Estimation, Specifications & Contracts Earthworks Lecture .5
1
Dr. Muthanna Adil Najm Northern Technical University
Earthworks for various engineering projects
Earthworks, in general, may be encountered in any civil engineering
project.
In building and small projects, the quantities of earthworks can be
calculated easily as have been shown in previous subjects and solved examples,
whereas other kinds of projects, such as roads, canals, bridges, tunnels, dams
and others, involve a huge quantities of earthworks, the calculations of which
may be somewhat complex due to random changes or variations in the natural
ground level.
DEFINITIONS
Lead: it is the average horizontal straight practical distance through which the
excavated soil is carried from the sources to the place of spreading or
dumping. Usually the work site is divided into areas or blocks and haul
distance is calculated from the centre of each block to the destination
location. When the haul distance is too long the transport must be
calculated separately.
Lift: It is the average vertical distance (height) above which the soil has to be
lifted from the source. مسافة الرفع
Quantity survey: the process of calculating the quantity of materials required to
build a project.
Mass Excavation: the requirement to excavate substantial volume of material,
usually at considerable depth or over a large area.
Structural excavation: excavation undertaken in support of structural element
construction, usually involve removing materials
from a limited area.
Estimation, Specifications & Contracts Earthworks Lecture .5
2
Dr. Muthanna Adil Najm Northern Technical University
Plan view: a construction drawing representing the horizontal alignment of the
work.
Profile view: a construction drawing depicting a vertical plane cut through the
centerline of the work . it shows the vertical relationship of the
ground surface and the finished work.
Cross section view: a construction drawing depicting a vertical section of
earthwork at right angles to the centerline of the work.
Cross sections: earthwork drawings cheated by combining the project design
with field measurements of existing conditions.
Stripping: the upper layer of organic material that must be removed before
beginning an excavation or embedment. التعرية أو القشط
Mass diagram: It is a graph showing the accumulation of cut and fill with
distance from a starting, or origin, or reference point. Cut is
usually considered positive & fill negative. Mass diagram is
very useful for determining the quantities of earthworks,
computing hall distances and specifying the proper types of
equipment to perform the works.
(refer to attached details and examples – photo copy from Peurifoy)
percent وعامل التقلص %(20مناطق القطع )عادة في percent swell يتم اعتبار نسبة االنتفاخ .
shrinkage التربة المدفونة المرصوصة الحتساب حجم الحفريات أو%( 10)عادة في مناطق الدفن
.على التوالي
Bank (× 100حجمها الطبيعي ) –بعد الحفر ) رخوة ( حجم التربة = نسبة االنتفاخ )%( ( Bحجمها الطبيعي )
100 × (compacted) بعد الرصحجمها –قبل الرصحجم التربة = )%( التقلصنسبة قبل الرصحجم التربة
Estimation, Specifications & Contracts Earthworks Lecture .5
3
Dr. Muthanna Adil Najm Northern Technical University
إذا كان مخطط الكميات بين محطتين أفقيا، فهذا يعني انه ال توجد مواد مطلوب نقلها في هذا الجزء من المشروع. في الواقع قد يكون هناك قطع وإمالء ضمن هذا الجزء لكنها متوازنة )أي كمية القطع تساوي تقريبا كمية اإلمالء(. وإذا كان العمل يشتمل على قطع من جانب وإمالء من جانب آخر، فان منحني الكميات ينزع أو يميل إلى االستواء الن كميات القطع يمكن نقلها من
. cross hallجانب إلى آخر وليس من محطة إلى أخرى، وهذه العملية تسمى النقل "العرضي"
إن ميل أو انحدار منحنى الكميات يزداد مع زيادة الحجوم بين المحطات، فالمنحنى وجود قطع بينما المنحنى النازل يدل على أعمال إمالئيات. يصل المنحنى إلى الصاعد يشير إلى
مناطق الذروة حيث ينتهي القطع ويبدأ اإلمالء، والى المناطق الدنيا حيث ينتهي اإلمالء ويبدأ القطع.
