kinetics of prototype hea`vy water reactor ...the reactor power soon recovered to the rated power....
TRANSCRIPT
Th;s material has been copiedunder licence from CANCOPY.
Resale or further copying of this material i3strictly prohibited.
Le presont document a t reproduitavec l'autorisation de CANC!OPY.
La revente ou la reproduction ultirieuroen sont strictement interdites.
N 341 72-08
PAPERS PRESENTED BY JAPANAT THE MEETING ON VOID COEFFICIENTOF HEAVY WATE RMODERATED BOILINGLIGHT WATER COOLED REACTORS, PARIS.18-20 SEPT. 1972
KINETICS OF PROTOTYPE HEA`VYWATER REACTOR (FUGEN)
September, 1972
Power Reactor and Nuclear Fuel
Development Corporation, Tokyo, Japan
C 0 N T E N T S
I. Instrumentation and Control
I.1 Reactivity Control
1.2 Reactor Power Control
1.3 Reactor Protection
I.4 Nuclear Instrumentation
II. Analysis of Plant Dynamics
List of Figure
Fig. 1 Core configuration
Fig. 2 Safety circuit
Fig. 3 Schematic diagram of scram circuit
Fig. 4 Schematic diagram of. nuclear instrumentation
Fig. 5 Reactor control scheme
Fig. 6 Response for recirculation pumps trip
Fig. 7 Response for turbine trip (By-pass valve does not work)
Fig. 8 Response for reactivity disturbance at rated power
(corresponding to 10% power reduction)
Fig. 9 Response for reactivity disturbance at half power
Fig. 10 Response for reactivity disturbance with region power
control
Fig. 11 Response for steam drum level set point change
(0.1 m change of setting water level)
Fig. 12 Response for initial pressure set point change
(1 atm change of pressure setting)
I. Instrumentation and Control
In the FUGEN plant, the main instrumentation and control systems are
concentrated at a central control room. These system are designed to be
as testable as possible in operating conditions. The reactor power is
controlled manually over the entire power range and also automatically
in that over 40 % power.-
The steam drum pressure .in operating condition is maintained constant
by an initial pressure regulator (IPR).
I.1 Reactivity Control
Control rods and liquid poison in the moderator are prepared for
reactivity control. The moderator poison is used to suppress the excess
reactivity in the initial core and to compensate such slow reactivity
change as burnup.
I;2 Reactor Power Control
49 control rods. are distributed throughout the core as shown in Pig. 1.
4 control rods located in the center of each region are used for power
regulation. These four rods are called regulating rods. The position of
each regulating rod is automatically controlled by a signal of deviation
between averaged regional power and the setting power. The other 45 control
rods are used for reactor. shutdown with sufficient margin (one most ef-
fective rod stuck is considered), and some are also used for flattening
the power distribution.
I.3 Reactor Protection
The reactor protection system has two functions. The first is to give
an alarm, to block control rod withdrawal, to scram and to dump moderator
in off-normal operating conditions. The second is to close reactor
isolation valves, to operate emergency core cooling system; high pressure
core injection system (EPCI), low pressure core injection system (LPCI),
accumulated pressure core injection system (APCI), etc., in accident con-
ditions. Figure 2 shows the diagram of safety protection. A diagram of
the reactor scram logic is shown in Fig. 3. This system consists of a
dual one out of two circuits.
I.4 Nuclear Instrumentation
The reactor power is measured by -the in-core neutron monitoring systems
from the neutron source level to the power operation level through about
nine decades.
- I -
In order to obtain sufficient sensitivity to start up the reactor
and to secure detailed information of the neutron flux throughout the core,
all the neutron detectors are installed in the core. (see Fig. 1)
In-core neutron monitoring systems consist of the source range
monitor (SRM), the intermediate range monitor (11M) and the power range
monitor (PRII). The measurable ranges of these monitors are partially
overlapped and fission counters and chambers are used as neutron detectors
for these monitors.
I.4.1 Source Range Monitor
In order to obtain information on the neutron flux at start-up we
have four SRM. The detectors are movable fission counters. With SRM, the
neutron flux and reactor period are monitored.
I.4.2 Intermediate Range Monitor
In order to obtain information on the neutron flux in the intermediate
range, we have six SRM. Each consists of a fission chamber and a mean
square circuit etc. The measurable range of IR1I is changed adequately with
a range switch. If the indication of IRM exceeds over setting point in
the range, the reactor is scrammed for -protecting against an undesirable
power increase. IRM and SR11 are drawn out of the core in full power range.
1.4.3 Power Range Monitor
In power range, 64 local power range monitors (LPRM), 8 region average
power range monitors (R.APIM), 2 total region average power range monitors
(T.APRM) and the rod block monitor (RB4) are prepared to obtain detailed
information on the neutron flux throughout the core. Besides these, in
order to calibrate these monitors and to measure axial distribution of
neutron flux, we have the traverse incore probe (TIP).
LPRM are installed at 16 channels as shown in Fig. 1. Each channel
has four independent detectors at regular intervals vertically as illus-
trated in Fig. 4. Total number of LPRI is 64 (16 x 4). The detectors are
fission chambers (6 imm). Each detector assembly has a guide tube for TIP.
