langdon environmental llc · 2020. 12. 4. · ms. susan ruch massdep –northeast regional office...

8
Langdon Environmental LLC 241 Boston Post Rd., West 1st Floor Marlborough, Massachusetts 01752 April 4, 2016 Ms. Susan Ruch Deputy Regional Director Massachusetts Department of Environmental Protection Northeast Regional Office 205B Lowell Street Wilmington, Massachusetts 01887 Subject: Quarterly Landfill Gas Monitoring Results – February 26, 2016 Haverhill Municipal Landfill Site Dear Ms. Ruch: On February 26, 2016, Cooperstown Environmental LLC personnel under subcontract to Langdon Environmental LLC (Langdon) performed a quarterly landfill gas monitoring round at the Haverhill Landfill in Haverhill, Massachusetts. The sampling procedure was performed in accordance with the SW-45 permit application for the Southern Mound Landfill Gas Scope of Work dated March 24, 2014 (2014 SOW) as presumptively approved by the Massachusetts Department of Environmental Protection (MassDEP). As required by MassDEP in the April 13, 2012 permit approving the removal of the solar flares from the Southern Mound vents, the passive gas vents installed throughout the Southern Mound were also sampled for methane. Summary of Monitoring Program Figure 1 attached from the 2014 SOW shows the location of the sampling locations for the landfill gas monitoring program. Note that well location CDM 11/11A could not be located again during this round as was the case in December 2015. Vent #13 and CDM-5/5D are located closest to this well cluster and are considered representative of conditions in the CDM 11/11A area at the property line. It is possible that soil from over the landfill cap has covered these wells but they can no longer be located, even with the limited winter vegetation. Procedures and equipment for the sampling program were conducted in accordance with the MassDEP standard methods as used during prior monitoring rounds. Landfill Gas Monitoring Results The results from the landfill gas monitoring wells and probes are summarized in the attached Table 1 and the results for the passive vents within the capped Southern Mound are provided in Table 2. Both initial and final readings are presented for the monitoring wells and probes. The following is a summary of the results of the February 2016 round compared to prior sampling events:

Upload: others

Post on 09-Feb-2021

0 views

Category:

Documents


0 download

TRANSCRIPT

  • Langdon Environmental LLC 241 Boston Post Rd., West 1st Floor

    Marlborough, Massachusetts 01752

    April 4, 2016

    Ms. Susan Ruch

    Deputy Regional Director

    Massachusetts Department of Environmental Protection

    Northeast Regional Office

    205B Lowell Street

    Wilmington, Massachusetts 01887

    Subject: Quarterly Landfill Gas Monitoring Results – February 26, 2016 Haverhill Municipal Landfill Site

    Dear Ms. Ruch:

    On February 26, 2016, Cooperstown Environmental LLC personnel under subcontract to Langdon

    Environmental LLC (Langdon) performed a quarterly landfill gas monitoring round at the Haverhill

    Landfill in Haverhill, Massachusetts. The sampling procedure was performed in accordance with the

    SW-45 permit application for the Southern Mound Landfill Gas Scope of Work dated March 24, 2014

    (2014 SOW) as presumptively approved by the Massachusetts Department of Environmental

    Protection (MassDEP). As required by MassDEP in the April 13, 2012 permit approving the removal of

    the solar flares from the Southern Mound vents, the passive gas vents installed throughout the

    Southern Mound were also sampled for methane.

    Summary of Monitoring Program Figure 1 attached from the 2014 SOW shows the location of the sampling locations for the landfill gas

    monitoring program. Note that well location CDM 11/11A could not be located again during this

    round as was the case in December 2015. Vent #13 and CDM-5/5D are located closest to this well

    cluster and are considered representative of conditions in the CDM 11/11A area at the property line.

    It is possible that soil from over the landfill cap has covered these wells but they can no longer be

    located, even with the limited winter vegetation.

    Procedures and equipment for the sampling program were conducted in accordance with the

    MassDEP standard methods as used during prior monitoring rounds.

    Landfill Gas Monitoring Results The results from the landfill gas monitoring wells and probes are summarized in the attached Table 1

    and the results for the passive vents within the capped Southern Mound are provided in Table 2. Both

    initial and final readings are presented for the monitoring wells and probes. The following is a

    summary of the results of the February 2016 round compared to prior sampling events:

  • Ms. Susan Ruch

    MassDEP – Northeast Regional Office April 4, 2016

    Page 2

    Notifications – During the February 2016 round, there were no exceedances of 25 percent of the Lower Explosive Limit (LEL) in property line monitoring wells that require

    24-hour notification to MassDEP in accordance with 310 CMR 19.132(4)(h).

