kvaerner approach to in-time and on-budget execution of...
TRANSCRIPT
Kvaerner
approach to in-time and
on-budget execution of offshore
projects
Meeting on PJSC "Gazprom“ technology development
October 4, 2017
© Kvaerner 2017
Edit date:
Via “Presentation Information” in the “Kvaerner” menu
or
via Slide Master “View”/”Master”/”Slide Master”
Industrial Holdings
Aker BP 40.0%
Aker Solutions 34.8%
Akastor 36.7%
Kvaerner 28.7%
Ocean Yield 66.2%
Aker BioMarine 99.5%
Kvaerner at a glance
2
Aker ASA Holding Structure
Projects execution (including EPCI) in the range from pre-
conceptual and up to utilization of offshore facilities
• Concrete GBS foundations (26)
• Jackets (45)
• Topsides (24)
• Floaters
• On-shore facilities
~2.600 employees in 6 countries
Revenue 2015 ~ USD 1.8 B
Revenue 2016 ~ USD 1.3 B
Share prices last 12 month +50%
Annual output >18 million of man/hours
Statoil Johan Sverdrup
Topsides, Jackets
GBS foundations
Onshore facilities
Statoil Johan Sverdrup Lundin Edvard Grieg
Hebron
Shell Norge Nyhamna
Large scale projects and phases of the
projects
© Kvaerner 2017
Edit date:
Via “Presentation Information” in the “Kvaerner” menu
or
via Slide Master “View”/”Master”/”Slide Master”
Kvaerner – EPC Scope
3
Construction
Fabrication
Assembly
Hook-up
Site engineering
Commissioning
Equipment and system
installations
Engineering
Engineering management
Studies & concepts
FEEDs
Detail engineering
Procurement
Procurement &
Subcontracting
Logistics
Quality assurance
Vendor management
Telecom
Project management HSSE & Quality
Contract management
Marine operations
Construction management
Personnel management
Commissioning
Concrete
solutions
Steel jacket
substructures
Platform
topsides
Onshore
oil and gas plants
Market leader,
Norway
Leading position Market leader,
Europe
Market leader
globally
© Kvaerner 2017
Edit date:
Via “Presentation Information” in the “Kvaerner” menu
or
via Slide Master “View”/”Master”/”Slide Master”
Some of Kvaerner’s EPC projects
4
Two Sakhalin-2 GBS (111000 and 120000 t) installed in 2005, and
one Sakhalin-1 GBS (160000 t) installed in 2012,
GBS foundation construction sites Bull Arm, Newfoundland, Canada for Hibernia GBS in
1990th, and Hebron GBS in 2010th
Vostochniy Dry Dock (Russia), construction in 2003 for
Sakhalin-2, modernization in 2012 for Sakhalin-1 project
Johan Swerdrup Project: Utilities and Living Quarters topsides (18 300 t),
completion 2018,
Johan Swerdrup Jackets for Riser Platform (22 800 t /
140 m), installed, and for Drilling (18 300 t / 140 m) and
Process Platforms (17 700 t / 140 m), completion 2018
Hebron Project GBS (685 000 t) installed
in 2017
Nyhamna Gas Plant new onshore
facilities completed in 2007, expansion
and modification completed in 2013
© Kvaerner 2017
Edit date:
Via “Presentation Information” in the “Kvaerner” menu
or
via Slide Master “View”/”Master”/”Slide Master”
Bulk concrete blocks for artificial islands
5
Fabrication and transportation
Arkhangelsk or Murmansk areas,
Series production by placing concrete in slip-forms,
Size L x W x H = 100 m x 20 m x 11 m,
Weight 14 000 t,
Transportation by heavy load vessel,
Offloading at the depth of ~ 20 m and towing to the
site,
Installation
Ballasting and setting on sea bottom
Loading of caissons and gaps with earth
extracted at the site,
Applicable for water depth 4-12 m,
Positive experience – Tarsuit caisson retained
island, Beaufort Sea.
© Kvaerner 2017
Edit date:
Via “Presentation Information” in the “Kvaerner” menu
or
via Slide Master “View”/”Master”/”Slide Master”
Bulk concrete blocks for artificial islands (second
version)
6
Each block consists of caissons with potential for towing,
Series fabrication of caissons onshore, transportation by heavy load vessel, offloading and
towing to site,
Caissons are binding together by post-tension reinforcement,
Installation of topsides modules at the site by crane vessel.
