kekb rf cavity commissioning and operation

32
KEKB RF Cavity Commissioning and Operation Yoshiyuki MORITA KEK Introduction Commissioning Frequency tuner Oscillation of high current crabbing beam Trip rate HOM dampers Beam-induced RF spectrum Summary

Upload: mercer

Post on 01-Feb-2016

44 views

Category:

Documents


0 download

DESCRIPTION

KEKB RF Cavity Commissioning and Operation. Introduction Commissioning Frequency tuner Oscillation of high current crabbing beam Trip rate HOM dampers Beam-induced RF spectrum Summary. Yoshiyuki MORITA KEK. KEKB. He Refrigerator. LER Crab cavity. LER: e+ 3.5 GeV 1.7A - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: KEKB RF Cavity Commissioning and Operation

KEKB RF Cavity Commissioning and Operation

Yoshiyuki MORITA

KEK

Introduction

Commissioning

Frequency tuner

Oscillation of high current crabbing beam

Trip rate

HOM dampers

Beam-induced RF spectrum

Summary

Page 2: KEKB RF Cavity Commissioning and Operation

LER: e+ 3.5 GeV 1.7AHER: e- 8.0 GeV 1.4ARF freq.: 509 MHzCross. Angle: 22 mrad

KEKBLER Crab cavity

HER Crab cavity

8 SC cavities

ARES cavitiesARES cavities

BELLEIP

HER

LER

e+ Linac

e- Linac

He Refrigerator

Present crab crossing scheme

One cavity in one ringBeam bunches wiggle in the ringLuminosity increase (K. Ohmi)

NIKKO AREA ~1 km away from the IP He refrigerator (8 [email protected]) Reduce the construction costs

Page 3: KEKB RF Cavity Commissioning and Operation

K. AkaiUnique characteristicsCoaxial CouplerSquashed CellHigh Field

Vkick=1.4 MVEsp=21 MV/m

B

E

EB

E

ECrab Mode: TM110-like mode (high R/Q)Coaxial coupler: LOM dampingSquashed cell: UWP > 600 MHzNotch filter: TEM-coupled Crab mode rejectionStub support: support for inner conductor

Crab CavityConceptual Design

(RF Absorber)

Page 4: KEKB RF Cavity Commissioning and Operation

Commissioning and operation

• Coupler aging at room temperature (up to 200 kW)

• Cool down (2 K/h for 1 week)

• Tuner adjustment

• Cavity conditioning – HER: >1.8 MV– LER: 1.5 -> 1.3 -> 1.1 MV

• Low beam current tuning for crab crossing

• Warm-up to 80 K and to room temperature

• High current operation and physics run

Page 5: KEKB RF Cavity Commissioning and Operation

System adjustment

• Crabbing voltage

– R/Q, Input RF power, Qext measured at Horizontal test

• Field center

– Beam-induced crabbing amplitude with crab detuned

– Local bump orbit

• Crabbing phase

– Beam orbit difference (Crab ON/OFF)

– Determine crabbing phase

– Determine crabbing voltage

• Tilting angle of beam bunch

– Streak camera (H. Ikeda)

HER LER

Page 6: KEKB RF Cavity Commissioning and Operation

Co

nd

itio

nin

g

Wa

rm-u

p t

o 8

0 K

Wa

rm-u

p t

o 8

0 K

Wa

rm-u

p t

o 3

00

K

Cra

b d

etu

ne

d

Cra

b d

etu

ne

d

1st h

igh

cu

rre

nt

tria

l

2nd h

igh

cu

rre

nt

tria

l

3/1

7V

c d

eg

rad

ed

to 1

MV

HER

LER

Overview of the crab commissioning (1st period)

1.2

A(d

etu

ne

d)

1.4

A(d

etu

ne

d)

1.7

A(d

etu

ne

d)

1.3

5A

(de

tun

ed

)

1.3

A (

cra

b O

N)

0.7

A (

cra

b O

N)

Hig

h t

rip

ra

te

2/1

9 F

irs

t c

rab

be

d b

ea

m

2/2

1 F

irs

t c

rab

co

llis

ion

Page 7: KEKB RF Cavity Commissioning and Operation

Overview of the crab commissioning (2nd and 3rd periods)

HER

LER

Physics run with crab ON

1.6

2A

(c

rab

ON

)0

.95

A (

cra

b O

N)

Win

ter

sh

utd

ow

n

3.06 spacing (Oct. 26)3.5 spacing

Page 8: KEKB RF Cavity Commissioning and Operation

Main Liq. He VesselInput Coupler

Stub SupportRF Monitor

Coaxial Coupler

Beam

Frequency Tuner

Main TunerMechanical + Piezo

Bellows

Driving Plate

Cryostat Vacuum End Cell

Sub Liq. He Vessel

Pick up Probe

Frequency Tuning ~30 kHz / mmAdjust the Tip Position of Coaxial Coupler

Tuning Rod

Sub TunerMechanical

Support Pipe

K. Hosoyama

Main tuner (motor+piezo): Frequency tuning (21 kHz/mm)Sub tuner (motor): Alignment of the coaxial couplerPick-up probe for monitoring crabbing-mode leakage

Page 9: KEKB RF Cavity Commissioning and Operation

Tuner test A. Kabe

Main tuner (motor) Main tuner (piezo) Sub tuner (motor)

Alignment of the coaxTuning parameter: 21 kHz/mm Fluctuation: +/-1 deg.

