kestrel pres feb 13, 13

22
Stormwater Impacts Assessment Update February 13 th , 2013

Post on 19-Oct-2014

347 views

Category:

Documents


3 download

DESCRIPTION

 

TRANSCRIPT

Page 1: Kestrel pres feb 13, 13

Stormwater Impacts Assessment Update

February 13th, 2013

Page 2: Kestrel pres feb 13, 13

Addressing historical and emerging ecological impacts

Page 3: Kestrel pres feb 13, 13

Purpose of the Study

The main purpose of the Stormwater Impacts Assessment Study was; •  To Identify stormwater related

impacts on McVicar Creek •  To characterize these impacts

through a Unified Stream Assessment •  To identify the 3 most representative

stormwater subwatersheds along the creek

•  To pursue further research on these 3 sites and;

•  To develop remediation recommendations for the 3 identified sites and McVicar Creek as a whole

Page 4: Kestrel pres feb 13, 13

How to achieve the purpose of the study

An initial assessment was completed along the entirety of the creek, from that assessment, the 3 sites were identified. Further research was completed to; •  Develop a feasibility criteria of site-

specific stormwater remediation options for each site

•  Implement a decision-support criterion to identify the most effective stormwater remedial options based on; Low Impact Development (LID), education, policy/regulation and maintenance

•  Produce a remediation option plan using expert feedback along with data collection

Page 5: Kestrel pres feb 13, 13

Initial Unified Stream Assessment

The initial Unified Stream Assessment (USA) confirmed the suspected theory of stormwater pollution being contributed to McVicar Creek, and proved the need for continued research. •  Stormwater outfalls are in fact contributing to degraded water

quality such as elevated levels of nutrients and metals •  Effects of pollution found to degrade infrastructure integrity,

cause declined aesthetics and cause impairments to aquatic habitats

•  Future research is recommended to assess localized and detailed stormwater impacts along the creek (RAP, 2010)

Results

Page 6: Kestrel pres feb 13, 13

•  The results of the USA determined the 3 most representative sites along the creek for future study; Court Street, Castlegreen and County Fair

•  The USSR study assessed the impacts of stormwater from a subwatershed perspective based on behaviours within the terrestrial environment

•  The results and recommendations drawn from USSR were used to complete the final recommendations for remediation options along the creek.

USSR Site Assessment Results

Detailed Unified Subwatershed and Site Reconnaissance study

Page 7: Kestrel pres feb 13, 13

Court Street

Site Characterization: Residential, 22 hectares,

39% impervious Concerning Urban Activity: Home vehicle repair shops,

disconnected rainbarrels and excess sediment

Water Quality Exceedance: Chloride, ammonia,

aluminum, cadmium, copper, iron, vanadium and lead

Page 8: Kestrel pres feb 13, 13

Castlegreen

Site Characterization: Residential, 7 hectares,

45% impervious Concerning Urban Activity:

Private gardens, pet waste and buckling of

street Water Quality Exceedance:

Chloride, ammonia, nitrate, aluminum,

copper, iron, lead and zinc

Page 9: Kestrel pres feb 13, 13

County Fair

Site Characterization: Commercial/Residential, 20 hectares, 62% impervious

Concerning Urban Activity: Use of parking lot, presence of gas station, outdoor

garden center and drive-through Water Quality Exceedance:

Chloride, ammonia, nitrite, copper, iron and zinc

Page 10: Kestrel pres feb 13, 13

•  Court Street: •  A focus on community education in properly connected rainbarrels,

effects of auto fluids from home vehicle repair shops on the aquatic environment, and alternative snow removal

•  Castlegreen: •  Focus on community education in the effects of gardening

chemicals and pet waste on aquatic systems. Also landscaping of the 100% impervious parking lots

•  County Fair: •  Possible end-of-pipe LID design and policy enforcement and

maintenance on the back mall parking lot

Recommendations:

Initial USSR Study Resulting Recommendations

Page 11: Kestrel pres feb 13, 13

•  Continued Quantitative data collection on all three sites: •  Water quality testing based on seasonal collection to monitor

water quality discharge into the Creek •  Development of a case study plan based on a possible end-of-

pipe LID on County Fair •  Further water quality testing done upstream and downstream of

outfall, soil nutrient, organic and composition testing and infiltration rate testing

•  This additional testing was to determine if County Fair was a suitable LID site and aide in final remediation recommendations.

