Page 1: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

1

Page 2: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

Keolis Commuter

Services

SNOW PLAN

2014-2015

Page 3: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

Revision 1

Contents

1. SNOW PLAN ABSTRACT 3

1.1. PURPOSE 3 1.2. CRITERIA 3 1.3. ACTION 3 1.4. RESPONSIBILITIES 3

2. RAILROAD OPERATIONS SNOW MANAGEMENT PLAN 5

3. SAFETY 5

4. GLOBAL ORGANIZATION 5

4.1 BEFORE WINTER 5 4.2 AS THE STORM APPROACHES 6

4.3 AFTER THE STORM 6

5. SNOW REMOVAL 7

5.3 PRIORITY 1 7 5.2 PRIORITY 2 7

5.3 PRIORITY 3 7

6. PREVENTIVE TREATMENT 8

7. FUEL SOURCES 10

8. STORM CONTROL CENTER 11

9. ENGINEERING DEPARTMENT 12

9.1 ENGINEERING DEPARTMENT STAFF 13

9.2 ENGINEERING TECHNICAL DEPARTMENT 13 9.3 TRACK DEPARTMENT 14

9.4 COMMUNICATION AND SIGNAL DEPARTMENT 15 9.5 B&B DEPARTMENT 16

9.6 FACILITIES DEPARTMENT 18 9.7 FORCE ACCOUNT DEPARTMENT 18 9.8 ENGINEERING DEPARTMENT – SPECIAL INSTRUCTIONS 19

10. TRANSPORTATION DEPARTMENT RESPONSIBILITIES 22

10.1 TRANSPORTATION DEPARTMENT SPECIAL INSTRUCTIONS 23

11. MECHANICAL DEPARTMENT 24

11.1 SNOW PLOWS 24 11.2 RESPONSIBILITIES 25 11.3 PRE-SNOW PREPARATION 26 11.4 STORM ACTIVITY 26

12. CUSTOMER SERVICE DEPARTMENT 27

Page 4: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 2

Revision 1

12.1 RESPONSIBILITIES 27 12.2 PRE-STORM PREPARATION 27 12.3 STORM ACTIVITY 27 12.4 POST STORM ACTIVITY 27

13. STATION SNOW REMOVAL RESPONSIBILITIES (SUBJECT TO CHANGE) 28

14. CRITICAL SWITCH SNOW REMOVAL ASSIGNMENTS 50

15. KCS SNOW REMOVAL EQUIPMENT* 52

16. SWITCH HEATERS 54

17. GAS SWITCH HEATERS 59

16.1 PROCEDURE FOR ACTIVATING GAS SWITCH HEATERS IN BOSTON TERMINAL 59

16.2 INSTRUCTIONS FOR OPERATIONS OF GAS SWITCH HEATERS 59 16.3 LOG BOOK 59

16.4 LIGHTING TOWER A GAS FIRED HOT AIR BLOWERS 59

18. MBTA ORGANIZATION 62

19. KCS ORGANIZATION 63

18.1 TRANSPORTATION DEPARTMENT 63

18.2 CUSTOMER SERVICE DEPARTMENT 66 18.4 ENGINEERING DEPARTMENT 67

18.5 CROSSING TENDERS 68 18.6 MECHANICAL DEPARTMENT 69

20. MISCELLANEOUS TELEPHONE NUMBERS 71

21. OTHER PHONE NUMBERS 73

APPENDIX 1 – STORM SPECIFIC SNOW PLAN-DRAFT 74

Page 5: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 3

Revision 1

1. SNOW PLAN ABSTRACT

1.1. PU

RPOSE To establish procedures and assign responsibilities and priorities for snow

removal and salting/sanding operations, as required, to produce safe conditions for vehicular and foot traffic for commuter rail users and personnel.

1.2. CR

ITERIA Snow removal and/or sanding/salting operations will begin when a snowfall of

2 inches has accumulated or 4 or more inches are forecast or when icy conditions on streets and walkways require sanding or salting. A strong

coordination with the service of the MBTA in charge of the clearing of some parking lots will have to be implemented to assure that a complete response is

provided to customers during all severe weather conditions.

Applicable sections (8.1.9 and 8.1.10) of the operating agreement and common sense will be used in carrying out an effective snow removal plan.

1.3. AC

TION MBTA and KCS Engineering Department staffs will initiate the storm specific

snow removal plan. The Radio Room or Chief Train Dispatcher will notify the Section Chief and/or

KCS Chief Engineering Officer, when there is precipitation of snow, sleet, or freezing rain. Whenever heavy snowfall is predicted, necessary employees and

crews will be recalled as necessary to make sure snow removal operations begin in a timely manner. The storm specific plan will be developed as far in advance

as is possible to allow as much time as possible to notify personnel of the storm and the plan.

MBTA and KCS staffs will update the storm specific snow removal plan as

conditions warrant.

1.4. RESPONSIBILITIES

All departments will assist in the coordination and implementation of snow removal actions.

The Engineering Department is responsible for snow removal, sanding, and salting operations at station platforms, walkways, and parking lots as indicated

on Station Snow Removal Responsibilities table on page 28 and tracks on the MBTA Commuter Rail System.

The Mechanical Department is responsible for pre-season equipment preparation, management of yard and layover operations and the performance

Page 6: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 4

Revision 1

of any special maintenance and recovery efforts under severe weather

conditions. The Transportation Department is responsible for coordinating staff movements

to enable provision of full service in all conditions and for reporting on operating and equipment conditions throughout any severe weather.

The Customer Service Department is responsible for special communications efforts and customer coordination during snow events. The Customer Service

hotline will handle customer concerns and coordinate with Engineering staff during storms to ensure these concerns are handled.

Page 7: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 5

Revision 1

2. RAILROAD OPERATIONS SNOW MANAGEMENT PLAN

KCS has developed the present Snow Management Plan utilizing all of its resources

including Managers, Supervisors, Manpower and Equipment. This is an integrated plan whereby the efforts of KCS personnel and its contractors will work in conjunction

with MBTA Railroad Operations personnel and their contractors.

Accessibility and safety of all stations for commuters is a top priority of KCS for the winter period. In order to achieve this primary goal, KCS has implemented a “Snow

Management Plan” to clear all platforms and as quickly and efficiently as possible.

The objective is to have all stations and parking lots clear within 18-24 hours after snow has STOPPED FALLING. This plan, with our patrons’ cooperation, will ensure

the best use of time, resources, equipment and manpower during snow removal.

As the snow episodes may be numerous and strong, KCS will ensure that all team has

sufficient rest to stay efficient all winter long.

The present Snow Removal Plan will be updated as necessary.

3. SAFETY

During all the winter period, KCS and/or MBTA may need to hire contractors to do part of the job. If the missions of cleaning performed by any contractor are situated

within 15 feet of an active track, all personnel of the contractor shall be trained and qualified to the RWP. Necessary flagmen will be provided by KCS Engineering

Department.

4. GLOBAL ORGANIZATION

4.1 BE

FORE WINTER The engineering department review all actions and improvement plans that took

place during the last 5 years The engineering Department assess the level of all the stocks of sand and salt.

If necessary the complement orders are placed sufficiently in advance to get ready for a level of use corresponding at least at the 2013-2014 consumption

and avoid the risk of stock rupture. On each site, the tools are checked and necessary tool ordered

The equipment are checked and tested before winter. They are all prepositioned according to the strategy of snow removal and the priorities

The Chief Engineering Officer will organize a meeting with the Service of the MBTA in charge of some parking lots to coordinate our actions with theirs.

Page 8: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 6

Revision 1

Look for alternative solutions to experiment on the network. All potential

improvements will have to be assessed and will be subject to prior approval of the MBTA.

4.2 AS

THE STORM APPROACHES National and local Weather Services provide the Engineering Department with

periodic reports that specifically predict the impact of a storm on our service area. This allows KCS management to anticipate by notifying staff, loading salt,

and calcium chloride on trucks, and readying equipment. Any necessary preliminary preparation will have to be conducted before engaging the crew.

The Roadmasters will check their stocks of sand and salt to ensure that they will be able to face the global event that is forecasted + 12 hours

The Engineering Department maintains a standby crew all winter long that can be called to work when a storm begins, including after normal working hours

and weekends. Platforms are treated first.

The Engineering Department begins clearing platforms and parking lots when it is determined that at least 2 inches of snow can be measured on the road

and that at least 2 additional inches are forecast. Plows are ineffective in smaller amounts of snow.

4.3 AF

TER THE STORM The current plan is reviewed to correct potential difficulties or inconsistencies

The level of stocks is assessed and necessary ordered are placed

Page 9: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 7

Revision 1

5. SNOW REMOVAL

When snow removal becomes necessary, crews will work around the clock to improve

travel conditions for commuter rail customers, making every effort to diminish the amount of interruption.

5.3 PR

IORITY 1 Platforms: Prepare for the next rush hour; i.e. inbound in the morning outbound for

the afternoon. Sufficient length of platform cleaned to allow confined boarding or detraining in safety. Ensure full accessibility to disable passengers. The most used

stations will be prioritized. All Access to these platforms will be cleared (paths, staircases, lifts access…)

Parking lots: KCS will coordinate with the service in charge of parking lots (MBTA) Safety Equipment: All safety equipment (standpipes, emergency exits/hatches) will

be cleared from all blocking snow. In an emergency, requiring the use of these exits,

crews will be diverted to ensure access and egress for additional personnel and equipment.

5.2 PRIORITY 2

Platform: Cleaned for full length of all snow and ice and sufficiently salted to retard formation of ice. Complete the cleaning of station platforms

All Access to these platforms will be cleared (paths, staircases, lifts access, etc.) Parking lots: KCS will coordinate with the service in charge of the parking lots (MBTA).

Snow is piled up along perimeter and at various points. It shall never become an obstacle to the safe use of the parking lots, nor prevent from accessing facilities, nor

prevent the emergency services to operate in any station. Safety Equipment: All safety equipment (standpipes, emergency exits/hatches) will

be cleared from all blocking snow.

5.3 PR

IORITY 3 Platforms: Bare pavement as quickly as possible after snowfall. Open up additional

openings in snow banks to increase options of access to station. All Access to these platforms will be cleared (paths, staircases, lifts access, etc.)

Parking lots: Snow piles removed; every possible parking space is available. Safety Equipment: All safety equipment (standpipes, emergency exits/hatches) will

be cleared from all blocking snow.

Page 10: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 8

Revision 1

6. PREVENTIVE TREATMENT

In order to avoid compacted snow to transform in ice, a preventive treatment of the surface may be necessary. The objective of this preventive treatment is to

guarantee the best safety level and the best efficiency. The preventive treatment will have to be organized as close as possible of the freezing periods and not too

early as the salt will be cleared by the steps of stations users. This emphasis the need to check very often the temperatures forecasts

The quantity of salt will have to be as limited as possible in order to limit the acidic and carbonation processes of the treated concrete surfaces. As an example the

following chart states some max quantities recommended for road asphalt preventive treatment

solid salt Brine Wet salt

10 à 15 g/10 sqf 12,5 to 25 cm3/10 sqf ( 4 à 8 g/m2 of salt)

8 to 10 g/10 sqf of salt + 15 à 25 % of brine

As concrete is much more sensitive to the effects of salt, the necessary quantities are still to be assessed and no literature has been found yet to define the recommended quantities and concentrations.

Concrete damages due to salt:

The following text is an abstract from the website: http://cretedefender.com/how-salt-damages-concrete/

“While the exact mechanism of salt damage is not known, a number of known, related factors

instigated by exposure to salt contribute to the deterioration of concrete.

First, salt, a mild acid, lowers the pH in the concrete. The acidic reaction attacks the

concrete paste and aggregate, increasing the pore size and allowing additional water and

chemicals into the concrete which can exacerbate the freeze/thaw cycle damage.

Secondly, salt is hygroscopic, meaning that salt attracts and retains water. When salts are

applied to concrete, they attract additional water (up to 10% more) into the pore structure of

the concrete. This process leaves less room for expansion in the pore structure which, in

turn, creates more pressure inside the concrete when it freezes, causing the surface to chip,

Third, salt accelerates the carbonation process. Carbonation is a process that slowly

reduces the pH levels in concrete through contact with Carbon Dioxide (air) and contributes

to the corrosion of reinforcing steel. Most salts are neutral to mildly acidic (pH of 4.5 – 7),

and absorption of the salts (brine) by the concrete will accelerate the pH reduction of the

concrete.

Fourth, salts are the primary source of chlorides introduced into concrete. Chlorides are also a

major player in the corrosion of reinforcement, as they pierce the thin, protective iron oxide layer

surrounding the reinforcement and initiate a corrosive reaction in the steel.”

Page 11: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 9

Revision 1

Potential evolutions:

Where possible Asphalt will have to be preferred to concrete in the design of new stations and in capital improvement works.

Where not possible a coating will have to be implemented to prevent the reaction with the salt during winters.

Alternative products may be considered for test in order to demonstrate the

absence of harm for environment, efficiency before requesting for the MBTA approval for use on the network. A benchmark is to be conducted with other

railroad companies in Northern America (USA and Canada)

Page 12: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 10

Revision 1

7. FUEL SOURCES

All crews have a commercial credit card enabling the purchase of diesel fuel and

gasoline at service stations throughout the systems. A 2,000-gallon reserve tank of diesel fuel is located at T-Pad maintenance of

way headquarters. Fuel and lube trucks are available from maintenance of way headquarters

capable of distributing 400-900 gallons of diesel and various lubricants to any point in the system as needed.

An account has been opened with major fuel suppliers. These suppliers are open 24 hours a day, seven days a week.

1) EAST COAST PETROLUEM - 781-318-5800

2) TAYLOR OIL - 781-389-0562 / 781-767-5400 3) LUB-O-LINE - 617-776-4490

Page 13: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 11

Revision 1

8. STORM CONTROL CENTER

For storms of such severity and duration that extraordinary coordination and

resources are required, KCS will establish a Storm Control Center. The KCS Storm Control Center will be located at 32 Cobble Hill Road in the MBTA

Conference Room. It will act in strong coordination with the situation room located at the 470 Atlantic

Avenue The Chief Engineering Officer, Chief Mechanical Officer, Chief Transportation Officer

and the Chief Customer Service Officer, or their designees, will staff the Storm Control Center.

Storms of 12 inches or greater or a series of storms in a limited time frame may require the staffing of the Storm Control Center.

The Chief Engineering Officer, in conjunction with the General Manager will make a decision prior to the start of a storm whether the forecast requires the staffing of the

Storm Control Center.

The purpose of the Storm Control Center is to ensure all departments are aware of all issues throughout the commuter rail system for the duration of the storm and that

each department is able to work at maximum efficiency for the duration of the storm.

The Chief Transportation Officer must confer with the MBTA Railroad Operations, Section Chief Transportation, to determine whether the “Severe Weather Reduced

Schedule” will be implemented.