60 m
35 m
40 m
© Kvaerner 2017
Edit date:
Via “Presentation Information” in the “Kvaerner” menu
or
via Slide Master “View”/”Master”/”Slide Master”
Large scale comprehensive offshore projects.
Adriatic LNG Terminal
7
Concrete foundation180 х 88 х 48 m
2 steel storage reservoirs each 250 000 m3
GBS foundation weight 290 000 t
Total weight of the terminal 640 000 t
Capacity 8 billion m3 of natural gas per year
Water depth 30 m
Lifetime 25 years
© Kvaerner 2017
Edit date:
Via “Presentation Information” in the “Kvaerner” menu
or
via Slide Master “View”/”Master”/”Slide Master”
Adriatic LNG Terminal
Proven Execution Methodology
8
Topsides and GBS integration
Campamento, June 2008 – flooding
of dock
Construction of cellar walls
and tank slab
Tank walls and roof
construction
Topsides and GBS integration
© Kvaerner 2017
Edit date:
Via “Presentation Information” in the “Kvaerner” menu
or
via Slide Master “View”/”Master”/”Slide Master”
GBS EPCI project experience past and present
9
2014 2013 2012 2011 2010 2009 2008 2007 2006 2005 2004 2003
Sakhalin 2 Lun-A
Sakhalin 2 PA-B
Adriatic
Sakhalin 1 AD – Berkut
Hebron
34 000m3
27 000m3
82 000 m3
51 000 m3
2017 2016 2015
136 000 m3
© Kvaerner 2017
Edit date:
Via “Presentation Information” in the “Kvaerner” menu
or
via Slide Master “View”/”Master”/”Slide Master”
On-shore projects: Nyhamna Gaz Plant EPCM
10
2007: EPC for new onshore facilities; 2013: EPCM for expansion and modifications (20 000+ t of new
modules)
Main drivers:
Importance for EU energy supply including 20% of the UK’s total gas consumption since 2009 and
22 mln. households in the UK and continental Europe upon completion of expansion project
Depletion of Ormen Lange field, connection of Aasta Hansteen and potentially other fields
Long term contract: six years, and options for additional two plus two years
Ormen Lange
Aasta Hansteen
Nyhamna
Easington
http://www.kvaerner.no/en/toolsmenu/Media/Press-releases/2015/Kvarner-ASA--Kvaerner-awarded-additional-work-at-the-Nyhamna-gas-plant/
© Kvaerner 2017
Edit date:
Via “Presentation Information” in the “Kvaerner” menu
or
via Slide Master “View”/”Master”/”Slide Master”
Kvaerner Project Execution Model
Kvaerner completes projects in-time and on-budget
The core of Kvaerner’s success is implementation of
Project Execution Model (PEMTM)
40+ years of Kvaerner EPCI experience are consolidated in Project Execution Model, which is a
system of Kvaerner Corporate Regulations defining:
Sequence of project Phases, Stages, and Activities
Composition and content of design, fabrication, and management activities
Criteria for completion of preceding and initiation of subsequent activities
PEM regulations are consolidated into interdependent Modules
11
© Kvaerner 2017
Edit date:
Via “Presentation Information” in the “Kvaerner” menu
or
via Slide Master “View”/”Master”/”Slide Master”
Project Execution Model (PEMTM)
12
Is applicable to Jackets, Topsides, GBS Foundations, and on-shore facilities
Feasibility & concept
System definition
Detailing & fabrication
Assembly & erection
System completion
Opportunity
appraisal
Feasibility studies
Concept selection
Concept definition
System definition
System design &
layout
development
Global design
Detailed design
Work preparation
Prefabrication
Fabrication
Contract completion
Transport &
positioning
Assembly
Mechanical
completion
Commissioning
Transport &
installation
Start-up
Take-over
Service &
assistance
Warranty,
insurance & legal
handling complete
Work accepted &
contract closed
Comprises the whole life cycle of offshore or onshore facility – from idea to close of
EPCI Contract
© Kvaerner 2017
Edit date:
Via “Presentation Information” in the “Kvaerner” menu
or
via Slide Master “View”/”Master”/”Slide Master”
Factors leading to successful large-scale oil and gas
projects
13
According to “Independent Project Analysis” (IPA), Inc. (http://www.ipaglobal.com/)
the success or failure of the large-scale oil and gas project depends upon:
1. Quality of Front-End loading including feasibility and concept, pre-FEED, FEED,
2. Continuity of control through the entire life-cycle of the project,
3. Ability to effectively manage more aggressive schedules of oil and gas projects in
comparison with other industries.
