(keshav) report file on kali sindh thermal power project, jhalawar

40
1 CHAPTER -1 INTRODUCTION OF K.S.T.P.P Kali Sindh Thermal Power Project located near the Kalisindh river . Thermal power station requires large quantity of water for formation of steam in steam tubes, it also require water for cooling tower & for cooling of different accessories. For generation of steam fuel ( Coal ) require it should be available from mines to power plant through Rail/ Ship/ Road transportation. The nearby Rly station Jhalawar city is only 8 KM from the Power Plant. The generated power to be fed in the transmission line The 400 / 220 KV GSS is near the power plant .Huge land also available in near area for ash disposal. These all factors make favor for site selection for Power Plant at Jhalawar City. At present K.S.T.P.P. having 2 nos. units for generation of 1200 MW as under: Stage-I 2 x 600MW Date of C.O.D.. for Unit #1 Stage-II 2 x 660 MW Proposed Table no.1 The design of steam power station requires wide experience as the subsequent operation and maintenance are greatly affected by its design. The most efficient design consist of properly sized component designed to operate safely and conveniently along with its auxiliaries and installation.

Upload: keshav-meena

Post on 02-Jul-2015

357 views

Category:

Engineering


2 download

DESCRIPTION

A report file on kali sindh thermal power project, jhalawar

TRANSCRIPT

Page 1: (Keshav) report file on kali sindh thermal power project, jhalawar

1

CHAPTER -1

INTRODUCTION OF K.S.T.P.P

Kali Sindh Thermal Power Project located near the Kalisindh river . Thermal

power station requires large quantity of water for formation of steam in steam tubes, it

also require water for cooling tower & for cooling of different accessories. For

generation of steam fuel ( Coal ) require it should be available from mines to power

plant through Rail/ Ship/ Road transportation. The nearby Rly station Jhalawar city is

only 8 KM from the Power Plant. The generated power to be fed in the transmission

line The 400 / 220 KV GSS is near the power plant .Huge land also available in near

area for ash disposal. These all factors make favor for site selection for Power Plant at

Jhalawar City. At present K.S.T.P.P. having 2 nos. units for generation of 1200 MW

as under:

Stage-I 2 x 600MW Date of C.O.D.. for Unit

#1

Stage-II 2 x 660 MW Proposed

Table no.1

The design of steam power station requires wide experience as the subsequent

operation and maintenance are greatly affected by its design. The most efficient

design consist of properly sized component designed to operate safely and

conveniently along with its auxiliaries and installation.

Page 2: (Keshav) report file on kali sindh thermal power project, jhalawar

2

CHAPTER -2

GENERAL LAYOUT & BASIC IDEA:-

The Steam turbine converts thermal energy of steam into mechanical energy and

Generator converts this mechanical energy to Electrical energy. The operation of

steam turbine generator involves the expansion of steam through numerous stages in

turbine causing turbine rotor to rotate which in turn rotate Generator rotor. The

Generator rotor is manetised and its rotation generates the electric power in the

Generator Stator.

2.1 Basics of Steam Plant Cycle:

The Basics of Steam Plant is Rankine Cycle: See Plant Over view

(i) In Boiler heat addition takes place it is represented by Line 1-1’

( Sensible heat) & 1’-2 (Latent heat of water)

(ii) This Steam expands in turbine & causing turbine to rotate ,

(iii) this expansion is isentropic as entropy remain constant it is represented by

line 2-3

(iv) Steam is being condensed in condenser ,here heat rejection tooks place,

show by line 3-4

(v) This condensed steam completed the closed cycle through Boiler feed

pump as shown by Line 4-1

Fig. no. 2.1 Rankine Cycle

Page 3: (Keshav) report file on kali sindh thermal power project, jhalawar

3

Power Station may be divided into four main circuits :

Fuel and Ash Circuit.

Air and Gas Circuit.

Feed water and Steam Circuit.

Cooling Water Circuit.

2.1.1 Fuel & Ash Circuit:-

Fuel from the storage is fed to the boiler through fuel handling device. The fuel used

in KSTPP is coal, which on combustion in the boiler produced the ash. This ash is

collected at the back of the boiler and removed to ash storage tank through ash

disposal equipment

2.1.2 Air and Gas Circuit:-

Air from the atmosphere is supplied to the combustion chamber of Boiler through the

action of forced draft fan and induced draft fan. The flue gas are first pass around the

boiler tubes and super heated tubes in the furnace, next through dust collector (ESP)

& then economizer. Finally, they are exhausted to the atmosphere through fans.

2.1.3 Feed Water and Steam Circuit:-

The condensate leaving the condenser is first heated in low pressure (LP) heaters

through extracted steam from the lower pressure extraction of the turbine. Then its

goes to deaerator where extra air and non-condensable gases are removed. From

deaerator it goes to boiler feed pump which increases the pressure of the water. From

the BFP it passes through the high pressure heaters. A small part of water and steam

is lost while passing through different components therefore water is added in hot

well. This water is called the make up water. Thereafter, feed water enters into the

boiler drum through economizer. In boiler tubes water circulates because of density

difference in lower and higher temperature section of the boiler. The wet steam passes

through superheater. From superheated it goes into the HP turbine after expanding in

the HP turbine. The low pressure steam called the cold reheat steam (CRH) goes to

the reheater (boiler). From reheater it goes to IP turbine and then to the LP turbine

and then exhausted through the condenser into hot well.

