KRESA New Special Education Building Portage, Michigan, USA Special Education Category Design Concept Award TowerPinkster 2009 Exhibition of School Planning and Architecture

Upload: sarila

Post on 12-Jan-2016

33 views

Category:

Documents


0 download

DESCRIPTION

2009 Exhibition of School Planning and Architecture. KRESA New Special Education Building. Portage, Michigan, USA Special Education Category Design Concept Award TowerPinkster. KRESA New Special Education Building. Site Concept Design. Community Environment: - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: KRESA New Special Education Building

KRESANew Special Education Building

Portage, Michigan, USASpecial Education Category

Design Concept AwardTowerPinkster

2009 Exhibition of School Planning and Architecture

Page 2: KRESA New Special Education Building

KRESA New Special Education Building

Page 3: KRESA New Special Education Building

Site Concept Design

Community Environment:

In 200__, the Kalamazoo RESA (Regional Educational Service Agency) identified the need to create a new, word-class facility to better serve its 200 special needs students. Working diligently to engage the community and promote the benefits of better learning environments for autistic, physically and cognitively impaired students, KRESA passed a $23 million bond millage. Outreach efforts also resulted in an anonymous $3 million donation from a community member.

The 117,000 SF New Special Education Building (NSEB) will be located adjacent to the current KRESA Service Center and will replace the existing 30 year old Croyden School. This maximizes use of the already- established 70-acre site and allows parents, staff and the community, easy access to support services located in the Service Center. The project’s site design also incorporates outdoor play areas and a barrier-free nature trail to increase the school’s connection to the outdoors and to create amenities that would engage and support the surrounding community.

Page 4: KRESA New Special Education Building

Community Environment:

The goal for this project was to create a safe, healthy, nurturing environment for special needs students ages 2-26. A variety of spaces and environments will respond to their physical and cognitive needs, support the teaching strategies and programs of the 186 dedicated staff members, and prepare each student for life in the larger community.

While the facility’s impact on the community was a vital consideration, the physical limitations of the students was a primary concern. Many have mobility issues, and are either assisted by staff or use devices such as wheelchairs and walkers. A single-story building, exterior exit doors from student-occupied spaces, and 11,800 SF of canopies and covered walks ensure ease of movement, gross motor skill development, and independence.

Exterior Renderings

Page 5: KRESA New Special Education Building

Spatial OrganizationLearning Environment:To reflect the vision for the NESB, a “village” concept was created. Smaller, more intimate environments and larger community spaces provide learning spaces that support educational programs, as well as reflect the larger community outside the doors of the building. This fosters the students’ evolution from school to real world settings.

The building’s design allows for the progressive downsizing of spaces from the busy “Main Street” to the smaller “Village Commons”, to the quieter “Classroom Homes” and finally to intimate window seats.

The positive benefits of small learning communities for regular education populations are well documented, but this design approach is more unique in a special needs setting. The facility is organized along a daylight filled “Main Street”. Specialty Use, Multi-Purpose, Cafeteria, Therapy Pool and Administration spaces are located on one side of the Street. The other side of the Street transitions students to three pairs of “Learning Villages”.

Page 6: KRESA New Special Education Building

Village Plan (Commons, Classrooms and Support Spaces)

Learning Environment:

Each “Village” supports a variety of smaller group learning environments, consisting of a “Commons” and four classrooms or “Homes”. Although designed similarly to create maximum flexibility, each pair of Villages has a different, complimentary color palette, creating a strong sense of identity. Office and support spaces are located in the center of the Commons and resemble small buildings, reinforcing the village theme. The massing of the Villages maximizes daylighting and connection to the out of doors while minimizing circulation requirements.

The southernmost pair of Villages house a pre-school and elementary aged population. The central pair is planned for middle and high school ages; while the northernmost Villages house post-high school adults. All classrooms are designed similarly to promote maximum flexibility.

Page 7: KRESA New Special Education Building

Material SelectionsPhysical Environment

The exterior building materials were selected to reflect the “village” theme. To visually reduce the building scale, 8” x 16” brick masonry was used and resin wall panels provide color coding for the Villages.

Inside the building, “Main Street” utilizes these same exterior materials to replicate an actual streetscape, as well as offering durability, tactile and visual differences. Views to the outdoors and into Specialty Space “storefronts” provide visual interest for students and visitors and improved visibility for staff.

Natural daylight penetrates the heart of the building through clerestory windows located along “Main Street”. Concrete and steel columns support heavy timber trusses and acoustic metal decking.

Linoleum was also chosen as the most appropriate flooring for students with mobility and cognitive difficulties. The “Street” scale allows ample room for gross motor skill activities for pedestrians, crutches, wheelchairs and tricycles.

Page 8: KRESA New Special Education Building

Building Section (Village, Main Street, Specialty Rooms)

Physical Environment

The smaller “Village Commons” provide a more subdued environment. Clerestory windows utilize translucent, insulated fiberglass panels for softer, more diffused daylighting. Acoustic decking, corrugated metal and fabric wrapped panels, as well as carpeted flooring create a “quieter” space.

The classroom “Homes” feature a high performance ceiling tile for maximum acoustic control. And the window seat “Cave” spaces have lower ceilings to create a feeling of greater intimacy.

