last 3 year employment history

13
My last 3 Year Employment History 11th July to 25th August, 2012: Offshore operations engineer onboard S355 at ExxonMobil Edop and Asasa Field, Nigeria Activities - Installation of new 8.2 Km long 12" gas injection pipeline from Edop QI platform to Asasa Va platform - Installation of riser clamps and hanger flange clamps at Edop QI and Asasa VA - Installation of risers at Edop QI and Asasa Va - Installation of riser guard for 12" riser at Asasa VA - Installation of subsea tie-in spools/ expansion loop for the pipeline at both Edop QI and Asasa Va October 25th to November 17th, 2012: Offshore operations Engineer onboard S355 at ExxonMobil field; Edop, Nigeria Activities - Installation of 24" replacement pipeline parallel to and west of existing 24"line from QIT shore pull point to Edop SSM of length 5.7Km approximately 28th November to 27th December, 2012: Pipeline Pre-commissioning Representative for Saipem at ExxonMobil Qua-Iboe Terminal (QIT) Activities - Flooding, Cleaning and gauging of 24" Edop SSM to QIT pipeline. - Hydrostatic testing of 24" Edop SSM to QIT pipeline - Flooding, Cleaning and gauging of 24" Ubit SSM to QIT pipeline. - Hydrostatic testing of 24" Ubit SSM to QIT pipeline

Upload: weli-ezioho

Post on 18-Aug-2015

16 views

Category:

Documents


8 download

TRANSCRIPT

Page 1: last 3 year employment history

My last 3 Year Employment History

11th July to 25th August, 2012: Offshore operations engineer onboard S355 at ExxonMobil Edop and Asasa Field, Nigeria

Activities

- Installation of new 8.2 Km long 12" gas injection pipeline from Edop QI platform to Asasa Va platform

- Installation of riser clamps and hanger flange clamps at Edop QI and Asasa VA

- Installation of risers at Edop QI and Asasa Va

- Installation of riser guard for 12" riser at Asasa VA

- Installation of subsea tie-in spools/ expansion loop for the pipeline at both Edop QI and Asasa Va

October 25th to November 17th, 2012: Offshore operations Engineer onboard S355 at ExxonMobil field; Edop, Nigeria

Activities

- Installation of 24" replacement pipeline parallel to and west of existing 24"line from QIT shore pull point to Edop SSM of length 5.7Km approximately

28th November to 27th December, 2012: Pipeline Pre-commissioning Representative for Saipem at ExxonMobil Qua-Iboe Terminal (QIT)

Activities

- Flooding, Cleaning and gauging of 24" Edop SSM to QIT pipeline.

- Hydrostatic testing of 24" Edop SSM to QIT pipeline

- Flooding, Cleaning and gauging of 24" Ubit SSM to QIT pipeline.

- Hydrostatic testing of 24" Ubit SSM to QIT pipeline

Page 2: last 3 year employment history

Riser moved from S355 to Edop QI platform for installation

Riser being installed at EDOP QI Platform

Page 3: last 3 year employment history

Riser guard re-installation at Edop QI

Laydown head passes through S355 tensioner during recovery operation of the 24” Edop SSM –QIT pipeline

Application of FBE on welded joint

Page 4: last 3 year employment history

Foam application on welded joint

Pipe joint in water

Page 5: last 3 year employment history

Concrete mattresses being laid at pipeline crossing.

24” PIG Receiver installed on Edop SSM – QIT Pipeline during pre-commissioning at ExxonMobil Facility; Qua-Iboe Terminal, Nigeria

Page 6: last 3 year employment history

Gauging PIG being retrieved from the PIG receiver

Hydro-static testing on 24”Edop SSM – QIT pipeline

Page 7: last 3 year employment history

Inspection of crew boat (MOP 1201) for the project

Page 8: last 3 year employment history

Inspection of Cybi Island – a shallow water tug boat

24th March to 25th June, 2013: Method engineer for Total Nigeria Ofon phase 2 at Saipem Office, France.

Activities

-Preparation of procedure for the installation of all jacket appurtenances

-Preparation and organization of site integration tests for all jacket installation aids

-Inspection of cargo barges, supply vessels and crew boats.

1st July to 25th October, 2013: Saipem sa Representative at Saipem yard, Nigeria for Ofon 2 project.

Activities

- Supervision of the installation of Globestar pipeline initiation rigging and J-tube messenger cables

- Supervision of the welding of riser guard upper bracing.

- Monitoring of Ofon 2 jacket installation aids welding/installation

- Supervision of the site integration of all caissons, riser guard, surfer landing and jacket installation aids

- Helped in preparation of checklist for Jackets load-out

- Installation of jacket and piles grillages on cargo barges

- Load out and seafastening of jacket piles.

- Load out and seafastening of Ofon 2 jacket.

Page 9: last 3 year employment history

1st November to December 23, 2013: Installation Engineer onboard Saipem 7000 at Ofon field, Nigeria

Activities

- Lifting and set-down of Jacket

- Lead and add-on piles installation

- Caissons upending and installation

-Riser guard upending and installation

- Installation of transition pieces for deck float-over

- Installation of Ofon accommodation jacket; OFQ

-Installation of OFQ modules and Helideck

Site integration of riser guard and welding of upper support bracing of the guard to the jacket

Page 10: last 3 year employment history

Site integration of the upper section of the surfer landing to the OFP2 jacket

Installation and testing of Fugro EDM equipment on the jacket walkway.

confirmation of the bore uniformity of the J-tube before the installation of messenger wire.

Page 11: last 3 year employment history

J-tube messenger wire and ROV shackle installed. The picture shows the bell mouth configuration of the J-tube

Site trial installation of the Jacket’s caissons. The photo shows the trial installation of the second firewater lift pump caisson.

Page 12: last 3 year employment history

Site installation of metrology brackets and risers’ blind flanges.

Site installation of Pipeline initiation rigging on three legs of the jacket.

Page 13: last 3 year employment history

OFP2 jacket on multi-wheeled trailers ready for loadout.

Page 14: last 3 year employment history

Inspection of cargo barge; Triumph 1. The cargo barge was used to transport jacket piles to Ofon field .

Inspection of enclosed spaces of Triumph 1

Jacket piles loaded on Triump1 ready to be sent offshore.

Page 15: last 3 year employment history

Jacket’s piles offloading from ENL Triumph 1 on to the main deck of Saipem 7000.

Page 16: last 3 year employment history

OFP2 jacket arrives Ofon field on board AMT Challenger towed by Red Dolphin.

Set-down of Jacket completed, piling starts

Page 17: last 3 year employment history

23rd March till date: Installation Engineer for Total Nigeria Egina field development project

- UFR offshore installation engineer