Page 4: (Keshav) report file on kali sindh thermal power project, jhalawar

4

2.1.4 Cooling Water Circuit:-

A large quantity of cooling water is required to condense the steam in condenser and

maintaining low pressure in it. The water is drawn from reservoir and after use it is

drained into the river

A complete Plant overview shown as under:

.

Fig. no. 2.2 plant overview

Page 5: (Keshav) report file on kali sindh thermal power project, jhalawar

5

CHAPTER -3

COAL HANDLING PLANT OF K.S.T.P.P

We receive coal from Parsakanta Mines fromThe average distances of SECL, ECL &

BCCL are 800, 950 and 1350 Kms. Respectively

3.2 COAL HANDLING

It can be called the heart of thermal power plantbecause it provided the fuel for

combustion in boiler. The coal is brought to the KSTPP through rails there are

tracks in all for transportation of coal through rails. The Daily requirement of coal

remain approximately –

3000 Tons for Stage-I Thus approximately 16500 Tons coal is

5700 Tons for Stage-II required daily for Generation of 1045MW

At present everyday 2 to 3 Rakes of coal are to be unloaded at KSTPP. Each Rake

consists of 58 wagons and each wagons consists of app 55 tonnes of coal. The coal is

first unloaded from wagon by wagon triplers then crushed by crushers and send to

different Bunkers with the conveyor system.

The coal handling plant can broadly be divided into three sections :-

1) Wagon Unloading System.

2) Crushing System.

3) Conveying System.

3.2.1 WAGON UNLOADING SYSTEM:-

Wagon Tripler:-

It unloads the coal from wagon to hopper. In the hopper, Iron Jali is provided so that

pieces of only equal to and less than 250 mm. size pass through it. The bigger ones

are broken by the workers with the help of hammers

Page 6: (Keshav) report file on kali sindh thermal power project, jhalawar

6

Fig. no. 3.1 Wagon Tripler:-

.

Fifififiifffffffffffffffffffffffffffffffffff

Wagon Tripl

Fig. no. 3.2 Wagon Tripler

Page 7: (Keshav) report file on kali sindh thermal power project, jhalawar

7

3.2.2 CRUSHING SYSTEM:-

Crusher House:-

It consists of crushers which are used to crush the coal to 20 mm. size. There are

mainly two type of crushers

Primary Crushers i.e. i) Two roll crushers & ii) Rotary breaker.

Secondary Crushers. i.e. Ring granulators.

Primary Crushers:-

Primary crushers are provided in only CHP stage 3 system, while breaking of coal in

CHP Stage 1 & Stage 2 system is done at wagon tripler hopper jali up to the size (-)

250 mm.

Roll Crusher:-

Type : 80” 5 A breakers.

Capacity : 1350 TPH Rates/ 1500 TPH Design.

Feed material : Rom Coal.

Feed size. : (-) 1200 mm. (approx.)

End Product size : (-) 500 mm.

Motor rating. : 2 Nos. 125 KW, 100 rpm.

Rotary Breaker:-

Type : 12’ x 21’ Rotary Breaker.

Capacity : 800 TPH Rated/ 1000 TPH Design.

Secondary Crusher:-

Ring granulators crush by compressing accompanied by impact and shearing.The

unique feature of this granulator is the minimum power required for crushing per ton.

Page 8: (Keshav) report file on kali sindh thermal power project, jhalawar

8

Construction & Operation:-

Secondary crushers are ring type granulators crushing at the rate of 550 TPH / 750

TPH for input size of 250 mm. and output size of 20 mm. The crusher is coupled with

motor and gearbox by fluid coupling.

Main parts of granulator like breaker plates, cages , crushing rings and other internal

parts are made of tough manganese (Mn) steel.

The rotor consists of four rows of crushing rings each set having 20 Nos. of toothed

rings and 18 Nos. of plain rings.

Crushers of this type employ the centrifugal force of swinging rings stroking the coal

to produce the crushing action

3.2.3 CONVEYING SYSTEM:-

Stacker Reclaimer:-

The stacker re-claimer unit can stack the material in the form of pilein the coal stock

yard area& it may reclaim the stacked material and fed on to the bunker side

conveyors. While stacking material is being fed from the main line conveyor via

tripler unit and vibrating feeder on the intermediate conveyor which feds the material

on the boom conveyor of the stacker cum reclaimer. From this boom conveyor

material discharged on the coal stock yard area for Stacker reclaimer where it

properly stacked uniformely with the help of Travel Mechanism, Boom Luffing

mechanism, Boom Slewing Mechanism.

During reclaiming the material discharged on to the boom conveyor by the bucket

fitted to the bucket wheel body and boom conveyor feeds the material on the yard

conveyor running in the reverse direction.

Specification of Stacker / Reclaimer:-

Belt width. : 1400 mm..

Bucket wheel motor : 90 KW.

Boom Conveyor motor : 70 KW.

Intermediate Conveyor Motor : 90 KW.

