kick of wp3 steps towards building oxford, first project meeting 23-05-2006 10:30 am – 11:15 am
TRANSCRIPT
Current status WP3
"WP3 is on hold until:
the transistion from conceptual framework to implemenation is more clear, and there is a consensus on the architecture.
We hope to overcome these issues at the Oxford project meeting."
Outline next 40 min..
Definition of work Contributions of the partners
(5 min. Presentations) Setting up a planning
Project plan DoW
Conceptual Framework
Pilots
Technical infrastructure
Architecture(compontents & environments)
Formative evaluation
User needs
Evaluation methodology
Evaluations Researches Realisation
Components of the DoW
The principal components are:The attention detection component: Its role is to observe the action of the user, establish current user focus, and update the user model (and in particular
attentional state)
The agent reasoning component. Its role is to analyze the attentional state of the user, and to
construct some possible interventions through the evaluation of possible alternative foci.
The agent intervention component. Its role is to select and execute a particular intervention.
3.1 Implementation Plan
3.4 Validation of the pilots
3.3 Integration in pilot enviroments
3.2 Atgentive Module
Steps of WP3
Defening the steps
T3.1: Implementation preparation, methodology & plan. Technical approaches are analysed and technical decisions are taken, the development methodology (XP based) is clarified and an implementation plan (for both the components and the e-learning platforms) is elaborated.
T3.2 Implementation of the attention recognition component, the agent reasoning component and the agent intervention component. The different components are developed according to the specifications in WP2. Central to this iterative development process will be the modularity and flexibility of the components.
T3.3: Global integration and technical testing for two pilots. The different components of AtGentive will be integrated in the collaborative e-learning platforms, resulting in first prototypes of AtGentSchool and AtGentNet. Elaboration of the general user’s documentation (integrated as much as possible into the platform).
T3.4: Implementation, setting-up and execution of the validation of the user interaction using eye-tracking.The prototypes will be validated in user tests in which eye-tracking technology will play and important role to asses the functioning of the different components with the AtGentSchool and AtGentNet environment.
Steps of WP3
AtGentive Module Interface Application
Implementation methodoly & plan for the Atgentive module
Embedding in the enviroment
Global integration / setting up two prototypes, Atgentnet & Atgentschool
Implemantation + internal validation
3.1
WP3
3.4
3.3
3.2
Implementation methodoly & plan for the applications
Contribution Ontdeknet WP3
Project management + securing the overview
Building specific compontents Ontdeknet Developing the interface between
Atgentive module and Ontdeknet Implementation of Atgentive
Planning milestones
WP Milestone Month Description
WP1 M1.1 M04 State of the art completed
WP1 M1.2 M06 Conceptual Framework first draft done
WP2 M2.1 M07 Design of the components completed
WP2 M2.2 M12 Design of the learning platforms completed
WP3 M3.1 M12 First delivery of components
WP3 M3.2 M16 Working prototypes AtGentSchool and AtGentNet
WP4 M4.1 M06 Evaluation approach has been defined
WP4 M4.2 M09 Formative evaluation has been completed
Planning
ID Task Name Start FinishQ1 06 Q2 06 Q3 06 Q4 06 Q1 07 Q2 07 Q3 07 Q4 07
dec jan feb mrt apr mei jun jul aug sep okt nov dec jan feb mrt apr mei jun jul aug sep okt nov dec
4 31-3-200631-3-20061.2 Report; Conceptual Framework
7 30-6-200630-6-20062.1 Design components
8 30-11-200630-11-20062.2 Learning platforms
12 30-11-200630-11-20063.1 First Delivery Components
13 30-3-200730-3-20073.2 Implementation Prototype
16 31-5-200631-5-20064.1 Evaluation approach
17 31-8-200631-8-20064.2 Formative evaluation
18 30-11-200630-11-20064.3 Evaluation plan
19 31-10-200731-10-20074.4 Evaluation Report
22 30-11-200630-11-20065.1 Specification of implementation
23 30-4-200730-4-20075.2 Pilot Schools
24 30-4-200730-4-20075.3 Pilot business
27 31-1-200631-1-20066.1 Website v1
28 31-5-200631-5-20066.2 Exploitation plan
29 31-1-200731-1-20076.3 Website v2
32 30-11-200630-11-20067.1 Mid term report
33 30-11-200730-11-20077.2 Final report
1 1-6-20061-12-2005WP1
6 31-10-20061-3-2006WP2
11 27-7-20071-5-2006WP3
15 30-11-20072-1-2006WP4
21 30-11-20071-9-2006WP5
26 30-11-20071-12-2005WP6
31 30-11-20071-12-2005WP7
2 24-1-200623-1-2006*planned* Workshop
25 31-10-200731-10-20075.4 Report pilots
30 31-10-200731-10-20076.4 Final exploitation
9 30-11-200630-11-20062.3 Approaches
10
3 31-1-200631-1-20061.1 Workshop
5 31-7-200631-7-20061.3 Final Conceptual Framework (M06; draft)
24-5-200623-5-2006*Planned* First Project meeting
14 27-11-200627-11-2006*Second Project meeting (IST-conference Helsinki)
20 15-5-200715-5-2007*Third Project meeting