Total number of O&G projects
studied 200+
Cost growth Production
failures
Schedule slip
Successes – 22% of total 0% 0% 0%
Failures 40% 63% 30%
Sources:
1. Merrow, E. 2003, Reflections on 10 Years of Upstream Asset Development Benchmarking. Paper Oral presentation presented at
the Offshore Technology Conference, Houston, 5-8 May.
2. Merrow, Edward W. 2011. Industrial Megaprojects: Concepts, Strategies, and Practices for Success. New Jersey, USA: John
Willey & Sons.
3. Edward W. Merrow, Independent Project Analysis, Inc. Oil and Gas Industry Megaprojects: Our Recent Track Record. Oil and Gas
Facilities, Vol. 1, Iss. 2, 24 March 2012.
© Kvaerner 2017
Edit date:
Via “Presentation Information” in the “Kvaerner” menu
or
via Slide Master “View”/”Master”/”Slide Master”
Kvaerner’s perception of failure factors with respect to
offshore projects
14
Insufficient elaboration of interdependent aspects of the project life-cycle in the course of
conceptual phase. For instance, the lack of due consideration to selection of fabrication
facilities and/or assessment of their capabilities will hinder manufacturing and integration of
components for offshore facility including need in partial or total redesign of the project,
Turnover of general contractors at sequential phases of the project,
General contractor’s lack of appropriate internal regulations and/or expertise required for
successful execution of large-scale projects,
Lack of compatibility between Oil & Gas Company's regulations for management of
exploration and production project and EPCI Contractor’s regulations for design and
development of offshore facility project.
Operation Execution
(Production started)
Definition (Development plan
defined)
Selection (Development concept
selected)
Appraisal (Reserves approved)
System Completion
Assembly and Erection
Detailing and Fabrication
System Definition
Feasibility and Concept
Oil &Gas Company’s Exploration and Production Project Life Cycle
EPC Contractor’s Offshore Facility Project Life Cycle
© Kvaerner 2017
Edit date:
Via “Presentation Information” in the “Kvaerner” menu
or
via Slide Master “View”/”Master”/”Slide Master”
Amount of conceptual and feasibility works
15
ExxonMobil
Statoil
Chevron
Conoco Phillips
Lundin Norway
Total
Eni
Shell
Bayern Gas Norge
Det Norske
Fluor
Husky Energy
Maersk Oil
Amec Inpex
Dong Energy
Repsol Argentina
Idemitsu
Operation Execution
(Production started) Definition
(Development plan defined)
Selection (Development concept
selected)
Apprisal (Reserves approved)
During the period 2011-2016 Kvaerner
completed 130+ conceptual and
feasibility studies
Typical for North Sea
% of Total Project Cost
Typical EPCI cost
distribution
Level of influence
© Kvaerner 2017
Edit date:
Via “Presentation Information” in the “Kvaerner” menu
or
via Slide Master “View”/”Master”/”Slide Master”
16
Check List Quality Levels
Typical Phase
Milestones
Phase
Stages
Activity Work Flows
Key Deliverables
Quality Level Description
Status requirem. Status
Activity Descriptions
28/09/2017 16
Typical Stage
PEM Structure
© Kvaerner 2017
Edit date:
Via “Presentation Information” in the “Kvaerner” menu
or
via Slide Master “View”/”Master”/”Slide Master”
Gate reviews
17
Carried out at predefined stage milestones to evaluate compliance
Prime gate review objectives are to:
Verify that the PEM™ and contractual requirements are fulfilled (quality, time,
cost, HSSE, etc.)
