kinnickinnic river: rehabilitation in an urban watershed...hec-ras model and bed material gradations...

1
Objectives The Kinnickinnic River (KKR) watershed and its mainstem and tributary channels have undergone significant man-induced changes since the 1830’s (Figure 1). These include: Urbanization of about 97 percent of the watershed; Conversion of hardwood forests to farmland (1858-1870); Drainage of the valley-bottom marshes ; Elimination of riparian vegetation; Construction of small dams and reservoirs on some of the tributaries; Channelization, straightening, concrete lining (38 percent; 9.6 miles) and enclosure (25 percent; 6.4 miles) of watershed channels (Figure 2); and Installation of infrastructure (bed and bank protection structures as well as bridges and culverts) (Figure 3). Figure 1. Kinnickinnic River Watershed showing the location of the mainstem and major tributaries. The urbanization resulted in an approximately 10-fold increase in the magnitude of the peak flows. Much of the existing concrete lining (installed between the late 1950’s and early 1970’s) is aged and deteriorating (Figure 4) and the channels no longer convey the design flows. The Milwaukee Metropolitan Sewerage District (MMSD) is exploring options for removing the concrete and rehabilitating the channels. MMSD’s goals include improved aquatic and riparian habitat and enhanced recreational opportunities while providing increased public safety and reduced impacts from flooding. In the channels that are not concrete-lined, MMSD is concerned with bank erosion (Figure 5) and vertical downcutting, as well as resulting sedimentation in the Lake Michigan estuary. An extensive field reconnaissance was carried to evaluate the existing morphology of the unlined channels, assess the condition of the channel infrastructure, identify geomorphic and hydraulic controls, and characterize the channel boundary materials (Figure 6). During the field reconnaissance, areas exhibiting bed or bank erosion were mapped to identify potential sites for rehabilitation. Representative cross sections were surveyed as part of the this study to facilitate development of the hydraulic model. The objective of the study conducted by Tetra Tech was to provide a supplementary planning tool for flood management, channel stabilization, and rehabilitation activities within the KKR watershed, primarily within MMSD’s jurisdiction. Specific objectives included: Collecting and evaluating relevant sediment and geomorphic data in the context of channel stability, flood management, and overall watershed management; Identifying existing problem areas and opportunities for improvement of watershed condition, to be integrated with flood management initiatives; Providing a comprehensive database of geomorphic and sediment-transport characteristics to enable effective watershed management and decision making; Providing guidance and prioritization of identified projects within MMSD jurisdiction. Kinnickinnic River: Rehabilitation in an Urban Watershed Stuart C. Trabant, Michael D. Harvey, Robert A. Mussetter (Tetra Tech, Inc.), David Fowler (Milwaukee Metropolitan Sewerage District) The Issues Analytical Methods (cont.) Analytical Methods (cont.) Rehabilitation Opportunities (cont.) For purposes of this analysis, the KKR and its tributaries were divided into 47 subreaches. Reach-averaged hydraulics from the HEC-RAS model and bed material gradations for the individual subreaches were used to conduct a sediment continuity analysis of the KKR for existing and future conditions. The results indicate that the most significant erosion will occur in the unlined reaches of the KKR and Lyons Park Creek, and that aggradation in the lined reaches is unlikely (Figure 9). Analytical Methods Figure 6. Bed material gradation curves for the 10 bulk samples and 4 pebble counts collected along the KKR, and the representative curves for each subreach. Figure 10. Conceptual design for the replaced channel in the Kinnickinnic River. Field Reconnaissance Sediment-transport Figure 5. Bank erosion in the unlined portion of the KKR. Figure 4. Damaged concrete lining in Holmes Avenue Creek. USGS gage information was used in conjunction with HSPF hydrologic modeling to assess the more frequently occurring flows that will be the basis for the design of the rehabilitated low flow channels and the extreme flood events that are the basis for the design of the overall flood conveyance channels under existing and future (2020 planned land use) conditions. The existing conditions analyses indicate that 10 percent mean daily flow exceedence level ranges from about 4.4 cfs in the upstream portion of the KKR to about 48 cfs at the downstream limit of the study reach, while the 100-year peak flow ranges from 1,960 cfs to 8,050 cfs at these two locations (Figure 7). Hydrology HEC-RAS modeling was used to identify the channel capacity along the KKR (Figure 