HOLIDAY COMPLEX construction period11/10/2005-30/11/2006Kavarna townKavarna municipality
AC-142-05
project team: АСА
design: arch. mariana kostova
construction: company BUILDEX
client: IC
plot area 1346м2
gross area 4777м2
70 apartments, 20 garages
project budget 2.2 Mio Euro
06
![Page 2: Kavarna 1-05-en-hd](https://reader030.vdocument.in/reader030/viewer/2022032616/55a394ef1a28ab105c8b46e1/html5/thumbnails/2.jpg)
SUPPORT WALLSconstruction period11/10/2005-30/12/2005kavarna townкavarna мunicipality
AC-142-05
project: team: ACA
project manager: george vitanov
civil works: BUILDEX
client: IC
gross area 346м2
volume 120 м3
support walls
project budget: 100 000 EURO