lab3ea2y
DESCRIPTION
LabTRANSCRIPT
![Page 1: LAB3EA2Y](https://reader035.vdocument.in/reader035/viewer/2022062409/55cf8fc2550346703b9f85dc/html5/thumbnails/1.jpg)
Practice - Researching Planning Results
Distribution
Oracle Advanced Supply Chain Planning
Job Title*
Ownership
The Job Title [[email protected]?Subject=LAB3EA2Y] is responsible for ensuring that this document is necessary and that it reflects actual practice.
Copyright © Oracle Corporation, 2003. All rights reserved.
Practice - Researching Planning Results document.docEffective Paradigm_effective Page 1 of 27 Rev Paradigm_revision
![Page 2: LAB3EA2Y](https://reader035.vdocument.in/reader035/viewer/2022062409/55cf8fc2550346703b9f85dc/html5/thumbnails/2.jpg)
Practice - Researching Planning Results
Please mention lab identifier 3EA2 in course evaluation comments.
Overview
This practice covers researching plan results.
Tasks
1. From the Advanced Supply Chain Planner responsibility, navigate to the Planner Workbench in the Instance : Organization TST:M1.
(N) Supply Chain Plan > Workbench
2. Select plan XX_Unconstr.
3. Find Item AS66331 in the Planner Workbench navigator.
4. View the horizontal plan and projected available balance graph for some items in the supply chain bill.
5. View Planner Workbench preferences.
6. View supply and demand information for some items in the supply chain. For pegging, follow the pegging tree for supplies and demands in different organizations and verify that the planning process followed the supply chain bill.
7. Look at detailed information about some items in the plan.
8. Find the Supply/Demand fields that relate to date. Look first at fields that display in the Supply/Demand window. Then look at those that do not display; differentiate between those that seem to relate to demands and those that relate to supplies.
9. Make a folder for your use in which you sort records by Sugg Due Date.
10. View only the supply information and only the demand information for some items in the supply chain.
11. View resource information in the supply chain.
12. View requirements against some resources.
13. View availability of some resources.
14. View safety stock information for item AS66311 in organization D2.
Copyright © Oracle Corporation, 2003. All rights reserved.
Practice - Researching Planning Results document.docEffective Paradigm_effective Page 2 of 27 Rev Paradigm_revision
![Page 3: LAB3EA2Y](https://reader035.vdocument.in/reader035/viewer/2022062409/55cf8fc2550346703b9f85dc/html5/thumbnails/3.jpg)
15. View key indicators for the plan and some organizations, item categories, and items in the supply chain.
Copyright © Oracle Corporation, 2003. All rights reserved.
Practice - Researching Planning Results document.docEffective Paradigm_effective Page 3 of 27 Rev Paradigm_revision
![Page 4: LAB3EA2Y](https://reader035.vdocument.in/reader035/viewer/2022062409/55cf8fc2550346703b9f85dc/html5/thumbnails/4.jpg)
Solution – Researching Planning Results
1. From the Advanced Supply Chain Planner responsibility, navigate to the Planner Workbench in the Instance : Organization TST:M1.
(N) Supply Chain Plan > Workbench
2. Select your plan.
View by = Organizations
Expand the Plans directory
Select your plan XX_Unconst.
3. Find Item AS66331 in the Planner Workbench navigator.
TST:M1 > COMPUTER.HANDHELD > AS66331
4. View the horizontal plan projected available balance for some items in the supply chain bill.
In the Planner Workbench navigator, highlight AS66331, and then click the Horizontal Plan icon, or right click AS66331, and then select Horizontal Plan > Detail from the right-click menu.
The Projected Available Balance in the first period is 758.
Copyright © Oracle Corporation, 2003. All rights reserved.
Practice - Researching Planning Results document.docEffective Paradigm_effective Page 4 of 27 Rev Paradigm_revision
![Page 5: LAB3EA2Y](https://reader035.vdocument.in/reader035/viewer/2022062409/55cf8fc2550346703b9f85dc/html5/thumbnails/5.jpg)
Notes:
Additional information: Item AS66311 item category is COMPUTER.HANDHELD Item CM66321 item category is COMPONENT.ELECTRICAL Item CM66326 item category is COMPONENT.MECHANICAL Item CM66331 item category is COMPONENT.ELECTRICAL Item CM66332 item category is COMPONENT.ELECTRICAL Item CM66333 item category is COMPONENT.ELECTRICAL Item SB66328 item category is ASSEMBLY.SUBASSY
5. View Planner Workbench preferences.
(M) Tools > Preferences
Copyright © Oracle Corporation, 2003. All rights reserved.