لو رسمنا خطا أفقيا من نقطة المرجع فانه سيقطع منحنى الكميات في نقاط معينة، وفي هذه الحالة فان كميات القطع واإلمالء ستتوازن )أي تتساوى تقريبا( بين نقاط التقاطع. إن مجموع أو حصيلة مسافة النقل الكلية يمكن حسابها من حاصل ضرب الكمية الكلية للحفريات بمعدل
. أما مركز كميات القطع أو اإلمالء فيمكن تحديده كما average haul distanceة النقل مساف يلي:
. balancing lineنرسم خطا عموديا من نقطة الذروة إلى خط الموازنة -1
نرسم خطا أفقيا يمر بمنتصف الخط المرسوم أعاله ويقطع منحنى الكميات في نقطتين -2 أو المحطات التي تقابل نقطتي التقاطع(. متقابلتين. )الحظ النقاط
Estimation, Specifications & Contracts Earthworks Lecture .5
4
Dr. Muthanna Adil Najm Northern Technical University
إن النقطة أو المحطة الواقعة في الجزء الصاعد من المنحنى تمثل مركز كميات القطع -3والمحطة الواقعة في الجزء النازل هي مركز االمالئيات. أما المسافة بين هاتين المحطتين فتمثل
. haul distanceمسافة النقل لهذا الجزء
صعب لوجود عدة عوامل تؤثر في رأمالحفر بصورة دقيقة أعمالتقدير معدل انجاز إن -بمجموعتين من العوامل هي : إيجازهاويمكن ،هذا المعدل
sJob factor: عوامل تتعلق بظروف العمل والموقع منها : نوع التربة، مستوى الرطوبة والمياهالجوفية، الظروف المناخية، حرية حركة العمال والمعدات حجم العمل ومسافة نقل
Fill (m3)
Cut (m3)
Balance points
Haul distance
cut center of mass
fill center of mass
Estimation, Specifications & Contracts Earthworks Lecture .5
5
Dr. Muthanna Adil Najm Northern Technical University
ظروف العمل هذه كلها مفروضة إن ... الخ .الطريق المحفورة وظروفالتربة يمكنها تغييرها. على الجهة المنفذة وال
Management factors وتتضمن تنظيم العمل، والحفاظ على الروح المعنوية اإلدارة: عواملالعالية للعمال واختيار واستخدام المعدات والعدد والطرق المناسبة
كل اية بالمعدات والحفاظ على معدالت االنجاز وغيرها.للعمل، العنالجهة المنفذة ويمكن السيطرة إدارةهذه العوامل تعتمد على حسن
عليها.
Principles of Earthworks حساب األعمال الترابية مبادئ Calculation
.تقاس كميات األعمال الترابية عادة بالمتر المكعب، إال إن ذكر خالف ذلك
.األعمال الترابية ألنواع مختلفة من التربة يجب أن تحسب بصورة منفصلة
.تحسب الكميات الترابية بعد قياسها بعناية وتستخدم طريقة مناسبة لذلك
كساء والتسوية يجب أن تشمل في الفقرة.اإل أعمال
يد حسابات الكميات الترابية يجب أن تتضمن رفع ونقل الكميات الترابية وهنا يجب تحد مسافة النقل لكل عملية.
Estimation, Specifications & Contracts Earthworks Lecture .5
6
Dr. Muthanna Adil Najm Northern Technical University
Earth Computation Methodsطرق حساب الكميات الترابية
إن المقطع العرضي لطرق السيارات والسكك الحديدية والقنوات في منااطق الحفار أو القطاع cutting واإلمااالءfilling والتعبئااةbanking يكااون عااادة بشااكل حاابه منحاارفtrapezoidal ،
ويمكن حساب مساحة القطع لهذا الشكل كما يلي:
Area = ABCEF +AABF + AEDC
= bh + 0.5h.sh + 0.5 h.ah
Area= h [b + (ah + sh)/2] -----------------------------(1)
االنحدار متساو للجانبين( نحصل على: أي) s = aعندما
Area= h (b + sh) = hb + sh2 ---------------------------(2)
-هناك عدة طرق مستخدمة لحساب كمية األعمال الترابية وأهمها:
Average end area method -I طريقة معدل المساحات
يحسب معدل مساحة المقطع العرضي عند طرفي الجزء أو القطاع ويضرب في طول الجزء للحصول على الحجم.
on Formula Mid Secti -II المقطع الوسطي أو معادلة صيغة
A
B
F E D
C
a:1 s:1
b b ah sh
a:1 s:1 h
Estimation, Specifications & Contracts Earthworks Lecture .5
7
Dr. Muthanna Adil Najm Northern Technical University
الطرفين حسب مساحة المقطع عند وسط أو منتصف الجزء، وهنا يعتمد معدل االرتفاع عند ت لحساب المساحة.