In this tube, a micro fission chamber is traversed to correct LPRI4 and
measure axial distribution of neutron flux.
R.APRT1 consists of the instrument which averages the signals of LPRM
in 1/4 core. 'When average neutron flux exceeds over 120 % of rated power,
R.APF14 gives scram signal.
- 2 -
T.APBM sums the signals of R.APRM.
RBE4 prevents the control rods being drawn out continuously by mis-
operation. When one of the 64 LPRM reaches the setting neutron flux, the
RBM works.
I : , I::
_ , _
I
CALANDRIA TANK
/ HEAVEY WATEI
/.~ 00 0 0
/ 00 0000
/ * 00 0 0 0 00/ 0.000 0000
+ ~ + +0 0+0 0+0 0+0 0
*0 0,0 0,0°0,0 0
I
0.0 0 ° 0
0 0+0 0+0 0 0
. 0+0 0o0 0 0
A A0.0000.00 00\
0 0,0 0+0 0+0 01
- . . .I1000 0 00o 0a0o0
0+00 0 0 0 0
\ *06 0+0 0-00 0-000 0 0000
0 00000
0 0'0 0'0 0'0 0'O 0+0 0+0 0 0 00 0 0 0 0 0 0 0
O'o00000*0 0-000 000 00
000000 /
0 FUEL ASSEMBLY 224 * LPRM 16 x 4+ CONTROL ROD 45 D r R M 6- REGULATING ROD 4 A S R M 4
@ I NEUTRON SOURCE I_
Fig. 1 CORE CONFIGURATION
- 4 -
I Mode switch dump I
Steam drum water level extremely low
I Container pressure high .
I He pressure high
-
Earthquake
Manual
Mode switch dump
Mode switch- shut down
Container pressure high
Steam drum pressure ah h
Steam drum water level low
Neutron flux hi gh
Neutron flux Indicate low
-
I Condeser vacuum low I
Turbin main stop valve close
[ Recirculation flow rate low
| He pressure high
[ Electric power loss
Nuclear instrumentation. -not work .
| D20 level low
Earthquoke
Manual
i Steam line radiation level high
Steam pipe rupture
Manual
Steam drum water level low
| Manua I --- }
Steam drum water level extremely low
Manual I. - f
|Container radiation level ~!high
Container pressure high
Steam drum water level extremely low
Manual
Air ejector radiation level high
I-
Steam isolation
valve close
0.N
E
* 0
*0
I.z
'0
0
Reactor core isolation
cooling operation
Container ventilation
Emergency core coolingsystem operation
IEjector outlet valve close
Fig. 2 Safety circuit
-5 -
Line A L in e B
Fig. 3 Schematic diagram of scram circuit
- 6 -
I
-1 0
Construction of power range -instrumentation
Each RPRM has twoindicator
I
Region averaged power. range monitor -
R..A PR M .
Same us left; -4 ; - . , I
.- Sme~as right
- . i
1 1 1 1 I-I
I4
1 .4
I* *oat tpw
\ Local powl
4
I I
or r(
I 4p 4I I
I 4 I
inge monitor (LPRM ) 16 x4 64)
-Power range monitor assembly ( T I P guide tube and 4 LPRM )
Region 2 Region 4Region i Region 3
Fig. 4 Schematic diagram of nuclear instrumentation
j *--
II. Analysis of Plant Dynamics
The analysis of the plant dynamics was studied using the ATM (Advanced
Thermal Reactor) plant dynamic analysis code, "TETRAC".
Some of the analysis is shown in Figs. 6-12. The following points are
noted. The plant has stable response against perturbation due to change of
setting pressure, setting drum water level, setting power level, change of
recirculation flow rate, and other perturbation in the normal operation
mode.
Stable reactor power control will be established against some fluctu-
ations in terms of the Doppler coefficient or the void coefficient from
their respective design values.
Fig. 5 shows the reactor control scheme. As mentioned above, reactor
power is controlled with control rods. Steam drum level is controlled
with three signals: drum level, steam flow and feed water flow.
Fig. 6 shows the response for recirculation pumps trip. In this
case, all of four recirculation pumps are tripped. After about one
sec.reactor is scrammed owing to low recirculation flor wate (of Fig. 2)
Fig. 7 shows the response for turbine trip. When the turbine is
tripped, the main stop valve is closed and the turbine bypass valve will
work. At present we assume that bypass valve does not work. The steam
drum pressure increases and reaches scram level (cf Fig. 2). Negative
void coefficient brings neutron flux increase till the reactor is scrammed.
Fig. 8 shows the response for reactivity disturbance at rated power.
Negative reactivity corresponding to 10% power-reduction is inserted by
step. The neutron flux undershoots but soon are stable.
Fig. 9 shows the response for reactivity disturbance at half power.
Positive reactivity corresponding to 10% power-up is inserted by step.
The neutron flux overshoots but soon are stable as described above.
Fig. 10 shows the response for reactivity disturbance with region
power control. Negative step reactivity is inserted into No.1 region.