Practice - Researching Planning Results document.docEffective Paradigm_effective Page 5 of 27 Rev Paradigm_revision
![Page 6: LAB3EA2Y](https://reader035.vdocument.in/reader035/viewer/2022062409/55cf8fc2550346703b9f85dc/html5/thumbnails/6.jpg)
Notes:
On the Material Plan tab, change Show Graph to Yes.
Change the Supplies dropdown to Demands
Select the Sales Orders check box.
Click Save.
Close Preferences.
Return to the horizontal plan. Horizontal Plan > Detail
Copyright © Oracle Corporation, 2003. All rights reserved.
Practice - Researching Planning Results document.docEffective Paradigm_effective Page 6 of 27 Rev Paradigm_revision
![Page 7: LAB3EA2Y](https://reader035.vdocument.in/reader035/viewer/2022062409/55cf8fc2550346703b9f85dc/html5/thumbnails/7.jpg)
6. Return to Preferences.
On the Material Plan tab, change Show Graph to No.
On Demands, deselect the Sales Orders check box.
Click Save.
7. Review the preference settings available on the remaining preferences tabs.
Capacity Plan
Copyright © Oracle Corporation, 2003. All rights reserved.
Practice - Researching Planning Results document.docEffective Paradigm_effective Page 7 of 27 Rev Paradigm_revision
![Page 8: LAB3EA2Y](https://reader035.vdocument.in/reader035/viewer/2022062409/55cf8fc2550346703b9f85dc/html5/thumbnails/8.jpg)
Notes:
Supplier Plan
Copyright © Oracle Corporation, 2003. All rights reserved.
Practice - Researching Planning Results document.docEffective Paradigm_effective Page 8 of 27 Rev Paradigm_revision
![Page 9: LAB3EA2Y](https://reader035.vdocument.in/reader035/viewer/2022062409/55cf8fc2550346703b9f85dc/html5/thumbnails/9.jpg)
Notes:
Copyright © Oracle Corporation, 2003. All rights reserved.
Practice - Researching Planning Results document.docEffective Paradigm_effective Page 9 of 27 Rev Paradigm_revision
![Page 10: LAB3EA2Y](https://reader035.vdocument.in/reader035/viewer/2022062409/55cf8fc2550346703b9f85dc/html5/thumbnails/10.jpg)
Transportation Plan
Notes:
Copyright © Oracle Corporation, 2003. All rights reserved.
Practice - Researching Planning Results document.docEffective Paradigm_effective Page 10 of 27 Rev Paradigm_revision
![Page 11: LAB3EA2Y](https://reader035.vdocument.in/reader035/viewer/2022062409/55cf8fc2550346703b9f85dc/html5/thumbnails/11.jpg)
Allocated ATP
Notes:
Copyright © Oracle Corporation, 2003. All rights reserved.
Practice - Researching Planning Results document.docEffective Paradigm_effective Page 11 of 27 Rev Paradigm_revision
![Page 12: LAB3EA2Y](https://reader035.vdocument.in/reader035/viewer/2022062409/55cf8fc2550346703b9f85dc/html5/thumbnails/12.jpg)
Gantt
Notes:
Copyright © Oracle Corporation, 2003. All rights reserved.
Practice - Researching Planning Results document.docEffective Paradigm_effective Page 12 of 27 Rev Paradigm_revision
![Page 13: LAB3EA2Y](https://reader035.vdocument.in/reader035/viewer/2022062409/55cf8fc2550346703b9f85dc/html5/thumbnails/13.jpg)
Other
Notes:
Copyright © Oracle Corporation, 2003. All rights reserved.
Practice - Researching Planning Results document.docEffective Paradigm_effective Page 13 of 27 Rev Paradigm_revision
![Page 14: LAB3EA2Y](https://reader035.vdocument.in/reader035/viewer/2022062409/55cf8fc2550346703b9f85dc/html5/thumbnails/14.jpg)
8. View supply and demand information for some items in the supply chain.
The Supply Demand (TST:M1) window opens.