Boom Luffing Motor : 22 KW.

Slewing assembly. : 10 KWx 2 nos.

Page 9: (Keshav) report file on kali sindh thermal power project, jhalawar

9

Travel Motor : 7.5 KW x 6 nos.

Vibrating Feeder : 2x6 KW.

Fig. no. 3.3 Stacker

Conveyor Specification:-

Capacity of Conveyors

1. 1350 tons per hour. From Wagon Tipplers to Coal Stock Yard Area

2. 750 tons per hour from Stock YardTo Bunker side conveyors

.

Page 10: (Keshav) report file on kali sindh thermal power project, jhalawar

10

No. of conveyors : more than 50

From Wagon Tippler 1,2 to

Stacker Reclaimer-1

From Wagon Tippler 3,4 to

Stacker Reclaimer-2

From Wagon

Tippler -5

Conveyors for Bunker Side

Con 1A,1B Con 1C, 1D 6A,6B

Con-2A,2B,2C Con 2B,2C 7A,7B,7C,7D

Con 3A,3B,3C,4B Con 4C 8A,8B,8C,8D

Shuttle Conveyor Con 12 9A,9B,9C,9D 13A,13B

Telescopic Chute 14A,14B,19A,21A,21B,21C ,22A,22B

23A,24A,25A,25B,

Table no. 2

3.3 PLOW FEEDERS:-

From the Wagon Tippler No.1 & 2 the coal may be stock in the coal stock yard

below the shuttle conveyor , As through the shuttle conveyor the coal discharged on

the coal stock yard from a height of about 25 M so for minimizing the problem of

emission of dust in atmosphere the Telescopic chute is provided.

Below the coal Stock yard an Underground machines are installed known as plow

feeder machines. These machines collect the coal from stock yard and discharge it

on conveyor with the help plow feeder .This coal is takento Bunkers by different

conveyors.

Page 11: (Keshav) report file on kali sindh thermal power project, jhalawar

11

CHAPTER -4

ASH HANDLING PLANT OF K.S.T.P.P

Ash produced as the result of combustion of coal is collected andremoved by ash

handling plant. Ash Handling Plant at KSTPP consists of specially designed bottom

ash and fly ash handling system

4.1 Ash Disposal & Dust Collection Plant:-

KSTPP has dry bottom furnace. Ash Handling Plant consists of especially designed

bottom and fly ash system for two path boiler. The system for both units is identical

and following description is applied to both the units the water compounded bottom

ash hopper receives the bottom ash from the furnace from where it is stores and

discharged through the clinker grinder. Two slurry pumps are provided which is

common to both units & used to make slurry and further transportation to ash dyke

through pipe line.

Dry free fly ash is collected in two number of 31 fly ash hoppers which are handled

by two independent fly ash system. The ash is removed from fly ash hoppers in dry

state is carried to the collecting equipment where it is mixed with water and resulting

slurry sump is discharged

Utilisation:- Utilisation of coal-ash is always practise than its disposal. There are

various methods of utilisation of coal-ash along with established engineering

technologies some of them are mentioned below:

11.. Manufacturing of building materials.

22.. Making of concrete.

33.. Manufacturing of pozzuolana cement.

44.. Road construction etc.

Page 12: (Keshav) report file on kali sindh thermal power project, jhalawar

12

CHAPTER -5

ELECTRO-STATIC PRECIPITATOR

5.1 Scope & Principle of Operation:-

In an ESP the dust laden gas is passed through an intense electric field, which causes

ionization of the gases & they changed into ion while traveling towards opposite

charged electrodes it get deposited as particles and thus Fly ash is deposited on

electrode , this fly ash removed from the electrode with the help of agitating reapers

This Fly Ash collected in different hoppers from where it removes by Ash Handling

system. .

5.2 controller:-

Now a day micro-processor based intelligent controllers are used to regulate the

power fed to the HVR. The controls the firing / ignition angle of the thyristor

connected in parallel mode. The average power fed to ESP field can be controlled by

variation of the firing angle of thyristor. The output of controller with respect to time

is also controlled by microprocessor, so that ESP operation is smooth and efficient .

Controller also takes care of fault in KVR and gives a tripping - alarm

Page 13: (Keshav) report file on kali sindh thermal power project, jhalawar

13

Fig no. 5.1 Controller

5.3 HIGH VOLTAGE RECTIFIER TRANSFORMER:-

HVR receives the regulated supply from controller. It steps upto high voltage rectifier.

The D.C. supply is fed to E.S.P. field through its negative bushing. The positive

bushing so connected to earth through small resistance which forms a current feed

back circuit

Page 14: (Keshav) report file on kali sindh thermal power project, jhalawar

14

5.4 E.S.P. FIELD:-

The field consists of emitting and collecting electrodes structure which are totally

isolated from each other and hanging with the top roof of field. The supply to these

electrodes is fed through support insulators. The collecting electrodes are of the shape

of flat plates. By several similar plates while the emitting electrodes are of the shape

of spring. The ash depositing on these electrode is rapped down by separate rapping

mechanism happens at the bottom of the field. From these hoppers ash is evacuated

by ash handling system and dispose to the disposal area. The rapping system is

automatically controlled with the help of the programmable metal controller, located

in the ESP auxiliaries control panels.