    Results along the Southern Compliance Boundary and Lot 26 – There were very low levels of methane (0.2% or less) detected in some of the wells located along the southern

    property line compliance boundary including CDM-2R, CDM-4A, CDM-5D, CDM-6A/6D,

    CDM-7/7D, which are located between the Southern Mound and the homes along Old

    Groveland Road. The remaining vents installed at the limit of the Southern Mound (Vents

    3-22) also were monitored and methane was detected only at Vent 5 (0.1% methane),

    Vent 8 (0.2% methane and 1% of the LEL, and Vent 13 (0.1% methane). Because there

    were only very low levels of methane detected wells and vents along the southern

    compliance boundary including 0% LEL at CDM-4/4A, temporary probes SGP-4/4A were

    not installed and sampled during this round.

    Results along the West/Wetlands Compliance Boundary - Two landfill gas monitoring wells (CDM-1 and CDM-13) and four temporary landfill gas probes (SGP-1, SGP-2, SGP-3,

    and SGP-21) were sampled to assess soil gas conditions along the western compliance

    boundary including the western side of the National Grid right-of-way. These locations

    were sampled for compliance with the 2014 SOW. Methane was not detected in initial or

    final readings at any of the wells or probes along the western compliance boundary

    during the February 2016 sampling event.

    Results in Passive Gas Vents- Passive gas vents were monitored for methane. As shown in Table 2, methane was detected in 35 of the 39 passive vents installed during Southern

    Mound construction.

    Summary The results of the February 2016 round were similar to the past several quarterly sampling rounds and

    continue to demonstrate control of lateral landfill gas migration, particularly along the southeastern

    property line. This suggests that the passive gas vent system installed as part of Southern Mound

    closure continues to work as designed.

    Since there is adequate monitoring well coverage at the property line in the vicinity of the CDM-10

    and CDM-11 monitoring wells that cannot be located, Langdon will prepare an SW-45 permit

    application for submission to MassDEP to request the removal of these locations from the ongoing

    monitoring program. We intend on submitting this permit application to MassDEP prior to completion

    of the next gas monitoring well (May 2016).

    Signed copies of the certifications from the site owners required by the MassDEP Solid Waste

    Management Regulations (310 CMR 19.000) are attached.

  • Ms. Susan Ruch

    MassDEP – Northeast Regional Office April 4, 2016

    Page 3

    We appreciate your attention to this project and review of this request. Do not hesitate to contact me

    at (508) 630-0351 or (617) 875-3693 if you have any questions or require anything further on this

    matter.

    Very truly yours,

    Bruce W. Haskell, P.E.

    Langdon Environmental LLC

    cc: Janet Waldron – MassDEP Rick Spieler, MassDEP Derrick Golden – EPA Robert Ward – Haverhill Water/Wastewater Joel Nickel – Aggregate Industries Michael Leon, Esq. – Nutter, McClennen & Fish, LLP Gary Gill-Austern, Esq. – Nutter McClennen & Fish, LLP Jeanne Westervelt, Cooperstown Environmental

  • G r o v e l a nd H a v e r h i l l

    G r o v e l a n d

    H a v e r h i l l

    a n d R o ad

    l e v o r

    d G l O

    n i M a S t r e et

    Y e m m a R o a d

    Merrimack River

    JohnsonCreek

    National Grid

    Substation

    20-ft Access Easement

    60-ft Electric Easement

    Southern Mound

    Northern Mound

    0 150 300

    Scale In Feet

    600

    L E G E N D

    Landfill (approximate)

    Property Boundaries

    House

    Municipal Boundary

    Edge of Wetlands Approved by Haverhill Conservation Commission (2010)

    Approximate Limits of Ash

    Proposed Landfill Gas Compliance Boundary

    Existing Landfill Gas Monitoring Well

    Proposed Landfill Gas Monitoring Well

    Existing Soil Gas Probe Location

    Proposed Soil Gas Probe Location

    N a t i o n a l G r id

    (capped)

