Keeping San Diego MovingSANDAG Capital Program Update
Bill Prey, P.E., Principal Engineer, SANDAG
Ramon Ruelas, PE, Principal Construction Engineer, SANDAG
SANDAG Capital Program Update
I-5 North Coast Corridor Program
LOSSAN Coastal Rail Corridor
Light Rail Projects -
Trolley Renewal Program
Mid-Coast Corridor Trolley Project
Construction Delivery Methods
Doing Business with SANDAG
2
Keeping San Diego MovingSANDAG Capital Program Update
I-5 North Coast Corridor Program
North Coast Corridor Program
A $6.5 billion integrated program that includes:• Highway, bike, and
pedestrian improvements• Coastal rail and transit
improvements• Environmental protections
and enhancements
4
5
NCC Public Works Plan
Keeping San Diego MovingSANDAG Capital Program Update
LOSSAN Coastal Rail Corridor
LOSSAN Corridor in San Diego
• 60 miles in SD County• 50 percent single track• Six coastal lagoons• Two right-of-way owners:
NCTD and MTS• NCTD Maintains and
Manages Operations• Service by: COASTER,
Amtrak, Metrolink, and BNSF Railway
7
Goal: Double Tracking the Corridor
8
LOSSAN Corridor - Current Projects
• 23 projects currently in the program
• 15 funded through construction
• $467 million in funding
• $915 million estimate cost at completion
• Schedule currently funded through 2017
9
San Diego
Carlsbad
Oceanside
Encinitas
Solana BeachDel Mar
Camp PendletonMarine Corps
Base
78
S13
5
8
5
LOSSAN Corridor Schedule
10
Projects in Construction
11
Projects In Construction
12
Santa Margarita River Bridge and Double Track
$41 million - 0.8 miles
Estimated Completion April 2014
Sorrento to Miramar Double Track Phase 1
$44 million – 1.4 miles
Estimated Completion January 2014
Tecolote/Washington Street Crossovers
$11 million – universal and single crossovers
Estimated Completion December 2013
Sorrento to Miramar 1
Tecolote Crossover Washington Crossover
Santa Margarita River Bridge
LOSSAN Corridor Projects in Design
13
• Six of 14 projects fully funded through construction
San Onofre to Pulgas Double Track$37.6 m - 6 miles
Oceanside Transit Center$19.5 m - platform and passing track
Sorrento Valley Double Track$33.7 m – 1 mile
Los Peñasquitos Lagoon Bridges$22.2 m – 3 bridges
14
Projects Near Construction
San Onofre Double Track Oceanside Transit Center
Sorrento Valley Double Track Los Peñasquitos Bridges
Projects in Design
15
Carlsbad Village Double Track1 mile, $6 M funded to date for engineering
Batiquitos Lagoon Double Track2.7 miles, $ 3 M to date for engineering
San Elijo Lagoon Double Track1.5 mile, $76.7 million through construction
San Dieguito Double Track and Platform1 mile, $9.5 M funded to date for engineering
Batiquitos Double Track
San Elijo Double Track San Dieguito Double Track
Carlsbad Village Double Track
Station Improvements
16
Moving Trains Through the Stations
Oceanside Transit Center $19.5 M
Poinsettia Station $13 M
Sorrento Valley Station $37.7 M
Del Mar Fairgrounds Platform $9.5 M
Oceanside Transit Center
Sorrento Valley Station Del Mar Fairgrounds Platform
Poinsettia Station
Keeping San Diego MovingSANDAG Capital Program Update
Light Rail Projects
Trolley Renewal Project
18
Mid-Coast Trolley Project
SANDAG TransNet Early Action Project
Extends MTS Trolley Blue Line from Santa Fe Depot through UCSD to UTC
Project features: 11 miles of LRT 4 miles aerial 9 stations
Project Budget: $1.7 billion
19
Mid-Coast Project Schedule
Mid-2013 Released Draft
SEIS/SEIR
Mid-2014 Approve Project/Record
of Decision
Mid-2015 Full Funding Grant
Agreement
Late 2015 Begin construction
Late 2018 Open for service20
Keeping San Diego MovingSANDAG Capital Program Update
Construction Delivery Methods
CM/GC Delivery Method
Enabling CM/GC legislation for SANDAG – January 2013
SANDAG awards two-phase contract:
• Phase 1 - QBS contract for pre-construction services input to finalize design
• Phase 2 - negotiated GMP contract to construct project
• If GMP cannot be negotiated, SANDAG competitively bids contract
22
CM/GC Delivery Method
May/June 2013 - SANDAG issued RFC to solicit industry comments on RFP template
SANDAG Board approved projects for CM/CG • Mid-Coast Trolley Project• Elvira to Morena Double Track• San Diego River Bridge
CM/GC RFP for approved projects anticipated late August/September 2013
23
Keeping San Diego MovingSANDAG Capital Program Update
Doing Business with SANDAGRamon Ruelas, PE, Principal Construction Engineer
SANDAG CM On-Call Procurement
25
Current CM Resources 4 CM contracts executed in Mid 2009 Initial term for each contract was 3 yrs Original value for each contract was $10 M Each contract contains four 1-year option
extensions Each contract contains options that could
increase contract value by add’l $15 M Options have increased total value of all
contracts to $81.25 M
SANDAG Funded Construction Activity
26
FY10 FY11 FY12 FY13 FY14 FY15 FY16 FY17 FY18 FY190
50
100
150
200
250
300
350
400
450
500
550
Construction Capital Expenditures by FY
TransNet Funded Caltrans Projects Mid-Coast Trolley Project Other SANDAG Construction Projects
Fiscal Year (FY)
Mill
ions
($)
Expenditures Forecasts
SANDAG CM On-Call Procurement
27
Future CM Resources Three to five on-call contracts to be awarded Estimated value of contracts - $15 to $30 M
each Mid-Coast Trolley CM contract - up to $120 M Contract duration - 3 years with four 1-year
options A&E Bench – resource for prime consultant
candidates to include SBE and DBE firms
SANDAG CM On-Call Procurement
Solicitation Process Board approval to issue RFQ – Late October
2013
RFQ advertisement: October/November 2013
SOQ’s due: Mid-January 2014
Interviews: March 2014
Negotiations: Commence Late March 2014
Board approval: Late June 2014
28
SANDAG CM On-Call Procurement
SANDAG Considering Solicitation Options: One RFQ adv.; separate SOQ submittals
General CM Services Mid-Coast Trolley Project CM Services
Two distinct RFQ adv.; separate SOQ submittals General CM Services Mid-Coast Trolley Project CM Services
Independent cost estimating for Mid-Coast Trolley Project Part of Mid-Coast CM Services Solicitation Separate RFQ solicitation
29
SANDAG CM On-Call Procurement
30
Construction Contract Quality Assurance/Safety Compliance
Field Inspection (RE, Assistant RE, and Field Inspectors
Transit Inspection Field Office Engineering (Change Orders, Daily Diaries, As-Builts, etc.)
Field Office Engineering (Change Orders, Daily Diaries, As-Builts, etc.)
Field Office Administration
Project Scheduling Contract Dispute Assistance and Claims Resolution
Materials Sampling and Testing Constructability Reviews
Potential Scope of CM Services
SANDAG CM On-Call Procurement
31
Storm Water Monitoring & Research Material/Product Plant and Source Inspection (Asphalt, Concrete, Manufacturing, etc.)
Surveying and Construction Staking Traffic Handling Support
Systems Start-up and Testing Records and File Auditing
Construction Management Software Acquisition, Training, Upgrades, and Support
Hazardous/contaminated materials assessment and disposal administration
Potential Scope of CM Services (cont.)
Doing Business with SANDAG
Register your firm online: www.sandag.org/organization/rfps/registerinfo.asp
SANDAG Encourages SB & DBE Participation: www.sandag.org/index.asp?fuseaction=rfps.bench
Bid opportunities on Planet Bids: www.sandag.org/index.asp?fuseaction=rfps.home
Online project information: KeepSanDiegoMoving.com: TransNet projects SANDAG.org: Other capital projects
32Oceanside Transit Center
Keeping San Diego MovingSANDAG Capital Program Update
QUESTIONS & ANSWERS
More Information: SANDAG.org and KeepSanDiegoMoving.com