Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI) Ministry of Public Works and Housing World Bank www.jufmp.com 1 Korea Engineering Consultant Corp of Korea, in association with PT. Puser Bumi Mekon PT. Tetira International Consultants PT. Duta Cipta Mandiri Engineering Consultants

Upload: tjik-mail

Post on 20-Dec-2015

33 views

Category:

Documents


5 download

DESCRIPTION

Laporan Bulan Maret 2015 Proyek Penanganan Darurat Banjir Jakarta atau JUFMP/JEDI oleh Konsultan Supervisi Pelaksanaan JUFMP/JEDI, Construction SUpervision Consultant (CSC) for JUFMP/JEDI

TRANSCRIPT

Page 1: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

Ministry of Public Works and Housing World Bank

www.jufmp.com 1

Korea Engineering Consultant Corp of Korea,

in association with

PT. Puser Bumi Mekon

PT. Tetira International Consultants

PT. Duta Cipta Mandiri Engineering Consultants

Page 2: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

Ministry of Public Works and Housing World Bank

www.jufmp.com 2 Korea Engineering Consultant Corporation (KECC)

1. JUFMP/JEDI General Information 2. Consultant Services 3. Executive Summary 4. Issues 5. Ongoing Construction Packages * Package 1 * Package 2A * Package 2B * Package 3 * Package 5 6. Photo Gallery

Table of Contents

Page 3: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

Project Information

Project Name : JUFMP/JEDI

Loan Agreement : 8121 ID

Date of Loan Sign : February 17, 2012

Effective Date : August 8, 2012

Closing Date : March 31, 2017

Loan Amount : USD 139,640,000

Executing Agency : 1. Directorate General Water Resources, MoPW 2. Directorate General Cipta Karya, MoPW 3. Provincial Government of DKI Jaya

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

Ministry of Public Works and Housing World Bank

www.jufmp.com 3 Korea Engineering Consultant Corporation (KECC)

Page 4: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

1. Reduce the frequency and extend of flooding in Jakarta through dredging,

and rehabilitation and construction of embankment of key waterways and

flood retention basins;

2. Establishing institutional coordination between, and strengthening their

capacity of the three responsible agencies, to improve the operations,

maintenance and management of Jakarta’s flood management system.

The project is intended to reduce the economic and social cost of flooding by

partially restoring the capacity of the city’s flood control system to its original

design level.

Project Component

1. Dredging and rehabilitation of selected floodways, canals and retention

basins: USD 176.1 million

2. Technical assistance for project management, social safeguards, and capacity

building: USD 13.4 million

Project Development Objective (PDO)

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

Ministry of Public Works and Housing World Bank

www.jufmp.com 4 Korea Engineering Consultant Corporation (KECC)

Page 5: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

Project Organization

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

Ministry of Public Works and Housing World Bank

www.jufmp.com 5 Korea Engineering Consultant Corporation (KECC)

Page 6: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

Project Location

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

Ministry of Public Works and Housing World Bank

www.jufmp.com 6 Korea Engineering Consultant Corporation (KECC)

Page 7: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

Construction Supervision Consultant (CSC) for JUFMP/JEDI

Project Name : Construction Supervision Consultant for JUFMP{/JEDI

Source of Fund : World Bank

Addendum No.1 : 1,784,300 USD + 38,494,770,000 IDR

Contract Amount : 2,072,400 USD + 38,153,170,999 IDR

Engineer : Directorate of River and Coastal, Directorate General Water Resources, Ministry of Public Work and Housing

Contractor : Korea Engineering Consultants Corporation with PT. Puser Bumi Mekon joint venture and sub consultancy PT. Tetira International Consultant and PT. Duta Cipta Mandiri Engineering Consultant

Contract No. : 06/KTR/PPK-Ad-Satker/X/2013 September 11, 2013

Notice to Proceed : HI.0102-Ad/496 October 18, 2013

Time Period : 40.5 months Add No.1, originally 60 months

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

Ministry of Public Works and Housing World Bank

www.jufmp.com 7 Korea Engineering Consultant Corporation (KECC)

Page 8: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

Outline of Consultant Services

The main services of the Consultant for JUFMP/JEDI are: • Supervision of Dredging Work and Construction/Rehabilitation

of Embankment • Quality Assurances and Quality Control • Assist in Implementation of Environmental Management

(RKL/RPL) • Assist in Implementation of Resettlement Plans (RPs) • Implementation of Grievance Redress System (GRS) and

Complaint Handling • Monitoring, Reporting and Recording • Assist CPMU, CPIU and PIUs in Project Management

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

Ministry of Public Works and Housing World Bank

www.jufmp.com 8 Korea Engineering Consultant Corporation (KECC)

Page 9: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

Executive Summary

Figure 1. Budget Allocation for Component 1of JUFMP (in million USD)

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

Ministry of Public Works and Housing World Bank

www.jufmp.com 9 Korea Engineering Consultant Corporation (KECC)

103.5

58%

53.0

30% 22.3

12%

Total Budget 178.7

Prov Gov of DKI (37%) + IBRD (67%)

DG Water Resources (20%) + IBRD (80%)

DG Cipta Karya (20%) + IBRD (80%)

Page 10: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

Executive Summary

Table 1. Budget Allocation for Component 1 by Packages

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

Ministry of Public Works and Housing World Bank

www.jufmp.com 10 Korea Engineering Consultant Corporation (KECC)

Executing Agencies/ Packages Budget (Loan +

APBN/D) Loan Allocation

APBD/N

Sharing USD USD USD

1 4 = 2 + 3 2 3

DKI Jakarta 103,492,537 69,340,000 34,152,537

Package 1 36,716,418 24,600,000 12,116,418

Package 4 47,014,925 31,500,000 15,514,925

Package 7 19,761,194 13,240,000 6,521,194

DGWR 53,000,000 42,400,000 10,600,000

Package 2A 31,000,000 24,800,000 6,200,000

Package 2B 8,125,000 6,500,000 1,625,000

Package 6 13,875,000 11,100,000 2,775,000

DGCK 22,250,000 17,800,000 4,450,000

Package 3 6,717,421 5,373,937 1,343,484

Package 5 15,532,579 12,426,063 3,106,516

TOTAL 178,742,537 129,540,000 49,202,537

Page 11: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

Executive Summary

Table 2. Budget Allocation for Component 2

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

Ministry of Public Works and Housing World Bank

www.jufmp.com 11 Korea Engineering Consultant Corporation (KECC)