Page 15: (Keshav) report file on kali sindh thermal power project, jhalawar

15

CHAPTER -6

BOILER:-

A boiler (or steam generator) is a closed vessel in which water, under pressure is

converted into steam. It is one of the major components of a thermal power plant. A

boiler is always designed to absorb maximum amount of heat released in process of

combustion. This is transferred to the boiler by all the three modes of heat transfer i.e.

conduction, convection and radiation.

6.1 Water tube boiler:-

In this type of boiler water flows inside the tubes and hot gases flow outside the

tubes. These tubes are interconnected to common water channels and to steam outlet.

In KSTPP, Natural circulation, tangentially fired, over hanged type, Water tube

boilers are used. Oil burners are provided between coal burners for initial start up and

flame stabilization. Firstly, light oil (diesel oil) is sprayed for initialization then heavy

oil (high speed diesel oil) is used for stabilization of flame. Pulverized coal is directly

fed from the coal mills to the burners at the four corners of the furnace through coal

pipes with the help of heated air coming from PA fan. Four nos. of ball mills of

34MT/hr. capacity each have been installed for each boiler. The pressure inside boiler

is -ive so as to minimized the pollution and looses & to prevent the accidents outside

the boiler.

Page 16: (Keshav) report file on kali sindh thermal power project, jhalawar

16

Fig. no. 6.1 Boiler

For ensuring safe operation of boilers, furnace safe guard supervisory system (FSSS)

has been installed. This equipment systematically feed fuel to furnace as per load

requirement flame scanners installed to scan the flame conditions and in case of

unsafe working conditions trip the boiler and consequently the turbine. Turbine -

boiler interlocks safe guarding the boiler against possibility of furnace explosion

owing to flame failure.

Page 17: (Keshav) report file on kali sindh thermal power project, jhalawar

17

6.2 Furnace:-

Furnace is primary part of the boiler where the chemical energy available in the fuel is

converted into thermal energy by combustion.,

Fig. no. 6.2 Furnance

6.3 WATER:-

The source of water for power station is reservoir formed by Kota Barrage on the

Chambal River. In case of large capacity plants huge quantities of coal and water is

required.

Page 18: (Keshav) report file on kali sindh thermal power project, jhalawar

18

6.4 PULVERISED FUEL SYSTEM:-

The boiler fuel firing system is tangentially firing system in which the fuel is

introduced from wind nozzle located in the four corners inside the boiler.

The crushed coal from the coal crusher is transferred into the unit coalbunkers where

the coal is stored for feeding into pulverizing mill through rotary feeder

Fig. no. 6.3 Pulverised Fuel System

6.4.1 Fuel Oil System:-

The functional requirement of the fuel burning system is to supply a controllable and

uninterrupted flammable furnace input of fuel and air and to continuously ignite and

burn the fuel as rapidly as it is introduced into the furnace. The Fuel air (secondary

air) provided FD fan, surrounds the fuel nozzles. Dampers are provided so that

quantity of air can be controlled . Coal burners distribute the fuel and air evenly in the

furnace. Ignition takes place when the flammable furnace input is heated above the

ignition temperature..

6.5 Boiler Drum:-

The drum is a pressure vessel. Its function is to separate water and steam from the

mixture (of steam & water) generated in the furnace walls. It provides water storage

for preventing the saturation of tubes. It is made up of two halves of carbon steel

plates.

Page 19: (Keshav) report file on kali sindh thermal power project, jhalawar

19

Fig. no. 6.4 Boiler Drum

Boiler drum is located at a height of 53m from ground.The drum form the part of

boiler circulating system i.e. movement of fluid from the drum to the combustion

zone and back to boiler drum. Feed water is supplied to the drum from the economizer

through feed nozzles. Water from the drum goes to water walls through six

downcomers.

6.6 Draft System:-

The combustion process in a furnace can take place only when it receives a steady

flow of air and has the combustion gases continuously removed. Theoretically

balanced draft means keeping furnace pressure equal to atmospheric pressure, but in

practice the furnace is kept slightly below atmospheric pressure. It ensures that there

is no egress of air or hot gas and ash into boiler house.

Primary air fan (P.A. fan) or Exhauster fan-

Pulverized coal is directly fed from coal mills to the burners at the four corners of the

furnace through coal pipes with the help of heated air coming from PA fan. Secondly,

this fan also dries the coal. Usually sized for 1500 RPM due to high pressure.

Page 20: (Keshav) report file on kali sindh thermal power project, jhalawar

20

Forced draught fan (F.D. fan):-

The combustion process in the furnace can take place only when it receives a steady

flow of air. This air is supplied by FD fan. Thus FD fan takes air from atmosphere at

ambient temperature & so provides additional draught. Its speed varies from 600-1500

RPM.

Induced draught fan (I.D. fan):-

The flue gases coming out of the boiler are passed to the ESP & then dust free gases

are discharged up by the chimney to the atmosphere through the ID fan.

Scanner Air Fan:-

Used to provide necessary cooling air to the flame scanners. Two air fans are usually

provided. One will run and other will remain as stand by. When F.D. fans trip the

scanner air fan will draw air from atmosphere through emergency damper. Typical

speed 3000 RPM.

