la guardia airport, worst to first - carl galioto, hok
TRANSCRIPT
PowerPoint Presentation
LaGuardia Airport: Worst to FirstThe Planning, Design, and Implementation of the new LaGuardia Airport Including the Nations Largest P3
February 9, 2017
Carl Galioto Managing Principal
Text in questions - (267) 573-0623
1
ATCTGARAGECENTRAL TERMINAL B
Existing
Political Will
The New LaGuardia Airport MASTERPLAN
GOALS Based on Governor Cuomos Airport Advisory Panel A Single, Unified AirportImprove Airside OperationsImproved Access to the AirportAppealing ArchitectureTomorrows Airport TodayEnvironment and Sustainability
Text in questions - (267) 573-0623
The New LaGuardia Airport - MASTERPLAN
The New LaGuardia Airport - MASTERPLAN
The New LaGuardia Airport - MASTERPLAN
The New LaGuardia Airport - MASTERPLAN
The New LaGuardia Airport - MASTERPLAN
Resiliency
The New LaGuardia Airport - MASTERPLAN
The New LaGuardia Airport - MASTERPLAN
Flanking TerminalsText in questions - (267) 573-0623
The New LaGuardia Airport - MASTERPLAN
Continuous EdgeText in questions - (267) 573-0623
The New LaGuardia Airport - MASTERPLAN
Folded Roof PlatesText in questions - (267) 573-0623
The New LaGuardia Airport - MASTERPLAN
Passenger BridgesText in questions - (267) 573-0623
Considerations
Aging/Unadaptable FacilitiesP3 (Public-Private PartnershipThe Importance of Customer SatisfactionConstrained SitesOpportunities for Collateral DevelopmentTransit/Airport AccessSecuritySustainabilityResiliencyText in questions - (267) 573-0623
The TeamPANY&NJ
EQUITYMANAGEMENTOPERATIONSCOMMERCIALText in questions - (267) 573-0623
CONSTRUCTION
ARCHITECTURE & ENGINEERING
DESIGN / BUILD
The TeamText in questions - (267) 573-0623
19
Existing Terminal B Site
2016201720182019202020212022
20
Construction Phasing
Construction Phasing
2016201720182019202020212022
Construction Phasing2016201720182019202020212022
Construction Phasing2016201720182019202020212022
Construction Phasing2016201720182019202020212022
Construction Phasing2016201720182019202020212022
Construction Phasing2016201720182019202020212022
Construction Phasing2016201720182019202020212022
Construction Phasing2016201720182019202020212022
Completion2016201720182019202020212022
DESIGN PRINCIPLES
CENTRAL TERMINAL B CENTRAL HALLATCTCONCOURSE ACONCOURSE BWEST GARAGE
THE URBAN AIRPORT
A CITY OF ISLANDS AND BRIDGES
PASSENGER EXPERIENCEDEPARTURES HALL
PASSENGER EXPERIENCECONCOURSES
CIVIC SPACECENTRAL HALL
THANK YOU