Before each storm, KCS will discuss and submit a storm specific plan in order to identify at least:

- A forecast of the storm, - Stations and platform to be cleaned,

- Crews and their rotation for the duration of the event, - Potential special equipment needed, and

- Storm number for tracking of expenses.

A draft of the storm specific plan is included as Appendix 1.

Page 14: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 12

Revision 1

9. ENGINEERING DEPARTMENT

The Engineering Department is responsible for resolving any storm related difficulties

encountered on the Commuter Rail property that would affect the normal operation of the service.

The key to its success is communication and responsiveness. For this purpose, the following plan has been prepared:

The Radio Room is established as the central point of contact during snow events; it is located at 32 Cobble Hill Road in Somerville. It will be operational

24 hours a day and will handle all complaints and condition reports. It has the capability to communicate with all crews. The emergency number is (617) 222-

3628 for snow related problems or operation-related problems. Crews will be mobilized with the forecast of any storm, forecasting the

accumulation of four or more inches of snow or any reported ice condition. Snow removal priority will be given first to the operation of the trains, second

to station platforms, third to overhead walkways to follow. Parking lots will

have to be cleared in coordination with the service in charge (MBTA). Depending on the time of the storm, priority of platforms will be the direction of the next

rush hour traffic. Field crews will be required to notify the Radio Room at completion of snow

removal at each station and to report at least every two hours, identifying their present location and progress.

An Engineering Dept. Manager will review the snow removal log every two hours during the storm and report any stations not reported and, if necessary, will

contact any crews that have not reported in to the Radio Room for an extended period of time.

Some Engineering Dept. Managers will inspect all locations during/after the storm to ensure all areas have been cleared. During the storm, these managers

will advise the Radio Room if there are locations that require attention. The Radio Room or Engineering Dept. Managers will inform crews of locations

that need attention.

A snow jet and an on-track snow blower will be stationed in the Tower A/CRMF area and will be responsible for clearing all switches.

A second snow jet operated by Pan Am Railways will be stationed in Ayer. The snow jet will clear the switches from Haverhill to Wilmington on the Haverhill

Line and the switches between Lowell and Wilmington on the Lowell Line. The second snow jet if necessary can be diverted to other areas on the Commuter

Rail. A bucket loader or swing loader with a portable snow jet attachment and a

bucket loader with an auger snow blower attachment will be located at Readville to clear Readville Yard.

A second portable snow jet attachment for a bucket loader or swing loader will be located at Beverly Jct.

Page 15: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 13

Revision 1

A second bucket loader with an auger snow blower attachment will be located

on the Newburyport Line. For snow storm with more than 4 inches, a front end loader will be provided to

the CRMF under contract with L&M Holding

9.1 ENGINEERING DEPARTMENT STAFF

CHIEF ENGINEERING OFFICER

The Chief Engineering Officer is responsible for the mobilization of engineering forces.

The Chief Engineering Officer or his Deputy will be on duty throughout the snow emergency.

The Chief Engineering Officer will communicate with the Officers of the Mechanical, Customer Service and Transportation Departments to evaluate the

condition and special needs of the service.

The Chief Engineering Officer will frequently communicate with the Chief Engineering and Maintenance Officer of the MBTA concerning clean up progress

and disruptions to the service. The Chief Engineering Officer will take whatever steps are necessary to minimize the storm’s effect on the service.

DEPUTY CHIEF ENGINEERING OFFICER

Ensure all departments are prepared and have coverage during snow events. Periodically communicate with Engineering Department Managers for condition

reports and possible problem locations. Ensure manpower and materials are available for the duration of the event. In

the event that the Chief Engineering Officer is unavailable for any reason perform the duties assigned to the Chief Engineering Officer.

Ensure inspections of all locations are being performed during and after storms and problem areas are addressed.

Reviews logbook after each storm event.

9.2 ENGINEERING TECHNICAL DEPARTMENT

SENIOR ENGINEER WORK EQUIPMENT Ensure all snow equipment is available for storm duty.

Supervise & dispatch mechanics as needed during the storm. Ensure that frequently used spare parts are available.

Secure rental equipment as necessary.

ENGINEER TRACK Duties as assigned by Deputy Chief Engineering Officer.

Page 16: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 14

Revision 1

ROADMASTER - MATERIALS Coordinate the distribution of tools, material, parts and fuel as required.

9.3 TRACK DEPARTMENT

ASSISTANT CHIEF ENGINEERING OFFICER – TRACK

Provide the Chief Engineering Officer with information on track and station condition. Ensure that the snow assignments are properly covered and the

work activity is proceeding safely and expeditiously. Dispatch crews to areas of critical need. Adjust assignments to cover areas as

storm conditions warrant. Ensure inspections of all locations are being performed during and after

storms and problem areas are addressed. Order the operation of snow jets.

SENIOR ENGINEER TRACK – NORTH

Supervise crew utilization and problems that arise on the North Side of the Commuter Rail System. Dispatch crews to areas of critical need. Adjust

assignments to cover areas as storm conditions warrant. Ensure inspections of all locations are being performed during and after

storms and problem areas are addressed.

SENIOR ENGINEER TRACK – SOUTH Supervise crew utilization and problems that arise on the South Side of the

Commuter Rail System. Dispatch crews to areas of critical need. Adjust assignments to cover areas as storm conditions warrant.

Ensure inspections of all locations are being performed during and after storms and problem areas are addressed.

ROADMASTER TRACK– WEST

Field supervise crews performing snow removal activity on the Lowell and

Fitchburg Lines and the Wildcat Branch. Ensure progress and conditions are being communicated to Radio Room.

Ensure layover facilities are accessible at all times.

ROADMASTER TRACK - NORTH Field supervise crews performing snow removal activity on the Haverhill,

Newburyport and Gloucester Lines. Ensure progress and conditions are being communicated to Radio Room.

Ensure layover facilities are accessible at all times.

ROADMASTER TRACK – SOUTH Field supervise crews performing snow removal activity on the Stoughton,

Franklin, Needham and Dorchester Lines.

Page 17: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 15

Revision 1

Ensure progress and conditions are being communicated to Radio Room.

Ensure layover facilities are accessible at all times.

ROADMASTER TRACK – OLD COLONY Field supervise crews performing snow removal activity on the Middleboro,

Plymouth, Kingston and Greenbush Lines. Ensure progress and conditions are being communicated to Radio Room.

Ensure layover facilities are accessible at all times.

ROADMASTER TRACK - WORCESTER Field supervise crews performing snow removal activity on the Worcester Line

and other locations as needed. Ensure progress and conditions are being communicated to Radio Room.

Ensure layover facilities are accessible at all times.

ROADMASTER TRACK - PRODUCTION

Field supervise crews performing snow removal activity on the Terminal switches and other locations as needed.

Ensure progress and conditions are being communicated to Radio Room. Ensure layover facilities are accessible at all times.

9.4 COMMUNICATION AND SIGNAL DEPARTMENT

ASSISTANT CHIEF ENGINEERING OFFICER – COMMUNICATION AND SIGNAL

Provide condition reports to the Chief Engineering Officer for Communications and Signal.

Ensure crews are available for the duration of the event in order to correct and repair any signal failure with the best diligence

SENIOR ENGINEER C&S - NORTH

Ensure the Signal and Communication systems function for all north side

commuter lines in the best possible manner. Provide condition reports to the Deputy Chief of Engineering Operations. Ensure

available manpower. Investigate C&S failures on Pan Am territory through communication with Pan

Am staff.

SENIOR ENGINEER C&S - SOUTH Ensure the Signal and Communication systems function for all south side

commuter lines in the best possible manner. Provide condition reports to the Deputy Chief of Engineering Operations.

Ensure available manpower. Investigate C&S failures on the Amtrak Main Line through Amtrak staff.

Page 18: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 16

Revision 1

ROADMASTER C&S - NORTH

Newburyport Line Haverhill Line

Gloucester Line

ROADMASTER C&S - WEST Lowell Line

Fitchburg Line

ROADMASTER C&S – OLD COLONY Middleboro Line

Kingston Line Plymouth Line

Greenbush Line

ROADMASTER C&S - SOUTH

Dorchester Line Needham Line

Franklin Line Stoughton Line

ROADMASTER C&S - WORCESTER

Worcester Line

SENIOR ENGINEER C&S CONSTRUCTION

Assignments as directed by Assistant Chief Engineer – C&S.

ROADMASTERS SIGNAL CONSTRUCTION

Assignments as directed by Assistant Chief Engineer – C&S.

9.5 B&B DEPARTMENT

ASSISTANT CHIEF ENGINEERING OFFICER – BRIDGE & BUILDING Provide the Chief Engineering Officer with information pertaining to bridge and

station conditions. Ensure gas-fired switch heaters are properly manned by plumbers.

Dispatch crews to areas of critical need. Adjust assignments to cover areas as storm conditions warrant.

Ensure inspections of all locations are being performed during and after storms and problem areas are addressed.

Page 19: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 17

Revision 1

SENIOR ENGINEER BRIDGE AND BUILDING - NORTH

Field supervise B&B crews on the MBTA Commuter Rail System and examine the function of moveable bridges. Mobilize pumping equipment and crews as

needed.

SENIOR ENGINEER BRIDGE AND BUILDING - SOUTH Field supervise B&B crews on the MBTA Commuter Rail System and examine

the function of moveable bridges. Mobilize pumping equipment and crews as needed.

ROADMASTER BRIDGE AND BUILDING – SOUTH

Field supervise B&B crews on all south side lines. Mobilize pumping equipment and crews as needed.

The emergency exit from Hingham Tunnel will be monitored during the storm to ensure access. If snow builds to the point of blocking the doorway it will be

cleared. In the case of an emergency, crews will be diverted to ensure the exit

is cleared. (Back Bay emergency exit is into an overhead structure.) Standpipes at South Station, Back Bay, Ruggles and Forest Hills Stations will

be monitored during the storm to ensure snow is not impeding access. After the platforms are completed, the standpipes will be cleared if necessary. KCS

will coordinate with the personnel who clear the snow at the street level so snow is not piled in such a way to block access to the standpipes.

ROADMASTER BRIDGE AND BUILDING – NORTH

Field supervise B&B crews on all north side lines. Mobilize pumping equipment and crews as needed.

The escape hatch from Salem Tunnel will be monitored during the storm to ensure access. If snow builds to the point of blocking the doorway it will be

cleared. In the case of an emergency, crews will be diverted to ensure the exit is cleared.

SENIOR ENGINEER – ELECTRICAL and ROADMASTER ELECTRICAL Ensure all electric switch heaters are functional. Provide emergency service as

required.

BRIDGE INSPECTOR – NORTH Field supervise North side B&B crews performing snow removal as assigned.

Ensure progress and conditions are communicated to Radio Room. Ensure drawbridges are in operable condition at all times.

BRIDGE INSPECTOR – SOUTH

Field supervise South side B&B crews performing snow removal as assigned. Ensure progress and conditions are communicated to Radio Room. Ensure

drawbridges are in operable condition at all times.

Page 20: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 18

Revision 1

BRIDGE INSPECTOR – WORCESTER Field supervise Worcester B&B crews performing snow removal as assigned.

Ensure progress and conditions are communicated to Radio Room. Ensure drawbridges are in operable condition at all times.

9.6 FACILITIES DEPARTMENT

ASSISTANT CHIEF ENGINEERING OFFICER - FACILITIES

Ensure working status of all facilities and buildings. Ensure entrances into major train maintenance facilities and parking lots are

clear of snow. Coordinate snow removal from North Station platforms, CRMF and the South

Side S&I.

SENIOR ENGINEER-FACILITIES & ROADMASTERS FACILITIES

Ensure working status of all facilities and buildings. Ensure entrances into major train maintenance facilities and parking lots are

clear of snow. Coordinate snow removal from North Station platforms, CRMF and the South

Side S&I.

9.7 FORCE ACCOUNT DEPARTMENT

ASSISTANT CHIEF ENGINEERING OFFICER - FORCE ACCOUNT

Oversee snow cleaning contractors and other assignments as directed by Chief Engineering Officer.

SENIOR ENGINEER CONSTRUCTION and ENGINEERS CONSTRUCTION

Provide flagmen for outside contractors involved in cleaning platforms.

Supervise flagmen and snow cleaning contractors during snow cleaning operations.

Page 21: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 19

Revision 1

9.8 ENGINEERING DEPARTMENT – SPECIAL INSTRUCTIONS

GENERAL INSTRUCTIONS

Before winter sets in, the forces assigned to clean station platforms will have

shovels, brooms, snow blower, gas, oil, sand and salt stored at all locations. Each crew receives a minimum of 3 shovels, 3 brooms and 2 snow blowers.

Supervision assigned to snow duty will report to their assignments when 2” of snow has accumulated on the ground and it is still snowing with a forecast

snowfall of 4” or better. In the event the storm starts during the daytime working hours, all gangs will

be notified when to return from their daily assignments to headquarters to prepare for snow duty.

Forces assigned to draw and swing span bridges will be equipped with brooms, shovels, salt and sand.

The staff performing cleaning operations at each drawbridge will call the Radio

Room at (617) 222-3628 to report the completion. They will report any unusual events.

Forces assigned to cleaning station platforms will call the Radio Room when they are finished cleaning a station.

Station cleaning forces will salt and sand each platform before departing that station. In some storms, platforms will be cleaned with the predominant traffic

i.e.: inbound platforms first in the morning and outbound first in the evening. All sand and salt used at various locations will be replenished as needed.

All snow blowers will be test-run for a few minutes before any predicted storm. All defects must be reported to a Supervisor’s office at once.

It will be up to the Supervisor or his assistants to call staff out prior to the occurrence of the conditions set forth above. This would normally occur in ice

storms, freezing rain and local storms affecting one section of the service area but not the others.

All trucks are to have a full tank of gas on the last regular work day prior to

predicted storm events.

TRACK DEPARMENT Remove dirt, stone, etc., for entire length of switch point to at least one of the

half depth of tie prior to snow season. Provide drainage from all switches.

Check all snow plow and flanger signs. Check all crossings – surface and roadway – 19 ft. wide area not higher than

plane of rail. Clean all flangeways in crossings.

Tunnels will be monitored for ice buildup and ice buildup will be removed when necessary.

Page 22: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 20

Revision 1

PRE-STORM PREPARATION

In the event snow is forecast for the Commuter Rail Operating territory, the following activities will commence dependent of the forecasted severity of the storm:

Engineering Management will meet to determine a storm plan and submit the storm plan to the MBTA and other KCS Departments.

Engineering employees will be called to determine availability and assignments will be determined.

Equipment will be checked to ensure operation and problems will be reported to the Work Equipment group and the cars and trucks fleet manager.

POST-STORM CHECKLIST

Within forty-eight hours of the completion of a storm event, the Engineering Department Managers will meet to discuss how the storm was handled. Problem

areas will be discussed and if possible solutions will be put in place prior to the next

storm event. If the solution cannot be implemented prior to the next storm event, the problem area will be given special attention until the solution can be in place.