    Approx. Location of Stormwater

    Basin

    Quonset Hut

    SGP-1

    SGP-21

    SGP-2

    SGP-3

    SGP-4

    SGP-4A

    CDM-13

    CDM-2

    CDM-1

    CDM-12

    CDM-7

    CDM-7M/7D

    CDM-3

    CDM-5

    CDM-5D CDM-6D

    CDM-6/6A

    CDM-10/10A CDM-11/11A

    CDM-4/4A

    Haverhill Municipal LandfillFigure 1 Haverhill, MassachusettsLandfill Gas Compliance Boundary Northern Mound CAAA

    Prepared by:and Assessment Phase Landfill Gas Monitoring Network

  •     

      

     

        

    Table 1 Landfill Gas Monitoring Results Monitoring Wells and Probes

    Interim Monitoring ‐ February 26, 2016 Haverhill Landfill, Haverhill, Massachusetts

    Monitoring Location

    Methane (% vol.)

    LEL (% vol.)

    CO2 (% vol.)

    O2 (% vol.)

    H2S (ppm)

    VOCs (ppm)

    Atomospheric Pressure (in Hg)

    Initial Final Initial Final Initial Final Initial Final Initial Final Initial Final Initial Final CDM‐1 0 0 0 0 0.1 0.2 20.2 20.1 0 0 0 0.1 29.42 29.42 CDM‐2R 0.1 0 0 0 0.3 0 20.3 20.2 0 0 0 0 29.42 29.42 CDM‐3 0 0 0 0 0.1 0.1 20.1 20.4 0 0 0.1 0 29.42 29.42 CDM‐4 0 0 0 0 0.1 0.2 20.6 20.3 0 0 0.1 0.1 29.42 29.42 CDM‐4A 0.1 0.1 0 0 0.3 1.1 19.9 20.1 0 0 0 0 29.42 29.42 CDM‐5 0 0 0 1 0.1 0.2 20.1 20.1 0 0 0 0 29.42 29.42 CDM‐5D 0.3 0 0 0 0.1 0.1 20.2 20.1 0 0 0 0.1 29.42 29.42 CDM‐6 0 0.2 0 1 0.2 0.1 20.3 20 0 0 0 0 29.42 29.42 CDM‐6A 0.1 0 0 0 0.3 0.1 20.2 20.1 0 0 0 0 29.42 29.42 CDM‐6D 0.3 0 0 0 0.1 0.1 20.2 20.1 0 0 0 0 29.42 29.42 CDM‐7 0.1 0 0 0 0.2 0.4 20.1 20.1 0 0 0 0.1 29.42 29.42 CDM‐7M 0 0.1 0 1 0.1 0.1 20.1 20.0 0 0 0 0 29.42 29.42 CDM‐7D 0.1 0.1 0 0 0 0.1 20.1 20.1 0 0 0.1 0.1 29.42 29.42 CDM‐10 4 Destroyed CDM‐10A 4 Destroyed CDM‐11 5 Not Located CDM‐11A 5 Not Located CDM‐12 0 0 0 0 0.1 0.3 20.0 20.3 0 0 0 0.1 29.42 29.42 CDM‐13 0 0 0 0 0.1 0 20.1 20.1 0 0 0 0 29.42 29.42 Vent 3 6  ‐ 0 ‐ 0  ‐ 0.1  ‐ 20.1  ‐ 0 ‐ 0  ‐ 29.42 Vent 4  ‐ 0 ‐ 0 ‐ 0 ‐ 20.6 ‐ 0 ‐ 0  ‐ 29.42 Vent 5  ‐ 0.1 ‐ 0  ‐ 0.1 ‐ 21.2 ‐ 0 ‐ 0  ‐ 29.42 Vent 6  ‐ 0 ‐ 0 ‐ 0.1 ‐ 20.2 ‐ 0 ‐ 0.1  ‐ 29.42 Vent 7  ‐ 0 ‐ 0 ‐ 0.2 ‐ 20.0 ‐ 0 ‐ 0.1  ‐ 29.42 Vent 8  ‐ 0.2 ‐ 1  ‐ 0.8 ‐ 19.6 ‐ 0 ‐ 0  ‐ 29.42 Vent 10  ‐ 0 ‐ 0 ‐ 0.1 ‐ 20.5 ‐ 0 ‐ 0  ‐ 29.42 Vent 13  ‐ 0.1 ‐ 0  ‐ 0.3 ‐ 20.2 ‐ 0 ‐ 0  ‐ 29.42 Vent 19  ‐ 0 ‐ 0 ‐ 0.1 ‐ 20.2 ‐ 0 ‐ 0  ‐ 29.42 Vent 20  ‐ 0 ‐ 0 ‐ 0.1 ‐ 20.8 ‐ 0 ‐ 0.1  ‐ 29.42 Vent 21  ‐ 0 ‐ 0 ‐ 0.1 ‐ 21.1 ‐ 0 ‐ 0  ‐ 29.42 Vent 22  ‐ 0 ‐ 0 ‐ 0.1 ‐ 20.1 ‐ 0 ‐ 0  ‐ 29.42 SGP‐1 0 0 0 0 0.1 0 20.6 20.7 0 0 0 0 29.42 29.42 SGP‐2 0 0 0 0 0 0.4 20.8 20.4 0 0 0 0 29.42 29.42 SGP‐3 0 0 0 0 0.1 0.1 20.1 20.2 0 0 0 0 29.42 29.42 SGP‐G21 0 0 0 0 0.2 0.2 20.6 20.6 0 0 0 0 29.42 29.42

