Page 1: Öksüt Gold Project Photographic Construction Update 8 · 2015 Feasibility Highlights EIAapproval received in November 2015 Forestry Permit & GSM License receivedJuly 2016 Pastureland

March 27, 2019TSX: CGwww.centerragold.com

Öksüt Gold ProjectPhotographic Construction Update 8

Page 2: Öksüt Gold Project Photographic Construction Update 8 · 2015 Feasibility Highlights EIAapproval received in November 2015 Forestry Permit & GSM License receivedJuly 2016 Pastureland

Öksüt: Funded High Margin Gold Production

Mine Type Open Pit, Heap Leach

Avg. LOM Annual Production 110koz Au

Avg. LOM AISC(1) (US$/oz) $490

Reserve Mine Life 8 years

Development Capex (US$MM) $221

LOM Sustaining Capital(1) (US$MM) $10

P&P Reserves(2)(Moz) 1.3

Au grade (g/t)(2) 1.4

Life of Mine Strip Ratio (w:o) 2:1

First Gold Pour (3) Q1-2020

2015 Feasibility Highlights

EIA approval received in November 2015

Forestry Permit & GSM License received July 2016

Pastureland Permit received January 2018

Investment Incentive Certificate received February 2018

Construction commenced late-March 2018

Bought back Stratex and Teck royalties

US$150MM low-cost financing in-place

Admin AreaCatalyst Schedule

Öksüt Gold Project

(1) Non-GAAP measure see “Non-GAAP Measures” in Centerra’s MD&A and news release of February 22, 2019.(2) Refer to February 22, 2019 news release and Technical Report on Öksüt Gold Project dated September 3, 2015.(3) Forward-looking information refer to news release of February 22, 2019.March 2019 2

Page 3: Öksüt Gold Project Photographic Construction Update 8 · 2015 Feasibility Highlights EIAapproval received in November 2015 Forestry Permit & GSM License receivedJuly 2016 Pastureland

General Mine Site Layout

March 2019 3

Page 4: Öksüt Gold Project Photographic Construction Update 8 · 2015 Feasibility Highlights EIAapproval received in November 2015 Forestry Permit & GSM License receivedJuly 2016 Pastureland

Admin Office Area Overview

March 2019 4

Page 5: Öksüt Gold Project Photographic Construction Update 8 · 2015 Feasibility Highlights EIAapproval received in November 2015 Forestry Permit & GSM License receivedJuly 2016 Pastureland

Haul Road and Keltepe Open Pit Location

March 2019 5

Page 6: Öksüt Gold Project Photographic Construction Update 8 · 2015 Feasibility Highlights EIAapproval received in November 2015 Forestry Permit & GSM License receivedJuly 2016 Pastureland

Primary Crusher Steel Work 

March 2019 6

Page 7: Öksüt Gold Project Photographic Construction Update 8 · 2015 Feasibility Highlights EIAapproval received in November 2015 Forestry Permit & GSM License receivedJuly 2016 Pastureland

Crushing Area ‐ Crushers in Place

March 2019 7

Page 8: Öksüt Gold Project Photographic Construction Update 8 · 2015 Feasibility Highlights EIAapproval received in November 2015 Forestry Permit & GSM License receivedJuly 2016 Pastureland

Hydraulic Rock Breaker Onsite

March 2019 8

Page 9: Öksüt Gold Project Photographic Construction Update 8 · 2015 Feasibility Highlights EIAapproval received in November 2015 Forestry Permit & GSM License receivedJuly 2016 Pastureland

Stacker Conveyor Installation

March 2019 9

Page 10: Öksüt Gold Project Photographic Construction Update 8 · 2015 Feasibility Highlights EIAapproval received in November 2015 Forestry Permit & GSM License receivedJuly 2016 Pastureland

ADR Plant Construction

March 2019 10

Page 11: Öksüt Gold Project Photographic Construction Update 8 · 2015 Feasibility Highlights EIAapproval received in November 2015 Forestry Permit & GSM License receivedJuly 2016 Pastureland

ADR Plant Construction

March 2019 11

Page 12: Öksüt Gold Project Photographic Construction Update 8 · 2015 Feasibility Highlights EIAapproval received in November 2015 Forestry Permit & GSM License receivedJuly 2016 Pastureland

ADR Plant ‐ Tanks/Regen Plant

March 2019 12

Page 13: Öksüt Gold Project Photographic Construction Update 8 · 2015 Feasibility Highlights EIAapproval received in November 2015 Forestry Permit & GSM License receivedJuly 2016 Pastureland

ADR Plant – Carbon Tanks

March 2019 13

Carbon Regen Plant

Carbon Fines Tank

Quench Tank

Carbon Attrition

Tank

Page 14: Öksüt Gold Project Photographic Construction Update 8 · 2015 Feasibility Highlights EIAapproval received in November 2015 Forestry Permit & GSM License receivedJuly 2016 Pastureland

Barren Ellution Tank Installed

March 2019 14

Page 15: Öksüt Gold Project Photographic Construction Update 8 · 2015 Feasibility Highlights EIAapproval received in November 2015 Forestry Permit & GSM License receivedJuly 2016 Pastureland

Electro Winning / Filter Press Installed

March 2019 15

Page 16: Öksüt Gold Project Photographic Construction Update 8 · 2015 Feasibility Highlights EIAapproval received in November 2015 Forestry Permit & GSM License receivedJuly 2016 Pastureland

Vibrating Carbon Screen Onsite

16March 2019

Page 17: Öksüt Gold Project Photographic Construction Update 8 · 2015 Feasibility Highlights EIAapproval received in November 2015 Forestry Permit & GSM License receivedJuly 2016 Pastureland

Electric Sub‐Station Construction

March 2019 17

Page 18: Öksüt Gold Project Photographic Construction Update 8 · 2015 Feasibility Highlights EIAapproval received in November 2015 Forestry Permit & GSM License receivedJuly 2016 Pastureland

TSX: CGwww.centerragold.com