Items Total Loan IBRD

APBD/N

Sharing

Bilateral

Grant USD USD USD USD

Supervision Consultant 10,100,000 10,100,000 - -

Flood Management Information System 500,000 - - 500,000

Panel of Experts 500,000 - 500,000 -

Resetlement Cost (DKI Jaya) 2,800,000 - 2,800,000 -

Total Component 2 13,900,000 10,100,000 3,300,000 500,000

Total Project Cost (Comp 1+2) 192,642,537 139,640,000 52,502,537 500,000

Page 12: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

Executive Summary

Table 3. Contract Amount by Packages (in million IDR)

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

Ministry of Public Works and Housing World Bank

www.jufmp.com 12 Korea Engineering Consultant Corporation (KECC)

Executing Agencies/

Packages Contract Amount Loan APBN/D Sharing

DKI Jakarta 284,180,000,000 190,400,600,000 93,779,400,000

Package 1 284,180,000,000 190,400,600,000 93,779,400,000

Package 4 - - -

Package 7 - - -

DGWR 334,965,463,260 267,972,370,608 66,993,092,652

Package 2A 260,000,000,000 208,000,000,000 52,000,000,000

Package 2B 74,965,463,260 59,972,370,608 14,993,092,652

Package 6 - - -

DGCK 208,214,431,000 166,571,544,800 41,642,886,200

Package 3 68,514,386,000 54,811,508,800 13,702,877,200

Package 5 139,700,045,000 111,760,036,000 27,940,009,000

TOTAL 827,359,894,260 624,944,515,408 202,415,378,852

Page 13: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

Executive Summary

Figure 4. Financial Progress (in billion IDR)

-

50

100

150

200

250

300

Package 1 Package 2A Package 2B Package 3 Package 5

163.6 148.6

33.9

19.8 22.2

208.7 201.5

54.9 54.0

32.9

284.2

260.0

75.0 68.5

139.7

Disbursed Disbursement + Un-disbursement Contract Amount

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

Ministry of Public Works and Housing World Bank

www.jufmp.com 13 Korea Engineering Consultant Corporation (KECC)

Page 14: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

Executive Summary

Table 4. Volume of Dredge Material of On-going Packages

* Based on the latest addendum

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

Ministry of Public Works and Housing World Bank

www.jufmp.com 14 Korea Engineering Consultant Corporation (KECC)

Package Sign Date Notice to

Proceed

Period

Volume (thousand m3)

Weight Garbage Sludge

Garbage +

Sludge

(days) (m3) (m3) (m3) (%)

Package 1 Nov 26,2013 Dec 02,2013 730 2.8 165.6 168.4 8.3

Ciliwung-Gn. Sahari 1.5 85.1 86.6 4.2

Waduk Melati 1.4 80.5 81.9 4.0

Package 2A Nov 11,2013 Nov 11,2013 730 18.8 1,007.3 1,026.1 50.4

Package 2B Nov 11,2013 Nov 11,2013 730 20.0 513.7 533.7 26.2

Package 3 Nov 15,2013 Nov 15,2013 730 0.8 48.4 49.2 2.4

Package 5 Sep 3,2014 Sep 3,2014 730 6.2 253.0 259.2 12.7

Tanjungan Drain 0.0 11.2 11.2 0.6

Lower Angke Drain 6.2 241.8 248.0 12.2

T O T A L 48.7 1,988.0 2,036.7 100.0

Page 15: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

Executive Summary

Table 5. Progress of Dredging Works (on-going packages)

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

Ministry of Public Works and Housing World Bank

www.jufmp.com 15 Korea Engineering Consultant Corporation (KECC)

Package Trip of

Truck

Volume (thousand m3)

Garbage Sludge Garbage + Sludge

Package 1 8,072 - 149.2 149.2 88.6%

Ciliwung-Gn.Sahari 4,290 - 78.2 78.2 90.3%

Waduk Melati 3,782 - 71.0 71.0 86.7%

Package 2A 42,390 - 711.7 711.7 69.4%

Package 2B 19,377 - 334.2 334.2 62.6%

Package 3 209 - 3.6 3.6 7.3%

Package 5 - - - - -

Tanjungan Drain - - - - -

Lower Angke Drain - - - - -

T O T A L 70,048 - 1,198.7 1,198.7 58.9%

Page 16: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

Executive Summary

Figure 5. Schedule and Progress of Construction Works (%)

0 10 20 30 40 50 60 70 80 90

Package 5

Package 3

Package 2B

Package 2A

Package 1

13.0

81.9

74.0

66.3

72.4

13.6

78.8

73.3

77.5

73.4

Progress Schedule

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

Ministry of Public Works and Housing World Bank

www.jufmp.com 16 Korea Engineering Consultant Corporation (KECC)

Page 17: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

Issues

1. Package 1 – Ciliwung-Gunung Sahari and Waduk Melati

a) At waduk Melati, additional work will include railing to be installed around the waduk (original contract for installing fencing was deleted during MC 0).

b) Construction of Waduk Melati pump (4 m3/s) has tight work schedule c) At Gunung Sahari drain, several several need to be completed such as

gaps between embankment edge and bridges, U-ditch along the right bank and side walk along Jl. Gunung Sahari DKI request to heighten thje side walk as it plans).

2. Package 2A – Cengkareng Floodway

a) Embankment work at both sides of the floodway between bridges at STA 2+250 – STA 2+500 has not been started yet. Contractor propose using stone masonry rather than piles for the reason of working space limitation.

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

Ministry of Public Works and Housing World Bank

www.jufmp.com 17 Korea Engineering Consultant Corporation (KECC)

Page 18: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

Issues

b) At STA 3+400 – STA 5+050, there are several missing portion (gaps) on the presence of road crossings and culverts.

c) Remedial works have not been started . d) Water intake at Kembangan (PAM) is not relocated yet.

