1-Slop pail

1- Racks for crockery and cutlery

1- Refrigerator for abt.283 ltr. With 2 doors

1-Icebox (15 Ft3)

1-Microwave oven (with barbecuing function)

1-Electric toaster

1-Water boiler

2- Electric cooker (for 15P)

1-Ice Maker

1- Extractor to smoke with two fans and filters Equipping bowl, dish, basin for 15P Crockery, Cutlery, tumblers, Jugs, Serving dishes and spoons, cups and saucers, tea milk and sugar pots, sufficient for 15 persons shall be provide

7.5 Officer’s mess room

1- 22inch color TV set

1- Refrigerator (75 L)

1- Water boiler

7.6 Crew’s mess room

1-22 inch color TV set

1-Refrigerator (75L)

1- Water boiler

1- Water fountain with filtrating

Page 285: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

7.7 Stores & Workshops

Following store rooms/ lockers for onboard stocking:

a. Bos’n seamanship and replenishment gear store.

b. Paint/ Chemical store.

c. Mechanical Engineering store.

d. General store for any additional requirement of stowage.

8. Painting and Cathodic protection

8.1 Surface, preparation

8.1.1Generally steel plates and sections of thickness and above to be shot blast cleaned on both sides to Sa2.5 (Swedish standard SIS) for checking and judging steel surface preparation. Grit or sand blasting to Sa 2.5 or pitching may be applied instead of shot blasting when shot blasting is considered impractical.

8.1.2 generally just after primary surface preparation one coat of 15µm shop primer to be applied on the steel plate’s/section’s surface for prevent steel corrosion at period in construction of the ship. Where priming film to be destroy by cutting and welding to be grited to St2 ~ St3 with hand tools (including manual blasting). Usually where shop primer takes off by machine and cleaning not to be touch up except after surface preparation not to be painted immediately as construction schedule of shipyard.

8.1.3 Before over coating steel surfaces to be cleaned rust, dust, slop ol and moisture etc. with sand disc or wire brush according to shipyard practice except prescriptive steel surface that to be shot last cleaned.

Page 286: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

8.1.4 About secondary surface preparation, grade of treatment, manner, requirement of humidity and temperature, the thickness of dry film to be in accordance with paint maker’s recommendation.

8.2 Painting Following be complied for the protection of the barge’s hull (topside/boottop/bottom):

a) Paint scheme of International Paints (IP) to be applied throughout the barge confirming to latest War Paints issue.

b) Underwater paint scheme as per Lloyd’s / BV Rules or Equivalent International Paint scheme acceptable to KPT, having a minimum of 5 years satisfactory performance.

c) 5 years warranty for entire paint system.

e) The thickness of dry film to be measured after a coat to guarantee enough thickness. The dry film thickness specified in the painting schedule to be attained on at least 85% of the measuring points.

8.3 Cathodic Protection

a) Sacrificial anodes (Zinc alloy anodes) to provide protection against galvanic corrosion on underwater hull, sea chests and rudders etc with anode life of minimum of 24 months.

b) Zinc alloy anodes to be installed in ballast tanks and hydraulic oil cylinder compartments with 2 year life.

Page 287: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

9. Flags and Books10.

All charts and nautical books, national flags of PAKISTAN to be provided by owner with pigeon hole locker for flags.

Following items to be provided by Builder:

1 – National flag case

1 – International signal flag (middle type)

1 – Disembogue flag

1 – Ship’s name flag (middle type)

1 – Quarantine flag (middle type)

1 – Hand flag

Necessary flag ropes, small tackles, etc. to be fitted.

9.1 Distress call, etc.

12 – Rocket parachute4 – Orange colour smocking signal5– Black ball shape

1- Black cylindrical shape

1-Black diamond shape

9.2 General

Spares and tools to be provided according to maker’s standard except specified other parts.

Page 288: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

9.3 Spares

Spares and tools for windlass, capstan, steering gear, working boat, davit for working boat etc. to be provided according to the rule and maker’s standard.