Fluctuation: +/-13 deg.

Page 10: KEKB RF Cavity Commissioning and Operation

Tuning mechanism improvement

• Piezo actuators broke several times.

– HER: 2 (Oct., 2007)

– LER: 2 (June, 2007), 1(Oct, 2007)

• Coil spring added. (Jan., 2008)– No breakdown since then

• Pulling force is the cause ?

A. Kabe

Load cell

Coil spring

Shaft

Shaft guide

Page 11: KEKB RF Cavity Commissioning and Operation

Phase stability

Span 200 kHzSideband peaks at 32kHz and 64kHz.

Span 10 kHz Span 500 HzSideband peaks at 32, 37, 46, 50, 100 Hz.

• Spectrum of pick up signal is consistent with phase detector data.• Phase fluctuation faster than 1 kHz is less than ± 0.01°, and slow fluctuation

from ten to several hundreds of hertz is about ± 0.1°. • They are much less than the allowed phase error obtained from the beam-beam

simulations for the crabbing beams in KEKB.

According to b-b simulation by Ohmi-san, allowed phase error for N-turn correlation is 0.1×√N (degree).

Spectrum around the crabbing mode measured at a pick up port of the LER crab cavity. Beam current was between 450 and 600 mA.

LER crab phase

HER crab phase

± 1 deg

Phase detector signal. Beam current was 385mA (HER) and 600 mA (LER).

K. Akai

Page 12: KEKB RF Cavity Commissioning and Operation

Oscillation of high-current crabbing beams

• A large-amplitude oscillation was observed in high-current crab-crossing operation in June.

– It caused unstable collision, short beam life time and luminosity degradation.

– Crab amplitude and phase were modulated at 540 Hz. Horizontal oscillation of beams was also observed at the same frequency.

– None of the beam orbit feedback systems is responsible, since their time constants are 1 to 20 sec, much slower than the oscillation.

– The oscillation occurred when the LER tuning phase migrated to the positive side. This gave us a hint to understand the phenomena.

Beam-beam kick is shaken.

K. Akai

Page 13: KEKB RF Cavity Commissioning and Operation

A remedy for the oscillation was found

• Observations at a machine study

– The oscillation occurred only with high-current colliding beams: it never occurred with a single beam, even at a high current.

– Both beams oscillates coherently.– The threshold for the oscillation is

dependent on the crab phase and tuning phase (see left).

• Cause and remedy– We concluded that the oscillation is

caused by beam loading on crab cavities together with beam-beam force at the IP (see, next slide).

– We found that it can be avoided by shifting the crabbing phase by +10° and controlling the tuning offset angle appropriately.

Both crab phase (degree)

LER

tu

ning

off

set

(deg

ree)

HER tuning offset: φtun (HER)

φtun (HER) = 0°

φtun (HER) = -10°

φtun (HER) = +10°

oscillationoccurs

stable

Dependence on the crab phase and tuning phase.Beam current was 1150 mA (LER) and 620 mA (HER).

K. Akai

Page 14: KEKB RF Cavity Commissioning and Operation

Trip statisticsKirk

0.95 MV

HER:1.2/dayLER:0.4/day

1.48 -> 1.36 MV

Warm-up of coax

HER:1.6/dayLER:1.3/day

HER:3.5->2.7/dayLER:0.4/day

Page 15: KEKB RF Cavity Commissioning and Operation

HOM dampers

• Ferrite dampers– Beam pipe damper (LBP damper)– Coaxial damper (Coax damper)

• During the crab commissioning– LBP damper absorbed up to 10 kW– Coax damper up to 2 kW

• HOM power– HER: agree with calculation– LER: 60 %

• SiC damper • Bunch length

LER crab cavity only

Page 16: KEKB RF Cavity Commissioning and Operation

Absorbed HOM power: 9.4 kW (LBP) + 2.4 kW (coax) @ 1.62 ACoax/LBP=0.20(LER) for 3.5-spCoax/LBP=0.25(LER) for 3.06-spAbsorbed HOM power of the LBP HOM damper is significantly smaller than calculated values.SiC damper contributes for HOM power absorption.Calculation well reproduces total HOM power.

Coaxial damper slightly higher than calculationSeveral resonantly build-up RF mode increase HOM power.