Secure readiness for the next project phase
Secure that the next project phase is adequately planned and prepared for
execution
Ensure that project management and stakeholders are informed about the
actual status
Identify and implement appropriate actions to secure optimal project
execution results
Gate reviews ensure avoiding rework – get it right the first time
© Kvaerner 2017
Edit date:
Via “Presentation Information” in the “Kvaerner” menu
or
via Slide Master “View”/”Master”/”Slide Master”
Partner Companies Integration on the base of PEM
18
Kvaerner PEM priorities and key-deliverables are integrated into the
Partner Companies execution models
Focus for earliest possible fabrication start are embedded into the Stage
Engineering execution model
Agreements are established between engineering disciplines and
fabrication with the purpose of matching engineering deliveries with
fabrication expectations
Stage milestone quality levels are ensured through incorporation of
essential level of information as outlined in the Kvaerner PEM™ into the
Partner Companies execution model
Kvaerner fabrication method best practises are implemented by the
Partner Companies
Common model review and stage compliance checklists are established
© Kvaerner 2017
Edit date:
Via “Presentation Information” in the “Kvaerner” menu
or
via Slide Master “View”/”Master”/”Slide Master”
Projects implementation
19
Kvaerner could support various forms of cooperation with Russian Oil and Gas companies under
terms and conditions subject to elaboration in each particular case. That could be:
1. Conventional execution of projects under the contract with O&G Company (in the range from high-level
study to full scale EPC). In that particular case Kvaerner would structure activities and involve
subcontractors upon agreed between Kvaerner and O&G Company,
2. Creation of joint Kvaerner and O&G Company’s project teams with significant involvement of O&G
Company’s employees into project activities. It would be reasonable to start implementation of that
approach with feasibility and conceptual studies to ensure a strong foundation for EPC phases of the
project. Local and international engineering, fabrication and construction entities could be involved,
3. Execution of early project phases (feasibility, conceptual, pre-FEED) by project teams comprising
representatives of O&G Company and local contractors with minor involvement of Kvaerner in the role of
engineering advisor and project management supervisor to establish a base for EPC phases to be executed
as per items 1 and 2 above,
Fundamental principles would be:
1. Ensure transparency and controllability of project activities for the Client,
2. Focus on mitigation of project risks with emphasis on meeting schedule and budget targets,
3. Execution of project activities in Kvaerner Project Execution Model environment,
4. Identification of the most cost-efficient solutions,
5. Localization of technologies and transfer of competencies.
Thank you for your attention.
Questions?
Contact information:
(You also could ask your questions at any time in future)
Axel Thorsdal
General Director, Kvaerner LLC (Russia)
Tel: + 7 495 664 77 11
E-mail: [email protected]
Dmitry Kazakovtsev
Deputy General Director for Business Development,
Kvaerner LLC (Russia)
Tel: + 7 495 664 77 20
Cell: + 7 905 783 16 75
E-mail: [email protected]
Backup slides
© Kvaerner 2017
Edit date:
Via “Presentation Information” in the “Kvaerner” menu
or
via Slide Master “View”/”Master”/”Slide Master”
GBS foundations for Sakhalin 1 and Sakhalin 2 Projects
22
Piltun-Astokhskoye-B (PA-B) Platform
Located 12 km off the north-eastern
coast of Sakhalin Island,
Water depth of around 30 m
In operation since 2008
GBS installed in 2005
• Weight 118 000 t
• Size of caisson 94 х 91.5 х 11,5 m
• Columns heights 39 m
• Columns diameter 24 m
Topside built separately in South
Korea by Samsung and installed in
2007
• Weight 24 000 t
• Total staff 140 employees
Production capacity: oil 70,000 b/d
(11,130 m3/d); gas 100 mln scf/d (2.8
mln m3/d)
Lunskaya-A (LUN-A) Platform
Located 15 km off the north-eastern
coast of Sakhalin Island,
Water depth of 48 m
In operation since 2008
GBS foundation installed in 2005
• Weight 111 000 t
