KIDS FIT FOR LIFEKIDS FIT FOR LIFE
Prepared by:
Michael Helsel Project Manager
Lloyd West Business Analyst
Roger Miller Hardware Engineer
Daryl Basarab Graphic Designer
INITIAL ANALYSISINITIAL ANALYSIS
• Project descriptionProject description
• Project requirementsProject requirements
• BudgetBudget
• ScheduleSchedule
Final Status ReportFinal Status ReportProject Name: Kids Fit For LifeTeam Member Name: Roger MillerDate: 05/07/2008Reporting Period: 04/03/2008 – 05/07/2008
Work completed this reporting period:- Initial use case diagram and narratives- ERD and Class Diagram- Flow chart and Story Board- RFQ’s- Analysis specifications delivered and given tentative approval.
Work to complete next reporting period:- Purchase hardware- Hardware setup- Create web site- Roll out product
What’s going well and why: - The Team continues to work well together due to weekly meetings where
problems and conflicts are addressed and resolved. - Tentative approvals have been given by the Client on project analysis; this has been
accomplished due to the diligence and cooperation of all team members.
What’s not going well and why: - Content development. The content is taking longer to develop as a result of client
changes and modifications.
Suggestions/Issues:
Project changes - Content scope now requires an end user survey to start after the user exits the
program.
LESSONS LEARNEDLESSONS LEARNED
• TEAMWORK TEAMWORK
• TIME MANAGEMENTTIME MANAGEMENT
• COMMUNICATIONCOMMUNICATION
• PROJECT SPONSORPROJECT SPONSOR
SOFTWARE DEVELOPMENTSOFTWARE DEVELOPMENT
• USE CASESUSE CASES
• ERDERD
• CLASS DIAGRAMCLASS DIAGRAM
USE CASEUSE CASE
NARRATIVENARRATIVE
ERDERD
PRODUCT
PK ProductID
ProductDescription
PAGE_NAVIGATION
PK ScreenID
ScreenName ScreenText BackgroundImage Narration Narrator ContentType BackgroundSoundFK1 ProductID
CONTROL_INTERACTION
PK ControlID
ControlName ControlProperty ControlValueFK1 ScreenID
CLASS DIAGRAMCLASS DIAGRAM
Get Health Information
SELECT LANGUAGESELECT LANGUAGE
SELECT CONTENT PAGESELECT CONTENT PAGE
EXERCISE PAGEEXERCISE PAGE
HARDWARE DEVELOPMENTHARDWARE DEVELOPMENT
Initial requirementsInitial requirements
- Kiosk- Kiosk
- Small Form PC (- Small Form PC (wireless capable)wireless capable)
- Touch-screen monitor- Touch-screen monitor
- Speakers- Speakers
- Phone- Phone
- Power protection- Power protection
- Accessories (cables, velcro, etc.)- Accessories (cables, velcro, etc.)
HardwareHardware
• Selection processSelection process– Preferred vendorsPreferred vendors– Research alternative vendorsResearch alternative vendors– Issue RFQ’sIssue RFQ’s
HardwareHardware• Comparison MatrixComparison Matrix
Dell Optiplex Dell Optiplex 755755
HP DC 5750HP DC 5750
CriteriaCriteria
Case SizeCase Size Small FormSmall Form Small FormSmall Form
Hard drive sizeHard drive size 80 GB80 GB 80 GB80 GB
MemoryMemory 1 GB PC53001 GB PC5300 1 GB DDR1 GB DDR
Processor SpeedProcessor Speed Intel Duo Intel Duo Core2.2 GHzCore2.2 GHz
AMD Athion Dual AMD Athion Dual Core 2.3 GHzCore 2.3 GHz
Service ContractService Contract 3 Yr NBD on site3 Yr NBD on site 3 Yr NBD on site3 Yr NBD on site
PricePrice $ 1056$ 1056 $ 1196$ 1196
Build TimeBuild Time 7 days7 days 7 days7 days
Notes: St. Andrews prefers to use Dell products. As the matrix shows similar products are available for close to the same price. Since HP is priced higher we chose to go with Dell. Using Dell products also simplifies St. Andrews Hardware support by keeping it uniform and consistent.
RFQRFQ
FLOW CHARTFLOW CHART
CONTENT DEVELOPMENTCONTENT DEVELOPMENT