6.7 Economizer:-

The flue gases coming out of the boiler carry lot of heat. An economiser extracts a

part of this heat from the flue gases and uses it for heating the feed water before it

enters into the steam drum. The use of economiser results in saving fuel consumption

and higher boiler efficiency but needs extra investment. In an economizer, a large

number of small diameter thin walled tubes are placed between two headers. Feed

water enters the tubes through the other. The flue gases flow outside the tubes

.

Page 21: (Keshav) report file on kali sindh thermal power project, jhalawar

21

Fig.. No. 6.5 Economizer

Air preheaters:-

Air preheaters are employed to recover the heat from the flue gases leaving the

economiser and are used to heat the incoming air for combustion. This raises the

temperature of the furnace gases, improves combustion rates and efficiency and

lowers the stack (chimney) temperature, thus improving the overall efficiency of the

boiler.

Fig. no. 6.6 Air preheaters

Superheater:-

Superheated steam is that steam, which contains more heat than the saturated steam at

the same pressure i.e. it, has been heated above the temperature corresponding to its

pressure. This additional heat provides more energy to the turbine and thus the

Page 22: (Keshav) report file on kali sindh thermal power project, jhalawar

22

electrical power output is more.The steam is superheated to the highest economical

temperature increase the efficiency–

Reheater:-

Reheaters are provided to raise the temperature of the steam from which part of

energy has already been extracted by HP turbine. This is done so that the steam

remains dry as far as possible through the last stage of the turbine.. From economizer

the water enters the drum and thus joins the circulation system through down covering

water wall tubes. In water wall tubes a part of the water is converted to steam due to

boiler and the mixture flows back to the drum. In the drum, the steam is separated out

through the steam separators and passed to the super heater. After the super heater

when the steam temperature becomes high and pressure upto 150 Kg./cm3 steam is

allowed to enter the turbine to convert potential energy to kinetic energy.

Soot Blower:-

The boiler tubes are cleaned with the help of steam by the process called soot

blowing.

6.8 TECHNICAL SPECIFICATION OF BOILER

1.Type : Direct fired, natural circulation

balance draft water tube boiler.

2. No. of Units. : Two.

3.Make : BHEL.

4.Capacity. : 375 tonnes per hour.

5.Steam Pressure. : 139 Kg./Cm2

6.Efficiency : 86.6 %.

7.No. of fans in service.

a) ID fans. : 2 Nos.

b) FD fans. : 2 Nos.

c) PA fans. : 2 Nos.

d) Seal Air fan. : 1 No.

Page 23: (Keshav) report file on kali sindh thermal power project, jhalawar

23

e) Scanner Air fan. : 1 No.

f) Igniter fan. : 1 No.

8. Steam Temperature : 540oC.

9. No. of coal mills in : 3 Nos.service.

6.9 FUEL :-

a) COAL:-.

No. of chimney / stack. : 1 / 2.

Height of Chimney : 180 Meters

6.10 GENERAL DESCRIPTION:-

Boilers are tangentially fired, balance draft, natural circulation , radiant type, dry

bottom with direct fired pulverized coal from bowl mills. They are designed for

burning low grade coal with high ash content.

Page 24: (Keshav) report file on kali sindh thermal power project, jhalawar

24

CHAPTER - 7

STEAM TURBINE

7.1 INTRODUCTION:-

Turbine is a machine in which a shaft is rotated steadily by impact or reaction of

current or stream of working substance ( steam , air , water, gases etc) upon blades of

a wheel. It converts the potential or kinetic energy of the working substance into

mechanical power by virtue of dynamic action of working substance. When the

working substance is steam it is called the steam turbine.

Fig. No. 7.1 Turbine

7.2 PRINCIPAL OF OPERATION OF STEAM TURBINE:-

Although the fundamental principles on which all steam turbine operate the same , yet

the methods where by these principles carried into effect very end as a result, certain

types of turbine have come into existence

Page 25: (Keshav) report file on kali sindh thermal power project, jhalawar

25

1. TECHNICAL DATA OF TURBINE :-

The main technical data of 110 MW turbine is given below:-

Rated output. 110 MW.

Rated speed. 3000 rpm

Rated steam pressure before 130 ata

stop valve.

Maximum steam pressure before 146 ata

stop valve.

Rated temperature of steam before stop valve 535oC.

Rated pressure of steam MP Casing 31.6 ata

Rated pressure of steam before MP Casing 35 ata

HP Cylinder 2 row carts wheel

+ 8 moving wheels.

MP Cylinder 2 moving wheels.

LP cylinder 4 moving wheels of

Double row design.

Single flow HP turbine with 25 reaction stages.

Double flow IP turbine with 20 reaction stages per flow.

Double flow LP turbinewith 8 reaction stages per flow.

2 main stop & control valves. & 2 steam check valve in CRH.

2 reheat stop & control valves. & 2 bypass stop & control valve.