HER

LER

LBP

LBP

coax

coax

SiC

Total

Total

Typical HOM powers in the beam operation

Absorbed HOM power: 4.1 kW (LBP) + 1.6 kW (coax) @ 0.95 ACalculation well reproduces total HOM power.Coax/LBP=0.22 for 3.5-spCoax/LBP=0.4 for 3.06-sp

Page 17: KEKB RF Cavity Commissioning and Operation

CalculationLER: 0.927 V/pCCoax: 0.2 V/pC

LOM: 408 MHz

3.5

3.27

3.06

2.88

revb fNI

Pk

2

Loss parameter: kP: HOM powerI: CurrentNb: Number of bunchesfrev: Revolution frequency

Beam spectrum

HER-LBP

HER-coax

Page 18: KEKB RF Cavity Commissioning and Operation

Achieved parameters during beam operation

LER HER unit

Beam current (Crab ON) 1620 950 mA

Beam current (Crab detuned) 1700 1350 mA

Crab voltage (max) 1.5→1.1 →1.27 >1.8 MV

Crab voltage (operation) 0.8 〜 0.95 1.3 〜 1.48 MV

HOM + LOM power 12+15(SiC) 12 kW/cavity

Tuner phase stability (w/piezo)

(w/o piezo)

± 13

± 15

± 1

± 3

degree

degree

Crab phase stability ± 0.1 ± 0.1 degree

Average trip rate (1st period)

(2nd period)

(3rd period)

Average

1.6

0.4

0.4

0.7

1.3

2.7

1.2

1.4

times/day

Page 19: KEKB RF Cavity Commissioning and Operation

Beam-Induced RF spectrum

HOM3 port

HOM4 port

RF3 port

RF4 portBeam

Crab Cavity

Coaxial Coupler

Notch Filter

CoaxialHOM Damper

Large Beam Pipe

LBP HOM Damper

Stub Support

Cavity Cell

Pickup antenna

Crab cavity has several RF ports to measure beam-induced RF spectrum.They are pick-up antennae.Four antennae are set on the coaxial coupler.Four antennae are set on the beam pipe.

Page 20: KEKB RF Cavity Commissioning and Operation

Conceptual design of the crab cavity(Damping scheme of parasitic modes)

•Monopole modes (including LOM) can propagate along the coaxial coupler.•Dipole modes above 600 MHz can propagate.•Crab mode (509 MHz) can not propagate.•Attenuation factor of this mode is 60 dB/m•If the coaxial coupler deflects, crab mode can propagate as TEM mode in the coupler.•Notch filter push this mode back to the cavity.•Stub support supports the long inner conductor.

K. Akai et al, PAC 1993.

509MHz

Page 21: KEKB RF Cavity Commissioning and Operation

TEM modes in the coaxial

1/4 f=57 MHz

3/4 f=99 MHz

5/4 f=170 MHz

7/4 f=198 MHz

Like a quarter wave resonator, the coaxial coupler has several parasitic modes, that have frequencies below 500 MHz.

Freq(MHz) Mode57 co-TEM 1/499 co-TEM 3/4170 co-TEM 5/4198 co-TEM 7/4283 co-TEM 9/4327 co-TEM 11/4396 co-TEM 13/4440 co-TEM 15/4473 co-TEM 17/4

Page 22: KEKB RF Cavity Commissioning and Operation

Single bunch operation at a machine study

Co-

TE

M1/

4

LO

M, T

M11

0

Co-

TE

M13

/4

Co-

TE

M11

/4

Co-

TE

M9/

4

Co-

TE

M7/

4

Co-

TE

M

TM

310

TM

111

TM

130

6/21 LER: 0.86MV,0.48mA

LOMf0: 408.3Q: 140

f0: 408.3Q: 140Measured at horizontal test(@ room temperature)

Freq(MHz) Mode56 co-TEM 1/4195 co-TEM 7/4282 co-TEM 9/4327 co-TEM 11/4395 co-TEM 13/4408 TM110, LOM550 co-TEM 19/4672 TM310696 TM310907 TM111979 TM130

The most gengerouse mode, TM110 (accelerating mode) is heavily damped.

Single bunch operation is suitable to measure beam-induced RF modes since its spectrum is flat with a revolution interval (100 kHz)

ConsistentMainly observe beam spectrum.

Mainly observe beam-induced RF modes.