The general condition and the problems/solutions will be documented. The present snow Removal Plan will be updated as needed.

Equipment and tools checklist and status reports will be updated on a monthly basis.

PRESEASON CHECKLIST

Proper preparation will go a long way toward minimizing the bad effects of winter storms when they actually materialize. The following actions will be organized by the

Assistant Chief Engineering Officer of each department for what is relevant of his/her department. They will be supervised by the Deputy Chief Engineering Officer.

Things to be given advance consideration and preparation include: Snow equipment – inspect, repair, test and move to its assigned location for

storage in a readily accessible location. 175 snow blowers, 50 Kubotas and 12

Gravelys. Dual purpose machinery – release from summertime assignments, inspect,

repair, and install winter attachments and move to its wintertime assignment. Flanger signs – install properly where required with special emphasis on all Rail

Lubricator locations. Switch rods – clean cribs and provide drainage to prevent ice from blocking

movement. Electrical and gas switch heaters – start October 1st to give each a full service

test. Make necessary repairs and report each when ready for service. Supplies – check requirements, order requirements and distribute to proper

locations. Items include shovels, brooms, bulk salt, shims, and propane. Material – gather it into central locations where it will be readily accessible and

not lost in the snow.

Page 23: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 21

Revision 1

Drainage systems – clean and repair. Hard to drain locations can be corrected

by auguring holes to a depth lower than the frost line and backfilling them with stone and salt. Sump pump locations will be cleaned.

Radios – inventory all available, inspect and repair, assign to winter locations. Yards – clear of scrap and debris.

Contractors and suppliers – check for day and night telephone numbers and the types of equipment or services that will be available.

Hazard markers – install to guide equipment in clearing roadways and parking area: to warn of walls and other obstructions and to prevent operation into pits,

holes and openings. Snow manual – review and furnish all necessary corrections for the new issue.

POST SEASON CHECKLIST Any amount of planning will not produce a perfect operation. All issues encountered

during the winter season will have to be recorded along with the improvement actions and their efficiency in order profit by the experience gained. Our best planning for

next year can be obtained by a quick analysis of the one just completed. Things to do

should include: Review the invoices from all contractors and suppliers.

1. Did we get value received? 2. Which provided the best and the most reliable service at a competitive

price? Review all deficiencies of snow equipment and write them up for correction by

repair, modification, re-design, or budget presentation. Remove, repair and store items exclusively in wintertime operation such as pot

heaters, snow blowers and bagged salt. Backfill cribs with clean ballast. Send in all notes and suggestions for revision of the snow manual to the KCS

Engineering Department Staff Engineer. It is advisable for each supervisor to write a summary of his observations and experience to create a detailed record.

Were users of the service property safe and liability for the MBTA and KCS minimized?

Page 24: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 22

Revision 1

10. TRANSPORTATION DEPARTMENT RESPONSIBILITIES

Maintain scheduled level of service. This includes the Severe Weather Reduced

Schedule Inform public of delays.

Report field conditions. Provide liaison from to MBTA Operations Control Center (O.C.C.) at 45 High

Street, Boston as required.

PRE-SNOW PREPARATION In the event snow is forecast for the Commuter Rail Operating territory, the following

activities will commence dependent of the forecasted severity of the storm: Coordinate with Mechanical Department for light engines or extra equipment

for snow clearing duty. Verify with Trainmasters that North and South Stations have an adequate

supply of shovels and brooms available for onboard use.

Verify with Mechanical Department that outlying service areas have an adequate supply of brooms and shovels at their locations to stock inbound

trains. As necessary, communicate with Amtrak, Pan Am and CSX Transportation

personnel to ensure a coordinated effort in the movement of Commuter Trains over their respective territories.

Determine the assignment of supervision within the service area. Supervisors will ensure that radios are working properly with fully charged batteries.

STORM ACTIVITY

Transportation Storm Headquarters will be located in the Chief Transportation Officer’s Office. The Chief Transportation Officer or his designee will staff the

office. This office will be continually staffed, as storm intensity and duration require. This office will update storm profile information and disseminate as

necessary, maintaining an open line of communication between the Train

Dispatcher, Customer Service, Engineering, and Mechanical Departments and MBTA. This office will coordinate with Engineering and Mechanical Departments

to ensure that all efforts are directed at maintaining service during the duration of storm activity.

Page 25: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 23

Revision 1

10.1 TRANSPORTATION DEPARTMENT SPECIAL INSTRUCTIONS

FIELD SUPERVISION Field supervisory activity will be assigned as the storm forecast dictates. The

field supervisor will coordinate activities from an assigned location in an effort to maintain established service standards. Such activities will include field

coordination of crews, maintenance of storm activity, reports to Transportation office and local coordination between Mechanical and Engineering Departments.

The field supervisor will ensure that crews have proper platform condition reports and that trains are equipped with a broom and shovel for use by train

crews.

TRAIN DISPATCHER RESPONSIBILITIES Attendant to snow forecast, train dispatchers will instruct all Tower locations

equipped with snow melters to test the same prior to need and monitor during

use to ensure that the same are operable. In addition, the Assistant Chief Train Dispatcher will request Engineering to start all manual heaters prior to start of

snowfall. When snowfall commences, the ACTD will notify all dispatchers to start

operation of snow melters and to monitor their status throughout storm. When snow accumulation reaches one inch, the ACTD will confer with

dispatchers and consult Engineering personnel to determine if diverging routes may continue to be used.

The following switches must be carefully monitored during all snow storms: a. Ash Street – Reading k. Franklin Layover

b. Wilson Spring Switch – Gloucester

l. Fitchburg Layover

c. Beverly Junction m. Needham Layover d. Bradford Layover n. Old Colony – all switches

e. Tower A (all gas burners) –

Boston

o. Middleboro Layover

f. Newburyport Layover p. Kingston Layover

g. Pawtucket Layover q. Worcester Layover h. Rockport Layover r. Greenbush Layover

i. Reading Jct. s. Greenbush Line – all switches j. Stoughton Runaround

During a storm, each dispatcher must remain in contact with and aware of the

location of Engineering personnel in their territory. When the reliability of operating power switches is in question, the train dispatcher must ensure

Engineering personnel are consulted before switch is operated.

Page 26: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 24

Revision 1

As snowfall continues, the Assistant Chief Train Dispatcher and Chief

Transportation Officer (or designee) will converse regarding straight railing of routes within the service area.

11. MECHANICAL DEPARTMENT

The Mechanical Department will assure all locomotives are fully fueled on the day of

anticipated storms. They will also advise the radio room of yard and facility conditions that could impact service with emphasis on service and inspection operations.

Winter Preparation

The Mechanical Department has established procedures for trains on layover during cold weather or snow which are reviewed and distributed to Mechanical staff. Any

deviations to these procedures for a specific storm must be issued by the Chief Mechanical Officer or designee. Information on special winter operations actions

directed by Mechanical management will be provided to the Transportation,

Engineering and Customer Service staff as necessary.

Portable Air Compressors – All but one of the outside point layover facilities that

do not have ground air are equipped with a portable air compressor to support

locomotive layover and start-up. The facility at Rockport does not have either type of air; a portable solution is impractical due to its track configuration. A fall

inspection by a qualified specialist is performed to ensure each compressor is ready for winter use.

Snowplows and Flangers – There are two Russell Snow Plows and one Flanger

available for snow duty. KCS Mechanical shall do a mechanical inspection of the functional aspects of the equipment and make the required corrections annually prior

to November 1. The KCS Chief Mechanical Officer will advise the KCS Chief Engineering Officer of the readiness of the snowplows.

The two Russell Snow Plows will be used primarily on the North Side Commuter Rail

Lines and the Flanger will be used primarily on the South Side Commuter Rail Lines as necessary.

During the month of April each year, KCS shall prepare the equipment for storage taking all required precautions to prevent deterioration and protect components and

systems during the idle season.

11.1 SNOW PLOWS SPEED RESTRICTIONS AND SPECIAL INSTRUCTIONS

A plow train shall consist of one or more locomotives with a working plow ahead, a second, non-working plow and or other cars may be trailed behind the

Page 27: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 25

Revision 1

locomotives. When plowing the snowplow must be coupled directly to a

locomotive powering the plow train and under the control of the engineman. Snowplow trains shall not exceed 35 miles per hour or the authorized timetable

speed for a freight train and shall be operated at a slower speed where conditions warrant.

Caution must be exercised when passing through stations, over at-grade crossings or at any location where flying snow could cause harm.

Extreme care must be afforded when the snowplow is being shoved on track covered by ice or packed snow; a very high potential for derailment should be

anticipated when operating in these conditions. On ground inspection by a qualified employee is appropriate.

Snowplows must be equipped with a working headlight on the lead whenever being operated.

Snowplows shall only be placed ahead of the locomotive in double track territory when in plowing operation and will stop when met by trains operating on the

opposite track.

Snowplow wings shall be used only when a qualified conductor or engineman is in the monitor of the plow to observe signals, communicate with the locomotive

and/or dispatcher, and otherwise control the movement of the plow train. The snowplow shall not operate attached to any revenue train except under the

written authority of the Chief Train Dispatcher and shall then be governed by snowplow speeds.

A qualified conductor or engineman shall be assigned to ride on the plow. Clear and Audible radio communication must be maintained at all times between

the engineman and the conductor assigned to ride the plow. If this communication is lost the plow must cease the plowing operation until

communication is restored. Signals shall be communicated to the engineman on the locomotive of the plow

train who will regulate its movements, except that in the case of an emergency requiring prompt action, stop to be made by use of the air-brake valve located

in the plow.

Wings and flanger must be completely closed and properly secured when being moved in other than a plow train.

When moving in a revenue train, plows shall be placed to the rear of the consist. Only qualified Engineering Department employees or Train and Engine

crewmembers shall operate or be assigned to operate a snowplow. The Chief Engineering Officer, Chief Transportation Officer and Chief Mechanical

Officer will determine when the operation of the snow plows and flangers are necessary.

11.2 RESPONSIBILITIES

Maintain consist requirements. Report deficiencies of layover points.

Maintain Field Response Team.

Page 28: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 26

Revision 1

Maintain fuel and supply requirements for winter equipment.

Provide light engines as required. Advise of access to fuel and sand supplies.

Protect unused equipment stored in yards. Coordinate any special operations needs with other departments

Engines will be equipped with a switch broom. Engines will have a sufficient quantity of sand and working sanders.

Snow bags will be placed on the knuckles of the control car and engine and all 480 cables will have the “O” rings secured.

11.3 PRE-SNOW PREPARATION

In the event snow is forecast for the service area, the following activities will commence dependent on the forecasted severity of the storm:

Increase staffing at layovers as needed. Ensure adequate supply of materials is on hand prior to the storm.

11.4 STORM ACTIVITY Mechanical Storm Headquarters will be located in the Chief Mechanical Officer’s

Office at CRMF. The Chief Mechanical Officer or his designee will staff the office. This office will be continually staffed, as storm intensity and duration require.

This office will update storm profile information and disseminate as necessary, maintaining an open line of communication between the Transportation, and

Engineering Departments and MBTA. This office will coordinate with Transportation and Engineering Departments to ensure that all efforts are

directed at maintaining service during the duration of storm activity. Coordinate with the Transportation Department to move equipment as

necessary to maintain access to the S&I and PI tracks of the CRMF. Depending upon length and severity of storm Mechanical Department managers

will be assigned to various Mechanical facilities to assist in the provision of passenger service before, during and after a storm event.

Page 29: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 27

Revision 1

12. CUSTOMER SERVICE DEPARTMENT

12.1 RESPONSIBILITIES

Pre-Snow Customer communication Monitor information on train and through LED messaging systems.

Report field conditions, from customer emails, phone calls and correspondence. Execution of a customer recovery plan when required.

12.2 PRE-STORM PREPARATION

Prior to the winter snow season, communicate to customers the snow plan, managing expectations, phone numbers, through all available venues i.e.

RailMails, T-Alerts, LEDs, KCS Web-site and social media.

12.3 STORM ACTIVITY The call center will be fully staffed during storm periods

The customer service team has a member of staff on call 24/7, who will be

called to assist with customer recovery. All other customer service representatives will remain available to support any

service disruption or service recovery and respond to necessary station locations to provide assistance to customers.

During the storm, all T-Alerts, LED and customer announcements will be

monitored.

12.4 POST STORM ACTIVITY Respond to all customer correspondence, inform all departments of service

failures and work as a team to review and develop solutions to feedback.

Page 30: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 28

Revision 1

13. STATION SNOW REMOVAL RESPONSIBILITIES (subject to change)

STATION RIDER- SHIP

# OF PLATFORMS

PLATFORMS PARKING LOTS

EQUIPMENT LOCATED AT THE

STATION

MOBILE EQUIPMENT

SNOW REMOVAL CREW

EQUIPMENT/ MANAGEMENT

SNOW REMOVAL

CREW

North Station

5 Platforms 1 Kubota and 2 Small Snow

Blowers

Facilities N/A N/A

South

Station

8 Platforms 1 Gravely, 1

Kubota and 3

Small Snow Blowers

B&B South Station

Crew (3)

Kubota B&B

PROVIDENCE LINE

Back Bay 287 2 Platforms MBTA MBTA N/A N/A

Ruggles 24 1 Platform MBTA MBTA N/A N/A

Forest Hills 85 1 Platform MBTA MBTA N/A N/A

Hyde Park 1,592 2 Platforms w/Handicap

Platform

1 Kubota 2 Big and 2 Small Snow

Blowers

B&B Readville Crew (2)

LAZ Parking (781)794-1791

Case Snow Mgmt. John

Case 508-509-5551

Readville 980 2 Platforms

w/Handicap Platform

2 Sidewalk

Tractors (Located at Readville

Headquarters)

2 Small and 2

Big Snow Blowers

Readville Track Crew

#1 (4)

LAZ Parking

(781)794-1791

Case Snow

Mgmt. John Case 508-

509-5551

Route 128 2,753 2 Platforms Amtrak LAZ Parking

Seth Shurtleff

(617)417-0170

Canton

Junction

2,520 4 Platforms

w/Handicap Platform

KCS Contractor LAZ Parking

(781)794-1791

Case Snow

Mgmt. John Case 508-

509-5551

Sharon 1,390 2 Platforms w/Handicap

Platform

2 Big and 2 Small Snow

Blowers

B&B Bridge Crew (4) Town of Sharon (781) 784-1525

Page 31: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 29

Revision 1

STATION RIDER- SHIP

# OF PLATFORMS

PLATFORMS PARKING LOTS

EQUIPMENT LOCATED AT THE

STATION

MOBILE EQUIPMENT

SNOW REMOVAL CREW

EQUIPMENT/ MANAGEMENT

SNOW REMOVAL

CREW

Mansfield 1,854 2 Platforms w/Handicap

Platform

2 Big and 2 Small Snow

Blowers

B&B Bridge Crew (4) Town of Mansfield (508) 261-7335

Attleboro 1,807 2 Platforms

w/Handicap Platform

1 Kubota, 2 Big

Snow Blowers

2 Small Snow

Blowers

B&B Pawtucket Crew

(3)

GATRA

South

Attleboro

1,877 2 Platforms

w/Handicap Platform

1 Kubota

w/Trailer, 2 Big and 2 Small Snow

Blowers

B&B Pawtucket Crew

(3)

LAZ Parking

(781)794-1791

Case Snow

Mgmt. John Case 508-

509-5551

Providence 1,018 Amtrak Amtrak

TF Green Amtrak Amtrak

Wickford

Junction

Amtrak Amtrak

FAIRMOUNT LINE

Readville (Upper)

98 1 Platform w/Handicap

Platform

2 Sidewalk Tractors (Located

at Readville Headquarters)

2 Small and 2 Big Snow

Blowers

Readville Track Maintenance Crew

#2 (4)

MBTA Case Snow Mgmt.

