keith h. lundin, quality unit-bts. team mission materials certification lean team current status ...
TRANSCRIPT
Keith H. Lundin, Quality Unit-BTS
Team Mission Materials Certification Lean Team Current Status Materials Certification Issues Materials Certification Process Prioritization Matrix Solutions Benefits Next Steps
2
Review the materials certification process (preconstruction, during construction, and post-construction) to identify and eliminate non-conformities in process
Primary Focus: Identify ways to reduce the lead time from Substantially Complete through Materials Certification (signed DT1310) to 45 days.
3
Keith Lundin, Bureau of Technical Services, Team Leader Greg Brecka, SW Region PDS Steven Krebs, Bureau of Technical Services Richard Marz, Bureau of Structures/coming from SER Jennifer McCartney Grube – NE Region PDS Brenda McCauley – SW Region PDS Jeff Michalski, NC Region TSS Matt Smith, SE Region PDS Matt Grove, WTBA Contractor Dee Miller, UW Madison – Team Facilitator
4
Current Status: Statewide 2011 - 2012
Missing materials tests
Improper certification
Incomplete or inaccurate Materials Information Tracking System (MITS) reports
Materials Review conducted two years after project completion
Submission of materials records one or more years after project completion
6
7
Materials Certification Process
45 days
8
Materials Certification Tracking Process in MTS entered by Materials Engineer/Specialist
9
DT 1310 Signatures
WisDOT Project Materials Coordinator ____________________Date_______Or
Project Leader (Signature) __________________ Date________
Project Manager (Signature) __________________ Date________
10
Proposed Solutions
WPMC & CPMC Communication
Weekly Data Review
Identifying & Resolving Issues
Final MRS Review
Create 155/900
Resolving Issues
Create Sign DT 1310 Score
Weekly Meetings 3 0 9 0 0 0 0 33
Interim Review of Materials 0 0 9 9 9 0 0 42
Designate WPMC & CPMC 9 0 3 0 0 9 0 39
Materials Helpline (Central Office) 1 0 0 0 1 3 0 7
WDMP for Multiple Projects 3 3 3 3 3 3 3 40
Weekly Requirement between WPMC and CPMC 3 0 3 9 0 9 0 42
Required On-line CPMC/WPMC Training 0 1 3 3 3 3 1 34
Defining Communication Expectations 9 1 3 3 0 3 0 47
Development of Quick Guide for CMM & Spec 3 1 3 1 0 0 0 12
Interim 30-60-Final Review of Materials During construction at 30% and 60% Pilot Regions: SER and NCR
On-line Training of Materials Certification Process WisDOT Project Materials Coordinator (WPMC) Contractor Project Materials Coordinator (CPMC)
11
12
Resolve Non-conformance/Non-performance Issues upstream in a timely manner
Enhance Quality of Materials’ Record Submittal
Assure Central Office Testing is being Conducted in a Timely Manner
Assure Contractors are Submitting Materials Documentation as Required by Specifications
Oct/Nov 2013 Identify and confirm on-line course modules
Nov 2013 Contract consultant from UW-Platteville for development content
for course module
Dec 2013/Mar 2014 Development of on-line training and pilot testing
April 2014 Implementation of Training
13
Nov 2013 Development of documentation for interim review Select/Confirm the person who will conduct interim review
process
Nov/Dec 2013 Review interim process in NCR and SER and make changes
Feb/Mar 2014 Training on Interim Review process
April 2014 Implement Interim Review Process for all regions
14
Communication is Key!
Resolving issues at lowest level reduces the risk of issues being handled later in the process
Material Specifications include a large amount ofrequirements making the materials certification process very complicated.
Bar coding and scanning technologies need to be researched to determine what impact there could be on improving the materials certification process.
15
Keith H. Lundin Quality Assurance Unit Bureau of Technical Services Division of Transportation System Development Wisconsin Dept. of Transportation Cell: 608-220-8847 FAX: 608-245-8959 [email protected]