Page 23: KEKB RF Cavity Commissioning and Operation

Bunch fill pattern

• Low current operation (30mA)– Number of bunches: 30 (160 RF bucket spacing)– Bunch current: 1 mA– To reach medium current operation (24.5 or 3.5 bucket spacing)

• Avoid new HOM resonance• 51 bunches, 98 bucket spacing• 51 bunches, 49 bucket spacing, 8 trains

• Medium current operation (200mA)– Number of bunches: 200 (24.5 RF bucket spacing)

• 7 bucket spacing, 8 trains• 3.5 bucket spacing, 8 or 16 trains

• High current operation (1.7 A (LER) x1.3 A (HER))– Number of bunches: 1389 (3.5 RF bucket spacing)– Bunch current >1 mA

• In the 2nd and 3rd period – Specific luminosity decreases as the bunch current increases.– To increase luminosity, bunch fill patterns with a smaller RF bucket spacing were

applied.• small bunch current and large number of bunches• 3.5 sp (1389 bunches), 3.27(1485), 3.06(1585), 2.88(1678)

Page 24: KEKB RF Cavity Commissioning and Operation

51 bunches, 49 bucket spacing x 8 trains51 bunches, 98 bucket spacing

Example of bunch fill pattern

Page 25: KEKB RF Cavity Commissioning and Operation

aging aging

HER 2007/3/2-2007/3/7 51bunches, 98-spacing

COAX vacuum pressureHPC vacuum pressureCavity vacuum pressure

COAX-LOM Cavity-LOM

Effect of bunch fill patternLOMs are heavily damped, however, they can be resonantly built up when the beam spectrum hits them.

Port: COAX-RF4 Port: COAX-RF4

Page 26: KEKB RF Cavity Commissioning and Operation

1389 bunches with 3.5 bucket spacing

Co-

TE

M1/

4

LO

M, T

M11

0

Co-

TE

M13

/4

Co-

TE

M11

/4

Co-

TE

M9/

4

Co-

TE

M7/

4

Co-

TE

M

TM

310

TM

111

TM

130

Beam spectrum

Beam-induced spectrum (port HOM4)

Page 27: KEKB RF Cavity Commissioning and Operation

1389 bunches with 3.06 bucket spacing

Co-

TE

M1/

4

LO

M, T

M11

0

Co-

TE

M13

/4

Co-

TE

M11

/4

Co-

TE

M9/

4

Co-

TE

M7/

4

Co-

TE

M

TM

310

TM

111

TM

130

Beam spectrum

Beam-induced spectrum (port HOM4)

Beam spectrum hits some RF modes

Page 28: KEKB RF Cavity Commissioning and Operation

Coupler mode excitation

3.5 spacingHorizontally inserted antenna on the beam pipe (HOM-H) observes Horizontally polarized TE mode in the beam pipe.This mode is a RF mode in the stub-type high power coupler.

3.06 spacing

RF mode in the stub-type HPC

Page 29: KEKB RF Cavity Commissioning and Operation

Cavity trip due to unbalanced beam filling

Cavity-LOM

coax-LOM

Cavity trip(Coax-upstream)

Unbalanced beam filling Its spectrum

• Beam loss results in unbalanced beam filling• Deform beam spectrum• Coax-LOM and Cavity-LOM are built up• Increase vacuum pressure• Induce multipacting in the coaxial coupler• Lead cavity trip

Coax-LOM Cavity-LOM

LER current

Page 30: KEKB RF Cavity Commissioning and Operation

Need for higher Vc

• Large beta function at crab cavity causes beam loss.

• Using coaxial coupler, physical aperture is limited to ~100 mm.

• Need for higher Vc for lowering beta.

– Low temperature operation may improve.

Vertical Cold Test (prototype cavity)

Cavity performance at lower temperature

Page 31: KEKB RF Cavity Commissioning and Operation

Lower temperature operation

Main He Vessel

Sub He Vessel

Beam

Gas He

Bellows

RF Absorber

RF Absorber

Cooling Water

Notch Filter

Connection Pipe

Connection Pipe

Liquid He

Stub Support

減圧用排気ポンプ

Cooling Water

Cooling Water

Multi-transfer Line

Helium Compressor Suction

EdwardsE2M2754900 l / min x 2

100 W 0.2 bar

Input Coupler

K. Hosoyama

Page 32: KEKB RF Cavity Commissioning and Operation

Summary

• High beam currents (1.7/1.35 A) were stored with crab cavities.• No serious beam instabilities caused by LOM/HOM were observed.• HOM powers were successfully absorbed up to 12 kW in the ferrite

dampers.• Physics run with CRAB ON with high beam currents (1.62/0.95 A).

– Peak luminosity: 16 /nb/s• LER crab voltage degraded to 1.1 MV (recovered to 1.27 MV).

– Still applicable by increasing beta-x at the LER crab cavity.• Crab phase was well controlled, although the LER tuner phase has large

fluctuation.• The beam oscillation observed with high current crabbing operation.

– Can be avoided by shifting crab phase by +10 deg.• Trip rate during the physics run 0.4(LER)/1.2(HER) par day (3rd period).• KEKB crab cavities have been working with high beam currents to conduct

physics run with the crab crossing !!• We are preparing for the low temperature operation.