Jason Case 508-509-5551

Fairmont 499 2 Platforms KCS Contractor MBTA

Case Snow Mgmt. Jason Case 508-509-5551

Morton St. 328 2 Platforms KCS Contractor KCS Contractor

Talbot

Station

KCS Contractor KCS Contractor

Four Corners

KCS Contractor N/A N/A

Page 32: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 30

Revision 1

STATION RIDER- SHIP

# OF PLATFORMS

PLATFORMS PARKING LOTS

EQUIPMENT LOCATED AT THE

STATION

MOBILE EQUIPMENT

SNOW REMOVAL CREW

EQUIPMENT/ MANAGEMENT

SNOW REMOVAL

CREW

Uphams Corner

185 2 Platforms KCS Contractor KCS Contractor

Newmarket KCS Contractor N/A N/A

FITCHBURG LINE

Porter Square

131 1 Platform MBTA N/A N/A

Belmont Center

101 2 Platforms 2 Small and 2 Big Snow

Blowers, 1 Kubota

West Cambridge Track Maintenance

Crew (8)

Belmont DPW (617) 489-8210

Waverly 99 2 Platforms 1 John Deere

Tractor

2 Small and 2

Big Snow Blowers, 1

Kubota

West Cambridge

Track Maintenance Crew (8)

N/A N/A

Waltham 559 2 Platforms 2 Small and 2

Big Snow Blowers, 1

Kubota

West Cambridge

Track Maintenance Crew (8)

Waltham DPW

(781) 314-3855

Brandeis-Roberts

433 2 Platforms w/Handicap

Platform

2 Small and 2 Big Snow

Blowers, 1 Kubota

West Cambridge Track Maintenance

Crew (8)

LAZ Parking (781)794-1791

DeVincent Landscpg

Jim-781-893-1650

Brandeis College

Kendall

Green

112 2 Platforms 2 Small and 2

Big Snow Blowers, 1

Kubota

West Cambridge

Track Maintenance Crew (8)

Weston DPW

(781) 893-1263

Page 33: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 31

Revision 1

STATION RIDER- SHIP

# OF PLATFORMS

PLATFORMS PARKING LOTS

EQUIPMENT LOCATED AT THE

STATION

MOBILE EQUIPMENT

SNOW REMOVAL CREW

EQUIPMENT/ MANAGEMENT

SNOW REMOVAL

CREW

Hastings 38 1 Platform 2 Small and 2 Big Snow

Blowers, 1 Kubota

West Cambridge Track Maintenance

Crew (8)

Dump truck Track

Silver Hill 22 1 Platform 2 Small and 2 Big Snow

Blowers, 1

Kubota

West Cambridge Track Maintenance

Crew (8)

Dump truck Track

Lincoln 335 2 Platforms 1 Kubota 2 Small and 2

Big Snow Blowers, 1

Kubota

West Cambridge

Track Maintenance Crew (8)

Lincoln DPW

(781) 259-8999

Concord 423 2 Platforms 2 Small and 2 Big Snow

Blowers, 1 Sidewalk

Tractor

West Concord Track I&R (2) & Machine

Operator (1)

Concord DPW (978) 369-1827

West Concord

427 2 Platforms w/Handicap

Platform

1 Kubota 2 Small and 2 Big Snow

Blowers, 1 Sidewalk

Tractor

West Concord Track I&R (2) & Machine

Operator (1)

Concord DPW (978) 369-1827

South Acton 622 1 Platform 2 Small and 2

Big Snow Blowers, 1 Plow

Truck

Ayer Welders &

Fitchburg Greasers (4)

Acton DPW

(978) 369-1827

Littleton - 495

177 1 Platform 2 Small and 2 Big Snow

Blowers

Ayer Welders & Fitchburg Greasers

(4)

DeVincent Landscpg Jim-781-893-1650

Page 34: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 32

Revision 1

STATION RIDER- SHIP

# OF PLATFORMS

PLATFORMS PARKING LOTS

EQUIPMENT LOCATED AT THE

STATION

MOBILE EQUIPMENT

SNOW REMOVAL CREW

EQUIPMENT/ MANAGEMENT

SNOW REMOVAL

CREW

Ayer 259 2 Platforms 1 Kubota 2 Small and 2 Big Snow

Blowers

Ayer Welders & Fitchburg Greasers

(4)

Ayer DPW

Shirley 128 2 Platforms

w/Handicap Platform

2 Small and 2

Big Snow Blowers

Fitchburg Track

Maintenance Crew (4)

Shirley DPW

(978) 425-2628

North

Leominster

197 2 Platforms

w/Handicap Platform

2 Small and 2

Big Snow Blowers

Fitchburg Track

Maintenance Crew (4)

MART

(978) 345-7711

Fitchburg 257 1 Platform w/Handicap

Platform

1 Kubota 2 Small and 2 Big Snow

Blowers

Fitchburg Track Maintenance Crew

(4)

MART (978) 345-7711

FRAMINGHAM / WORCESTER LINE

Back Bay 287 1 Platform MBTA MBTA

Yawkey Station

26 1 Platform w/Handicap

Platform

2 Small Snow Blowers

Framingham Track Crew (5)

N/A N/A

Newtonville 406 1 Platform 1 Big Snow Blower 2 Small Snow Blowers

Framingham Track Crew (5)

N/A N/A

West Newton

355 1 Platform 1 Big Snow Blower 2 Small Snow Blowers

Framingham Track Crew (5)

LAZ Parking (781)794-1791

DeVincent Landscpg

Jim-781-893-1650

Auburndale 384 1 Platform 1 Big Snow Blower 2 Small Snow

Blowers

Framingham Track

Crew (5)

LAZ Parking

(781)794-1791

DeVincent

Landscpg Jim-781-

893-1650

Page 35: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 33

Revision 1

STATION RIDER- SHIP

# OF PLATFORMS

PLATFORMS PARKING LOTS

EQUIPMENT LOCATED AT THE

STATION

MOBILE EQUIPMENT

SNOW REMOVAL CREW

EQUIPMENT/ MANAGEMENT

SNOW REMOVAL

CREW

Wellesley Farms

415 2 Platforms 1 Kubota 2 Small and 3 Big Snow

Blowers

B&B Readville Crew #1 (3)

Wellesley DPW (781) 235-7068

Wellesley Hills

572 2 Platforms 2 Small, 3 Big Snow Blowers &

1 Bombardier

B&B Readville Crew #1 (3)

Wellesley DPW (781) 235-7068

Wellesley

Square

848 2 Platforms 2 Small and 3

Big Snow

Blowers

B&B Readville

Crew#1 (3)

Wellesley DPW

(781) 235-7068

Natick 837 2 Platforms 2 Small and 2 Big

Snow Blowers

B&B Readville Crew

#2 (3)

N/A

West Natick 925 2 Platforms

w/Handicap Platform

2 Small Snow

Blowers and 1 Kubota

B&B Readville Crew

#2 (3)

LAZ Parking

(781)794-1791

Tufts, Inc.

Frank Spinosa

617-212-9413

Framingham 1,141 2 Platforms w/Handicap

Platform

1 Kubota 2 Small and 3 Big Snow

Blowers

B&B Readville Crew #2 (3)

MBTA Tufts

Ashland 390 2 Platforms w/Handicap

Platform

2 Small and 3 Big Snow Blowers and

1 Kubota (with trailer)

B&B Ashland Crew (2)

LAZ Parking (781)794-1791

DeVincent Landscapin

g Jim 781-983-1650

Southboro 413 2 Platforms

w/Handicap Platform

2 Small and 2

Big Snow Blowers

B&B Ashland Crew

(2)

LAZ

Parking(781)794-1791

DeVincent

Landscaping Jim 781-

983-1650

Page 36: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 34

Revision 1

STATION RIDER- SHIP

# OF PLATFORMS

PLATFORMS PARKING LOTS

EQUIPMENT LOCATED AT THE

STATION

MOBILE EQUIPMENT

SNOW REMOVAL CREW

EQUIPMENT/ MANAGEMENT

SNOW REMOVAL

CREW

Westboro 473 2 Platforms w/Handicap

Platform

2 Small and 2 Big Snow

Blowers

B&B Worcester Crew (3)

LAZ Parking (781)794-1791

DeVincent Landscapin

g Jim 781-983-1650

Grafton 2 Platforms w/Handicap

Platform

2 Small and 2 Big Snow Blowers and

1 Kubota

B&B Worcester Crew (3)

LAZ Parking (781)794-1791

DeVincent Landscapin

g Jim 781-

983-1650

Worcester

Station

1,243 Other Worcester DPW (508) 929-

1300 x4156

FRANKLIN LINE

Readville 980 1 Platform w/Handicap

Platform

2 Sidewalk Tractors (Located

at Readville Headquarters)

2 Small and 2 Big Snow

Blowers

Readville Track Crew #2 (4)

LAZ Parking (781)794-1791

Case Snow Mgmt.

Jason Case 508-509-

5551

Endicott 480 2 Platforms 2 Small Snow Blowers, 2

Sidewalk Tractors

Readville Track Crew #2 (4)

Town of

Dedham

Dedham 1,098 2 Platforms

w/Handicap Platform

2 Small Snow

Blowers, 2 Sidewalk

Tractors

Readville Track Crew

#2 (4)

LAZ Parking

(781)794-1791

Case Snow

Mgmt. Jason Case

508-509-5551

Islington 283 2 Platforms 2 Small Snow Blowers, 2

Sidewalk Tractors

Readville Track Crew #2 (4)

LAZ Parking (781)794-1791

Case Snow Mgmt.

Jason Case 508-509-

5551

Page 37: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 35

Revision 1

STATION RIDER- SHIP

# OF PLATFORMS

PLATFORMS PARKING LOTS

EQUIPMENT LOCATED AT THE

STATION

MOBILE EQUIPMENT

SNOW REMOVAL CREW

EQUIPMENT/ MANAGEMENT

SNOW REMOVAL

CREW

Norwood Depot

578 2 Platforms w/Handicap

Platform

2 Small Snow Blowers, 2

Sidewalk Tractors

Readville Track Crew #2 (4)

LAZ Parking (781)794-1791

Case Snow Mgmt.

Jason Case 508-509-

5551

Norwood

Central

1,328 2 Platforms

w/Handicap

Platform

1 Kubota 2 Small Snow

Blowers, 2

Sidewalk Tractors

Readville Track Crew

#2 (4)

LAZ Parking

(781)794-1791

Case Snow

Mgmt.

Jason Case 508-509-

5551

Windsor

Gardens

546 1 Platform N/A N/A N/A N/A

Plimptonville 3 1 Platform 2 Small and 2 Big Snow

Blowers, 1 Sidewalk

Tractor

Franklin Track Maintenance Crew

(6)

Dump Truck Track

Walpole 675 1 Platform 1 Kubota 2 Small and 2

Big Snow Blowers

Franklin Track

Maintenance Crew (6)

LAZ Parking

(781)794-1791

Case Snow

Mgmt. Jason Case

508-509-5551

Norfolk 939 1 Platform

w/Handicap Platform

2 Small and 2

Big Snow Blowers, 1

Sidewalk Tractor

Franklin Track

Maintenance Crew (6)

LAZ Parking

(781)794-1791

Case Snow

Mgmt. Jason Case

508-509-5551

Page 38: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 36

Revision 1

STATION RIDER- SHIP

# OF PLATFORMS

PLATFORMS PARKING LOTS

EQUIPMENT LOCATED AT THE

STATION

MOBILE EQUIPMENT

SNOW REMOVAL CREW

EQUIPMENT/ MANAGEMENT

SNOW REMOVAL

CREW

Franklin 906 1 Platform 1 Kubota 2 Small and 2 Big Snow

Blowers

Franklin Track Maintenance Crew

(6)

LAZ Parking (781)794-1791

Case Snow Mgmt.

Jason Case 508-509-

5551

Forge Park 1,388 2 Platforms

w/Handicap

Platform

2 Small and 2

Big Snow

Blowers, 1 Sidewalk

Tractor

Franklin Track

Maintenance Crew

(6)

LAZ Parking

(781)794-1791

Case Snow

Mgmt.

Jason Case 508-509-

5551

Foxboro 1 Platform Platform cleared as needed. Crews and equipment

assigned as required.

N/A N/A

GREENBUSH LINE

Weymouth

Landing

1 High Level

Platform

KCS Contractor LAZ Parking

Seth Shurtleff (617)417-0170

Case Snow

Mgmt. Jason Case

508-509-5551

East

Weymouth

1 High Level

Platform

KCS Contractor LAZ Parking

Seth Shurtleff (617)417-0170

Case Snow

Mgmt. Jason Case

508-509-5551

West Hingham

1 High Level Platform

KCS Contractor LAZ Parking Seth Shurtleff

(617)417-0170

Case Snow Mgmt.

Jason Case 508-509-

5551

Page 39: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 37

Revision 1

STATION RIDER- SHIP

# OF PLATFORMS

PLATFORMS PARKING LOTS

EQUIPMENT LOCATED AT THE

STATION

MOBILE EQUIPMENT

SNOW REMOVAL CREW

EQUIPMENT/ MANAGEMENT

SNOW REMOVAL

CREW

Nantasket Junction

1 High Level Platform

1 Kubota 2 Small and 2 Big Snow

Blowers

Greenbush Track Crew

LAZ Parking Seth Shurtleff

(617)417-0170

Case Snow Mgmt.

Jason Case 508-509-

5551

Cohasset 1 High Level

Platform

2 Small and 2

Big Snow

Blowers

Greenbush Track

Crew

LAZ Parking

Seth Shurtleff

(617)417-0170

Case Snow

Mgmt.