3. Package 2B – Lower Sunter Floodway

a) Temporary disposal using barges is still not being used.

4. Package 3 – Cideng-Thamrin Drain

-

5. Package 4 – Sentiong Sunter, Waduk Sunter Utara, Waduk Sunter Selatan and Waduk Sunter Timur III

a) Bid opened on March 24, 2015. PT. Adhi Karya has the lowest bidding price of 296.9 billion IDR

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

Ministry of Public Works and Housing World Bank

www.jufmp.com 18 Korea Engineering Consultant Corporation (KECC)

Page 19: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

Issues

6. Package 5 – Lower Angke and Tanjungan Drain

a) Not sufficient storage space available for CCSPs and heavy equipment (such as crane) at Lower Angke Drain.

b) DKI proposed a detention basin between Tanjungan drain and Kamal. c) Complaint from community to widen Tanjungan drain from 10 up to

14 m.

7. Package 6 – Banjir Kanal Barat (BKB)and Upper Sunter

a) Dredge from Karet to river mouth proposed to add to Package 6. b) Bidding is delayed due to LARAP.

8. Package 7 – Grogol Seketaris, Pakin, Kali Besar, Jelakeng and Krukut

a) Bid opened March 10, 2015. PT. Waskita Karya has the lowest bidding price of 226.8 billion IDR.

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

Ministry of Public Works and Housing World Bank

www.jufmp.com 19 Korea Engineering Consultant Corporation (KECC)

Page 20: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

Issues

9. LARAP a) Houses and buildings along upper Sunter Floodway (Package 6) in

Kayu Putih village of Pulo Gadung sub-district have been demolished by DKI Jaya Government. PAPs of JUFMP/JEDI located on Jatinegara Kaum were not affected by the demolition.

b) Due to problem at Lower Angke Muara, Dinas Tata Air DKI modify embankment work at Kel. Kapuk Muara to stone masonry in stead of piles.

c) LARAP reports for Sentiong Sunter, Waduk Sunter Utara and Waduk Sunter Selatan were prepared and second socialization is planned.

10.Construction Supervision Consultant a) Staff of site offices have faced difficulties due to shortage of

transportation (mainly motor cycles). b) Overtime payment for enumerators and drivers not yet resolved.

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

Ministry of Public Works and Housing World Bank

www.jufmp.com 20 Korea Engineering Consultant Corporation (KECC)

Page 21: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

www.jufmp.com 21 Korea Engineering Consultant Corporation (KECC)

Provincial Government of DKI Jaya World Bank

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

PACKAGE 1 CILIWUNG-GUNUNG SAHARI DRAIN AND WADUK MELATI

PT. Brantas Abipraya (Persero)

Contractor:

Page 22: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

www.jufmp.com 22 Korea Engineering Consultant Corporation (KECC)

Provincial Government of DKI Jaya World Bank

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

General Information

P I U : DPU - DKI

Contractor : PT. Brantas Abipraya

No Objection Letter : No. JUFMP 1

Letter of Acceptance : No. 14705/-7.793.2

Contract No. : 15380/-1.793.2 dated Nov 26, 2013

Contract Amount : IDR 284,180,000,000 (incl. PPN)

Signed Date : Nov 26, 2013

Notice to Proceed : 15452/-1.793.2 dated Nov 26, 2013

Completion Day : 730 Calendar days

Elapsed Days : 484 days (66.3 %)

Page 23: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

www.jufmp.com 23 Korea Engineering Consultant Corporation (KECC)

Provincial Government of DKI Jaya World Bank

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

Location and Scope of Works

ISTIQLAL MOSQUE

SHEET PILE 4,832 m

Dredging Volume: 86,557 m3

Progress : 78,185 m3 or 90.3% Embankment Repair : 4.600 m

LENGTH OF DREDGING

5,100 m

Ciliwung – Gunung Sahari Drain

Page 24: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

www.jufmp.com 24 Korea Engineering Consultant Corporation (KECC)

Provincial Government of DKI Jaya World Bank

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

Progress

I. Ciliwung-Gunung Sahari Drain 1. Dredging Work

Total volume = 86,557 m3 Progress = 78,185 m3 or 90.3% a) STA 0+500 – STA 5+100 (Upstream of Martadinata Bridge up to

Istiqlal – Pasar Baru) 2. Concrete Work

a) Total concrete = 2,033 m3 Length of concrete work 3,171 m

b) Form work type-B 450 at Ciliwung-Gunung Sahari - STA 0+625 – STA 1+037 (R) Length = 330.7 m - STA 1+050 – STA 1+120 (L) Length = 120.0 m - STA 1+731 – STA 1+997 (R+L) Length = 290.2 m - STA 2+000 – STA 1+900 (R+L) Length= 100 m

c) Reinforcement bar, deformed = 91.04 ton

Page 25: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

www.jufmp.com 25 Korea Engineering Consultant Corporation (KECC)

Provincial Government of DKI Jaya World Bank

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

Progress 3. Pilling Work

a) Furnishing of corrugated pre-stressed concrete pile (CCSP) W-450 i. CCSP W-450 L 12 m = 2,339 units ii. CCSP W-450 L 14 m = 1,573 units iii. CCSP W-450 L 17 m = 1,132 units iv. Square pile 40x40 cm= 392 units

b) Driving of CCSP W-450, total progress CCSP drived = 5,178 units i. Driving of CCSP W-450 L 12 m = 2,442 units

- STA 2+250 – STA 2+450 R = 184 units, L = 165 units - STA 2+600 – STA 2+800 R = 252 units, L = 249 units - STA 2+800 – STA 3+600 R = 780 units, L = 812 units

ii. Driving of CCSP W-450 L 14 m = 1,582 units - STA 0+550 – STA 1+300 R = 11 units, L = 143 units - STA 1+300 – STA 1+600 R = 270 units, L = 178 units - STA 1+700 – STA 2+150 R = 327 units, L = 371 units - STA 2+250 – STA 2+450 R = 144 units, L = 138 units

iii. Driving of CCSP W-450 L 17 m = 1,154 units - STA 0+550 – STA 1+300 R = 588 units, L = 566 units

