  • 8/3/2019 KDWfP_contractors Event_Woodfuel WIG Grant

    1/14

    Wood-fuel WIG -

    delivering in the South East

    Mike FurnessWood Fuel WIG Project Manager

  • 8/3/2019 KDWfP_contractors Event_Woodfuel WIG Grant

    2/14

    About ngage We are a not-for-profit organisation that

    has been providing business support

    since 2001.

    During 2010/11 we delivered 777k ofgrants in SE (inc. 476k for farm & rural

    businesses).

    Sustainable development is our main

    focus. We are currently involved in partnerships

    in 10 EU countries.

  • 8/3/2019 KDWfP_contractors Event_Woodfuel WIG Grant

    3/14

    Our role with the WF-WIG

    The facilitation and administration of WF-WIG in:

    South East Region

    South West Region Cumbria

    Our involvement starts with receipt of your application and

    ends with appraisal of your grant claim.

    We will support you with the process BUT we arentFCWoodland Officers.

  • 8/3/2019 KDWfP_contractors Event_Woodfuel WIG Grant

    4/14

    Our delivery model...

  • 8/3/2019 KDWfP_contractors Event_Woodfuel WIG Grant

    5/14

    What you can expect from us...

    Pre-application eligibility advice

    Processing of applications in accordance with the

    Citizens Charter(11 weeks from receipt of a properly completedapplication to offer of grant [where appropriate])

    At least one pre-contract visit

    A positive, responsive service (we want you to get

    the grant!)

    A local contact when you need it

  • 8/3/2019 KDWfP_contractors Event_Woodfuel WIG Grant

    6/14

    What we expect from you...

    Early contact to check eligibility

    Fully completed applications

    Accurate mapping of your plans Marking up on site

    Photographs with applications

    Flexible access to your woods

    Delivery of what you applied for

    Prompt advice of any problems

  • 8/3/2019 KDWfP_contractors Event_Woodfuel WIG Grant

    7/14

    The Woodfuel WIG2 in 1

    Total pot of 3 million in SE

    Short period for applicationsto

    October 2013 Timber fund and Roads fund

    Axis 1 funding imposes conditions:

    Must have three quotes Actual costs (Receipted invoices)

    Grant rate of 60%

    Grant amountde minimis

  • 8/3/2019 KDWfP_contractors Event_Woodfuel WIG Grant

    8/14

    What will WF-WIG support?

    The overall aim is to support the sustainable

    production of wood-fuel & other timber products

    Timber fundprep. for harvesting: Woodland inventory work

    Managing harvesting contracts

    Roads fundaccess infrastructure Haulage roads; forwarder roads/tracks

    Stacking/loading/turning areas

    Bellmouth access to highways

  • 8/3/2019 KDWfP_contractors Event_Woodfuel WIG Grant

    9/14

    Eligibility issues...

    Some common to both: RLR

    Approved up to date management plan (inc. Table10A)

    De minimis

    Necessary permissions

    Must result in timber harvesting

    Some is specific to the fund...

  • 8/3/2019 KDWfP_contractors Event_Woodfuel WIG Grant

    10/14

    Eligibility forTimber fund...

    Woodland/compartment under-managed

    (i.e. has missed 2 thinnings)

    Payment is based on standard costs

    Supports preparation of wood for sale and

    managing subsequent harvesting.

  • 8/3/2019 KDWfP_contractors Event_Woodfuel WIG Grant

    11/14

    Eligibility forRoads fund...

    Management plan must support the need for

    proposed infrastructure

    Scheme must last 20+ years (FC roading guidelines- ON25)

    Based on 3 quotes

    Grant must be matched with timber

    harvested (1 tonne per 50 grant)

    Grant paid on actualcosts

  • 8/3/2019 KDWfP_contractors Event_Woodfuel WIG Grant

    12/14

    How to apply... Call to discuss any eligibility issues

    Download the forms and email everything to meor post

    them:

    EWGS1

    Mastermap

    EWGS5

    WIG calculator Up to date management plan

    Technical drawings (for Road fund)

    Get quotes once weve agreed the outline scheme

  • 8/3/2019 KDWfP_contractors Event_Woodfuel WIG Grant

    13/14

    Myths and misconceptions...

    Doesnt need to be under-managed for Roads

    grants

    There doesnt have to be an increase in timber

    outputcan just be more efficient.

    Agents supervision and engineers design fees

    can be included

    Dont have to take cheapest quote

    Value of timber arising is not taken into

    account.

  • 8/3/2019 KDWfP_contractors Event_Woodfuel WIG Grant

    14/14

    Over to you for any questions...