The Village Commons, the Classroom Homes, the Pool and the Gross Motor Skill Rooms all have a unique overhead rail system that assists the most physically impaired students.

As many of the students suffer from allergies, high indoor air quality was a necessity. The building HVAC is a variable air volume system emanating from three mechanical penthouses. Since a lot of learning takes place on the floor of the NSEB, a radiant floor heating system is provided in all Commons, Classrooms and most Specialty Rooms to provide greater comfort.

As a result of daylighting strategies, enhanced indoor air quality, energy efficiency and material selection, the NSEB project is anticipating a LEED Silver Certification.

Page 9: KRESA New Special Education Building

Steering Committee and Planning ProcessPlanning Process:The Planning Process officially began with the successful Bond Proposal passage on November 6, 2007 and several planning committees were established:

– A Steering Committee comprised of KRESA and Croyden School Administrators, TowerPinkster architects and engineers ensured that the “environment would align with the Vision and Goals set during the planning phase.” The Steering Committee met every two weeks during the design phase, monthly since the receipt of bids in February 2009, and will continue to meet during post occupancy activities.

– A Design Team included the Steering Committee members and Croyden School Educational Staff.

The planning process involved:– Benchmarking visits to exemplary special education schools

around the state to identify cutting edge strategies and technologies

– A planning workshop that promoted collaboration among Committee and Board members, parents and neighbors. “Virtual tours” were an outcome of this workshop and the benchmarking efforts, to help all stakeholders better visualize spaces and provide detailed feedback.

– Intensive, all-day staff interviews were held at multiple times throughout the planning year with educational and administrative staff to provide input and review of design efforts.

Page 10: KRESA New Special Education Building

Timeline of Planning ProcessPlanning Process: By utilizing a holistic design approach, the unique views and perspectives of administrators, staff, parents, community members and design professionals were seamlessly incorporated into the final design. The Steering Committee’s leadership in establishing project goals, priorities and requirements served as the criteria against which design decisions were measured. This collaborative, yet focused, effort resulted in an exceptional design in which each element supports KRESA’s mission of educating, developing and supporting Kalamazoo’s special needs students.

Page 11: KRESA New Special Education Building

Exhibition of School Planning and Architecture 2009 Project Data

Submitting Firm : TowerPinksterProject Role Architects / EngineersProject Contact Richard M. Pratt, AIA, CEFPITitle Design Department HeadAddress 678 Front Avenue – Suite 255City, State or Province, Country Grand Rapids, MI 49504, USAPhone 616-456-9944

Joint Partner Firm:Project RoleProject ContactTitleAddressCity, State or Province, CountryPhone

Other Firm:Project RoleProject ContactTitleAddressCity, State or Province, CountryPhone

Construction Firm: Miller-Davis CompanyProject Role Construction ManagerProject Contact Mark McMullinTitle Senior Project ManagerAddress 1029 Portage StreetCity, State or Province, Country Kalamazoo, MI 49001, USAPhone 269-345-3561

Page 12: KRESA New Special Education Building

Exhibition of School Planning and Architecture 2009 Project Details

Project Name KRESA Special Education Building

City Portage 

State Michigan

District Name Kalamazoo Regional Educational Service Agency 

Supt/President Ron Fuller - Superintendent 

Occupancy Date August 2010 

Grades Housed Ages 2- 26 

 

Capacity (Students) 200

Site Size (acres) 70 acres – shared with KRESA Service Center 

Gross Area (sq. ft.) 123,600 SF 

Per Occupant (pupil) 618 SF/student 

gross/net please indicate 117,700 SF building – 11,800 SF of canopies 

 

Design and Build?  No

If yes, Total Cost:  

Includes:  

 

If no,  

Site Development: $ 1,957,000 

Building Construction: $ 16,565,000 

Fixed Equipment: $ 1,740,000 

Other: $ 2,636,000 

 

Total:  $ 22,898,000

Page 13: KRESA New Special Education Building

List of Participants

TowerPinkster Participants:Steve Hoekzema, AIA, NCARB, Principal-in-ChargeJim Ross, Sr. Project ManagerRichard Pratt, AIA, CEFPI, Design LeadRebecca Meggs, NCIDQ, LEED AP, Sr. Interior DesignerLentz Becraft, PE, LEED AP, Electrical EngineerPerry Hausman, PE, LEED AP, Mechanical EngineerShawn Parshall, AAIA, LEED AP, Architectural Designer

Miller-Davis Participants:John Van Stratt, Project ExecutivePaul Ickes, Chief EstimatorMark McMullin, Senior Project Manager

KRESA Participants:Ronald L. Fuller, SuperintendentHolly Norman, Assist. Superintendent - FinanceGarret Boersma, Assist. Superintendent – Spec. EducationLynne Cowart, Assist. Superintendent – InstructionalAngela Telfer, Principal – Croyden SchoolDave Flook, Owner’s RepresentativeAngela Moon, Physical TherapistChristi Craft, School NurseCasey Pawell, Occupational TherapistDebbie Siwula, SCI TeacherCarmen Jonaitis, ECDD TeacherDianle Merkel, Administrator of CI Programs