• Size of caisson 88 х 105 х 13,5 m
• Column height 56 m
• Column diameter 20 m
Topside built in South Korea by
Samsung yard and installed in 2006
• Weight 22 000 t
• Total staff 136 employees
Production capacity: gas – 51 mln
m3/d; condensate about 50,000 b/d
(8,000 m3/d)
Berkut Platform at Arkutun-Dagy Field
Located 25 km off Sakhalin’s north-
eastern coast,
Water depth of 30-40 m
In operation since 2014
GBS:
• Weight 160 000 t
• Caisson size 100 x 133 m
• Caisson height 10 m
• Height with columns 55 m
Topside built separately in South Korea by
Daewoo
Weight 42 000 t
Production capacity: 4.5 million tons per
year of crude oil, or 90 thousand barrels
per day
© Kvaerner 2017
Edit date:
Via “Presentation Information” in the “Kvaerner” menu
or
via Slide Master “View”/”Master”/”Slide Master”
Topsides for Johan Sverdrup project
23
Johan Sverdrup EPC for Utilities and Living
Quarters topsides*
Key figures
• Contract award June 2015
• Mechanical Completion October 2018
• Weight 18 300 t
• Living Quarters capacity 560 people
• Central control room for the field
Scope of work
• EPC
• JV with KBR (Kvaerner 51% - KBR 49%)
http://www.kvaerner.no/en/toolsmenu/Media/Press-releases/2015/Kvarner-ASA-Kvaerner-KBR-JV-wins-Johan-Sverdrup-platform-contract-/
© Kvaerner 2017
Edit date:
Via “Presentation Information” in the “Kvaerner” menu
or
via Slide Master “View”/”Master”/”Slide Master”
Jackets for Johan Sverdrup project
24
Riser Platform Jacket
(Installed*)
EPC 2014 – spring 2017
Weight: 22 800 t
Height: 140 m (all three)
Footprint top base:
28 m x 94 m
Footprint bottom base:
64 m x 94 m
Piles: 24
Process Platform Jacket
EPC 2015 – summer 2018
Weight: 17 700 t
Footprint top base:
28 m x 80 m
Footprint bottom base:
60 m x 80 m
Piles: 20
Drilling Platform Jacket
EPC 2014 – spring 2018
Weight: 18 300 t
Footprint top base:
33 m x 71 m
Footprint bottom base:
55 m x 85 m
Piles: 24
http://www.kvaerner.no/en/toolsmenu/Media/Press-releases/2017/The-first-jacket-for-Johan-Sverdrup-completed/
© Kvaerner 2017
Edit date:
Via “Presentation Information” in the “Kvaerner” menu
or
via Slide Master “View”/”Master”/”Slide Master”
HEBRON Project – 2017
25
Foundation
Water depth 93 m
Height 120 m
Diameter 130 m
Diameter of the cent. column 35 m
Concrete 132 000 m3
GBS weight 685 000 t
Reinforcement weight 40 000 t
Well slots 52
Storage 1.2 mln. bbls
Events
FEED 2010 г.
Planning, approvals,
modernization of
construction site 2011 г.
Construction of foundation 2012 г.
Fabrication of topsides 2013 г.
Integration 2016 г.
First oil 2017 г.
Kvaerner milestones
Sakhalin 2 LUN-A 2005 / 34 000 m3
Sakhalin 2 PA-B 2005 / 27 000 m3
Adriatic 2008 / 82 000 m3
Sakhalin 1 AD-Berkut 2012 / 51 000 m3
Hebron 2017 / 132 000 m3
http://www.kvaerner.no/en/Products/Concrete-structures-for-offshore-platforms/Hebron-GBS-Project/
http://www.kvaerner.no/en/toolsmenu/Media/Press-releases/2013/Kvarner-ASA--Kvaerner-wins-EPC-contract-for-Hebron-GBS-project/
http://www.hebronproject.com/
© Kvaerner 2017
Edit date:
Via “Presentation Information” in the “Kvaerner” menu
or
via Slide Master “View”/”Master”/”Slide Master”
GBS foundations construction sites
26
Welding
workshop
Welding
workshop
“Exotic
materials”
workshops
Warehouse
Rebar
workshops
100 t/day
Sewage
water
treatment
Bund wall
Vostochniy
Construction of gravity base structure for «Berkut» platform 2008-2012
Casting basin
265 x 138 x 14 m
Hibernia (1990-th) and Hebron (2010-th) GBS
construction site in Bull Arm, Newfoundland,
Canada
Administrative
area
Vostochniy Site establishment,
September 2003
© Kvaerner 2017
Edit date:
Via “Presentation Information” in the “Kvaerner” menu
or
via Slide Master “View”/”Master”/”Slide Master”
Conceptual Design impact on Risk and Project CAPEX
27
E
Example of Offshore platform Construction Project in the North Sea
P
Time
3 - 8 months
Concept FEED, Basic Engineering
Detailed Engineering Procurement Construction Installation
(commissioning)
~ 0.1-0,5%
6 – 8 months 6 - 8 months
14 – 19 months 30 months 6 - 8 months
~ 0,5-2% ~ 3-8% ~ 60-70% ~ 10-20%
Conceptual design has the greatest impact on the project alongside with a minimum costs and allows :
Determining the minimum profitable level of reserves’ volume for production platform;
Choosing strategy development and technology.