7.2.1 Description of Steam Turbines:-

1) Steam flow:-

210 MW steam turbine is a tandem compound machine with HP, IP & LP parts. The

HP part is single flow cylinder and HP & LP parts are double flow cylinders. The

individual turbine rotors and generator rotor are rigidly coupled. The HP cylinder has

a throttle control. Main steam is admitted before blending by two combined main

stop and control valves. The HP turbine exhaust (CRH) leading to reheated have tow

swing check valves that prevent back flow of hot steam from reheated, into HP

turbine. The steam coming from reheated called HRH is passed to turbine via two

combined stop and control valves. The IP turbine exhausts directly goes to LP turbine

by cross ground pipes.

Page 26: (Keshav) report file on kali sindh thermal power project, jhalawar

26

2) HP Turbine:-

The HP casing is a barrel type casing without axial joint. Because of its rotation

symmetry the barrel type casing remain constant in shape and leak proof during quick

change in temperature. The inner casing too is cylinder in shape as horizontal joint

flange are relieved by higher pressure arising outside and this can kept small. Due to

this reason barrel type casing are especially suitable for quick start up and loading.The

HP turbine consists of 25 reaction stages. The moving and stationary blades are

inserted into appropriately shapes into inner casing and the shaft to reduce leakage

losses at blade tips.

3) IP Turbine:-

The IP turbine consists of 20 reaction stages per flow.

4) LP Turbine:-

The casing of double flow type LP turbine is of three shell design. Steam admitted to

LP turbine from IP turbine flows into the inner casing from both sides through steam

inlet nozzles.

Page 27: (Keshav) report file on kali sindh thermal power project, jhalawar

27

CHAPTER - 8

TURBO GENERATOR

8.1 THEORY :-

TURBO GENERATOR manufactured by B.H.E.L. and incorporated with most

modern design concepts enclosing the stator windings, core and hydrogen coolers. .

The generator is driven by directly coupled steam turbine at a speed of 3000 r.p.m. the

Generator is designed for continuous operation at the rated output. The source of

excitation of rotor windings is thyristor controlled D.C. supply.

8.2 Main parts of generator:-

(A) STATOR:-

i. stator frame:-

The stator constructed in a single piece houses the core and windings. The

horizontally mounted water cooled gas coolers being so arranged that it may be

cleaned on the water side without opening the machine to atmosphere. All welded

joints exposed to hydrogen are specially made to prevent leakage. The complete

frame is subjected to hydraulic test at a pressure of 7 ATA.

ii. stator core:-

It is built up of special sheet laminations and whose assembly is supported by a

special guide bass. . Laminations are assembled on guide bass of group separated by

radial ducts to provide ventilation passage. plates. Use of non-magnetic steel reduces

considerably by heating of end iron clamping. special dampers are provided at either

ends of core.

Page 28: (Keshav) report file on kali sindh thermal power project, jhalawar

28

Fig. No. 8.1 Stator Core

iii. stoter bars:-

Stoter bars dampers are provided to prevent hunting in ac machines.. Conductor

material is electrolytic copper connections brazed with free coating silver alloy to

obtain joints , which are both electrically & mechanically sound.

iv.stator windings:-

Stator windings are double star layers , lap wound, three phase, short pitch type.

Phases are connected to form a double star winding. The arrangement of complete

stator winding electrical circuit is viewed from turbine end of generator & rotor

windings.. The winding is designed to withstand short circuit stresses.

Page 29: (Keshav) report file on kali sindh thermal power project, jhalawar

29

v. terminal bushings:-

Six output leads (3 long,3 short) have been brought out of the coming on the exciter

side. casing. Gaskets are provided between the Flange of terminal bushings and

castings to make it absolutely gas tight.

vi. bearings:-

Generator bearings have electrical seats of consists of steel bodies with removable

steel pads. supplies oils to the turbine , bearings & governing gears. .

vii ventilation system:-

The machine is designed with ventilation system having 2 atm rated hydrogen

pressure. Two axial fans mounted on either side of the rotor to ensure circulation of

hydrogen.

8.3 HYDROGEN COOLERS:-

Three Hydrogen Coolers each comprising of two individual units are mounted inside

the stator frame.

(B) ROTOR :-

Rotor shaft consists of single piece alloy steel forging of high mechanical and

magnetic properties performance test includes :-

VIBRATION OF ROTOR:-

Fig. No. 8.2 Vibration of Roter

Page 30: (Keshav) report file on kali sindh thermal power project, jhalawar

30

rotor windings:-

Rotor winding is of direct coil type and consists of parallel strips of very high

conductivity Silver Bearing Copper,

bearings:-

The bearings are self-aligned & consist of slip steel shells linked with special bearing

metal having very low coefficient of friction.

slip rings:-

The slip rings are made of forged steel. They are located at either side of Generator

Shaft.

bush gear assembly:-

Generator bushes are made from the various compositions of natural graphite and

binding material. They have a low coefficient of friction and are self lubricating.

drying of winding:-

Generator stator bars are insulated with mica insulation , which is homogeneous in

nature and practically impervious to moisture, and reduce time required to draught.

8.4 TECHNICAL DATA:-

(A) Generator (110 MW):-

Continuous apparent power : 1,37,500 KVA.

Active power : 7,10,000 KW.

Power factor : 0.8 (lagging).

Rated voltage : 1000 + 5% rated.