Page 26: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

www.jufmp.com 26 Korea Engineering Consultant Corporation (KECC)

Provincial Government of DKI Jaya World Bank

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

Progress

4. Miscellaneous Work a) Demolishing and disposal of existing concrete, total = 12.82 m3 b) Demolishing and disposal of existing stone masonry, total = 2,488 m3

- STA 1+700 – STA 2+700 = 1,157 m3

- STA 0+500 – STA 1+650 = 1,331 m3

Page 27: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

www.jufmp.com 27 Korea Engineering Consultant Corporation (KECC)

Provincial Government of DKI Jaya World Bank

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

Location and Scope of Works

WADUK MELATI

Waduk Melati

Dredging volume : 81,878m3

Progress = 71,015 or 88.2% Embankment Repair : 4,150 m (sheet piles)

Embankment Protection =

4,150 m

Area of dredging 4.9 ha

Page 28: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

www.jufmp.com 28 Korea Engineering Consultant Corporation (KECC)

Provincial Government of DKI Jaya World Bank

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

Progress

II. Waduk Melati

1. Dredging Work Total volume = 81,878 m3 Progress = 71,015 m3 or 88.2%

- STA 0+000 – STA 0+550

2. Concrete Work a) Total concrete = 570.25 m3, length = 1,229 m b) Form work at Waduk Melati c) Reinforcement bar, deformed = 30.95 ton

3. Pilling Works a) Furnishing of corrugated pre-stressed concrete pile (CCSP) W-450

i. CCSP W-450 L 10 m = 959 units ii. CCSP W-450 L 12 m = 249 units iii. CCSP W-450 L 14 m = 0 units

Page 29: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

www.jufmp.com 29 Korea Engineering Consultant Corporation (KECC)

Provincial Government of DKI Jaya World Bank

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

Progress

3. Pilling Works

a) Furnishing of corrugated pre-stressed concrete pile (CCSP) W-450 i. CCSP W-450 L 10 m = 959 units ii. CCSP W-450 L 12 m = 249 units iii. CCSP W-450 L 14 m = 0 units

b) Driving of CCSP W-450, total = 1,208 units i. Driving CCSP W-450, L 10 m = 959 units

- STA 0+305 – 0+427 R = 608 units, L = 351 units ii. Driving CCSP W-450, L 12 m = 249 units

- STA 0+250 – 0+305 R = 3 units, L = 246 units iii. Driving CCSP W-450, L 14 m = 0 units

4. Miscellaneous Work

a) Demolishing and disposal of stone masonry, total = 1,021 m3 - STA 0+250 – STA 0+700 Right = 541 m3

- STA 0+200 – STA 0+600 Left = 480 m3

Page 30: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

Package 1. Ciliwung-Gn Sahari Drain and Waduk Melati

Figure 1.1. Progress of Dredging and Disposal Work (thousand m3) May 2014-Mar 2015

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

Ministry of Public Works and Housing World Bank

www.jufmp.com 30 Korea Engineering Consultant Corporation (KECC)

0.1 0.1 0.1 2.3

27.3

55.8

81.3 97.6

116.6 132.3

149.2

0

20

40

60

80

100

120

140

160

May-14 Jun-14 Jul-14 Aug-14 Sep-14 Oct-14 Nov-14 Dec-14 Jan-15 Feb-15 Mar-15

Page 31: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

0 2

6 10

14

19 23

29

36

44

51

58

65

72

77

72

3 4 6 9

15 20

30

37

43

53

58

62 67

69 71

73

0

5

10

15

20

25

30

35

40

45

50

55

60

65

70

75

80

85

90

Package 1. Ciliwung-Gn Sahari Drain and Waduk Melati

Figure 1.2. Schedule and Progress of Construction Work (%) Dec 2013-- Mar 2015

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

Ministry of Public Works and Housing World Bank

www.jufmp.com 31 Korea Engineering Consultant Corporation (KECC)

Schedule Progress

Page 32: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

Package 1. Ciliwung-Gn Sahari Drain and Waduk Melati

Figure 1.3. Financial Progress (in billion IDR)

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

Ministry of Public Works and Housing World Bank

www.jufmp.com 32 Korea Engineering Consultant Corporation (KECC)

163.6

58%

45.1

16% 75.5

26%

Disbursed Undisbursed Remaining

Contract Value = 284.2

Page 33: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

www.jufmp.com 33 Korea Engineering Consultant Corporation (KECC)

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

Contractor:

PACKAGE 2A CENGKARENG FLOODWAY

Adhi Karya-Hutama Karya-Jaya Konstruksi JV

Ministry of Public Works and Housing World Bank

Page 34: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

www.jufmp.com 34 Korea Engineering Consultant Corporation (KECC)

General Information

P I U : BBWS Ciliwung-Cisadane, DGWR

Contractor : Adhi Karya-Hutama Karya-Jaya Konstruksi (JV)

No Objection Letter : No. JUFMP/107 dated Sep 7, 2013

Letter of Acceptance : No.KU.03.01/PPK SP-SNVT PJSA CC/XI/310.1 dated Nov 6, 2013

Contract No. : HK.02.03/PPK SP-SNVT PJSA CC/XI/315.4 dated Nov 11, 2013

Amendment IV : IDR 260,000,000,000 incl. 10% tax

Amendment II : IDR 234,627,368,750 incl. 10% tax

Original Contract : IDR 209,808,000,000 incl. 10% tax

Signed Date : Nov 11, 2013

Completion Day : 730 Calendar days

Elapsed Days : 505 days (69.2%)

Provincial Government of DKI Jaya World Bank

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

Page 35: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

www.jufmp.com 35 Korea Engineering Consultant Corporation (KECC)