Jason Case 508-509-

5551

North

Scituate

1 High Level

Platform

1 Kubota 2 Small and 2

Big Snow Blowers

Greenbush Track

Crew

LAZ Parking

Seth Shurtleff (617)417-0170

Case Snow

Mgmt. Jason Case

508-509-5551

Greenbush 1 High Level

Platform

1 Kubota 2 Small and 2

Big Snow Blowers

B&B Greenbush

Crew

LAZ Parking

Seth Shurtleff (617)417-0170

Case Snow

Mgmt. Jason Case

508-509-5551

HAVERHILL LINE

Malden 32 MBTA MBTA MBTA

(617) 222-3243

Wyoming Hills

243 2 Platforms 1 Kubota 2 Small and 2 Big Snow

Blowers

Boston Track Crew (6)

Melrose DPW (781) 979-4170

Melrose

Cedar Park

285 2 Platforms 2 Small and 2

Big Snow Blowers and 1

Kubota

Boston Track Crew

(6)

Melrose DPW

(781) 979-4170

Page 40: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 38

Revision 1

STATION RIDER- SHIP

# OF PLATFORMS

PLATFORMS PARKING LOTS

EQUIPMENT LOCATED AT THE

STATION

MOBILE EQUIPMENT

SNOW REMOVAL CREW

EQUIPMENT/ MANAGEMENT

SNOW REMOVAL

CREW

Melrose Highlands

422 2 Platforms 2 Small and 2 Big Snow

Blowers and 1 Kubota

Boston Track Crew (6)

Melrose DPW (781) 979-4170

Greenwood 216 2 Platforms 2 Small and 2 Big Snow

Blowers and 1

Kubota

Boston Track Crew (6)

Wakefield Savings (781) 942-9092

Wakefield 757 2 Platforms 2 Small and 2

Big Snow Blowers and 1

Kubota

Boston Track Crew

(6)

Wakefield DPW

(781) 246-6314

Reading 856 1 Platform w/Handicap

Platform

2 Small and 2 Big Snow

Blowers and 1 Kubota

Boston Track Crew (6)

Reading DPW (781) 942-9092

E. Reading Parking

N/A N/A N/A MBTA 617-438-8349 Dan Pasquarosa

North

Wilmington

173 1 Platform

w/Handicap Platform

2 Small and 2

Big Snow Blowers, 1

Trackless

Wilmington Track

Maintenance Crew (5)

Private

Ballardvale 340 1 Platform

w/Handicap Platform

2 Small and 2

Big Snow Blowers and 1

Kubota

Rosemont Track

Maintenance Crew (6)

LAZ Parking

(781)794-1791

CJ

Mabardy-Dan

617-438-8439

Page 41: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 39

Revision 1

STATION RIDER- SHIP

# OF PLATFORMS

PLATFORMS PARKING LOTS

EQUIPMENT LOCATED AT THE

STATION

MOBILE EQUIPMENT

SNOW REMOVAL CREW

EQUIPMENT/ MANAGEMENT

SNOW REMOVAL

CREW

Andover 747 1 Platform w/Handicap

Platform

1 Kubota 2 Small and 2 Big Snow

Blowers

Rosemont Track Maintenance Crew

(6)

LAZ Parking (781)794-1791

CJ Mabardy-

Dan 617-438-

8439

Lawrence 1 High Level

Platform

MVRTA

(978) 373-2948

MVRTA

(978) 373-2948

Bradford 412 2 Platforms

w/Handicap

Platform

1 Kubota 2 Small and 2

Big Snow

Blowers

Rosemont Track

Maintenance Crew

(6)

LAZ Parking

(781)794-1791

CJ

Mabardy-

Dan 617-438-

8439

Haverhill 554 2 Platforms

w/Handicap Platform

2 Small and 2

Big Snow Blowers and 1

Kubota

Rosemont Track

Maintenance Crew (6)

LAZ Parking

(781)794-1791

CJ

Mabardy-Dan

617-438-8439

LOWELL LINE

West Medford

435 2 Platforms 1 Kubota 2 Big and 2 Small Snow

Blowers

B&B Mystic Crew V862 (2)

Private

Wedgemere 408 2 Platforms Winchester Flag (1) Winchester DPW

(781) 721-7106

Winchester 633 2 Platforms Winchester Flag (1) Winchester DPW (781) 721-7106

Anderson 967 1 Platform 2 Small Snow

Blowers, 1 Gravely

T-Pad and Boston

Welders (4)

Massport

Mishawum 37 2 Platforms 2 Small Snow Blowers, 1

Gravely

T-Pad and Boston Welders (4)

N/A N/A

Page 42: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 40

Revision 1

STATION RIDER- SHIP

# OF PLATFORMS

PLATFORMS PARKING LOTS

EQUIPMENT LOCATED AT THE

STATION

MOBILE EQUIPMENT

SNOW REMOVAL CREW

EQUIPMENT/ MANAGEMENT

SNOW REMOVAL

CREW

Wilmington 515 2 Platforms w/Handicap

Platforms

2 Small and 2 Big Snow Blowers, 1

Kubota

Wilmington Track Maintenance Crew

(5)

LAZ Parking (781)794-1791

CJ Mabardy-

Dan 617-438-

8439

North

Billerica

837 2 Platforms

w/Handicap

Platforms

2 Small and 2

Big Snow

Blowers, 1 Kubota

Wilmington Track

Maintenance Crew

(5)

LRTA

(978) 495-0164

Lowell 1,325 LRTA N/A LRTA (978) 375-5476

MIDDLEBORO / LAKEVILLE LINE

JFK/UMass MBTA MBTA N/A N/A

Quincy

Center

250 1 High-Level

Platform

2 Small and 2

Big Snow Blowers

Readville Track

Flange Oiler Crew (2)

LAZ Parking

Seth Shurtleff (617)417-0170

Watson

Excavating John Margie

(508)245-

1062

Braintree 174 Center High-

Level Platform

1 Gravely 2 Small and 2

Big Snow Blowers

Readville Track

Flange Oiler Crew (2)

LAZ Parking

Seth Shurtleff (617)417-0170

Watson

Excavating John Margie

(508)245-1062

Holbrook/

Randolph

606 1 High-Level

Platform

1 Gravely 2 Small and 2

Big Snow Blowers

Braintree Track

Maintenance Crew (5)

LAZ Parking

Seth Shurtleff (617)417-0170

Watson

Excavating John Margie

(508)245-1062

Page 43: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 41

Revision 1

STATION RIDER- SHIP

# OF PLATFORMS

PLATFORMS PARKING LOTS

EQUIPMENT LOCATED AT THE

STATION

MOBILE EQUIPMENT

SNOW REMOVAL CREW

EQUIPMENT/ MANAGEMENT

SNOW REMOVAL

CREW

Montello 525 2 High Level 1 Gravely 2 Small and 2 Big Snow

Blowers

Braintree Track Maintenance Crew

(5)

LAZ Parking Seth Shurtleff

(617)417-0170

Watson Excavating

John Margie (508)245-

1062

Brockton 804 Center High-

Level Platform

1 Gravely 2 Small and 2

Big Snow

Blowers

Braintree Track

Maintenance Crew

(5)

Brockton Bus Authority

Campello 601 1 High-Level

Platform

1 Gravely 2 Small and 2

Big Snow Blowers

Middleboro Track

Maintenance Crew (5)

LAZ Parking

Seth Shurtleff (617)417-0170

Watson

Excavating John Margie

(508)245-1062

Bridgewater 614 1 High-Level

Platform

1 Gravely 2 Small and 2

Big Snow Blowers

Middleboro Track

Maintenance Crew (5)

LAZ Parking

Seth Shurtleff (617)417-0170

Watson

Excavating John Margie

(508)245-1062

Middleboro/ Lakeville

512 1 High-Level Platform

1 Gravely 2 Small and 2 Big Snow

Blowers

Middleboro Track Maintenance Crew

(5)

LAZ Parking Seth Shurtleff

(617)417-0170

Watson Excavating

John Margie (508)245-

1062

NEEDHAM LINE

Roslindale 482 1 Platform

w/Handicap Platform

2 Small and 2

Big Snow Blowers, 1

Kubota

Surface Crew (4) MBTA WelchCORP

Paul Mcmanus 617-590-7053

Page 44: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 42

Revision 1

STATION RIDER- SHIP

# OF PLATFORMS

PLATFORMS PARKING LOTS

EQUIPMENT LOCATED AT THE

STATION

MOBILE EQUIPMENT

SNOW REMOVAL CREW

EQUIPMENT/ MANAGEMENT

SNOW REMOVAL

CREW

Bellevue 347 1 Platform w/Handicap

Platform

2 Small and 2 Big Snow

Blowers, 1 Kubota

Surface Crew (4) MBTA Welch Corp

Highland 486 1 Platform w/Handicap

Platform

2 Small and 2 Big Snow

Blowers, 1

Kubota

Surface Crew (4) MBTA Welch Corp

West

Roxbury

513 1 Platform

w/Handicap Platform

2 Small and 2

Big Snow Blowers, 1

Kubota

Surface Crew (4) MBTA

Welch Corp

Hersey 560 1 Platform w/Handicap

Platform

2 Small and 2 Big Snow

Blowers, 1 Kubota

Calorite Welding Crew (6)

Needham DPW (617) 455-7550

Needham Junction

478 1 Platform w/Handicap

Platform

2 Small and 2 Big Snow

Blowers, 1 Kubota

Calorite Welding Crew (6)

Needham DPW (617) 455-7550

Needham

Center

409 1 Platform

w/Handicap Platform

2 Small and 2

Big Snow Blowers, 1

Kubota

Calorite Welding

Crew (6)

Needham DPW

(617) 455-7550

Needham

Heights

456 1 Platform

w/Handicap Platform

2 Small and 1 Big

Snow Blowers, 1 Sidewalk Tractor

(Located at Rosemary St.)

Calorite Welding

Crew (6)

Needham DPW

(617) 455-7550

NEWBURYPORT LINE

Page 45: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 43

Revision 1

STATION RIDER- SHIP

# OF PLATFORMS

PLATFORMS PARKING LOTS

EQUIPMENT LOCATED AT THE

STATION

MOBILE EQUIPMENT

SNOW REMOVAL CREW

EQUIPMENT/ MANAGEMENT

SNOW REMOVAL

CREW

Chelsea 275 2 Platforms 1 Kubota 2 Small Snow Blowers

B&B Mystic Crew (2) N/A N/A

Riverworks 51 GE GE GE

(617) 594-2591

Lynn 957 High-Level Island

Platform

1 John Deere Tractor, 2 Big and

3 Small Snow

Blowers

B&B Lynn Crew (3) Laz Parking Peter Furtado

(781) 443-3770

Swampscott 980 2 Platforms

w/ Handicap Platforms

2 Small and 1 Big

Snow Blowers

B&B Wilmington

Crew (3)

LAZ Parking

(781)794-1791

CJ

Mabardy-Dan

617-438-8439

Salem 2,199 1 Platform

w/Handicap Platform

1 Tractor, 1 Big

and 2 Small Snow Blowers

B&B Salem Crew

(3)

LAZ Parking

(781)794-1791

CJ

Mabardy-Dan

617-438-8439

Beverly 1,910 2 Platforms w/ Handicap

Platforms

1 Tractor, 2 Small Snow Blowers

B&B Lowell Crew (3)

Beverly Depot Restaurant (978) 927-5402

North Beverly

389 2 Platforms w/ Handicap

Platforms

1 Kubota, 2 Small and 1 Big Snow

Blowers

B&B Lowell Crew (3)

LAZ Parking (781)794-1791

CJ Mabardy-

Dan 617-438-

8439

Page 46: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 44

Revision 1

STATION RIDER- SHIP

# OF PLATFORMS

PLATFORMS PARKING LOTS

EQUIPMENT LOCATED AT THE

STATION

MOBILE EQUIPMENT

SNOW REMOVAL CREW

EQUIPMENT/ MANAGEMENT

SNOW REMOVAL

CREW

Hamilton Wenham

383 1 Platform w/Handicap

Platform

1 tractor and 2 snow blowers

2 Small and 2 Big Snow

Blowers

B&B Mystic Crew (2) LAZ Parking Peter Furtado

(781) 443-3770

Green+Gro

w Craig Green

978-361-634

Ipswich 529 1 Platform w/Handicap

Platform

1 Kubota, 2 Small and 2 Big Snow

Blowers

2 Small and 2 Big Snow

Blowers

B&B Mystic Crew (2) Ipswich DPW (978) 356-6612

Rowley 172 1 High-Level

Platform

2 Small and 2

Big Snow Blowers, 1

Kubota

Track Salem Crew

(7)

MBTA

Green+Gro

w Craig Green

978-361-634

Newburyport

745 1 High-Level Platform

2 Small and 2 Big Snow

Blowers, 1 Kubota

Track Salem Crew (7)

LAZ Parking Peter Furtado

(781) 443-3770

Green+Grow Craig

Green (978)361-

6340

Page 47: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 45

Revision 1

STATION RIDER- SHIP

# OF PLATFORMS

PLATFORMS PARKING LOTS

EQUIPMENT LOCATED AT THE

STATION

MOBILE EQUIPMENT

SNOW REMOVAL CREW

EQUIPMENT/ MANAGEMENT

SNOW REMOVAL

CREW

PLYMOUTH / KINGSTON LINE

South

Weymouth

728 1 High-Level

Platform

1 Gravely 1 Kubota (with

trailer), 1 Big and 2 Small

Snow Blowers

B&B Abington Crew

(4)

LAZ Parking

Seth Shurtleff (617)417-0170

Case Snow

Mgmt. Jason Case

508-509-5551

Abington 819 1 High-Level Platform

1 Gravely 1 Kubota (with trailer), 1 Big

and 2 Small Snow Blowers

B&B Abington Crew (4)

LAZ Parking Seth Shurtleff

(617)417-0170

Case Snow Mgmt.

Jason Case 508-509-

5551

Whitman 693 1 High-Level Platform

1 Gravely 1 Kubota (with trailer), 1 Big

and 2 Small Snow Blowers

B&B Abington Crew (4)

LAZ Parking Seth Shurtleff

(617)417-0170

Case Snow Mgmt.

Jason Case 508-509-

5551

Hanson 701 1 High-Level Platform

1 Gravely 1 Kubota (with trailer), 1 Big

and 2 Small Snow Blowers

B&B Abington Crew (4)

LAZ Parking Seth Shurtleff

(617)417-0170

Case Snow Mgmt.

Jason Case 508-509-

5551

Halifax 760 2 High-Level

Platform

1 Gravely 1 Kubota (with

trailer), 1 Big and 2 Small

Snow Blowers

B&B Abington Crew

(4)

LAZ Parking

Seth Shurtleff (617)417-0170

Case Snow

Mgmt. Jason Case

508-509-

5551

Plymouth 119 1 High-Level

Platform

1 Gravely 1 Kubota (with

trailer), 1 Big and 2 Small

Snow Blowers

B&B Kingston Crew

(4)

LAZ Parking

Seth Shurtleff (617)417-0170

Case Snow

Mgmt. Jason Case

508-509-5551

Page 48: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 46

Revision 1

STATION RIDER- SHIP

# OF PLATFORMS

PLATFORMS PARKING LOTS

EQUIPMENT LOCATED AT THE

STATION

MOBILE EQUIPMENT

SNOW REMOVAL CREW

EQUIPMENT/ MANAGEMENT

SNOW REMOVAL

CREW

Kingston 1,165 1 High-Level Platform

1 Gravely 1 Kubota (with trailer), 1 Big

and 2 Small Snow Blowers

B&B Kingston Crew (4)

LAZ Parking Seth Shurtleff

(617)417-0170

Case Snow Mgmt.