Current : 7,220 A

Critical speed : 3000 r.p.m. at

Frequency : 50 Hz.

Phase connection : double star.

No. of terminals : 6.

Main diameter of slip rings : 420 mm.

Page 31: (Keshav) report file on kali sindh thermal power project, jhalawar

31

Voltage regulation : 39%.

Reactance : Informative.

HYDROGEN COOLER:-

Nos. of elements : 6

Cooling medium : Water, H2 at 2 ATM

8.5COOLING SYSTEM:

In KSTPP hydrogen cooling system is employed for generator

cooling.

Page 32: (Keshav) report file on kali sindh thermal power project, jhalawar

32

CHAPTER – 9

EXCITATION SYSTEM

The electric power Generators requires direct current excited magnets for its field

system. Exciter supply is given from transformer and then rectified.

(A) Function of excitation system:-

The main function of excitation system is to supply required excitation current at

rated load condition of turbo Generator The excitation system makes contribution

improving power system stability steady state condition. The excitation system that

are commonly termed quick response system and have following principal feature :-

Exciter of quick response & high voltage of not less than 1.4 times the rated filed

voltage and nominal exciter response of minimum 0.5.

(B)Type of Excitation System:-

There have been many developments in excitation system design. There has been

continuing reach among the design and the use alike from improving the excitation

system performance. The ultimate is to achieve stability; accuracy etc. the modern

excitation system adopted presently on BHEL makes turbo-generator I. Conventional

DC excitation system. Brushes excitation system.

9.1 STATIC EXCITATION SYSTEM :-

In KSTPP static excitation system is provided it mainly consists of the following:-

1) Rectifier transformer.

2) Nos. of thyristor converters.

3) An automatic voltage regulator (AVR).

4) Field suppression equipment.

5) Field flashing equipment.

9.2 GENERAL ARRANGEMENT:-

In the excitation system the power required for excitation of Generation are tapped

from 11 KV bus ducts through a step down rectifier transformer. After rectification in

thermistor, converter, the DC power is fed to the Generator field winding through a

field breaker. The AVR control the o/p

Page 33: (Keshav) report file on kali sindh thermal power project, jhalawar

33

from thyristor converter by adjusting the firing angle depending upon Generator

voltages. The field flashing system facilitates initial built up of the Generator voltage

from the static AC or DC supply.

(I) RECTIFIER TRANSFORMER :-

This transformer steps down the bus voltage 11 KV to 640 V and has a rating of 1360

KVA. It is dry type, it is however provided with current relays and two temperature

sensors

(II) A THYRISTOR CONVERTOR :-

The thyristor panel and are intended for controlled rectification of AC Input power.

6. Thyristor converter are connected in parallel each rates for continuous current o/p

of 20 % of the rated capacity i.e. 20 % reserve. Each thyristor converter consists of 6

thyristor connected in 3-3 , full wave, 6-pulse bridge from and they are cooled by

fans provided with a fuse for protection against short circuit.

(III) AUTOMATIC VOLTAGE CONTROLS :-

The AVR is transistorized thyristor controlled equipment with very fast response.

The AVR is also having provision of stator and rotor currents limits and load angle

limits for optimum utilization of lagging and leading reactive capacities of generator.

(IV) FIELD SUPRESSION EQUIPMENT:-

The field equipment consists of a field breaker with discharge resistors. The field

breakers have 4 main breaking contacts and two discharge contacts, which close

before main contact break.

(a) A very fast response.

(b) Extremely reliable in view of static components.

(c) Low maintenance cost.

(d) High efficiency.

(e) Fast field suppression through field and discharge resistance as well as

through Thyristor Bridge, feeding the Generator field.

Page 34: (Keshav) report file on kali sindh thermal power project, jhalawar

34

9.3 OPERATION:-

After bringing the speed to operation speed say 3000 r.p.m. , the voltage is slowly

built up with the help of excitation system. This action is taken for synchronizing the

Generator.

(A) SYNCHRONIZING:-

For synchronizing the Generator to the grid system 5 condition of equality have to

be satisfied. These are

(I) Voltage

(II) Frequency

(III) Phase displacement

(IV) Phase sequence

(V) Wave form.

Wave form and phase sequence of the Generator are determined at the design of each

connection SYNCHRONIZING of the generator.

Page 35: (Keshav) report file on kali sindh thermal power project, jhalawar

35

CHAPTER – 10

WATER TREATMENT PLANT

The principle problem in high pressure boiler is to control corrosion and steam

quality. Internal corrosion costs power station crores of rupees in repair without strict

control impurities in steam also form deposit over turbine blades and nozzles.

10.1 D.M. PLANT:-

Equipment for demineralization cum softening plant consists of two streams each

stream with activated carbon filter, weak acid , cation exchanger and mixed bed

exchanger. The filter water to DM plant through 250 dia. header from where a heater

top off has been taken to softening plant. Two filtered water booster pumps are

provided on filtered water line for meeting the pressure requirement in DM

Plant.SodiumSulphate solution of required strength is dosed into different filtered

water by mean of dosing pump to neutralize chlorine prior to activated carbon filter.

