leaside & laird construction liaison committee - november 2017
TRANSCRIPT
4
Leaside Station: What to Expect
• Support of Excavation will continue to be underway until late 2018
• Support of Excavation includes:
– Piling
– Shallow Excavation
– Temporary decking installation
• Work is completed in stages around the intersection
• Temporary decking is installed over completed sections
• Once all the stages are complete, deep excavation will continue beneath the decking.
• Utility works will continue periodically over the next year.
5
Traffic Staging Look Ahead
Year Traffic Staging Changes
2017• Current Construction Stage 1B started in early October,
approximate 2-month duration
2018
• Construction Stage 2 starting in late 2017/early 2018, 4-
month duration
• Construction Stage 3 starting spring 2018, 3-month duration
• Construction Stage 4 following stage 3, 3-month duration
6
Stage 1B plus Wet Utilities Work
Starting November 8
Centre northbound lane will be temporarily closed.
X
New traffic set up to support wet utilities work.
7
Stage 2
There will be a period of time during Stage 2 where the east/west crossing will be closed and the north/south reopened.
13
Tunnel Fit Out: Invert Pour Stage 1
• Concrete trucks deliver loose concrete to the work area• Loose concrete mix is used to fill the bottom of the tunnel• Tunnel Fit Out crew flatten and smooth it
14
Tunnel Fit Out: Invert Pour Stage 2
• Workers install welded mesh which functions like rebar to help reinforce the next layer of concrete
• Higher strength concrete is poured to provide the flat track slab for the rail tracks• Workers spread the concrete, and a truss screed machine vibrates it into a perfectly level
surface
16
Laird Station: What to Expect
24 Hour Mining
• Mining operations are included in the 2010 Toronto Transit Project Noise By-Law Exemption to allow for tunneling and related work to occur 24 hours a day.
• A robust noise reduction plan based on major international projects such as the Boston Big Dig, Crossrail in London and the Thames Tideway Tunnel has been developed to minimize impacts on the local community.
– Implement noise reduction measures at the station construction sites
– Continually monitor noise and vibration throughout construction
– Adjust noise reduction measures at the construction sites as required
– If necessary, consider additional measures for residences in potentially sensitive zone
– Ensure proactive communications with the community before and during construction
Long Term Construction Activity Area Duration
24 hour mining work underway Main & Secondary Entrances Summer 2017 – to late 2019