  •                

      

        

      

       

          

      

      

      

     

       

    Table 2 Landfill Gas Monitoring Results

    Passive Gas Vents Within Capped Southern Mound Interim Monitoring ‐ February 26, 2016 Haverhill Landfill, Haverhill, Massachusetts

    Monitoring Location

    Methane 1 

    (% vol.) LEL (% vol.)

    CO2 1 

    (% vol.) O2 1 

    (% vol.) H2S 

    (ppm) VOCs 3 

    (ppm)

    Atomospheric Pressure (in Hg)

    Initial Final Initial Final Initial Final Initial Final Initial Final Initial Final Initial Final G‐1  ‐ 0.3 ‐ 1  ‐ NM ‐ NM ‐ NM ‐ NM ‐ 29.42 G‐2  ‐ 0.7 ‐ 4  ‐ NM ‐ NM ‐ NM ‐ NM ‐ 29.42 G‐3  ‐ 7.2 ‐ >999*  ‐ NM ‐ NM ‐ NM ‐ NM ‐ 29.42 G‐4  ‐ 21.3 ‐ >999*  ‐ NM ‐ NM ‐ NM ‐ NM ‐ 29.42 G‐5  ‐ 23.8 ‐ >999*  ‐ NM ‐ NM ‐ NM ‐ NM ‐ 29.42 G‐6  ‐ 42.1 ‐ >999*  ‐ NM ‐ NM ‐ NM ‐ NM ‐ 29.42 G‐7A  ‐ 33.9 ‐ >999*  ‐ NM ‐ NM ‐ NM ‐ NM ‐ 29.42 G‐8  ‐ 11.2 ‐ >999*  ‐ NM ‐ NM ‐ NM ‐ NM ‐ 29.42 G‐9  ‐ 30.7 ‐ >999*  ‐ NM ‐ NM ‐ NM ‐ NM ‐ 29.42 G‐10  ‐ 31.5 ‐ >999*  ‐ NM ‐ NM ‐ NM ‐ NM ‐ 29.42 G‐11A  ‐ 42.2 ‐ >999*  ‐ NM ‐ NM ‐ NM ‐ NM ‐ 29.42 G‐12  ‐ 40.9 ‐ >999*  ‐ NM ‐ NM ‐ NM ‐ NM ‐ 29.42 G‐13  ‐ 45.1 ‐ >999*  ‐ NM ‐ NM ‐ NM ‐ NM ‐ 29.42 G‐14  ‐ 30.3 ‐ >999*  ‐ NM ‐ NM ‐ NM ‐ NM ‐ 29.42 G‐15  ‐ 17.1 ‐ >999*  ‐ NM ‐ NM ‐ NM ‐ NM ‐ 29.42 G‐16  ‐ 10.9 ‐ 51 ‐ NM ‐ NM ‐ NM ‐ NM  ‐ 29.42 G‐17  ‐ 11.5 ‐ 44 ‐ NM ‐ NM ‐ NM ‐ NM  ‐ 29.42 G‐18  ‐ 0.3 ‐ 5  ‐ NM ‐ NM ‐ NM ‐ NM ‐ 29.42 G‐19  ‐ 0.1 ‐ 7  ‐ NM ‐ NM ‐ NM ‐ NM ‐ 29.42 G‐20  ‐ 0.1 ‐ 1  ‐ NM ‐ NM ‐ NM ‐ NM ‐ 29.42 G‐21  ‐ 11.7 ‐ >999*  ‐ NM ‐ NM ‐ NM ‐ NM ‐ 29.42 G‐22A  ‐ 25.0 ‐ 66 ‐ NM ‐ NM ‐ NM ‐ NM  ‐ 29.42 G‐23  ‐ 0 ‐ 2 ‐ NM ‐ NM ‐ NM ‐ NM  ‐ 29.42 G‐24  ‐ 7.6 ‐ >999*  ‐ NM ‐ NM ‐ NM ‐ NM ‐ 29.42 G‐25  ‐ 0.4 ‐ 6  ‐ NM ‐ NM ‐ NM ‐ NM ‐ 29.42 G‐26  ‐ 28.3 ‐ >999*  ‐ NM ‐ NM ‐ NM ‐ NM ‐ 29.42 G‐27  ‐ 2.5 ‐ 53 ‐ NM ‐ NM ‐ NM ‐ NM  ‐ 29.42 G‐28  ‐ 33.9 ‐ >999*  ‐ NM ‐ NM ‐ NM ‐ NM ‐ 29.42 G‐29  ‐ 48.2 ‐ >999*  ‐ NM ‐ NM ‐ NM ‐ NM ‐ 29.42 G‐30  ‐ 41.0 ‐ >999*  ‐ NM ‐ NM ‐ NM ‐ NM ‐ 29.42 G‐31  ‐ 23.9 ‐ >999*  ‐ NM ‐ NM ‐ NM ‐ NM ‐ 29.42 G‐32A  ‐ 33.6 ‐ >999*  ‐ NM ‐ NM ‐ NM ‐ NM ‐ 29.42 G‐33  ‐ 0 ‐ 3 ‐ NM ‐ NM ‐ NM ‐ NM  ‐ 29.42 G‐34  ‐ 0.2 ‐ 1  ‐ NM ‐ NM ‐ NM ‐ NM ‐ 29.42 G‐35A  ‐ 4.4 ‐ 44 ‐ NM ‐ NM ‐ NM ‐ NM  ‐ 29.42 G‐36  ‐ 0.8 ‐ 2  ‐ NM ‐ NM ‐ NM ‐ NM ‐ 29.42 G‐37  ‐ 0 ‐ 1 ‐ NM ‐ NM ‐ NM ‐ NM  ‐ 29.42 G‐38  ‐ 0.1 ‐ 1  ‐ NM ‐ NM ‐ NM ‐ NM ‐ 29.42 G‐39  ‐ 0 ‐ 3 ‐ NM ‐ NM ‐ NM ‐ NM  ‐ 29.42