The regulating rods in each region move to maintain the reactor power.
The reactor power soon recovered to the rated power.
Fig. 11 shows the response for steam drum level set point change.
The setting point of drum level is changed by 0.1 m. The level controller
works and after about one minute water level becomes stable.
- 8-
Fig. 12 shows the response for initial pressure set point change.
The setting point of steam pressure is changed by 1 atm. Steam pressure
controller works and soon all phenomena become stable.
- 9 -
Pressure setting
I DemandI I
GeneratorL_0n\ I Turbin by-pass
'Fe d water pump l
I 0 15) \Reactor
Recircu lotion pump
Fg 5 ReDZO leve scemcnrole or
Fi g. 5 Reactor controlI scheme,.
CO I= (D°I-
0
W > ¢, \ Maximum fuel temperature/
00 = N RN ; \ 2Minimum critical heat flux ratio0_
o E. -._
._03iO(x°S F j ~e~ flow rat
= 8 0 Surac heatX\< $>\~E _E
- 0 -O.
No o 262
E3 E -
*. . .- .0
E E-
C 04 8 12 1 2 0
Time after AC power loss (secl
Fig. 6 Response recirculation pumps trip
0T20:IrI-
0If)0
LC)~
EoC%
0CLi T
0)
01) O
C )_ _
I CM3E Ci_ I
-o
E0
0
0
-o0)
-0
- o
E
Cj
- 0-
0
.Lfl
0)
2
level
CL
Time after main steam valve close (sec
Fig. 7 Response for turbine trip ( By-passvalve does not work)
11 I
co 0 r CD - ° _ _ _ _ _
. I . '
co - ! -- 1 - Ico I
- . urface heat flux i Recirculation flow
- o 0
xEo E .-o __ _______________ --- ___________ _____
t .flux1I Id
. CSteam drum pressure V Steam drum water level Minimum ir~tem drm ;heat03
- - - - -- - - - - -- T__- - - -
E X Steam drt. oE, E.. ° -Minimum critical heat flux ratio
E e ~l n sI . I, I ,I.o ' . .
CD __ _ _ _ _ _j _ _ _ _ _ 60___ _ _ J _ __0 10 20 30 40 50 60 70 80
Fig. 8 Response for reactivity disturbance at rated power(corresponding to iO % power reduction)
90 100lime Nsec)
* P
A0DE
C-j
21-
(0
Ne
0
Q)
U)
LDi
.4-
C0
E:
0'
90 0ooTime (sec)
Fig. 9 Response for reactivity disturbance at half power
Sr-0
dQ -Li - -J._ _ _ _ _ - _
ID IS
-Steam drum water level
lI
II
, ..
.
0UI'
0
0onj
\3n
01-
E0
0.
0
C0U-
I,-
Cj
0
0
CS3
* If
E I0
LQ
I
-o- I0
a)
3:
a)
0* Lfl
-Steam drum pressure
coW
0N'
0N
NCMI,-
Ilr------r----------Il
! ~I!1-
0 o! 0
0
0kr
21
00
a) oM
tnina)CM.
E
-o0
C,,
0
or
I
x
0a)0
J= Rf
a), .
0
cn -
0
C00. _
* 0.
00. .oU
*. o
Q
.-
C0
z0
o~
0 o
.'.-* * I-
Surface heat flux |Neutron flux t) -, )
I----
. ~No.l.region control rod displacement
No.E.lZ region control rod displacement
I -- _-_____
II
I
1.------ _________.
~~~~~~~~~~I__--_----___-____
I
Ii
i
I
0) NP
I-No. .region control rod displacement
I I . I
I I
csC 10 20 30 40 50 60 70 80 90 100
- 'Time in sec
Fig. 10 Response for reactivity disturbance with region power control
ocO~ r -
o I coo -_ _ov ¢,
_ OSurface heat flux Recirculation flowo 0 e ron 0 o -- - - - - - _, - - - - - - - -ta rmwae ee
o E _ >
co ---- - -0_ I------LO O We 1
00
Surfacee (e se lo
FSteam drumxatio leveln( LO LO c c sl
E I -
= 0
LOC -. I ta drumr Ste eamdrmprssr00
E) FC) -
('a (0
0D 10 20 30 40 50 60 70 80 90 100Time (sec)
Fig. II Response f or steam drum level set point change(0.1 m change of setting water level)
-I
CQ
LOco 2o
co
I
I
a
a
0.
E2
E
C,,
>C.
=3 Cuj.4-
C)
a,
08
CnI-
_I_
3:
S0
a,Ct)
-
0-
.4
-0
C.)
~4
Surface heat flux i
I I I '
I_ ____ _ __-
Neutron: flux
o' 1- ! _ _
\-Recirculation, flow
co ----- --- --oeaw flow
o I I I
.,Steamd low pr ssur- - -- - - - - I- - - - - - - -
I _ _ _ _ _ _ II_ _ _ _ _ _
01
0o
0 10 20 30 40 50 60 70 80 90 100Time (sec)
Fig. 12 Response for initial pressure set point change ( latmi change of pressure setting )