10. Other Requirements / Provision

1. Guarantee engineer and guarantee master shall have the knowledge of English for speaking, reading and writing.

2. Soft and hard copies of as built drawings, maintenance and operational and spare parts manuals, instruction manuals and a separate CD / DVD for complete description of the boats backed up with background commentary shall be provided.

3. Anti ship paint at main deck shall be provided specially at all slopes.

4. Lights in bunkers shall be provided for proper illumination.

5. Provision and facilities for prompt repairs and remedy of warranty defects, renewal of parts, required if any, shall be provided during the one year guarantee period.

6. Fuel consumption for main and all auxiliary engines shall be indicated.

Page 289: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

7. Navigation and communication system shall include radar, alarm, auto pilot, gyro repeater, echo sounder, Doppler log, GPS, DGPS, VHF, Radio system, Navetax, Gyro compass, signal light, talk back system, loud hailer, light indicator, magnetic compass, search light, search and rescue transponder, whistle, bell, speed log etc. as applicable.

8. Letters for the names of the Hopper Barges and Port of Registry shall be welded on aft and name of Barge in English and Urdu on bow on Stbd. and Port Side. Name box of Hopper Barge shall be provided on top of wheelhouse to be illuminated during night for identification.

9. All pipes shall be with colours code marking and arrows to indicate liquid being carried and direction of flow.

10. Prominent name plates shall be provided with engraved letters shall be provided on all equipment all over the barges. Name Plates in engine room and other spaces other than accommodation shall be metallic.

11. To provide office with communication facilities and transport (to and from yard or places of work) to the supervision engineers.

12. Provision of visits by Purchaser’s representative at the events of keel laying, launching, tests and trials and completion, also at intermediate intervals for progress review meetings, as per contract. All costs of visit, expenses for traveling, boarding, lodging etc. shall be for the account of Supplier.

13. Welding plant / Gas cutting equipment and a portable fire fighting pump to be provided on board on each barge.

14. Digital flow at the out let of the fuel oil service line for accurate monitoring of fuel oil consumptions shall be provided.

15. For all sea water pipe line / connections, stainless steel will be preferred material.

16. Hydraulic pumps to be motor driven with one standby motor.

Page 290: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

17. 02 in Nos. stand by sea water pump for main engine and cooling system shall be provided.

Page 291: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

PART -6(a) GENERAL ARRANGEMENT PLAN

Page 292: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in
Page 293: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

PART VI – (b) TEST AND TRIALS

1. Model Test of the Split Hopper Barges shall be carried out at renowned Model Test Station to prove the performance of Split Hopper Barges according to requirements of the design to meet the Employer’s requirements as laid down in Technical Specifications. Builders to inform Employer at test 30 days in advance about the date and place of the test so that Engineer can witness the test and check data and calculations.

2. Of those materials for which no Classification certificate is required, the Engineer shall have the authority to require tensile, bend and/or others tests analysis for plates, sections and other material as the case may be, in such number as may be considered necessary to represent fairly the lot of articles and materials to be used in construction of Split Hopper Barges.

3. During construction of hull each panel. Space and compartment shall be presented for inspection of Engineer and Class surveyor to verify that all work is done according to drawings and best shipbuilding practice.

4. Welds will be tested by taking x-ray photographs and, if considered necessary by the Engineer and/or by the Class, will be judged by taking other tests, e.g magnetic particles or dye penetration tests etc.

5. On completion of construction of the Split Hopper Barges, and before application of paints, all fuel oil tanks, fresh water tank, etc. shall be hydrostatically tested with fresh water and inspected according to Classification Society’s requirements.

Prior to testing, all tanks shall be thoroughly cleaned and washed, and all slag, grit and debris shall be remove. Before painting of tanks, approval of such tests and cleaning shall be obtained from the Engineer.

6. At least four weeks before the commencement of the test and trials, the Yard will submit for approval to the Engineer a complete program, time schedule

Page 294: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

and specimen protocols of tests and trials which will be attended by the Engineer and representatives of the Employer.

