LANDFILL LIFE CYCLE COSTS
By: Jessica Sayers
May 2011
![Page 2: LANDFILL LIFE CYCLE COSTS By: Jessica Sayers May 2011](https://reader036.vdocument.in/reader036/viewer/2022062407/56649c985503460f949547a2/html5/thumbnails/2.jpg)
![Page 3: LANDFILL LIFE CYCLE COSTS By: Jessica Sayers May 2011](https://reader036.vdocument.in/reader036/viewer/2022062407/56649c985503460f949547a2/html5/thumbnails/3.jpg)
DEVELOPMENTPOST-
CLOSU
RE
ACTIVE
SUSTAINABLELANDFILL
![Page 4: LANDFILL LIFE CYCLE COSTS By: Jessica Sayers May 2011](https://reader036.vdocument.in/reader036/viewer/2022062407/56649c985503460f949547a2/html5/thumbnails/4.jpg)
DEVELOPMENTPOST-CLO
SURE
SUSTAINABLELANDFILL
Development Phase
ACTIVE
Time0 Open
$$$
Development Costs
Ideal: Funding=Development Costs
![Page 5: LANDFILL LIFE CYCLE COSTS By: Jessica Sayers May 2011](https://reader036.vdocument.in/reader036/viewer/2022062407/56649c985503460f949547a2/html5/thumbnails/5.jpg)
DEVELOPMENTPOST-CLO
SURE
SUSTAINABLELANDFILL
Development Phase
ACTIVE
Time0 Open
$$$
Funding Development Costs
Ideal: Funding=Development Costs
![Page 6: LANDFILL LIFE CYCLE COSTS By: Jessica Sayers May 2011](https://reader036.vdocument.in/reader036/viewer/2022062407/56649c985503460f949547a2/html5/thumbnails/6.jpg)
Active Phase
ACTIVE
Ideal: Fees=Normal O&M PLUS Other Costs
DEVELOPMENTPOST-CLO
SURE
SUSTAINABLELANDFILL
YEARSOPEN
*Begin Development New System
5 10 15 20 25 30
$$$
NEWCELL
EQUIPMENT
*
CLOSURE
Normal O&M Costs
![Page 7: LANDFILL LIFE CYCLE COSTS By: Jessica Sayers May 2011](https://reader036.vdocument.in/reader036/viewer/2022062407/56649c985503460f949547a2/html5/thumbnails/7.jpg)
Active Phase
ACTIVE
Ideal: Fees=Normal O&M PLUS Other Costs
DEVELOPMENTPOST-CLO
SURE
SUSTAINABLELANDFILL
YEARSOPEN
*Begin Development New System
5 10 15 20 25 30
$$$
NEWCELL
EQUIPMENT
*
CLOSURE
1
2
3
Normal O&M Costs
FEES
= NEW CELL COSTS
= EQUIPMENT COSTS
= * and CLOSURE COSTS
![Page 8: LANDFILL LIFE CYCLE COSTS By: Jessica Sayers May 2011](https://reader036.vdocument.in/reader036/viewer/2022062407/56649c985503460f949547a2/html5/thumbnails/8.jpg)
Post-Closure Phase
ACTIVE
Ideal: Fees=Active Costs PLUS Post-Closure Costs
DEVELOPMENTPOST-CLO
SURE
SUSTAINABLELANDFILL
YEARSOPEN
*Begin Development New System
5 10 15 20 25 30
$$$
NEWCELL
EQUIPMENT
*
CLOSURE
1
2
3
Normal O&M and Post-Closure Costs
NEXT System’s Active Cycle
![Page 9: LANDFILL LIFE CYCLE COSTS By: Jessica Sayers May 2011](https://reader036.vdocument.in/reader036/viewer/2022062407/56649c985503460f949547a2/html5/thumbnails/9.jpg)
Fees Development
SUSTAINABLE
![Page 10: LANDFILL LIFE CYCLE COSTS By: Jessica Sayers May 2011](https://reader036.vdocument.in/reader036/viewer/2022062407/56649c985503460f949547a2/html5/thumbnails/10.jpg)
QUESTIONS???How can I help???