leaside & laird construction liaison committee - november 2017

27
CROSSTOWN LRT Construction Liaison Committee November 8, 2017

Upload: crosstown-to

Post on 22-Jan-2018

1.424 views

Category:

Government & Nonprofit


1 download

TRANSCRIPT

CROSSTOWN LRTConstruction Liaison

CommitteeNovember 8, 2017

2

Agenda

• Leaside Station Update

• EEB3 Site Update

• Laird Station Update

• Shop Local Update

3

Leaside Station Update

4

Leaside Station: What to Expect

• Support of Excavation will continue to be underway until late 2018

• Support of Excavation includes:

– Piling

– Shallow Excavation

– Temporary decking installation

• Work is completed in stages around the intersection

• Temporary decking is installed over completed sections

• Once all the stages are complete, deep excavation will continue beneath the decking.

• Utility works will continue periodically over the next year.

5

Traffic Staging Look Ahead

Year Traffic Staging Changes

2017• Current Construction Stage 1B started in early October,

approximate 2-month duration

2018

• Construction Stage 2 starting in late 2017/early 2018, 4-

month duration

• Construction Stage 3 starting spring 2018, 3-month duration

• Construction Stage 4 following stage 3, 3-month duration

6

Stage 1B plus Wet Utilities Work

Starting November 8

Centre northbound lane will be temporarily closed.

X

New traffic set up to support wet utilities work.

7

Stage 2

There will be a period of time during Stage 2 where the east/west crossing will be closed and the north/south reopened.

8

October 2017

June 2017

Leaside Station – Main Entrance Progress

April 2016

March 2017

9

Progress Picture – Secondary Entrance

10

EEB3 Site Updates

11

LRT: Tunnel Fit Out

12

Tunnel Fit Out: Concrete Delivery

• Mini concrete trucks delivering concrete into tunnel.

13

Tunnel Fit Out: Invert Pour Stage 1

• Concrete trucks deliver loose concrete to the work area• Loose concrete mix is used to fill the bottom of the tunnel• Tunnel Fit Out crew flatten and smooth it

14

Tunnel Fit Out: Invert Pour Stage 2

• Workers install welded mesh which functions like rebar to help reinforce the next layer of concrete

• Higher strength concrete is poured to provide the flat track slab for the rail tracks• Workers spread the concrete, and a truss screed machine vibrates it into a perfectly level

surface

15

Laird Station Update

16

Laird Station: What to Expect

24 Hour Mining

• Mining operations are included in the 2010 Toronto Transit Project Noise By-Law Exemption to allow for tunneling and related work to occur 24 hours a day.

• A robust noise reduction plan based on major international projects such as the Boston Big Dig, Crossrail in London and the Thames Tideway Tunnel has been developed to minimize impacts on the local community.

– Implement noise reduction measures at the station construction sites

– Continually monitor noise and vibration throughout construction

– Adjust noise reduction measures at the construction sites as required

– If necessary, consider additional measures for residences in potentially sensitive zone

– Ensure proactive communications with the community before and during construction

Long Term Construction Activity Area Duration

24 hour mining work underway Main & Secondary Entrances Summer 2017 – to late 2019

17

Laird Long Term Closure

18

October 2017

June 2017

Laird Station – Main Entrance Progress

April 2016

November 2016

19

October 2017

April 2017

Laird Station – Secondary Entrance Progress

May 2016

October 2016

20

Shop Local Update

21

Business Marketing and Advertising Support

22

Experience Eglinton Ad Campaign

23

Holiday 2017 Ad Campaign

24

Experience Eglinton Signage

25

Business Signage (Directional)

26

Parking Support

Green P directional signage

Business support parking pamphlet

27

Local Area Map

Station(s) under construction