7. All machinery, equipment, articles, materials, etc. where individually required, shall be tested. After completion of the tests or workshop trials, if required, the Engineer and/or the Class may ask the removal of some parts for inspection and subsequent refitting which shall be complied with.

8. Well before the Endurance & Sea Trial trips are carried out, the complete machinery installations, the auxiliaries, the piping systems, the electric installation, including parallel operation of generators, the deck machinery the ventilation systems, the nautical instruments and all other equipment / instruments shall be tested by the Yard. These Yard tests shall be of adequate duration to ascertain good working and durability of machinery /equipment under test and to prove satisfactory working of the complete installation or system as a whole, to the entire satisfaction of the Engineer or the Class where so required. If under the tests and trials any part of the system or machinery, equipment etc. fails to fulfill adequately the specified requirements, the faulty part shall be altered, renewed or replaced and the test repeated at the Builder’s expense till such time that the Engineer and / or Class is satisfied. Complete protocol of these tests shall be prepared and signed by Builders, Class and Engineer. Six copies of test protocols shall be supplied with the delivery documents.

9. The main test and trials shall comprise basically of the following.

a) Inclining test of one of the Split Hopper Barges fully equipped and completed. Final calculations of stability for which this test forms the base, shall be submitted to the classification Society for approval immediately after carrying out the inclining test. Approved copy Stability Book shall be made available to the Engineer as soon as possible. Six copies of approved/stamped Stability Books to be handed over with other documents prior to delivery of Split Hopper Barges.

b) Dock moored trials with propulsion installation. These trials are to be maintained during at least 8 hours at a stretch.

c) Torsional vibration measurements on the shaft lines of the propulsion installation, including absorbed power shall be carried out during speed trials.

Page 295: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

d) Anchor trials during Sea Acceptance trials shall be carried out.

e) Speed trials on a measured mile to be carried out.

f) Brake tests to determine the time and distance necessary to stop & reverse the Split Hopper Barges, when sailing at full speed ahead.

g) Turning circle trials, both PS and SB. Turning circles to be measured and time to be recorded.

h) Endurance test for at least six hours, sailing full speed ahead with full output of the engines. Fuel consumption to be measured during these trails.

i) Splitting Barge test shall be carried out twice by filing the hopper to full capacity with dredged material of S.G as near to 1.6 as possible and discharging it by splitting the barge. Times for filling. Overflowing excess water and emptying the hopper to be recorded. This test is to be repeated twice.

10. All instruments required for the tests, such as torsion meters, tachometers and ammeter duly calibrated, shall be provided by the Builder. Results are to be measure and recorded. Extrapolation or Estimates will not be acceptable.

The Engineer shall have the right to decide whether the proposed test sites and water depths are suitable to carry out these trials.

Tests and trials which are considered unsatisfactory are to be repeated at the Builder’s expense until they are successfully carried out to the satisfaction of the Engineer.

11. The Builder has to report all date / measurements and results of the tests and trials to the Engineer and get his approval in six folds before delivery of the Split Hopper Barges to the owner at Karachi port.

Page 296: KARACHIkpt.gov.pk/.../156628_timage_457535203875.docx  · Web viewPainting and Cathodic protection . 8.1 Surface, preparation . 8.2 Painting . ... consent or approval shall be in

12. After all the trials have been carried out satisfactorily and test results documents submitted, the Split Hopper Barges shall be neatly finished, dried, Cleaned, oiled, etc. All paint and varnish is to be brought in a fairly good conditions. All defects and failing found shall be repaired and all spare parts and inventories shall be put on board so that the Split Hopper Barges are ready for transport and confirmatory trials for final delivery to the Owner at Karachi Port.

13. After arrival in Karachi confirmatory trials in respect of items. (d), (e) , (f), (g), (i), mentioned above, and a restricted endurance test (h) for at least 3 hours will be carried out prior to final acceptance at Karachi Port.

All tests and trials, including the repeated tests and trials, if any, shall be carried out by the Builder and be its full responsibility to carry out these tests to the full satisfaction of Engineer / Class. The builder shall also bear all costs inducing costs for the crew, fuel oil, lubricating oil, etc.