Location and Scope of Works Ministry of Pablic Works and Housing World Bank

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

Sta 7+800

Sta 6+750

Sta 5+000

Sta 3+750

Replacement of Water Gates Sta 4+500

Sta 5+875

W : 325 ; B : 1000 L : 14 meter

KAPUK PULO BRIDGE

KEMBANGAN BRIDGE

KAPUK RAYA

DREDGING WORK

Target Length = 8,380 m

Volume=1,026,125 m3 Finished Length = 4+700 m

Volume= 711,684 m3

PILLING WORK Target Length = 5,700 m

CCSP W-325 = 5,700 units

Pile 30x30 = 1,425 units Finished Length = ……... m

CCSP W-325 = 5,703 units

Pile 30x30 = 1,203 units

PILLING WORK

Length = 4,600 m

CCSP W-325 = 110,699 units

Pile 30x30 = 390,000 units

PILLING WORK Target Length = 2,100 m CCSP W-325 = 2,100 units Pile 30x30 = 525 units

Finished Length = 1,000 m CCSP W-325 = 1,071 units Pile 30x30 = 175 units

Cengkareng Floodway

Page 36: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

www.jufmp.com 36 Korea Engineering Consultant Corporation (KECC)

Progress Ministry of Pablic Works and Housing World Bank

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

1. General Items a) Preparation works b) Temporary access road c) Environmental test d) Environment monitoring and management e) Temporary storage area f) GPS vehicle tracking system (monitoring system) + server g) Rent of weight bridge

2. Dredging Work a) Total volume = 1,026,125 m3 Progress = 711,684 m3 (69.4%)

- STA 7+800 – STA 6+650

- STA 5+000 – STA 1+200

- STA 1+200 – STA 0+500

b) Rent of equipment for spreading on dumping area at CDF Ancol

Page 37: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

www.jufmp.com 37 Korea Engineering Consultant Corporation (KECC)

Progress Ministry of Pablic Works and Housing World Bank

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

3. Concrete Work a) Concrete capping beam, total = 2,292.1m3

- STA 2+100 – STA 1+359 R = 260.7 m3 - STA 5+000 – STA 2+500 R = 800.5 m3 - STA 7+700 – STA 6+531 R = 352.0 m3

- STA 5+000 – STA 2+500 L = 793.1 m3 - STA 7+700 – STA 7+280 L = 85.8 m3

b) Concrete back pile 50x50x50 cm = 1,203 units = 150.30 m3

- STA 5+000 – STA 2+500 R = 601 units = 65.12 m3 - STA 5+000 – STA 2+500 L = 602 units = 68.75 m3 - STA 2+208 – STA 1+359 R = 222 units = 27.75 m3

- STA 7+700 – STA 6+531 R = 310 units = 28.75 m3

c) Concrete walling steel = 86 m3

- STA 5+000 – STA 2+500 R = 550 units = 41 m3

- STA 5+000 – STA 2+500 L = 500 units =45 m3

Page 38: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

www.jufmp.com 38 Korea Engineering Consultant Corporation (KECC)

Progress Ministry of Pablic Works and Housing World Bank

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

4. Pilling Work a) Furnishing of CCSP, total = 8,057 units

i. CCSP W-325 A, L 12 m, total = 5,162 units ii. CCSP W-325 B, L 14 m, total = 2,567 units iii. CCSP W-325 B, L 15 m, total = 55 units iv. CCSP W-450 A, L 18 m, total = 273 units

b) Furnishing of concrete back pile 30x30, total = 2,064 units i. L 10 m, total = 1,656 units ii. L 12 m, total = 408 units

c) Driving of CCSP, total = 8,098 units - STA 5+000 – STA 2+500 at R W-325 A L 12 m, total = 1,194 units - STA 5+000 – STA 2+500 at R W-325 B L 14 m, total = 1,212 units - STA 5+000 – STA 2+500 at L W-325 A L 12 m, total = 1,632 units - STA 5+000 – STA 2+500 at L W-325 A L 12 m, total = 760 units

Page 39: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

www.jufmp.com 39 Korea Engineering Consultant Corporation (KECC)

Progress Ministry of Pablic Works and Housing World Bank

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

c) Driving of CCSP total = 7,576 units (cont.) - STA 2+515 – STA 2+361, R W-325 B L 15 m, total= 146 units - STA 2+200 – STA 1+206, L W-325 A L 14 m, total = 603 units - STA 2+200 – STA 1+206, L W-325 A L 15 m, total = 55 units - STA 2+200 – STA 1+206, L W-450 A L 18 m, total = 300 units - STA 7+700 – STA 6+531, R W-325 A L 12 m, total = 1,114 units - STA 7+700 – STA 6+522, L W-450 A L 12 m, total = 1,082 units

d) Driving back pile 30x30 cm, total = 1,842 units

- STA 5+000 – STA 2+500 at R L 10 m = 427 units, L 12 m = 129 units - STA 5+000 – STA 2+500 at L L 10 m = 603 units - STA 7+700 – STA 6+812 at L L 10 m = 310 units - STA 7+700 – STA 6+674 at L L 10 m = 151 units - STA 2+205 – STA 1+206 at R L 10 m = 22 units, L 12 m = 192 units - STA 2+361 – STA 2+393 ar R L 12 m = 8 units

Page 40: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

Package 2A. Cengkareng Floodway

Figure 2A.1. Progress of Dredging and Disposal Work (thousand m3) Mar 2014-- Mar 2015

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

Ministry of Public Works and Housing World Bank

www.jufmp.com 40 Korea Engineering Consultant Corporation (KECC)

13.7 29.4

67.1 92.8

123.4 134.7

182.5 246.7

377.4 457.5

530.1 605.5

711.7

0

80

160

240

320

400

480

560

640

720

800

Page 41: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

Package 2A. Cengkareng Floodway

Figure 2A.2. Progress of Dredging and Disposal Work (thousand m3) Dec 2014-- Mar 2015

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

Ministry of Public Works and Housing World Bank

www.jufmp.com 41 Korea Engineering Consultant Corporation (KECC)

1 3

3

8

17 19

32

38 41

46 49

53

60 62

65 66

11

23 27

29

34 37

40

46 47

54 57

65 66 69

73

78

0

5

10

15

20

25

30

35

40

45

50

55

60

65

70

75

80

85

Schedule Progress

Page 42: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

Package 2A. Cengkareng Floodway

Figure 2A.3. Financial Progress (billion IDR)