Jason Case 508-509-

5551

ROCKPORT LINE

Monserratt 389 2 Platforms

w/Handicap Platform

2 Small and 2

Big Snow Blowers, 1

Kubota

Track Salem Crew

(7)

MBTA

CJ Mabardy

Prides

Crossing

29 1 Platform 2 Small and 2

Big Snow

Blowers, 1 Kubota

Track Salem Crew

(7)

Private

Beverly Farms

145 2 Platforms w/Handicap

Platform

2 Small and 2 Big Snow

Blowers, 1 Kubota

Track Salem Crew (7)

711/SL 34 Track

Manchester 515 2 Platforms

w/Handicap Platform

1 Kubota 2 Small and 2

Big Snow Blowers

Track Salem Crew

(7)

Cape Anne RTA

(978) 283-7916

West Gloucester

130 2 Platforms w/Handicap

Platform

2 Small and 2 Big Snow

Blowers, 1 Kubota

Track Salem Crew (7)

MBTA CJ Mabardy

Gloucester 491 1 Platform

w/Handicap Platform

1 Kubota 2 Small and 2

Big Snow Blowers

Track Salem Crew

(7)

MBTA

CJ Mabardy

Page 49: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 47

Revision 1

STATION RIDER- SHIP

# OF PLATFORMS

PLATFORMS PARKING LOTS

EQUIPMENT LOCATED AT THE

STATION

MOBILE EQUIPMENT

SNOW REMOVAL CREW

EQUIPMENT/ MANAGEMENT

SNOW REMOVAL

CREW

Rockport 423 1 Platform 2 Small and 2 Big Snow

Blowers, 1 Kubota

Track Salem Crew (7)

Cape Anne RTA (978) 283-7916

STOUGHTON LINE

Canton Center

1,272 1 Platform w/Handicap

Platform

2 Small and 2 Big Snow Blowers, 1

Sidewalk Tractor

Readville Track Welding Crew (2)

LAZ Parking (781) 794-

1791

MBTA Case Snow

Mgmt. Jason Case

508-509-5551

Stoughton 1,865 1 Platform

w/Handicap Platform

2 Small and 2

Big Snow Blowers, 1

Sidewalk Tractor

Readville Track

Welding Crew (2)

LAZ Parking

(781) 794-1791

MBTA

Case Snow Mgmt.

Jason Case 508-509-

5551

PEDESTRIAN WALKWAYS (FAIRMOUNT LINE)

Bird Street Readville Track

Maintenance Crew (4)

N/A N/A

Park Street Readville Track Maintenance Crew

(4)

N/A N/A

Jones Ave. Readville Track Maintenance Crew

(4)

N/A N/A

Greenwood

Ave.

Readville Track

Maintenance Crew (4)

N/A N/A

EMERGENCY ESCAPE HATCHES AND EMERGENCY EXITS FROM TUNNELS

Page 50: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 48

Revision 1

STATION RIDER- SHIP

# OF PLATFORMS

PLATFORMS PARKING LOTS

EQUIPMENT LOCATED AT THE

STATION

MOBILE EQUIPMENT

SNOW REMOVAL CREW

EQUIPMENT/ MANAGEMENT

SNOW REMOVAL

CREW

Location Type Description Snow Removal Crew

Greenbush Tunnel 1 Doorway Doorway at street level B&B Greenbush Crew

Back Bay Tunnel 1 Doorway Doorway into Copley Plaza N/A-Exits into Copley Plaza

Salem Tunnel 1 Escape Hatch

Escape hatch through pump house, opens into the parking lot.

B&B Salem Crew

STANDPIPES

Location Description Snow Removal Crew

South Station Fire Dept. connection is on Atlantic Ave B&B South Station Crew

Back Bay–Tracks 5&7 Fire Dept. connection is on Clarendon St. B&B South Station Crew

Back Bay–Tracks 1,2&3 Fire Dept. connection is on Columbus Ave. B&B South Station Crew

Ruggles Station Fire Dept. connections on Ruggles St. and in the busway. B&B South Station Crew

Forest Hills Station Fire Dept. connection is busway on Washington St. B&B Readville Crew

CONTRACTORS

KCS currently is waiting for bids for snow removal. Once contractors have been identified the plan will be updated to identify the contractors and their responsibilities.

Page 51: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 49

Revision 1

LOCATION SWITCH CLEANING CREW ROADWAYS

CREW EQUIPMENT

LA

YO

VER

S

Bradford Rosemont I&R (2) Rosemont Track Crew (1) Bradford Swing Loader

Fitchburg Fitchburg Greaser (2) Fitchburg Track Crew (1) Fitchburg Swing Loader

Franklin Franklin I&R (2) Readville Track Crew (1) Franklin Swing Loader

Scituate Braintree I&R (2) B&B Greenbush Crew (1) Crew truck with plow

Kingston Kingston I&R (2) Kingston Track Crew (1) Dump truck

Middleboro Middleboro I&R (2) Middleboro Track Crew (1) Track Speed Swing

Needham Franklin I&R (2) Readville Track Crew (1) Track Plow Truck

Newburyport Newburyport I&R (2) Mystic B&B Crew (1) B&B Plow Truck

Pawtucket Readville I&R (2) Readville B&B Crew (1) B&B Dump Truck

Rockport Newburyport I&R (2) Mystic B&B Crew (1) B&B Plow Truck

Worcester Worcester I&R (2) Contractor Contractor

Cobble Hill/CRMF

Roadways

N/A T-Pad Track Crew (1) T-Pad Kawasaki

Page 52: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 50

Revision 1

14. CRITICAL SWITCH SNOW REMOVAL ASSIGNMENTS

ROUTE LOCATION RESPONSIBILITY PHONE FIRST

TRAIN

Providence Line

Pawtucket Layover Track-Readville I&R 617-222-8640 5:07AM

Fitchburg Line

South Acton Track-Concord I&R 617-222-3625 5:51AM

Willows Track-Fitchburg I&R 617-222-3625 5:34AM

Fitchburg Layover Track-Fitchburg Greaser 617-222-3625 5:15AM

Franklin Line

Franklin Layover Track-Franklin I&R 617-222-8640 5:05AM

Readville Maintenance Facility

Track and B&B 617-222-3690 5:45AM

Gloucester Line

Rockport Layover Track-Newburyport I&R 617-590-9852 5:05AM

Wilson’s Spring Switch Track-Newburyport I&R 617-590-9852 8:36AM

Greenbush Line

Scituate Layover Track-Braintree I&R 617-222-8640 5:40AM

Haverhill Line

Ash Street Spring

Switch

Track-Wilmington Maint.

Crew

617-222-3628 7:44AM

Wilmington Junction Track-Wilmington Maint.

Crew

617-222-8450 7:12AM

Bradford Layover Track-Rosemont I&R 617-222-3628 5:05AM

Lowell Junction Track-Rosemont I&R 617-222-3628 5:30AM

Andover Street Track-Rosemont I&R 617-222-3628 5:19AM

Lowell Line

Bleachery Track-Lowell I&R 617-222-3625 5:35AM

Kingston Line

Kingston Layover Track-Kingston I&R 617-222-8640 5:32AM

Middleboro Line

Middleboro Layover Track-Middleboro I&R 617-222-8640 5:10AM

Page 53: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 51

Revision 1

ROUTE LOCATION RESPONSIBILITY PHONE FIRST

TRAIN

Needham Line

Needham Layover Track-Calorite Welding Crew

617-222-8640 6:10AM

Newburyport Line

Newburyport Layover Track-Newburyport I&R 617-590-9852 5:22AM

Bagley Track-Newburyport I&R 617-590-9852 5:29AM

North Station

Tower A KCS 617-222-8450 24/7

Boston Eng. Terminal Eng. Facilities/Track 617-222-6328 24/7

South Station

Tower 1 Amtrak 617-345-7903 24/7

Southampton Street

Yard Mechanical Dept. 617-222-5347 6:28AM

Stoughton Line

Stoughton Runaround Track Readville Track

Welding Crew

617-222-8640 6:28AM

Worcester Line

CP 3 Track-Framingham Track

Crew

617-222-3625

CP 4 Track-Framingham Track

Crew

617-222-3625

CP 11 Track-Framingham Track

Crew

617-222-3625

CP 21 Track-Framingham I&R 617-222-3625

CP 22 Track-Framingham I&R 617-222-3625

CP 23 Track-Framingham I&R 617-222-3625

CP 29 Track-Worcester Welders 617-222-3625

CP 30 Track-Worcester Welders 617-222-3625

CP 42 Track-Worcester I&R 617-222-3625

CP 43 Track-Worcester I&R 617-222-3625

Worcester Layover Track-Worcester I&R 617-222-3625 4:45AM

Page 54: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 52

Revision 1

15. KCS SNOW REMOVAL EQUIPMENT*

Equipment # Description Headquarters

“T”# KCS #

T40104 A47942 Swing Loader with Snowplow Salem

T40106 A47945 Swing Loader with Snowplow Bradford

T40102 A47940 Swing Loader with Snow Bucket Readville

T40103 A47941 Swing Loader with Snow Bucket Tie Job

T40109 A47839 Swing Loader with Snow Bucket Abington

T40107 A47946 Swing Loader with Snowplow Franklin

T40101 A47939 Swing Loader with Snow Bucket Braintree

T47948 A47948 Swing Loader with Snow Bucket Wilmington

T41601 A47203 Terex Loader with 3.5 cu yd. Bucket Readville

T41602 A47634 Caterpillar Loader with Plow & 3.5 Bucket Mystic

T41603 A47113 TCM Bucket Loader with 4 cu yd. Bucket Boston

T48750 A48750 Case Backhoe Wilmington

T48738 A48738 Case Backhoe West Concord

T48715 A48715 Case Backhoe Mystic

T40108 A47644 John Deere Loader Pawtucket

T41604 A41604 Kawasaki Loader with 4 Yard Bucket Readville

T41605 A41605 Kawasaki Loader with 4 Yard Bucket Fitchburg

T41606 A41606 Kawasaki Loader with 4 Yard Bucket Forge Park

T41607 A41607 Kawasaki Loader with 4 Yard Bucket T-Pad

No T# AA53834 Pickup Truck with plow Somerville

No T# AA30028 Pickup Truck with plow Readville

No T# AA30029 Pickup Truck with plow Readville

No T# AA30030 Pick up Truck with plow Somerville

No T# AA69637 Pick up Truck with plow Mystic

No T# AA00009 Pick up Truck with plow Readville

No T# AA00026 Pickup Truck with plow Somerville

No T# AA00026 Pickup Truck with plow Readville

No T# AB00024 Small Dump Truck with plow & sander Readville

No T# AG22025 Small Dump Truck with plow & sander Readville

Page 55: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 53

Revision 1

Equipment # Description Headquarters

“T”# KCS #

No T# AG30092 Small Dump Truck with plow & sander Readville

No T# AG24296 Small Dump Truck with plow & sander Readville

No T# AG24398 Small Dump Truck with plow & sander Somerville

No T# AG24399 Small Dump Truck with plow & sander Readville

No T# AA0019 Large Dump Truck with plow & sander Mystic

No T# AA00020 Large Dump Truck with plow & sander Readville

No T# AA00022 Large Dump Truck with plow & sander Readville

No T# AA00023 Large Dump Truck with plow & sander Readville

No T# AN69640 Rack Truck with plow & sander Mystic

No T# AG39476 Large Dump Truck with plow & sander Readville

No T# AE23170 Large Dump Truck with plow & sander Somerville

No T# AG28531 Large Dump Truck with plow & sander Readville

No T# AG28532 Large Dump Truck with plow & sander Readville

No T# AG28711 Large Dump Truck with plow & sander Somerville

No T# AG37486 Large Dump Truck with plow & sander Somerville

No T# AG28710 Large Dump Truck with plow & sander Mystic

No T# AA23170 Large Dump Truck with plow & sander Somerville

*Subject to change.

Page 56: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 54

Revision 1

16. SWITCH HEATERS

Location Type

# of

Switches Control

Providence Line

South Station Electric Amtrak Shoreline Disp.

Cove Electric Amtrak Shoreline Disp.

Plains Electric Amtrak Shoreline Disp.

Forest Electric Amtrak Shoreline Disp.

Read Electric Amtrak Shoreline Disp.

Transfer Electric Amtrak Shoreline Disp.

Junction Electric Amtrak Shoreline Disp.

Mansfield Electric Amtrak Shoreline Disp.

Holden Electric Amtrak Shoreline Disp.

Boro Electric Amtrak Shoreline Disp.

Hebronville Electric Amtrak Shoreline Disp.

Orms Electric Amtrak Shoreline Disp.

Pawtucket Electric 10 Manual

Boston Area

Yard 5 CRMF Electric 52 Tower H

+ = #1 Switch Must be Kept Clean at All Times.

Zone 1 Electric 5 Terminal Dispatcher

Tower A City Gas 32 Track/Pipers

Swift Int. Electric 6 Terminal Dispatcher

Fairmount Line

South Bay Interlocking Electric Amtrak

Dana Electric 4 Dispatcher

Hill[1] Electric 5 Dispatcher

#2 Yard Electric 16 Manual

Fitchburg Line

West Cambridge 5 CROCC

Hill Crossing Electric 3 CROCC

Clematis Brook Electric 1 CROCC

Beaver Brook Electric 1 CROCC

Waltham Electric 1 CROCC

Hastings Electric

4-(2

Heaters) CROCC

S. Acton Electric 2 CROCC

Tenney Electric 4 CROCC

Willows to CPFWL Electric 5 Dist. 3 Train Disp.

CPFAY Electric 6 Dist. 3 Train Disp.

CPFFG Electric 7 Dist. 3 Train Disp.

Page 57: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 55

Revision 1

Location Type

# of

Switches Control

Gallagher Electric 1 Dist. 3 Train Disp.

Layover Facility Electric 4 Manual

Franklin Line

Sprague Street Electric 2 Dispatcher

Norwood Central Electric 1 Dispatcher

Walpole Electric 3 Dispatcher

Walpole West Electric 1 Dispatcher

Franklin Layover East Electric 1 Dispatcher

Franklin Layover Int. Electric 2 Dispatcher

Franklin/Industrial Electric 1 Manual

Gloucester Line

Wilson Electric 1 Boston East

Rockport Electric 4 Snow Sensor

Greenbush Line

Adams Junction 1 Old Colony Train Disp.

Shipyard 3 Old Colony Train Disp.

Allen 1 Old Colony Train Disp.