8), and to provide input to the sediment- transport analysis. The HEC-RAS model was initially developed by the Southeast Wisconsin Regional Planning Committee (SWERPC), and was updated for this study using the most recent topographic mapping and survey data. In the unlined portions of the KKR, the channel capacity ranges from the 2- to 10-yr RI peak flows. In the concrete-lined portions of the KKR, the channel capacity is generally greater than the 100-yr RI peak flow, except in areas that are affected by localized backwater zones created by bridges and in one reach with heavy residential encroachment where the channel capacity is less than the 25-yr RI peak flow. Hydraulics Rehabilitation Opportunities The primary problems identified within the KKR and tributaries by this study and the identified opportunities for rehabilitation are: Problem: Lack of hydraulic capacity (<100-year peak flow), primarily in the concrete-lined subreaches of the KKR between South 43rd Street and South 6th Avenue. Rehabilitation Opportunity: Replacement of the existing, concrete-lined channel with a larger channel geometry to provide increased flood conveyance. Successful replacement could be achieved with a compound channel, sized to convey the 100-yr RI design flow without eroding, including a low-flow, rock-lined channel sized to convey about the 0.1-percent mean daily exceedence flow (Figures 10 and 11). Appropriate vertical and lateral variability could be incorporated to provide fish passage and resting areas. 1.01 1.053 1.111 1.25 2 5 10 20 50 100 200 500 Return Period (Years) 0 0 1 1 2 5 10 20 30 40 50 60 70 80 90 95 98 99 Exceedence Probability 1,000 10,000 2,000 4,000 6,000 8,000 20,000 800 600 Discharge (cfs) Measured Values (WY77-WY08) Computed Frequency Curve, Measured Values (WY77-WY08) 0.5 0.2 U p p e r 9 0 % Confi de nce Li m i t Lower 90 % Co n f i d inec e Li mit Confluence with Lyons Park Creek Pedestrian Bridge at S. 51st St. S. 43rd St. Pedestrian Bridge Jackson Park Tunnel W. Kinnickinnic River Parkway (Jackson Park) W. Forest Home Avenue S. 35th Street Pedestrian Bridge W. Kinnickinnic River Parkway (Saint Lukes) S. 29th St. S. 27th St./US Hwy 41 Union Pacific Railroad Spur S. 20th St. Union Pacific Railroad W. Cleveland Ave Pedestrian Bridge S. 16th St. S. 13th St. S. 9th Pl. S. 6th St. W. Chase Ave./State Hwy 38 S. 1st St. (Upstream Bridge) W. Lincoln Ave. W. Becher St. S. 1st St. (Downstream Bridge) S. Kinnickinnic Ave./State Hwy 32 Union Pacific Railroad KKR11 KKR10 KKR9 KKR8 KKR7 KKR6 KKR5 KKR4 KKR3 KKR2 KKR1 500 520 540 560 580 600 620 640 660 680 700 0 5,000 10,000 15,000 20,000 25,000 30,000 35,000 40,000 45,000 Elevation (ft, NGVD 29) Station (ft) Channel Bed 50% MDQ 10% MDQ 1% MDQ 1.5-yr 2-yr 5-yr 10-yr 25-yr 50-yr 100-yr Top of Const. Chnl Left Top of Bank Right Top of Bank Figure 8. Channel capacity evaluation in the KKR. Figure 7. Flood frequency curve at the S. 11 th Street Gage. Figure 9. Results of the sediment-continuity analysis in Lyons Park Creek and the KKR. Natural Natural Concrete-Lined Enclosed Concrete-Lined Concrete-Lined Concrete-Lined Natural Natural Natural Natural Concrete-Lined Concrete-Lined Concrete-Lined Concrete-Lined Concrete-Lined Rock-Lined Natural 194.2 0.01 0.1 1 10 Annual Sediment Load (ac-ft/yr) Trib Supply U/S Supply Capacity Problem: Failed and poor-condition, open-channel concrete lining, primarily in the KKR that was constructed in the early 1960s and is coincident with the impaired hydraulic capacity. Rehabilitation Opportunity: Given the coincidence between the poor state of the concrete and the impaired hydraulic capacity, the compound channel identified to mitigate problems with channel capacity would also remedy the problems with the concrete lining. Problem: Eroding unlined channel segments in the KKR and tributaries that both threaten streamside infrastructure and supply sediment to the downstream estuary of the KKR where it is deposited. Rehabilitation Opportunity: Stabilization of the eroding banks that are currently threatening infrastructure could be achieved by installing a rock toe designed to withstand movement at the 100-yr RI flow with bio-engineered upper banks (Figure 12). Rock riffle grade control structures will be necessary in areas of downcutting, and will also enhance habitat (Figure 13). Figure 11. Photgraph of the existing KKR and conceptual rendering of the rehabilitated channel. Problem: Sedimentation in the Lake Michigan estuary. Rehabilitation Opportunity: Stabilization of the currently eroding banks and installation of grade control structures would reduce sediment loads delivered to the estuary by about 50 percent. Figure 12. Conceptual design of combination rock-toe and bio- engineered bank stabilization. Figure 13. Conceptual design of rock riffle grade control structure. Figure 3. 1960 photograph of riprap along the KKR. Figure 2. 1961 photograph of the recently lined KKR.