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

Ministry of Public Works and Housing World Bank

www.jufmp.com 42 Korea Engineering Consultant Corporation (KECC)

148.6

57%

52.9

20%

58.5

23%

Disbursed Undisbursed Remaining

Contract Value = 260.0

Page 43: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

www.jufmp.com 43 Korea Engineering Consultant Corporation (KECC)

Contractor:

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

Ministry of Public Works and Housing World Bank

PACKAGE 2B LOWER SUNTER FLOODWAY

PT. Hutama Karya (Persero)

Page 44: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

www.jufmp.com 44 Korea Engineering Consultant Corporation (KECC)

General Information

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

Ministry of Public Works and Housing World Bank

P I U : BBWS Ciliwung-Cisadane, DGWR

Contractor : PT. Hutama Karya

No Objection Letter : No. JUFMP/1

Letter of Acceptance : No.14705/-7.793.2

Contract No. : HK.02.03/PPK SP-SNVT CC/XI/315.4

Contract Amount : IDR 65,258,477,570

Amendment I No. : HK.02.03/AMD/PPK SP-SNVT/PJSA CC/II/38.5

Amendment I Amount : IDR 74,965,463,260

Signed Date : Nov 11, 2013

Notice to Proceed : Nov 11, 2013

Completion Day : 730 Calendar days

Elapsed Days : 505 days (69.2 %)

Page 45: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

www.jufmp.com 45 Korea Engineering Consultant Corporation (KECC)

Location and Scope of Works Ministry of Pablic Works and Housing World Bank

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

Concrete wall

1,000 m

Concrete Wall

400 m

Concrete Wall

400 m

Lower Sunter Floodway

Page 46: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

www.jufmp.com 46 Korea Engineering Consultant Corporation (KECC)

Progress Ministry of Pablic Works and Housing World Bank

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

1. General Items

a) Preparation works b) Environment test c) Environmental monitoring and management 2. Dredging works

Total volume = 533,689 m3 , progress = 334,215m3 or 62.6% - STA 0+025 – STA 7+350

3.Concrete works

a) Concrete type-A (K-225), total= 1,998 m3

- STA 7+263 – STA 6+933 = 400 m3 (Jul, 2014, Kodamar) - STA 6+911 – STA 6+758 = 185 m3 (Jul, 2014, Kodamar) - STA 6+758 – STA 6+614 = 261 m3 (Aug, 2014, Kodamar) - STA 6+614 – STA 6+398 = 45 m3 (Sep, 2014, Kodamar)

Page 47: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

www.jufmp.com 47 Korea Engineering Consultant Corporation (KECC)

Progress Ministry of Pablic Works and Housing World Bank

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

3. Concrete works

a) Concrete type-A (K-225), total= 1,998 m3 (continued)

- STA 6+407 – STA 6+442 = 58 m3 (Nov, 2014, Kodamar) - STA 7+855 – STA 7+902.82= 69 m3 (Dec 2015, Kodamar) - STA 5+775 – STA 6+357 = 63 m3 (Jan, 2015, Rumah Pompa) - STA 4+277 – STA 4+645 = 453 m3 (Feb 2015, Saingon)

- STA 5+775 – STA 6+357 = 170 m3 (Feb 2015, Rumah Pompa)

- STA 7+885 – STA 8+170 = 294 m3 (Feb 2015, Pedongkelan)

b) Formwork type A2 = 4,083 m2

c) Reinforcement bar, deformed = 87,305 kg d) Lean concrete t = 10 cm, total = 149 m3

e) Graded sand fill t = 10 cm, total = 149 m3

f) Stone masonry, total = 278 m3 - Parapet wall STA 6+300 – STA 7+241 = 35 m3 (Jan, 2015) - Parapet wall STA 6+096 – STA 5+880 =243 m3 (Feb, 2015)

Page 48: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

www.jufmp.com 48 Korea Engineering Consultant Corporation (KECC)

Progress Ministry of Pablic Works and Housing World Bank

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

4. Pilling works

a) Furnishing of concrete pile 20x20x400 cm, total = 3,600 units = 14,400 m

b) Driving of concrete pile 20x20x400 cm, total = 2,961 units = 12,744 m - STA 6+924 – STA 7+263 Left = 668 units (Jun 2014) - STA 6+911 – STA 6+375 Left = 918 units (Aug 2014) - STA 7+885 – STA 8+170.5 Left = 410 units (Oct 2014) - STA 6+100 – STA 6+233 Left = 267 units (Nov 2014) - STA 4+277 – STA 4+644 Left = 698 units (Feb 2015)

Page 49: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

Package 2B. Lower Sunter Floodway

Figure 2B.1. Progress of Dredging and Disposal Work (thousand m3) Mar 2014-- Mar 2015

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

Ministry of Public Works and Housing World Bank

www.jufmp.com 49 Korea Engineering Consultant Corporation (KECC)

3.0

16.8

47.6

57.3

68.0

81.3

126.8

185.0

243.6 282.7

306.5

314.2

334.2

0

50

100

150

200

250

300

350

400

Page 50: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

Package 2B. Lower Sunter Floodway

Figure 2B.2. Schedule and Progress of Construction Work (%) Dec 2014-- Mar 2015

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

Ministry of Public Works and Housing World Bank

www.jufmp.com 50 Korea Engineering Consultant Corporation (KECC)

0 2

5 9

13 17

23

29

37 37

44

51

58

64

68

74

13 13 14 18

24 27

31

37

42 44

47

56 59

65 68

73

0

5

10

15

20

25

30

35

40

45

50

55

60

65

70

75

80

Schedule Progress

Page 51: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

Package 2B. Lower Sunter Floodway

Figure 2B.3. Financial Progress (billion IDR)

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

Ministry of Public Works and Housing World Bank

www.jufmp.com 51 Korea Engineering Consultant Corporation (KECC)

33.9

45%

21.0

28% 20.0

27%

Disbursed Undisbursed Remaining

Contract Amount = 75.0

Page 52: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

www.jufmp.com 52 Korea Engineering Consultant Corporation (KECC)

Contractor:

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

Ministry of Public Works and Housing World Bank

PACKAGE 2B LOWER SUNTER FLOODWAY

PT. Hutama Karya (Persero)

PACKAGE 3 CIDENG THAMRIN DRAIN

PT. Dutaraya Dinametro

Contractor:

Page 53: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

General Information

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

Ministry of Public Works and Housing World Bank

www.jufmp.com 53 Korea Engineering Consultant Corporation (KECC)

P I U : Directorate of Environmental Sanitation Development, Directorate General Human Settlement, Ministry of Public Work and Housing

Contractor : PT. Dutaraya Dinametro

No Objection Letter : No. JUFMP-3

Contract No. : HK.02.03/JUFMP-FSK/XI/1

Contract Amount : IDR 62,324,785,000 (Addendum 2)

IDR 48,747,011,000 (Original Contract)

Signed Date : Nov 15, 2013

Notice to Proceed : Nov 15, 2013

Completion Day : 730 Calendar days

Elapsed Days : 501 days (68.6%)

Page 54: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

www.jufmp.com 54 Korea Engineering Consultant Corporation (KECC)

Location and Scope of Works Ministry of Pablic Works and Housing World Bank

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

Reinforced Concrete Block

EXISTING

SHEETPILES

NEW SHEETPILES

SUB MACRO

DRAIN

Cideng – Thamrin Drain

Page 55: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

www.jufmp.com 55 Korea Engineering Consultant Corporation (KECC)

Progress Ministry of Pablic Works and Housing World Bank

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

1. General Items a) Preparing works b) Environment test c) Environment monitoring and management

2. Dredging Work Total volume = 49,224 m3, progress = 3,598 m3 or 7.3% - STA CT-30 – CT-31, volume = 429 m3 - STA CT-4 – CT-7 , volume = 3,169 m3

3. Concrete Work, total = 898.8 m3 = 2,157.12 m a) Concrete Capping beam, total = 1,680 m3 = 700 m

- STA C-14 – C-18+27 = 94.17 m3 = 226 m, left and right - STA C-19 – C-25 = 122.08 m3 = 293 m, left and right - STA C-25+31 – C-26+15 = 20.00 m3 = 48 m, left and right - STA C-26+25 – C-27+25 = 22.08 m3 = 53 m, left and right - STA C-27+35 – C-32+22 = 43.33 m3 = 104 m, right - STA C-27+35 – C-32+22 = 48.33 m3 = 116 m, left

Page 56: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

www.jufmp.com 56 Korea Engineering Consultant Corporation (KECC)

Progress Ministry of Pablic Works and Housing World Bank

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

4. Pilling Works

a) Furnishing of corrugated pre-stressed concrete pile i. Furnishing CCSP W-325 L = 14 m, total = 602 units ii. Furnishing CCSP W-350 L = 16 m, total = 1,524 units

b) Driving of CCSP W-325 L = 14 m, total = 602 units - STA C-14 – C-20, left = 301 units, right= 301 units

c) Driving of CCSP W-350 L = 16 m, total = 1,524 units - STA C-20 – C-28, left = 318 units, right = 319 units - STA C-30 – C-28, left = 136 units, right = 136 units - STA CT-1 – CT-2, left = 71 units, right = 70 units - STA CT-3 – CT-7, left = 233 units, right = 241 units

Page 57: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

www.jufmp.com 57 Korea Engineering Consultant Corporation (KECC)

Progress Ministry of Pablic Works and Housing World Bank

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

4. Pilling Works

d) Driving of 6” Pipe 10 m under Bridges

Total target = 18,960 m = 1,896 pipes = 474 m Progress = 5,900 m = 590 pipes = 147 m - STA C-25+8 – C-25+21 Left = 50, Right = 52 pipes = 25.50 m - STA C-13+38 – C-14 Left = 16,Right = 36 pipes = 13.00 m - STA C-26+21 – C-26+26 Left = 16, Right =14 pipes = 7.50 m - STA C-27+28 – C-27+34 Left = 20, Right = 20 pipes = 10.00 m - STA C-28+10 – C-28+20 Left = 29, Right = 0 pipes = 7.25 m - STA C-30+41 – C-31+31 Left = 96, Right = 63 pipes = 39.75 m - STA C-32+28 – C-32+33 Left = 10, Right = 7 pipes = 4.25 m - STA CT-1 – CT-3 Left = 42, Right = 42 pipes = 21.00 m

Page 58: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

Package 3. Cideng Thamrin

Figure 3.1. Schedule and Progress of Construction Work (%) Dec 2013-- Mar 2015

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

Ministry of Public Works and Housing World Bank

www.jufmp.com 58 Korea Engineering Consultant Corporation (KECC)

5 5 3 6 10

13 16

20

25

33

41

47

62 62

71

82

0 0

5

11 15

21

26

34

41

48

63 62 64 64

72

79

0

5

10

15

20

25

30

35

40

45

50

55

60

65

70

75

80

85

90

Schedule Progress

Page 59: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

Package 3. Cideng Thamrin Drain

Figure 3.2. Financial Progress (billion IDR)

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

Ministry of Public Works and Housing World Bank

www.jufmp.com 59 Korea Engineering Consultant Corporation (KECC)

19.8

29%

34.2

50%

14.5

21%

Disbursed Undisbursed Remaining

Contract Amount = 68.5

Page 60: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

www.jufmp.com 60 Korea Engineering Consultant Corporation (KECC)

Ministry of Pablic Works and Housing World Bank

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

PACKAGE 5 TANJUNGAN DRAIN AND LOWER ANGKE DRAIN

PT. SAC Nusantara and PT. Penata Karya Utama (JO)

Page 61: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

General Information

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

Ministry of Public Works and Housing World Bank

www.jufmp.com 61 Korea Engineering Consultant Corporation (KECC)

P I U : Directorate of Environmental Sanitation Development, DGHS, MoPW

Contractor : PT. SAC Nusantara and PT. Penata Karya Keluarga Utama (JO)

No Objection Letter : -

Letter of Acceptance : No.KU.03.01/JUFMP/02/VIII/2014

Contract No. : HK.02.03/JUFMP-FSK/IX/2

Contract Amount : IDR 139,700,045,000 (incl. Tax)