East Weymouth 1 Old Colony Train Disp.

Herring 1 Old Colony Train Disp.

Fort 1 Old Colony Train Disp.

Blackrock 1 Old Colony Train Disp.

Circus 1 Old Colony Train Disp.

Parish 1 Old Colony Train Disp.

Davis 2 Old Colony Train Disp.

Scituate Layover 4 Track Foremen

Haverhill Line

FX Electric 1 Snow Sensor

Foley Street Electric 5 Terminal Dispatcher

Power Switch #669

Clean by

Hand

Reading Junction Electric 3 Terminal Dispatcher

Fells

Electric/

Manual 1 Terminal Dispatcher

Ash Street Electric 1 Snow Sensor

Wilmington Junction Electric 1 GTI Dist. 2 Train Disp.

Lowell Junction Electric 1 GTI Dist. 2 Train Disp.

Frye Int. Electric 2 GTI Dist. 2 Train Disp.

Andover St. Int. Electric 2 GTI Dist. 2 Train Disp.

Frost Electric 5 GTI Dist. 2 Train Disp.

Bradford Electric 4 GTI Dist. 2 Train Disp.

Page 58: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 56

Revision 1

Location Type

# of

Switches Control

Hall Electric 4 GTI Dist. 2 Train Disp.

Rosemont Electric 2 GTI Dist. 2 Train Disp.

Lowell Line

Somerville Junction Electric 5 Boston West

Winchester Electric 5 Boston West

Cawford Electric 3 Boston West

Wilbur Electric 4 Boston West

Wilmington Electric 5 Boston West

Shop Electric 6 Boston West

Bleachery 119 Electric 2 GTI Dist. 2 Train Disp.

Bleachery 123 Electric 2 GTI Dist. 2 Train Disp.

Bleachery 129 Electric 2 GTI Dist. 2 Train Disp.

Bleachery 149 Electric 2 GTI Dist. 2 Train Disp.

Bleachery 143 Electric 2 GTI Dist. 2 Train Disp.

Bleachery Clean by Hand

Middleboro Line

Fly Electric 2 Old Colony Train Disp.

Vic Electric 1 Old Colony Train Disp.

Squant Electric 1 Old Colony Train Disp.

Green Electric 2 Old Colony Train Disp.

Gross Electric 1 Old Colony Train Disp.

Pearl Electric 4 Old Colony Train Disp.

Hol Electric 1 Old Colony Train Disp.

Rand Electric 1 Old Colony Train Disp.

Howard Electric 1 Old Colony Train Disp.

Grove Electric 1 Old Colony Train Disp.

West Dale Electric 1 Old Colony Train Disp.

Stanley Electric 1 Old Colony Train Disp.

Mid Electric 1 Old Colony Train Disp.

Pilgrim Electric 1 Old Colony Train Disp.

Middleboro Layover Electric 8 Track Foreman

Needham Line

Dale Interlocking Electric 1 Dispatcher

Rox Interlocking Electric 1 Dispatcher

Baker Interlocking Electric 1 Dispatcher

Warren Interlocking Electric 1 Dispatcher

Need Interlocking Electric 1 Dispatcher

Heights Electric 1 Dispatcher

Layover Facility Electric 3 Dispatcher

Page 59: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 57

Revision 1

Location Type

# of

Switches Control

Newburyport Line

Everett Junction Electric/ Manual 6 Boston East

Wonderland Electric 4 Boston East

Brick Yard Electric 4 Boston East

Castle Hill Electric 5 Boston East

McNall Electric 1 Boston East

Northey Pt. Electric 2 Boston East

Beverly Junction Electric 6 Boston East

Chesley Electric 1 Boston East

Ipswich West Electric 1 Boston East

Bagley Electric 1 Boston East

Knight Interlocking Electric 1 Boston East

Port Interlocking Electric 4 Boston East

Newburyport Layover Electric 4 Boston East

Plymouth Line

Swey Electric 1 Old Colony Train Disp.

Abby Electric 5 Old Colony Train Disp.

Golf Electric 1 Old Colony Train Disp.

Bryant Electric 1 Old Colony Train Disp.

Burrage Electric 1 Old Colony Train Disp.

Oak Electric 1 Old Colony Train Disp.

Seaside Electric 2 Old Colony Train Disp.

Gravel Electric 1 Old Colony Train Disp.

Kingston Layover Electric 5 Track Dept.

Worcester Line

CP 3 Electric 5 Worcester Train Disp.

CP 4 Electric 6 Worcester Train Disp.

CP 11 Electric 4 Worcester Train Disp.

CP 21 Electric 6 Worcester Train Disp.

CP 22 Electric 7 Worcester Train Disp.

CP 23 Electric 2 Worcester Train Disp.

CP 24 Electric 4 Worcester Train Disp.

CP 28 Electric 4 Worcester Train Disp.

CP 29 Electric Worcester Train Disp.

CP 30 Electric Worcester Train Disp.

CP 33 Electric 4 Worcester Train Disp.

CP 39 Electric 2 Worcester Train Disp.

CP 42 Electric 1 Worcester Train Disp.

Page 60: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 58

Revision 1

Location Type

# of

Switches Control

CP 43 Electric 3 Worcester Train Disp.

CP 44 Manual 3 Track Dept.

[1] Straight rail toward Readville upper level station.

Page 61: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 59

Revision 1

17. GAS SWITCH HEATERS

16.1 PROCEDURE FOR ACTIVATING GAS SWITCH HEATERS IN BOSTON

TERMINAL When weather conditions result in a request to the Radio Room for the Gas Switch

Heaters to be activated, the following procedure is to be followed: 1) The Radio Room ((617) 222-3628) will call the piper designated by Bridge & Building

supervision to open the gas valve in the Gas Meter House. The Valve (the only one) is located in the southeast (front left as you face the

entry door) corner of the Gas House. Check the gas meter for gas flow and the gas regulator to ensure proper gas pressure is being maintained.

2) The pipers will first open the Gas Valves and then start lighting the individual gas switch heaters by turning on the individual Switch Heater Valves. During the storm

the pipers will operate the switch heaters and ensure they are operating throughout the storm.

3) When gas for the switch heaters is no longer needed, the radio room ((617) 222-

3628) will notify the designated piper who will shut down the switches. When all gas valves are shut, the designated PIPER will:

Check the Gas Meter to verify there is no flow of gas. Report to the Radio Room ((617) 222-3628) that the Gas Main Valve, he is

responsible that it is shut and that there is no gas flow through the Gas Meter.

16.2 INSTRUCTIONS FOR OPERATIONS OF GAS SWITCH HEATERS 1) Make sure all valves at burners are off.

2) Turn on main gas valve to field, which is located in the Gas House (See 1 above). 3) Go to each burner, turn on valve and wait about one minute for air to blow off line

or until the smell of gas is noticed whichever occurs first. Then light the burner. Always start at the heater nearest the Gas House and work further away all the

time. 4) When the plant is to be shut down, always turn off valve at each heater, then the

main valves. This is most important from a safety standpoint.

NO SMOKING OR OPEN LIGHTS IN THE GASHOUSE OR WITHIN FENCE

LIMITS OF A PROPANE TANK

16.3 LOG BOOK

The Bridge & Building Department (Structures) will install a LOG BOOK in the Gas Meter House. The designated PIPER will make an entry in the LOG BOOK indicating

the date and time of day that the Gas Valve in the meter house is opened or closed and meter reading at valve opening and valve closing. Also a notation is to be made

in the LOG BOOK of any deviation from normal operation of the Gas system.

16.4 LIGHTING TOWER A GAS FIRED HOT AIR BLOWERS 1) Ensure the main gas supply is turned on.

Page 62: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 60

Revision 1

2) Turn on the power to the hot air blowers. The power panel is located behind the

old compressor house at Tower A. 3) A green indicator light is dedicated to each heater. Confirm all green indicator

lights are illuminated. Failure of a green light to illuminate is an indication of a heater problem.

4) A yellow beacon is mounted on the outside of the main panel; illumination of this beacon indicates a problem with one of the heaters. A yellow light inside the

panel will identify the specific heater that has a problem.

Page 63: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 61

Revision 1

Winter Zone

At least 3 fully accessible cars

SNOW REMOVAL STRATEGY

Keolis is proposing the following methodology for snow removal contractual compliance. The stations have been prioritized based on 2 criteria, ridership and handicap accessibility. Stations are divided into 3

categories and snow removal procedures will vary based on these categories.

Level 1 is North and South Station, level 2 are the stations with 80% of the ridership for that side and level 3 are stations outside of the top 80% of ridership and are not handicap accessible.

Snow removal procedures at these stations will be the following:

Level 1 - dedicated crews.

Level 2 – entire platform will be cleared.

Level 3 – Winter waiting zones designated.

The Winter Waiting Zones will be designated by signage on the platform and will be coordinated with

Transportation to ensure that at a minimum of 3 coaches can stop in the zone and all access points from

parking lots will be cleared.

Page 64: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 62

Revision 1

18. MBTA ORGANIZATION

NAME TITLE OFFICE # HOME # CELL#

Kesler, Brad Senior Director of Railroad and Water Transportation

617-222-6536

Sekkat,

Mohammed

Director of Engineering

Maintenance/C=S

617-222-6176

Adkins, Steve Director of Mechanical 617-222-3434 617-680-2253

Jones, Steve Director of Railroad Operations-

Transportation/Customer Suc+Water Transp.

617-222-6400 781-662-5407 617-293-8058

Lannin, Marialaina Deputy Director of Railroad

Operations/Finance

617-222-6695

Aubuchon, Ken Section Chief mechanical 617-222-6356 978-537-3702 617-756-5893

Carrega, John Mechanical Assistant Director 617-222-6303 508-541-8925 617-835-1374

Carroll, Paul Section Chief Transportation 617-222-6536 978-458-2265 617-594-1980

Dias, Craig 617-222-6740 781-378-2106 617-293-9372

Duncan, Jim Engineering Officer-Structures 617-222-4465 781-245-6128 617-590-9821

Foster, Tom Trans. & Customer Service Mgr. 617-222-6586 617-480-4704 617-293-9127

Gallery, Jody Customer Service Officer 617-222-3441 617-512-3621

Helmar, Tilli Secretary 617-222-6178

Lally, Bill Deputy Section Chief Engineering 617-222-5439 617-594-0163

Tavernier, Edmund Section Chief Engineering 617-222-6176 617-828-6037

Vieira, Manuel Supervisor Construction Engineering & F/A 617-222-4467 978-532-1091 617-293-9435

Walsh, John Supervisor System Services Maint. 617-222-3442 781-848-5826 617-293-9106

Harper, Robin Construction Inspector 617-222-6312 781-231-5702 617-308-5009

Arnold, Rich Sr. Tech Project Manager-Engineering 617-222-3635 781-878-2231 617-594-0120

Manny Vieria Program Coordinator

Royston, Karen Admin. Assistance-Mechanical 617-222-6305

Howard, Robin Executive Assistant 617-222-4328

Harris, Hortense Admin. Assistant-Transportation 617-222-4771

Kaluski, Kamil Sr. Tech Project Mgr.-Mechanical 617-222-6333 617-959-6699 617-959-6699

Sheehan, Mark Mechanical Officer 617-222-6676 617-548-2480

Strahiloy, Sven Rolling Stock Maintenance Officer 617-222-3685 781-325-3086 617-596-0169

Page 65: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 63

Revision 1

19. KCS ORGANIZATION

NAME TITLE OFFICE # HOME # PAGER CELL#

Mulligan Tom General Manager

Francis Gerald Deputy General Manager

18.1 TRANSPORTATION DEPARTMENT

NAME TITLE OFFICE # HOME # PAGER CELL#

Treece Scott Chief Transportation Officer

Kennon Foster Deputy Chief Transportation Officer

617-222-8019 508-510-5176 617-963-6886

CETC A Desk Dispatcher Transfer to

Providence

617-222-8106

CETC Terminal Dispatcher-Amtrak 617-345-7565

CETC Trouble Desk-Amtrak 617-345-7572

CETC KCS Trouble Desk 617-222-3628

CETC Chief Train Dispatcher-Amtrak 617-345-7569/ 7570

CETC/KCS Chief Train Dispatcher - KCS 617-222-8100

CETC Southwest Corridor Dispatcher Cove to Transfer (Midland)-

Amtrak

617-345-7561

Train Disp. Dorchester-Amtrak 617-345-7492

Train Disp. Corridor-Amtrak 617-345-7561

Train Disp. Main Line-Amtrak 617-345-7562

Train Disp. KCS Branch Line 617-222-8106

Train Disp. KCS Old Colony 617-222-8105

Train Disp. South Bay-Amtrak 617-345-7908

CETC/KCS KCS Assistant Chief 617-222-8101

CETC/KCS KCS Assistant Chief 617-222-8102

Crew Disp. 617-222-2019

Page 66: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 64

Revision 1

NAME TITLE OFFICE # HOME # PAGER CELL#

Crew Disp. 617-222-2020

Crew Disp. WATTS Line (In MASS.) 800-589-2808

Crew Disp. WATTS Line (Out of MASS.) 888-824-3511

Fax Machine Crew Dispatchers 617-222-2022

Crew Room North Station 617-222-3676

North Station Operations Control

Center

North Station 617-222-3656

North Side 617-222-6114 617-473-1095 617-293-9088

CROCC Boston East Dispatcher 617-222-6109/

6110

CROCC Boston West Dispatcher 617-222-6111/ 6112

CROCC Fax Machine 617-723-3382

CROCC Terminal Dispatcher 617-222-6113

Information Booth North Station 617-222-3600/

3674

Information Desk South Station 617-222-8126

Lost and Found North Station 617-222-3600

Lost and Found South Station 617-222-8120

Tower “A” Operator 617-222-5686/

5978

Tower “H” Operator 617-222-6334

Trainmen’s Room CRMF 617-222-3056

Trainmen’s Room North Washington St. – North Side

617-222-3676

Almeder, John Trainmaster 617-222-8114 617-473-6619 617-438-2673

Allen, Felicia Director Manpower Utilization 617-222-8462 781-599-2988 617-473-1167 617-293-9098

Beauregard, Mark Chief Train Dispatcher-North 617-222-6114 617-905-6441

Page 67: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 65

Revision 1

NAME TITLE OFFICE # HOME # PAGER CELL#

Drumheller, Dennis

Road Foreman – North Station 617-222-3659 617-473-5940 617-293-9090

Dupes, Jamie Trainmaster – North Station 603-817-1399

Huggan, Robert Field Superintendent - South 617-222-8115 617-473-1523 617-293-9092

Kadlick, Kevin Director of Conductor Certification

617-222-8112 617-327-3075 617-473-1740 617-293-9091

Langley, Denise Trainmaster - North 617-590-9315

Le, Lisa Trainmaster - North 617-222-3656 617-359-1643

Kerry Woods Trainmaster/Road Foreman - South

617-304-2987

McGuire, Jean Trainmaster 617-222-8116 617-473-6470 617-438-7484

McLaughlin, William

Road Foreman – South 617-501-4339

Murphy, Richard P.