H = (h1+h2)/2معدل االرتفاع
Where H: mean depth
h1,h2: depth at start & end points.
ormula method Prismoidal f -III معادلة الموشور
حيث تستخدم الصيغة التالية لحساب الحجم لكل جزء
V= L/6 (A1+A2+4Am)-------------------------(3)
Where A1, A2: areas at end points
Am: mid section area
L: length or distance between the adjacent stations (A1, A2)
Example: Calculate the quantity of earthworks for the 150 m long cutting,
12m wide at crest and whose side slope is 2.0:1. The centre
heights at every 30 m intervals are 0.5m 0.75m, 1.0m, 1.25m,
1.5m. Try solving by all above described methods.
Solution:
A – average area method
Quantity
m3
Length
M
Mean
area (m2)
Area at station
bh + sh2
Depth
h(m) Station
or
chained
12x0.5+2x0.5x0.5= 6.5 0.5 0
249.3 30 8.3125
12x0.75+2x0.752 = 10.125 0.75 1
Estimation, Specifications & Contracts Earthworks Lecture .5
8
Dr. Muthanna Adil Najm Northern Technical University
Quantity
m3
Length
M
Mean
area (m2)
Area at station
bh + sh2
Depth
h(m) Station
or
chained
361.8 30 12.0625
12x1+2x12 = 14 1 2
481.8 30 16.0625
12x1.25+2x1.252 = 18.12 1.25 3
609.38 30 20.3125
12x1.5+2x1.52 = 22.5 1.5 4
1702.26 Total quantity =
B- Mid–Section Method
Quantity
(m3)
Distance
(m)
Area bh+sh2 (m
2) Mean
Depth (m)
Depth
(m)
Station
0.5 0
248.4 30 12(.625)+2(.625)2=8.281 0.625
0.75 1
360.9 30 12(.875)+2(.875)2=12.03 0.875
1.0 2
480.9 30 16.03 1.125
1.25 3
608.4 30 20.28 1.375
Estimation, Specifications & Contracts Earthworks Lecture .5
9
Dr. Muthanna Adil Najm Northern Technical University
1698.6m3 Total = 1.5 4
C- For odd number of stations eq. (3) may be modified to obtain the
following formula:
V = L/3 (1st Area + last Area + 4 x even areas + 2x odd areas)
Using this formula we can obtain the following (see areas in a):-
V = L/3 {A1+A5+4 (A2+A4)+2 (A3)}
= 30/3 {6.5+2205+4 (10.125+18.125)+2 (14)}
V = 1700 m3
Example: The ground levels at various chainage along line of a proposed
channel are as under, see the cross-section where some design
parameters are shown. The chain is s50m long.
222 221 220 219 218 217 216 215 Chainage
210.00 209.65 209.90 210.35 211.10 211.50 211.05 210.30 G.L. (m)
209.15 209.20 209.25 209.30 209.35 209.40 209.45 209.50 C.L. (m)
227 226 225 224 223 Chainage
211.30 211.60 211.20 210.90 210.25 G.L. (m)
208.90 208.95 209.00 209.05 209.10 C.L. (m)
Estimation, Specifications & Contracts Earthworks Lecture .5
10
Dr. Muthanna Adil Najm Northern Technical University
Solution: use mid – section formula.
Acutting = bh + sh2 = 4h + 0.5 h
2
Afilling = bh + sh2 = 2.5 (k-h) + 1 (k-h)
2 + 2 (k-h) + 1 (k-h)
2
= 4.5 (k-h) + 2 (k-h)2
= 4.5 (4-h) + 2 (4-h)2
(1) (2) (3) (2) - (3) (5) (6) (7) (8) (9) (10)
Qty.
Filling
(m3)
Area
Filling
(m2)
K–hmean
(m)
Qty.
cutting
(m3)
Area
Cutting
(m2)
hmean
(m)
h
(m)
C. L.
(m)
G. L
(m)
Running
Distance
(m)
Chainage
0.80 209.50 210.30 0 215
1414 28.28 2.8 276 5.52 1.20
1.60 209.45 211.05 50 216
946 18.93 2.15 456 9.12 1.85
2.10 209.40 211.50 100 217
894 17.89 2.07 479.5 9.59 1.93
1.75 209.35 211.10 150 218
1261 25.22 2.6 329 6.58 1.4
1.05 209.30 210.35 200 219
1701 34.03 3.15 188.5 3.77 0.85
0.65 209.25 209.90 250 220
1966 39.33 3.45 117.5 2.35 0.55
0.45 209.20 209.65 300 221
2.5
1:2 h 1:2
4.00
K = 4.0
1:1 1:1
2.0
H=k-h H=k-h 1:1
Estimation, Specifications & Contracts Earthworks Lecture .5
11
Dr. Muthanna Adil Najm Northern Technical University
Qty.