Research was aimed at finalizing a remediation option plan based on the initial recommendations produced from USSR

Development of Remediation Option Plan

Page 12: Kestrel pres feb 13, 13

•  Ownership of the land •  Overall end cost •  Feasibility based on Thunder Bay’s current stormwater

management practices •  Location for optimal community education and outreach and; •  Localized stormwater inputs

Reasons why the County Fair site was selected as a case study through USSR assessment

Why County Fair as an LID Case Study

Page 13: Kestrel pres feb 13, 13
Page 14: Kestrel pres feb 13, 13

•  Court street: •  Continued, concerning elevated

levels of ammonia, nitrate and chloride

•  Castlgreen: •  Continued, concerning elevated

levels of ammonia, nitrate, nitrite and phosphate

Results of the Quantitative data

Page 15: Kestrel pres feb 13, 13

•  Concerning water quality parameters (all locations sampled): ammonia, nitrate and phosphate

•  Soil: Soil testing results showed relatively suitable soil conditions (with some engineering alterations) for a vegetated infiltration LID at the current wetland, not downstream.

•  Infiltration: Infiltration rates at the current wetland showed suitable levels for infiltration LID, again, not downstream

Quantitative Results of County Fair (LID Case Study)

Page 16: Kestrel pres feb 13, 13

•  The quantitative data used in this research project included the involvement of a multi-stakeholder group throughout the process.

•  This multi-stakeholder group included representatives from; The City of Thunder Bay, EcoSuperior, Lakehead University, Earthwise®,  Ontario Ministry of Natural Resources, Ontario Ministry of the Environment, The Northshore Steelhead Association and the Lakehead Region Conservation Authority.

The quantitative data used throughout this project does not have the final say in the recommendations, the qualitative data does….

Quantitative data not the final say

Page 17: Kestrel pres feb 13, 13

•  Stage 1: Introduction •  This included the introduction to the project and background

information. •  Stage 2: Site Visit

•  This included a group visit to all three sites with information provided.

•  Stage 3: Workshop •  This included a Multi-Stakeholder Decision Making (MSDM)

workshop structured to produce final remediation recommendations for this project.

There were 3 main stages of Stakeholder involvement in decision-making.

Stakeholder Involvement

Page 18: Kestrel pres feb 13, 13

•  Final agreed upon Stormwater Management Objectives for Thunder Bay •  Social:

•  Context specific plans •  Ensure community safety

•  Economic: •  To internalize the cost of new stormwater management •  Integration of stormwater into asset management plan

•  Environmental: •  Reduce surface volume runoff •  Improve quality of runoff •  Increase and enhance integrity

•  Political •  Creation and adoption of the stormwater management plan •  Ensure balance between short and long-term planning

•  Most of all à CREATE PARTNERSHIPS

The Stakeholders were provided with all known information on the three sites and asked to complete specific tasks

Results of the Workshop

Page 19: Kestrel pres feb 13, 13

•  Court Street possible remediation options: •  1) Increase by-law enforcement •  2)Community Stewardship initiative •  3)Adopt LRCA’s previous education strategy

•  Most valued recommendation for meeting objectives •  Community education campaign

•  Castlegreen possible remediation options •  1) further investigate pipe system •  2) Work with the co-op to educate community •  3) Maintenance on heaving and buckling road

•  Most valued recommendation for meeting objectives: •  Partnership with the co-op

•  County Fair possible remediation options: •  1) remove section of pipe, or create end-of-pipe LID •  2) Educate and partner with land owner to remediate up-land •  3) Leave alone

•  Most valued recommendation for meeting objectives: •  Educate and partner with land owner

Final site specific Recommendations from Stakeholders

Page 20: Kestrel pres feb 13, 13

1)  First and foremost that the defined objectives for Thunder Bay stormwater management be considered in all further stromwater management

2)  Before further stormwater remediation plans are pursued on McVicar Creek that the final recommendations proposed by Stakeholders are completed; An education and outreach plan on McVicar Creek watershed hotspots and in the watershed as a whole

3)  That the process used in this research project be referenced to determine further stormwater remediation options within Thunder Bay

4)  That the baseline data collected in this project be used for any further LID proposal on the County Fair site

Final Remediation Recommendations for McVicar Creek Resulting from this Project

Page 21: Kestrel pres feb 13, 13

QUESTIONS?

Page 22: Kestrel pres feb 13, 13

northshorerap.ca