Chief Train Dispatcher-South 617-222-8100 781-356-2766 617-473-2083 617-590-8376

Neverett, Mark Senior Road Foreman 617-222-3654 617-473-2099 617-293-9093

O’Neal, William Terminal Superintendent-South 617-222-8110 617-293-3231

Patriacca, Mark Road Foreman-South Station 617-222-8118 617-964-3533 617-473-3861 617-293-9163

Rae, William C. Field Trainmaster-South 617-222-8110 617-269-4404 617-473-3717 617-293-9087

Reade, Ronald Road Foreman - North 508-816-2246

Reardon, Edward Lead Trainmaster-North 617-222-3685 617-473-6883 617-201-9372

Rossi, John Trainmaster-South 617-222-8116 617-560-4566 617-799-7824

Santamaria, John Field Superintendent - North 617-222-3650 617-245-9502 617-473-0102 617-293-9085

Silver, Juanetta Trainmaster – South Station 617-222-8115 781-961-3444 617-473-1595 617-293-9096

Vedder, Patrick Field Trainmaster - South 617-222-8115 617-596-1285

Page 68: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 66

Revision 1

18.2 CUSTOMER SERVICE DEPARTMENT

NAME TITLE OFFICE # HOME # PAGER CELL #

Coatanea, Ronan 617-222-8081

Dillon, Linda Deputy Chief of Customer Service

617-222-8066 617-473-3558 617-293-8598

White Jonathan Mgr. Operational Planning 617-473-7221 617-473-3562 617-293-9095

Vargas, Nadia Sr. Customer Service Adm. 617-222-8086 617-473-9764 617-908-0467

McDonough,

Kaitlyn

Customer Service Adm. 617-222-8084 617-473-3763 617-438-4324

Addonizio, Frank Customer Service Delivery

Mgr. North

617-222-3675 617-215-0716 781-438-9187

Santini, Lauren Customer Service Adm. 617-222-8083

Information

Booth

North Station 617-222-

3600/ 3674

Information Desk South Station 617-222-8126

Lost and Found North Station 617-222-3600

Lost and Found South Station 617-222-8120

18.3 SAFETY DEPARTMENT

NAME TITLE OFFICE # HOME # PAGER CELL #

Vonashek Justin Safety and Security Officer 617-222-8360 617-293-9088

Kaufman, Tracey Manager of Safety 617-222-8020

Machado, Manny Safety Advisor 617-222-8373

Mimms, Jack Safety Advisor 617-222-8366

Page 69: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 67

Revision 1

18.4 ENGINEERING DEPARTMENT

NAME TITLE OFFICE # HOME # CELL #

Baran, Pascal Chief Engineering Officer 617-222- 857-208-6363

Agnello, David Deputy Chief Engineering Officer

Mitchell, John ACEO – Com & Signal 617-222-3613 781-438-1978 617-590-9838

Callahan, John ACEO – Facilities 617-222-8255 603-929-0403 617-590-9815

Mallon, Patty ACEO – Bridges & Buildings 617-222-3617 978-658-4952 617-590-9828

Regan, Annmarie ACEO - Force Account 617-222-3620 617-438-7145

Trouble Desk Radio Room 617-222-3628

Mystic Junction Electricians Shop 617-222-3121

Readville Structures Garage 617-222-5338

Materials, Yard T-Pad 617-222-5340

Work Equipment Readville Shop 617-222-5430

Relay Shop 617-222-8420 617-222-6189

Allen, Ron Roadmaster Track South 617-777-5900

Berry, Robert Senior Engineer Signal Design 617-222-8412 978-957-3114 617-590-9808

Brady, Jim Construction Inspector 617-590-9844

Brown, Mike Mgr. of Materials Distribution 617-222-3609

Campione, Steve Sr. Engineer Electrical 617-222-3624 978-597-3062 617-590-9816

Collins, Ralph Sr. Eng.-Comm. 617-222-8483 617-590-9810

Coughlan, Dan Electronic Shop 617-222-6190

Desmond, John Sr. Eng. Work Equipment 617-222-4484 978-774-6656 617-590-9819

Doe, Rob Roadmaster-S&I 617-222-4657 617-438-4115

Donati, Elmer Roadmaster Track - Old Colony 617-222-8640 617-590-9820

Ferraro, James Roadmaster Track - West 617-222-8450 413-245-7339 617-438-9853

Foley, Bill Work Equipment Foreman 617-222-4496 508-226-5584

Ford, Thomas Senior Engineer – Facilities 617-222-6328 617-327-5634 617-590-9809

Howland, James Senior Engineer Track - North 617-222-3625 978-658-7369 617-590-9826

Jalbert, John Roadmaster Electrical 617-222-3624 617-756-8961

Keenan, Peter Bridge Inspector - North 617-596-0042

Page 70: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 68

Revision 1

NAME TITLE OFFICE # HOME # CELL #

Leblanc, Gene Bridge Inspector - Worcester

Lestan, Steve Roadmaster C&S – South 508-223-9194 617-293-9460

Marshall, Rich Roadmaster B&B – South 617-222-8641 401-722-2112 617-438-3230

McCabe, John Roadmaster Signal Construction 617-222-8422 781-935-8690 617-590-9832

McCabe, Joseph Roadmaster C&S - Old Colony 617-222-3063 781-545-7923 617-590-9831

McGuire, Dale Roadmaster B&B – North 617-222-3616 508-252-9296 617-293-1453

McNall, Daniel Sr. Eng. Signal Construction 617-222-8421 978-658-7688 617-590-9833

Neves, Joe Roadmaster Track - North 617-222-8450 978-532-4991 617-590-9817

Pigsley, John Roadmaster Facilities 617-222-6329 978-406-2408

O’Connell, Ed Sr. Engineer Control Systems 617-222-3618 781-231-0649 617-590-9858

Palazzolo, Marty Senior Engineer C&S – South 617-222-5789 781-681-9255 617-590-8565

Pelletier, Steve Roadmaster C&S – West 508-517-4969 617-293-9489

Rodricks, Dana Senior Engineer Track – South 617-222-5573 978-459-4335 617-590-9851

Routhier, Joseph Roadmaster C&S – North 617-222-3350 978-685-1204 617-590-9855

Sartori, Rich Roadmaster B&B – North 617-222-6329 617-438-7844

Smith, Owen Roadmaster Track - Production 617-222-8450

Wallis, Bob Roadmaster Comm.-North 617-222-8483 617-594-0885

Ward, Christopher Bridge Inspector B&B - South 617-222-8141 781-837-8188 617-590-9864

Welch, James Construction Inspector 617-438-2899

West, David Engineer Track 617-222-3615 781-246-4927 617-590-9865

Weldon, Derek Senior Engineer Signal 617-222-8145 617-590-8579

Wesson, Greg Roadmaster-Comm.

18.5 CROSSING TENDERS

Location Phone Number Hours of Operation

Forest Street, Wakefield 781-246-2811 M-F 6AM-12:30AM / Sat. & Sun. 7:45AM-12AM

High Street, West Medford 781-483-3720 All days 7AM-2AM

Cabot Street, Beverly 978-927-8810 M-F 6AM-11:50PM / Sat.6:30AM-11:50PM / Sun.

9AM-11:50PM

Page 71: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 69

Revision 1

18.6 MECHANICAL DEPARTMENT

NAME TITLE OFFICE # HOME # PAGER # CELL #

McCall, Bernie Chief Mechanical Officer 617-222-3680 518-368-3134

Allen, Mark Asst. Supt. S&I Southampton 617-222-3679 617-472-0204 617-293-9051

Belcaid, Khalil Electrical Engineer 617-222-6105 781-286-4287 617-590-9276

Blackburn, Cheryl Chief Clerk 617-222-6672

Casserly, Pat Force Account Manager 617-222-6478 781-585-4393 617-293-3270

Clough, David Manager Special Projects 617-222-6671 617-484-1684 617-473-3990 781-727-7148

Crowell, Richard Manager Vehicle Projects 617-222-6355 617-484-2091 617-799-7531

Cunningham, Paul Asst. Supt Coach Shop, Rdv 617-222-8603 781-461-1297 617-473-4282 617-293-1381

Fadden, David Asst. Supt. S&I, North 617-222-1770 603-434-4246 617-473-3432 617-594-7327

Flaherty, Martin Supt. Quality Engineering 617-222-6392 508-339-6653 617-438-3080

Flynn, Paul J. Asst. Supt., Readville 617-222-8600 781-335-0944 617-473-7494 617-438-2139

Goyette, Don Asst. Supt. Coach Shop, CRMF 617-222-6308 978-455-4044 617-293-9075

Hallman, Virginia Technical Writer 617-222-8473 978-463-2205

Hanlon, Paul Truck Shop Manager 617-222-6379 978-977-3927 617-438-1063

Hanson, Paul Director Train Servicing &

Scheduling

617-222-3767 781-331-3197 617-746-0964 617-293-9176

Horrocks, Randy Foreman III 6217-222-5452

Janshego, Steve Supt S&I - CRMF 617-222-6404 508-822-1323 617-560-5678 617-304-7873

Kapela, Michael Shop Manager 617-222-8448 302-475-9328 617-233-6660

Kirkham, Greg Supt. CRMF Shop Operations 617-222-4601 508-858-9604 617 473-6355 617-799-7056

Leetch, John Supt. S&I & Outlying Points

North

617-222-8272 781-391-2712 617-215-0724 617-293-9061

Lewis, Robert Supt. of Locomotives 617-222-8319 781-233-8341 617-201-9374

Long, Thomas Fabrication Manager 617-222-6379 781-449-2252 617-473-2260 617-594-5502

Material Control Stores Clerk 617-222-6387

Maguire, Dan Supt S&I & Outlying Points

South

617-222-8292 617-877-3495 617-473-6733 617-438-2958

McNemar, Robert Supt. Train Servicing and

Cleanliness

617-222-6307 617-268-6426 617-473-0871 617-293-9049

Page 72: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 70

Revision 1

NAME TITLE OFFICE # HOME # PAGER # CELL #

Mechanical Desk 617-222-8212

Murphy,

Darshawn

Manager Process Design 617-222-8472 508-297-2301 857-284-6565

O’Connell, Donald

Mgr. HVAC Systems Quality &

Reliability 617-222-8449 781-826-7688 617-504-6920

O'Shea, Gerald Asst. Supt. Outlying Points

South

617-222-3679 508-469-4303 617-473-6629 617-590-8554

Petruccelli, Sal Deputy Chief Mechanical Officer 617-222-6354 978-717-4106 617-473-4436 781-727-7150

Robinson, Patrick Supt. Technical Services 617-222-8307 508-223-3605 617-215-0728 617-293-9119

Schevis, Dave Manager Special Projects 617-222-8240 603-929-0403 617-473-1602 617-590-9857

Silva, Roy Asst. Supt. North Outlying Points

617-222-6308 603-594-0292 617-215-0729 617-293-9066

Slater, Reginald Manager Quality Services 617-222-3636 508-341-7989 617-590-9464

Taylor, Al Foreman III 617-222-6332

Page 73: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 71

Revision 1

20. MISCELLANEOUS TELEPHONE NUMBERS

AMTRAK Police 800-331-0008

KCS Radio Room 617-222-3628

Dispatch Office North Side 617-222-6115

Dispatch Office South Side 617-222-8101/8100

PAN AM Police 978-663-1168

Dave Fink 978-663-1186

Sid Culliford 978-663-9320

Dick Miller 978-663-9321

Warren Bostwick 978-663-9326

CSX Police 1-800-799-0994 (Ohio)

(GM) 518-767-6101

Bob McGovern, Trainmaster 518-767-6001 Pager: 1-800-944-2337/Pin

#52732

(Middleboro) 617-783-6255

(Readville) 617-783-6260

(Walpole) 617-783-6236

Mike Wojtas (Track) 617-783-6449/ 6448

Readville Yardmaster 617-364-1072

Boston Line Dispatcher Framingham BR

518-767-6111

Chief Dispatcher 518-617-6102

MBTA Police 617-222-1212

Central Control Center 617-222-5707 High Street, Boston

Dispatcher 617-222-5758

Back Bay Station 617-222-5777

Ticket Window 617-345-7961

MBTA Emergency Storm Control Center

617-222-3442

MASS. ELECTRIC

CO.

“OFF HOURS” i.e. Weekends, Monday thru

Friday

Before 8AM & After

4PM

North Andover

Facility

978-688-1535 or 978-688-

6085

Page 74: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 72

Revision 1

Normal Business Hours

Monday-Friday 8:00am-4:00pm

Malden Facility-617-324-5151

Jim Sullivan-Malden

Malden Engineering-617-

388-5254

800-542-2031

x5317

Phil Rohn 978-524-2231

Page 75: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 73

Revision 1

21. OTHER PHONE NUMBERS

DISPATCHERS -

NORTH

PHONE # DISPATCHERS -

SOUTH

PHONE #

Boston East 617-222-6109 Chief South 617-345-7569

Boston Valley 617-222-6110 Corridor Dispatcher 617-345-7561

Boston West 617-222-6112/

617-222-6111

Midland Dispatcher 617-222-8106

Fitchburg 617-222-6161 South Station Trouble Desk

617-345-7571/ 800-523-2709

Chief North 617-222-6114/

617-222-6115

Southside Terminal 617-345-7565

Code Rm C. Hill 617-523-4533 Old Colony 617-222-8105

Northside Terminal 617-222-6113

DRAWBRIDGES PHONE #

Draw 1 Tower A 617-222-5978/ 5986

Manchester 978-526-1089

Gloucester 978-281-6440

Beverly 978-921-4533 Saugus 617-222-6672

HEADQUARTERS PHONE # MISCELLANEOUS PHONE #

Abington 617-222-3063 ET Shop 617-222-6190

Ayer Trailer 978-772-

6804 (6760)

978-772-5230 Radio Shop-North 617-222-6189

Depot-W. Concord 978-369-2931

Signal Design

617-222-3611/ 8412/8413/8415 Greenbush

Readville 617-222-5789

Rosemont 617-222-3102 Signal Relay Shop 617-222-8420

Salem 222-1849 617-222-4980 Signal T-pad 617-222-3626/ 3609 Walpole 508-660-1698

Waltham Signal 617-222-2360 Radio Shop-South 617-222-3061

West Concord 978-369-2931

Wilmington 617-222-6885

Wilmington 617-222-3350

Page 76: Keolis Commuter Services - Donutsdocshare01.docshare.tips/files/25689/256899521.pdfKeolis Commuter Services SNOW PLAN 2014-2015. KCS / MBTA Commuter Rail Snow Plan 2014-2015 Page 1

ODRL 3.2-103 Snow Plan 2014-2015 Page 74

Revision 1

APPENDIX 1 – STORM SPECIFIC SNOW PLAN-DRAFT