Filling
(m3)
Area
Filling
(m2)
K–hmean
(m)
Qty.
cutting
(m3)
Area
Cutting
(m2)
hmean
(m)
h
(m)
C. L.
(m)
G. L
(m)
Running
Distance
(m)
Chainage
1876 37.52 3.35 140.5 2.81 0.65
0.85 209.15 210.00 350 222
1575 31.5 3.0 225 4.50 1.00
1.15 209.10 210.25 400 223
1187 23.75 2.5 356.5 7.13 1.50
1.85 209.05 210.90 450 224
831 16.63 1.97 509.5 10.19 2.03
2.20 209.00 211.20 500 225
600 12.0 1.57 634 12.68 2.43
2.65 208.95 211.60 550 226
547 10.94 1.47 666.5 13.33 2.53
2.40 208.90 211.30 600 227
14798 4378.5 Total
Example: Estimate the cost of excavating and backfilling a trench 1.5 m
wide, 1.2 m deep and 150 m long. Assume the team consists of
one foreman and a number of laborers to perform the job
within five labor days ( each equivalent to 8 working hours).
The job involves the following operations:
- Loosening earth with a pick ( 0.35m3 /hr-laborer)
- Shoveling earth from trench ( 0.475 m3 / hr-lab.)
- Backfilling trench ( 1.5 m3 / hr-lab.)
Wages : 30000 I.D. /day for the foreman; 15000 I.D. /day for laborer.
Solution:
V = 1.5 ×1.2 ×150 = 270m3
270 270 270
Estimation, Specifications & Contracts Earthworks Lecture .5
12
Dr. Muthanna Adil Najm Northern Technical University
No. of (laborer - days) required = ---------- + ---------- + ------------- 8×0.35 8×0.475 8×1. 5
= 96.43 + 71.05 +22.5 = 190 laborer- days
no. of laborers required to perform the job within 5 days=190/5= 38 laborers
Cost = ( 1×30.000 + 38×15.000) ×5 = 3.000.000 I.D.
Cost per 1m3 = 3.000.000 / 270 = 11111 I.D./m
3
Cost per 1m length = 3.000.000 / 150 = 20.000 I.D./m.
Example: Resolve the previous example using wheel type trenching
machine to perform the first two operations . i.e. backfilling by
laborers. Assume the average speed of trenching 6.25m 1hr.
Average cost of renting & operating the machine is = 35.000
I.D. /hr.
Solution : we need the trenching machine to operate for
150m. / 6.25m /hr. = 24hrs. or 24 / 8 = 3 days
Cost of machine : 24×3.500 = 840.000 I.D.
For backfilling we need 22.5 (say 24) days-laborer
no. of laborers to do backfilling within 3 days:
24 / 3 = 8 laborers
So we need a team of 8 laborers & one foreman for 3 days.
The cost (wages) is: (8×15.000 + 1×30.000)×3 = 450.000 I.D.
Total per job = 840.000+450.000=1.290.000 I.D.
Cost per m3 = 1.290.000 / 270 = 4780 I.D/m3
Cost per m length = 1.290.000 / 150= 8600 I.D./1m of term
Estimation, Specifications & Contracts Earthworks Lecture .5
13
Dr. Muthanna Adil Najm Northern Technical University
Example: Estimate the cost of materials required for installing solid
sheeting for 100 m of trench 2.1 m deep . use 4 cm × 25cm lumber 2.4 m
long for sheeting with two horizontal rows of 10cm × 15 cm wales on
each side of the trench for the full length of the trench. Assume that the
sheeting can be used 4 times and the wales ten times. Price = 520 000
I.D/m3.
Solution:
Vsh. = 0.04×2.4×100×2 = 19.2m3
V Wales = 0.1 ×0.15×100×2×2 = 6m3
Csh = 19.2×520000 / 4 = 2496000
Cw.= 6×520000 / 10 = 312000 I.D.
total 2808000 I.D.
حيث تكون Shoring اهي حالة خاصة في ال Solid Sheetingمالحظة هذه الحالة اي على مسافات محددة وليست متالصقة. األلواح