Copyright © Oracle Corporation, 2003. All rights reserved.
Practice - Researching Planning Results document.docEffective Paradigm_effective Page 14 of 27 Rev Paradigm_revision
![Page 15: LAB3EA2Y](https://reader035.vdocument.in/reader035/viewer/2022062409/55cf8fc2550346703b9f85dc/html5/thumbnails/15.jpg)
9. For pegging, follow the pegging tree for supplies and demands in different organizations and verify that the planning process followed the supply chain bill.
The left most icon (Demand Pegging) is selected.
There are two on hand quantities 747 + 11 = 758 as shown in the horizontal plan.
In the first row, 673 units are tied to the planned order for 02-NOV. This leaves (747 – 673) = 74.
In the second row, the On Hand of 11 units is to be transferred from organization TST:D2. Therefore, 74 + 11 = 85 units are available toward filling the 700 planned order of 03-NOV.
In the third row, 615 units are pegged to the 03-NOV Planned Order. That quantity, plus the 85 on hand is sufficient to cover the 700 quantity of the planned order.
Copyright © Oracle Corporation, 2003. All rights reserved.
Practice - Researching Planning Results document.docEffective Paradigm_effective Page 15 of 27 Rev Paradigm_revision
![Page 16: LAB3EA2Y](https://reader035.vdocument.in/reader035/viewer/2022062409/55cf8fc2550346703b9f85dc/html5/thumbnails/16.jpg)
10. Select the Pegging Supply icon, which is the second icon from the left.
11. Look at detailed information about some items in the plan.
Right click an item number, and then select the Items > Items from the right-click menu.
Copyright © Oracle Corporation, 2003. All rights reserved.
Practice - Researching Planning Results document.docEffective Paradigm_effective Page 16 of 27 Rev Paradigm_revision
![Page 17: LAB3EA2Y](https://reader035.vdocument.in/reader035/viewer/2022062409/55cf8fc2550346703b9f85dc/html5/thumbnails/17.jpg)
Review the information on the Items context window
Use the buttons and the right-click menu options to find resource, component and supplier information.
Refer to your supply chain bill diagram in your search and update it with information that is significant to note.
Notes:
Copyright © Oracle Corporation, 2003. All rights reserved.
Practice - Researching Planning Results document.docEffective Paradigm_effective Page 17 of 27 Rev Paradigm_revision
![Page 18: LAB3EA2Y](https://reader035.vdocument.in/reader035/viewer/2022062409/55cf8fc2550346703b9f85dc/html5/thumbnails/18.jpg)
12. Find the Supply/Demand fields that relate to date. Look first at fields that display in the Supply/Demand window. Then look at those that do not display; differentiate between those that seem to relate to demands and those that relate to supplies.
Some fields that display and apply to demands are Sugg Due Date and New Date
Notes:
Some fields that display apply to supplies are Sugg Due Date and Implement Date
Right click the Order Number column, and the select Folder > Show Field from the right-click menu.
In the Show Field window, set Find = %dat%
Click Find.
The Show Field window lists available fields.
Copyright © Oracle Corporation, 2003. All rights reserved.
Practice - Researching Planning Results document.docEffective Paradigm_effective Page 18 of 27 Rev Paradigm_revision
![Page 19: LAB3EA2Y](https://reader035.vdocument.in/reader035/viewer/2022062409/55cf8fc2550346703b9f85dc/html5/thumbnails/19.jpg)
Notes:
Some fields that do not display and relate to demands are Need By Date and Promised Arrival Date.
Some fields that do not display and relate to supplies are Expiration Date and Sugg Dock Date
Copyright © Oracle Corporation, 2003. All rights reserved.
Practice - Researching Planning Results document.docEffective Paradigm_effective Page 19 of 27 Rev Paradigm_revision
![Page 20: LAB3EA2Y](https://reader035.vdocument.in/reader035/viewer/2022062409/55cf8fc2550346703b9f85dc/html5/thumbnails/20.jpg)
13. Make a folder for your use in which you sort records by Sugg Due Date.
With the Supply Demand window open, from the menu bar navigate: (M) Folder > New
The Save Folder window appears.
Set the Folder name = XX_Supply/Demand
In the Autoquery region, select the radio button for Ask each time
Select the Public check box.