Upload: others

Post on 12-Mar-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Kinnickinnic River: Rehabilitation in an Urban Watershed...HEC-RAS model and bed material gradations for the individual subreaches were used to conduct a sediment continuity analysis

ObjectivesThe Kinnickinnic River (KKR) watershed and its mainstem andtributary channels have undergone significant man-inducedchanges since the 1830’s (Figure 1). These include:

� Urbanization of about 97 percent of the watershed;� Conversion of hardwood forests to farmland (1858-1870);� Drainage of the valley-bottom marshes ;� Elimination of riparian vegetation;� Construction of small dams and reservoirs on some of the

tributaries;� Channelization, straightening, concrete lining (38 percent; 9.6

miles) and enclosure (25 percent; 6.4 miles) of watershedchannels (Figure 2); and

� Installation of infrastructure (bed and bank protectionstructures as well as bridges and culverts) (Figure 3).

Figure 1. Kinnickinnic River Watershed showing the location of themainstem and major tributaries.

The urbanization resulted in an approximately 10-fold increase inthe magnitude of the peak flows. Much of the existing concretelining (installed between the late 1950’s and early 1970’s) is agedand deteriorating (Figure 4) and the channels no longer convey thedesign flows. The Milwaukee Metropolitan Sewerage District(MMSD) is exploring options for removing the concrete andrehabilitating the channels. MMSD’s goals include improvedaquatic and riparian habitat and enhanced recreationalopportunities while providing increased public safety and reducedimpacts from flooding. In the channels that are not concrete-lined,MMSD is concerned with bank erosion (Figure 5) and verticaldowncutting, as well as resulting sedimentation in the LakeMichigan estuary.

An extensive field reconnaissance was carried to evaluate theexisting morphology of the unlined channels, assess the conditionof the channel infrastructure, identify geomorphic and hydrauliccontrols, and characterize the channel boundary materials (Figure6). During the field reconnaissance, areas exhibiting bed or bankerosion were mapped to identify potential sites for rehabilitation.Representative cross sections were surveyed as part of the thisstudy to facilitate development of the hydraulic model.

The objective of the study conducted by Tetra Tech was to providea supplementary planning tool for flood management, channelstabilization, and rehabilitation activities within the KKR watershed,primarily within MMSD’s jurisdiction. Specific objectives included:

� Collecting and evaluating relevant sediment and geomorphicdata in the context of channel stability, flood management, andoverall watershed management;

� Identifying existing problem areas and opportunities forimprovement of watershed condition, to be integrated with floodmanagement initiatives;

� Providing a comprehensive database of geomorphic andsediment-transport characteristics to enable effective watershedmanagement and decision making;

� Providing guidance and prioritization of identified projects withinMMSD jurisdiction.