Identifying the ways of increasing economic profitability of project;
Reducing the risks of project financing;
Increasing the value of Total Field Development.
Conceptual
Design 10%
50% 35%
5%
90% 5%
3% 2%
-50%
-25%
0%
25%
50%
Возможность влиять на проект
Затраты проекта
FE – Front End
P – Procurement
C – Construction
I – Installation
С I
Opportunity to influence project
Costs of project
% of Total Project Cost Cost saving Design Phase
FE
© Kvaerner 2017
Edit date:
Via “Presentation Information” in the “Kvaerner” menu
or
via Slide Master “View”/”Master”/”Slide Master”
Copyright
Copyright of all published material including photographs, drawings and images in this document remains vested in Kvaerner and third party contributors as appropriate.
Accordingly, neither the whole nor any part of this document shall be reproduced in any form nor used in any manner without express prior permission and applicable
acknowledgements. No trademark, copyright or other notice shall be altered or removed from any reproduction.
Disclaimer
This Presentation includes and is based, inter alia, on forward-looking information and statements that are subject to risks and uncertainties that could cause actual results to
differ. These statements and this Presentation are based on current expectations, estimates and projections about global economic conditions, the economic conditions of the
regions and industries that are major markets for Kværner ASA and Kværner ASA’s (including subsidiaries and affiliates) lines of business. These expectations, estimates and
projections are generally identifiable by statements containing words such as “expects”, “believes”, “estimates” or similar expressions. Important factors that could cause actual
results to differ materially from those expectations include, among others, economic and market conditions in the geographic areas and industries that are or will be major markets
for Kvaerner’s businesses, oil prices, market acceptance of new products and services, changes in governmental regulations, interest rates, fluctuations in currency exchange
rates and such other factors as may be discussed from time to time in the Presentation. Although Kværner ASA believes that its expectations and the Presentation are based
upon reasonable assumptions, it can give no assurance that those expectations will be achieved or that the actual results will be as set out in the Presentation. Kværner ASA is
making no representation or warranty, expressed or implied, as to the accuracy, reliability or completeness of the Presentation, and neither Kværner ASA nor any of its directors,
officers or employees will have any liability to you or any other persons resulting from your use.
Copyright and disclaimer
Copyright
Copyright of all published material including photographs, drawings and images in this document remains vested in Kvaerner and third party contributors as appropriate.
Accordingly, neither the whole nor any part of this document shall be reproduced in any form nor used in any manner without express prior permission and applicable
acknowledgements. No trademark, copyright or other notice shall be altered or removed from any reproduction.
Disclaimer
This Presentation includes and is based, inter alia, on forward-looking information and statements that are subject to risks and uncertainties that could cause actual results to
differ. These statements and this Presentation are based on current expectations, estimates and projections about global economic conditions, the economic conditions of the
regions and industries that are major markets for Kværner ASA and Kværner ASA’s (including subsidiaries and affiliates) lines of business. These expectations, estimates and
projections are generally identifiable by statements containing words such as “expects”, “believes”, “estimates” or similar expressions. Important factors that could cause actual
results to differ materially from those expectations include, among others, economic and market conditions in the geographic areas and industries that are or will be major markets
for Kvaerner’s businesses, oil prices, market acceptance of new products and services, changes in governmental regulations, interest rates, fluctuations in currency exchange
rates and such other factors as may be discussed from time to time in the Presentation. Although Kværner ASA believes that its expectations and the Presentation are based
upon reasonable assumptions, it can give no assurance that those expectations will be achieved or that the actual results will be as set out in the Presentation. Kværner ASA is
making no representation or warranty, expressed or implied, as to the accuracy, reliability or completeness of the Presentation, and neither Kværner ASA nor any of its directors,
officers or employees will have any liability to you or any other persons resulting from your use.
Copyright and disclaimer
28