When water passed an activated carbon filter will remove residual chlorine from

water. Provision is made for back washing the activated carbon filter. When pressure

drop across filter exceeds a prescribed limit from the activated carbon filter the works

acid cation unit. The deception water the weak base anion exchanger unit water then

enters de-gasified unit where free CO2 is scrubbed out of water by upward counter

flow of low pr. air flow through degasified lower and degassed water is pumped to

strong base exchanger ( anion exchanger).Arrangement for dosing ammonia solution

into de-mineralized water after mixed bed unit has been provided p+1 correction

before water is taken in de-condensate transfer pump the DM water to unit condensor

as make up

Page 36: (Keshav) report file on kali sindh thermal power project, jhalawar

36

CHAPTER – 11

C.W. PLANT & B.C.W. Pump House

Circulating water pump house has pumps for condensing the steam for condensor.

Five pumps are used for condensing Unit No.1 & 2 and after condensing this water

isdischarged back into the river.

Two pump for unit 1 & 2 with one stand by is used for supplying raw water to

chlrofied chemical dosing is tone between and chlorified water is taken through main

line. From main line water passes through filter bed to filter the water.

11.1 B.C.W. PUMP HOUSE:-

Filter water after demineralization is used for bearing cooling from BCW pump house

after passing through strainer and heat exchanger it enters at 30-32oC and leave

exchanger at 38oC. BCW here stand for water used for cooling oil used for cooling the

bearing. In CW pump house water is discharged from nozzle and impinged for

traveling water screens for cleaning it.

Page 37: (Keshav) report file on kali sindh thermal power project, jhalawar

37

CHAPTER – 12

TRANSFORMER

Main transformers, which are necessary:

1. To step up the generated voltage.

2. To supply power to the auxiliaries from the generator.

3. To start the plant by taking the supply from the grid.

Are installed in a transformer yard. It is located in between the main plant and the

switchyard. The main transformers installed in the transformer yard are:

1. GENERATOR TRANSFORMER (GT – A):-

It steps up the voltage from 16.5 KV to 220 KV. It connects the plant

with the 220 KV switchyard.

2. GENERATOR TRANSFORMER (GT – B):-

It steps up the voltage from 16.5 KV to 400 KV. It connects the plant

with the 400 KV switchyard.

3. STATION TRANSFORMER (ST):-

It is a step down transformer with 50 MVA capacities. It is used to step

down 220 KV from the grid to 6.9 KV.

4. UNIT AUXILIARY TRANSFORMER (UAT):-

It is a step down transformer with 20 MVA capacities. It steps down

the voltage from 16.5 KV to 6.9 KV.

5. STATION SERVICE TRANSFORMER (SST):-

It is a step down transformer with 2MVA capacity. It is used to step

down from 6.6 KV to 0.4333 KV.

6. UNIT SERVICE TRANSFORMER (UST):-

It is a step down transformer with 2 MVA capacity. It is used to step

down from 6.6 kV to 0.4333 KV.

Page 38: (Keshav) report file on kali sindh thermal power project, jhalawar

38

CHAPTER – 13

SWITCH YARD

220 KV SYSTEM :-

Two 220 KV bus bars have been provided in switch yard and are inter-connected

through a bus coupler. Each of the two 110 MW generator is connected to this system

through a step up of 125 MVA 240/ 11 KV yard generator transformer. There are two

step down transformer each feeding 6.6 KV system ( Station Switchyard ) viz. BS-IS

& SB-IB. four feeder take off from 220 switch yard, two to SKATPURA GSS and

other to HEERAPURA , Jaipur GSS.

Page 39: (Keshav) report file on kali sindh thermal power project, jhalawar

39

CHAPTER -14

PROTECTION

1. Field Protection.

5. Negative Phase Sequence Protection.

6. Reverse Power Protection.

7. Forward Power Protection.

8. Under Frequency & Over Frequency Protection.

9. Generator Voltage Protection.

10. Rotor Earth Fault Protection.

14.1 General Protection:

It is most important electrical equipment of many generating station. Tripping of even

a generating unit may cause overloading of associated machines and even to system

un-stability . The basis function of protection applied to generator is to reduce

voltage to minimum by rapid discrimination clearance of faults. Unlike other

apparatus the opening of C.B. to isolate faulty generator is not sufficient to prevent

future damage.

Page 40: (Keshav) report file on kali sindh thermal power project, jhalawar

40

CHAPTER -15

CONCLUSION

The first phase of practical training has proved to be quiet fruitful. It provided an

opportunity for encounter with such huge machines like wagon tippler .110 MW &

210 MW turbines and generators.

The architecture of the power plant the way various units are linked and the way

working of whole plant is controlled make the student realize that engineering is not

just learning the structured description and working of various machines, but the

greater part is of planning proper management.

It also provides an opportunities to lean low technology used at proper place and time

can cave a lot of labour e.g. wagon Tripler (CHP).But there are few factors that

require special mention. Training is not carried out into its tree sprit. It is

recommended that there should be some project specially meant for students where

presence of authorities should be ensured. There should be strict monitoring of the

performance of students and system of grading be improved on the basis of work

done.

However training has proved to be quite fruitful. It has allowed an opportunity to get

an exposure of the practical implementation to theoretical fundamentals.