Kinnickinnic River: Rehabilitation in an Urban WatershedStuart C. Trabant, Michael D. Harvey, Robert A. Mussetter (Tetra Tech, Inc.),

David Fowler (Milwaukee Metropolitan Sewerage District)

The Issues Analytical Methods (cont.) Analytical Methods (cont.) Rehabilitation Opportunities (cont.)

For purposes of this analysis, the KKR and its tributaries weredivided into 47 subreaches. Reach-averaged hydraulics from theHEC-RAS model and bed material gradations for the individualsubreaches were used to conduct a sediment continuity analysis ofthe KKR for existing and future conditions. The results indicate thatthe most significant erosion will occur in the unlined reaches of theKKR and Lyons Park Creek, and that aggradation in the linedreaches is unlikely (Figure 9).

Analytical Methods

Figure 6. Bed material gradation curves for the 10 bulk samplesand 4 pebble counts collected along the KKR, and therepresentative curves for each subreach.

Figure 10. Conceptual design for the replaced channel in the Kinnickinnic River.

Field Reconnaissance

Sediment-transport

Figure 5. Bank erosion in the unlined portion of the KKR.

Figure 4. Damaged concrete lining in Holmes Avenue Creek.

USGS gage information was used in conjunction with HSPFhydrologic modeling to assess the more frequently occurring flowsthat will be the basis for the design of the rehabilitated low flowchannels and the extreme flood events that are the basis for thedesign of the overall flood conveyance channels under existingand future (2020 planned land use) conditions. The existingconditions analyses indicate that 10 percent mean daily flowexceedence level ranges from about 4.4 cfs in the upstreamportion of the KKR to about 48 cfs at the downstream limit of thestudy reach, while the 100-year peak flow ranges from 1,960 cfs to8,050 cfs at these two locations (Figure 7).

Hydrology

HEC-RAS modeling was used to identify the channel capacityalong the KKR (Figure 8), and to provide input to the sediment-transport analysis. The HEC-RAS model was initially developed bythe Southeast Wisconsin Regional Planning Committee(SWERPC), and was updated for this study using the most recenttopographic mapping and survey data. In the unlined portions ofthe KKR, the channel capacity ranges from the 2- to 10-yr RI peakflows. In the concrete-lined portions of the KKR, the channelcapacity is generally greater than the 100-yr RI peak flow, except inareas that are affected by localized backwater zones created bybridges and in one reach with heavy residential encroachmentwhere the channel capacity is less than the 25-yr RI peak flow.

Hydraulics

Rehabilitation OpportunitiesThe primary problems identified within the KKR and tributaries bythis study and the identified opportunities for rehabilitation are:

• Problem: Lack of hydraulic capacity (<100-year peak flow),primarily in the concrete-lined subreaches of the KKR betweenSouth 43rd Street and South 6th Avenue.

� Rehabilitation Opportunity: Replacement of the existing,concrete-lined channel with a larger channel geometry toprovide increased flood conveyance. Successful replacementcould be achieved with a compound channel, sized to conveythe 100-yr RI design flow without eroding, including a low-flow,rock-lined channel sized to convey about the 0.1-percent meandaily exceedence flow (Figures 10 and 11). Appropriate verticaland lateral variability could be incorporated to provide fishpassage and resting areas.

1.01 1.053 1.111 1.25 2 5 10 20 50 100 200 500

Return Period (Years)

001125102030405060708090959899

Exceedence Probability

1,000

10,000

2,000

4,000

6,000

8,000

20,000

800

600

Dis

char

ge (

cfs)

Measured Values (WY77-WY08)

Computed Frequency Curve, Measured Values (WY77-WY08)

0.5 0.2

Upper 90% Confidence Limit

Lower 90% Confidinece Limit

Co

nfl

ue

nc

e w

ith

Ly

on

s P

ark

Cre

ek

Pe

de

stri

an

Bri

dg

e a

t S

. 51

st S

t.

S. 4

3rd

St.

Pe

de

stri

an B

rid

ge

Jack

son

Par

k T

un

ne

l

W. K

inn

icki

nn

ic R

ive

r P

arkw

ay (

Jack

son

Pa

rk)

W. F

ore

st H

om

e A

ven

ue

S. 3

5th

Str

ee

t

Pe

de

stri

an B

rid

geW

. Kin

nic

kin

nic

Riv

er

Pa

rkw

ay

(Sa

int

Luk

es)

S. 2

9th

St.