Signed Date : Sep 3, 2014

Notice to Proceed : -

Completion Day : 730 Calendar days

Elapsed Days : 209 days (28.7%)

Page 62: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

Location and Scope of Works

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

Ministry of Public Works and Housing World Bank

www.jufmp.com 62 Korea Engineering Consultant Corporation (KECC)

LENGTH OF DREDGING

600 m SHEET PILE 1,092 m

Dredging : 11,210 m3

Embankment Repair: 1,092 m

TANJUNGAN DRAIN

Page 63: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

Location and Scope of Works

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

Ministry of Public Works and Housing World Bank

www.jufmp.com 63 Korea Engineering Consultant Corporation (KECC)

SHEET PILE 248 m

LENGTH OF DREDGING

4,050 m

RETAINING WALL 573 m

Dredging : 241,800 m3

Embankment Repair : 821 m

LOWER ANGKE

DRAIN

Page 64: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

Location and Scope of Works

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

Ministry of Public Works and Housing World Bank

www.jufmp.com 64 Korea Engineering Consultant Corporation (KECC)

I. General Items 1. Preparing works 2. Environmental test 3. Environment monitoring 4. Socialization of works at Kelurahan Pejagalan, Kecamatan

Penjaringan dan Kelurahan Kedaung Kali Angke, Kecamatan Cengkareng.

II. Tanjungan Drain

1. Pilling Works a) Furnishing of corrugate pre-stressed pile (CCSP)

i. CCSP W-500 L 16 m, total = 400 units ii. CCSP W-500 L 14 m, total = 600 units iii. Concrete square pile 0.3x0.3 m, L 10 m, total = 50 units

Page 65: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

Location and Scope of Works

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

Ministry of Public Works and Housing World Bank

www.jufmp.com 65 Korea Engineering Consultant Corporation (KECC)

b) Driving of CCSP W-500 L 14, total = 559 units - STA TJ.38 – STA TJ.36 at right = 98 units, at left = 91 units - STA TJ.35 – STA TJ.34 at right = 48 units, at left = 49 units - STA TJ.33 – STA TJ.32 at right = 47 units, at left = 49 units - STA TJ.30 – STA TJ.28 at right = 91 units at left = 86 units

c) Driving CCSP W-500 L 16, total = 376 units - STA TJ.36 – STA TJ.35 at right = 47 units, at left = 48 units - STA TJ.34 – STA TJ.33 at right = 47 units, at left = 48 units - STA TJ.32 – STA TJ.30 at right = 93 units, at left = 93 units

2. Concrete Works a) Concrete type A (K-225)

- Capping beam at STA Tj.37 - STA TJ.36 at left = 43.2 m3

2. Miscellaneous Work a) Rehabilitation of access bridge to Tanjungan Pump Station.

Page 66: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

Package 3. Tanjungan Drain and Lower Angke Drain

Figure 5.1. Schedule and Progress of Construction Work (%) Oct 2014-- Mar 2015

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

Ministry of Public Works and Housing World Bank

www.jufmp.com 66 Korea Engineering Consultant Corporation (KECC)

0.63

2.32

3.47

5.54

9.27

13.00

0.39

3.11

8.97

10.14

13.01

13.58

0

5

10

15

Oct 14 Nov 14 Dec 14 Jan 15 Feb 15 Mar 15

Schedule Progress

Page 67: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

Package 5. Tanjungan Drain and Lower Angke Drain

Figure 5.2. Financial Progress (billion IDR)

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

Ministry of Public Works and Housing World Bank

www.jufmp.com 67 Korea Engineering Consultant Corporation (KECC)

22.2

16%

10.7

8%

106.8

76%

Disbursed Undisbursed Remaining

Contract Value = 139.7

Page 68: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

Photo Gallery

Package 1. Ciliwung–Gn. Sahari Drain and Waduk Melati

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

Ministry of Public Works and Housing World Bank

www.jufmp.com 68 Korea Engineering Consultant Corporation (KECC)

Dredging under bridge using suction pump at STA 1+700

Concrete work at STA 2+700

Page 69: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

Photo Gallery

Package 2A. Cengkareng Floodway

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

Ministry of Public Works and Housing World Bank

www.jufmp.com 69 Korea Engineering Consultant Corporation (KECC)

STA 1+500( Trimaran): CCSP driving at the high voltage cable location (sutet).

STA 1+200( Trimaran): Temporary mud disposal for the drying

Page 70: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

Photo Gallery

Package 2A. Cengkareng Floodway

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

Ministry of Public Works and Housing World Bank

www.jufmp.com 70 Korea Engineering Consultant Corporation (KECC)

STA 2+400(Tol Sediyatmo): CCSP driving is doing near the tol bridge

STA 4+000 (Kp. Ambon): Concreting work for the canal steel (walling )

Page 71: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

Photo Gallery

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

Ministry of Public Works and Housing World Bank

www.jufmp.com 71 Korea Engineering Consultant Corporation (KECC)

Package 2B. Lower Sunter Floodway

Page 72: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

Photo Gallery

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

Ministry of Public Works and Housing World Bank

www.jufmp.com 72 Korea Engineering Consultant Corporation (KECC)

Package 3. Cideng – Thanrin Drain

Page 73: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

Photo Gallery

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

Ministry of Public Works and Housing World Bank

www.jufmp.com 73 Korea Engineering Consultant Corporation (KECC)

Package 5. Tanjungan Drain and Lower Angke Drain

Rehabilitation of acces bridge to Tanjungan Pump Station

Concrete Works at Tanjungan Drain

Page 74: Laporan Bulan Maret JUFMP/JEDI 2015 (Monthly Report March 2015) - Power Point

Photo Gallery

Construction Supervision Consultant for Jakarta Urgent Flood Mitigation Project (JUFMP)/ Jakarta Emergency Dredging Initiative (JEDI)

Ministry of Public Works and Housing World Bank

www.jufmp.com 74 Korea Engineering Consultant Corporation (KECC)

Package 5. Tanjungan Drain and Lower Angke Drain

Dredging work at Tanjungan drain Socialization