    Notes: * Exceeds instrument limit

  • Certification

    In accordance with the Massachusetts Solid Waste Management Regulations (310 CMR 19.011),

    Aggregate Industries - Northeast Region, Inc. submits this certification for the February 2016 Quarterly

    Landfill Gas Monitoring Report prepared for us by Langdon Environmental LLC.

    I, Joel Nickel, attest under the pains and penalties of perjury that: (a) I have personally examined and am familiar with the information contained in this submittal, including any and all documents

    accompanying this certification statement; (b) based on my inquiry of those persons responsible for obtaining the information, the information contained in this submittal is, to the best of my knowledge, true, accurate, and complete; (c) I am fully authorized to bind the entity required to submit these

    documents and to make this attestation on behalf of such entity; (d) I am aware that there are

    significant penalties, including, but not limited to, possible administrative and civil penalties for

    submitting false, inaccurate, or incomplete information and possible fines and imprisonment for

    knowingly submitting false, inaccurate, or incomplete information.

  • Certification

    In accordance with the Massachusetts Solid Waste Management Regulations (310 CMR 19.011), the City

    of Haverhill, Massachusetts submits this certification for the February 2016 Quarterly Landfill Gas Monitoring Report prepared for us by Langdon Environmental LLC.

    I, Robert Ward, attest under the pains and penalties of perjury that: (a) I have personally examined and am familiar with the information contained in this submittal, including any and all documents accompanying this certification statement; (b) based on my inquiry of those persons responsible for obtaining the information, the information contained in this submittal is, to the best of my knowledge,

    true, accurate, and complete; (c) I am fully authorized to bind the entity required to submit these documents and to make this attestation on behalf of such entity; (d) I am aware that there are significant penalties, including, but not limited to, possible administrative and civil penalties for

    submitting false, inaccurate, or incomplete information and possible fines and imprisonment for knowingly submitting false, inaccurate, or incomplete information.

    barcode: *587326*barcodetext: SEMS Doc ID 587326