S. 2

7th

St.

/US

Hw

y 4

1

Un

ion

Pa

cifi

c R

ailr

oad

Sp

ur

S. 2

0th

St.

Un

ion

Pa

cifi

c R

ailr

oad

W. C

leve

lan

d A

ve

Pe

de

stri

an

Bri

dg

eS.

16

th S

t.

S. 1

3th

St.

S. 9

th P

l.

S. 6

th S

t.

W. C

has

e A

ve./

Sta

te H

wy

38

S. 1

st S

t. (

Up

stre

am

Bri

dge

)W

. Lin

coln

Ave

.

W. B

ech

er

St.

S. 1

st S

t. (

Do

wn

stre

am B

rid

ge)

S. K

inn

icki

nn

ic A

ve

./St

ate

Hw

y 3

2

Un

ion

Pac

ific

Rai

lro

ad

KKR11 KKR10 KKR9 KKR8 KKR7 KKR6 KKR5 KKR4 KKR3 KKR2 KKR1

500

520

540

560

580

600

620

640

660

680

700

0 5,000 10,000 15,000 20,000 25,000 30,000 35,000 40,000 45,000

Ele

va

tio

n (

ft, N

GV

D 2

9)

Station (ft)

Channel Bed

50% MDQ

10% MDQ

1% MDQ

1.5-yr

2-yr

5-yr

10-yr

25-yr

50-yr

100-yr

Top of Const. Chnl

Left Top of Bank

Right Top of Bank

Figure 8. Channel capacity evaluation in the KKR.

Figure 7. Flood frequency curve at the S. 11th Street

Gage.

Figure 9. Results of the sediment-continuity analysis in Lyons Park Creek and the KKR.

Na

tura

l

Na

tura

l

Co

ncr

ete

-Lin

ed

En

clo

sed

Co

ncr

ete

-Lin

ed

Co

ncr

ete

-Lin

ed

Co

ncr

ete

-Lin

ed

Na

tura

l

Na

tura

l

Na

tura

l

Na

tura

l

Co

ncr

ete

-Lin

ed

Co

ncr

ete

-Lin

ed

Co

ncr

ete

-Lin

ed

Co

ncr

ete

-Lin

ed

Co

ncr

ete

-Lin

ed

Ro

ck-L

ine

d

Na

tura

l

194.2

0.01

0.1

1

10

An

nu

al S

ed

ime

nt

Loa

d (

ac-

ft/y

r)

Trib Supply

U/S Supply

Capacity

• Problem: Failed and poor-condition, open-channel concretelining, primarily in the KKR that was constructed in the early1960s and is coincident with the impaired hydraulic capacity.

� Rehabilitation Opportunity: Given the coincidence betweenthe poor state of the concrete and the impaired hydrauliccapacity, the compound channel identified to mitigate problemswith channel capacity would also remedy the problems with theconcrete lining.

• Problem: Eroding unlined channel segments in the KKR andtributaries that both threaten streamside infrastructure andsupply sediment to the downstream estuary of the KKR where itis deposited.

� Rehabilitation Opportunity: Stabilization of the eroding banksthat are currently threatening infrastructure could be achievedby installing a rock toe designed to withstand movement at the100-yr RI flow with bio-engineered upper banks (Figure 12).Rock riffle grade control structures will be necessary in areas ofdowncutting, and will also enhance habitat (Figure 13).

Figure 11. Photgraph of the existing KKR and conceptual rendering of the rehabilitated channel.

• Problem: Sedimentation in the Lake Michigan estuary.� Rehabilitation Opportunity: Stabilization of the currently

eroding banks and installation of grade control structures wouldreduce sediment loads delivered to the estuary by about 50percent.

Figure 12. Conceptual design of combination rock-toe and bio-engineered bank stabilization.

Figure 13. Conceptual design of rock riffle grade control structure.

Figure 3. 1960 photograph of riprap along the KKR.

Figure 2. 1961 photograph of the recently lined KKR.