Deselect the Open as Default check box.
Click (B) OK.
Notes:
From the menu bar navigate: (M) Folder > Sort Data
Select Suggested Due Date
Select Ascending
Select Run Query
Click OK.
Copyright © Oracle Corporation, 2003. All rights reserved.
Practice - Researching Planning Results document.docEffective Paradigm_effective Page 20 of 27 Rev Paradigm_revision
![Page 21: LAB3EA2Y](https://reader035.vdocument.in/reader035/viewer/2022062409/55cf8fc2550346703b9f85dc/html5/thumbnails/21.jpg)
Notes:
14. View only the supply information and only the demand information for some items in the supply chain.
From the Supply/Demand window, navigate (M) Tools > Supply
From the Supply/Demand window, navigate and (M) Tools > Demand
Notes:
Copyright © Oracle Corporation, 2003. All rights reserved.
Practice - Researching Planning Results document.docEffective Paradigm_effective Page 21 of 27 Rev Paradigm_revision
![Page 22: LAB3EA2Y](https://reader035.vdocument.in/reader035/viewer/2022062409/55cf8fc2550346703b9f85dc/html5/thumbnails/22.jpg)
15. View resource information in the supply chain.
From the Supply/Demand window, navigate (M) Tools > Resources.
Notes:
Copyright © Oracle Corporation, 2003. All rights reserved.
Practice - Researching Planning Results document.docEffective Paradigm_effective Page 22 of 27 Rev Paradigm_revision
![Page 23: LAB3EA2Y](https://reader035.vdocument.in/reader035/viewer/2022062409/55cf8fc2550346703b9f85dc/html5/thumbnails/23.jpg)
16. View requirements against some resources.
Use Planner Workbench context window Resource Requirements, accessible from the Resources window.
Click (B) Requirements.
The Resource Requirements (TST:M1) window appears.
Notes:
Close the Resource Requirements window.
Copyright © Oracle Corporation, 2003. All rights reserved.
Practice - Researching Planning Results document.docEffective Paradigm_effective Page 23 of 27 Rev Paradigm_revision
![Page 24: LAB3EA2Y](https://reader035.vdocument.in/reader035/viewer/2022062409/55cf8fc2550346703b9f85dc/html5/thumbnails/24.jpg)
17. View availability of some resources.
Use Planner Workbench context window Resource Availability, accessible from the Resources window.
Click Availability.
The Resource Capacity window appears.
Notes:
Close the Resource Capacity window.
Copyright © Oracle Corporation, 2003. All rights reserved.
Practice - Researching Planning Results document.docEffective Paradigm_effective Page 24 of 27 Rev Paradigm_revision
![Page 25: LAB3EA2Y](https://reader035.vdocument.in/reader035/viewer/2022062409/55cf8fc2550346703b9f85dc/html5/thumbnails/25.jpg)
18. View safety stock information for item AS66311 in organization D2.
Use Planner Workbench context window Safety Stock. Select a supply/demand row, right click, and select Items.
Notes:
Copyright © Oracle Corporation, 2003. All rights reserved.
Practice - Researching Planning Results document.docEffective Paradigm_effective Page 25 of 27 Rev Paradigm_revision
![Page 26: LAB3EA2Y](https://reader035.vdocument.in/reader035/viewer/2022062409/55cf8fc2550346703b9f85dc/html5/thumbnails/26.jpg)
The Safety Stock window is accessible from the Items window, click Safety Stock.
19. View key indicators for the plan and some organizations, item categories, and items in the supply chain.
In the Planner Workbench navigator, select the XX_Unconst plan, click the More icon, and select Key Indicators.
Copyright © Oracle Corporation, 2003. All rights reserved.
Practice - Researching Planning Results document.docEffective Paradigm_effective Page 26 of 27 Rev Paradigm_revision
![Page 27: LAB3EA2Y](https://reader035.vdocument.in/reader035/viewer/2022062409/55cf8fc2550346703b9f85dc/html5/thumbnails/27.jpg)
Notes:
Then, repeat using some organizations, item categories, and items.
Copyright © Oracle Corporation, 2003. All rights reserved.
Practice - Researching Planning Results document.docEffective Paradigm_effective Page 27 of 27 Rev Paradigm_revision