lecture on ctw - copy
TRANSCRIPT
-
8/12/2019 Lecture on CTW - Copy
1/103
-
8/12/2019 Lecture on CTW - Copy
2/103
POWER PLANT
REPAIR TECHNIQUESAT CENTRAL GAS
TURBINEMAINTENANCE
WORKSHOP
FAISALABAD
-
8/12/2019 Lecture on CTW - Copy
3/103
CENTRAL GAS TURBINE MAINTENANCE
WORKSHOP WAPDA FAISALABAD
-
8/12/2019 Lecture on CTW - Copy
4/103
CONTENTS
1. INTRODUCTION OF WORKSHOP2. OBJECTIVES.3. ORGANIZATION CHART.
4. FIELD OF SERVICES.5. SERVICES TO PRIVATE &
GOVERNMENT ORGANIZATIONS.6. FLOW DIAGRAM OF REPAIR PARTS.
7. INTRODUCTION OF REPAIR SHOPS.8. PARTS RECEIVED/DESPATCHED9. OVERALL VIEW OF REPAIRED PARTS10. SOME MAJOR WORKS DONE
-
8/12/2019 Lecture on CTW - Copy
5/103
After the commissioning of 200 MW GTPS
Faisalabad in order to keep the Power Plant ready for
operation necessity to have sufficient quantity of spare
parts was un-avoidable. This was only possible byimporting new parts or by sending the used ones abroad
for repair.
All the turbine hot gas path components are made ofhigh temperature (Nickel & Cobalt) alloys.It was not
possible to manufacture or repair of turbine parts in our
country so necessity to repair used parts within our
country was strongly felt.
INTRODUCTION OF CENTRAL GASTURBINE MAINTENANCE WORKSHOP
FAISALABAD
-
8/12/2019 Lecture on CTW - Copy
6/103
This idea was brought in the physical state by
Late Shakoor Ahmad, working as Chief Engineer
(Th) Faisalabad at that time. Which not only helped tointroduce repair of super alloys in Pakistan but on the
other hand helped a lot in decreasing the import of new
parts which resulted in saving precious foreign exchange
& reducing the down time of Power Plant as well asavailability at the earliest.
To establish a repair Workshop funds to import the
equipment from abroad in foreign currency and to
construct a building in pak currency were needed. For
this purpose left over amount after the completion of 200
MW GTPS Faisalabad was utilized local components of
cost of project was provided by Wapda.
-
8/12/2019 Lecture on CTW - Copy
7/103
CONSULTANCY OF TECHNICAL WORKS.
M/S FICHTNER Suttgart West Germany were appointed
as consultants where as their local counter part was M/S
MIDEAST Consultants Lahore.
SUPPLY OF EQUIPMENT.
Workshop equipment was supplied by M/S SIEMENSand Co Hamburg West Germany and their local counter
part was M/S MIDEAST Lahore.
-
8/12/2019 Lecture on CTW - Copy
8/103
CIVIL WORK CONTRACT.
M/S Syed Imdad Hussain Shah and Company were
awarded the contract of civil works to complete thebuilding. Total cost of the project was Rs.20.2 million.
The bifurcation of which is as under:-
1. Local = Rs.11.10 Million
2. Foreign = Rs. 9.10 MillionTotal:- Rs.20.20 Million
After the arrival of equipment it was installed in the
presence of Mr.W. Boll representative of M/S SIEMENS.Same gentleman later on trained the locally appointed
staff. In this way the repair of turbine hot gas path
components was initiated first time by Wapda itself. So
the old Workshop started functioning during 1983.
-
8/12/2019 Lecture on CTW - Copy
9/103
MAIN HALL OF OLD WORKSHOP BUILDING
-
8/12/2019 Lecture on CTW - Copy
10/103
EXTENSION OF WORKSHOP FACILITIES
With the passage of time Gas Turbines ranging from 90to 140 MW & Steam Turbines from 210 to 320 MW
started operating in Wapda Generation System. So the
necessity to have another Workshop to handle and
repair large parts of above said Gas & Steam Turbines infuture was strongly felt.
For this purpose M/S EU-BANK PRIECE UK wereappointed as consultants by Wapda who were
responsible for the supply of equipment. M/S ICL were
awarded to design and construct Workshop building.
-
8/12/2019 Lecture on CTW - Copy
11/103
Total cost of the extension project was 219.245 Million.
Bifurcation of which is as under:-
1. Cost of Civil Works = Rs. 59.400 Million
2. Cost of Equipment = Rs.159.845 Million
Total:- Rs.219.245 Million
The installation of most of the equipment was done by
Workshop staff, whereas installation of Heavy Duty
Lathe Machine, Over Head Crane and Vacuum Furnace
was completed by their respective representatives. This
new Workshop started rendering services during 1994.
-
8/12/2019 Lecture on CTW - Copy
12/103
MAIN HALL OF NEW WORKSHOP BUILDING
-
8/12/2019 Lecture on CTW - Copy
13/103
OBJECTIVES
TO PROVIDE INSPECTION AND REPAIR FACILITIES TOALL THERMAL POWER STATIONS OF WAPDA POWERGENERATION SYSTEM.
PREVIOUSLY TURBINE DAMAGED PARTS WERE BEINGSENT TO FOREIGN COUNTRIES FOR WANT OFREPAIRS.
THE FOREIGN REPAIR COST WAS ABOUT 40% OF THENEW PARTS PRICE AND ALSO IT REQUIRED LONGERDOWN TIME OF UNITS.
TO IMPROVE THE TECHNICAL KNOW HOW OF LOCALWAPDA STAFF
-
8/12/2019 Lecture on CTW - Copy
14/103
-
8/12/2019 Lecture on CTW - Copy
15/103
Workshop is equipped to provide following services:-
1. Repair of hot gas path components of GE Fiat,
Mitsubishi, Westinghouse & KWU Gas Turbines. 2.
Re-balding of Gas, Steam Turbine Axial and
Compressor Rotors.3. Re-insulation of Generator Rotors.
4. Re-winding of Electric Motors.
5. Re-babiting & machining of all type Bearings.
6. Dynamic balancing of Rotors ranging from 50 to
60,000 Kgs.
7. Non destructive testing of turbines parts.
8. Moment weighing of GE F-9 turbine blades.
9. NDT facilities at site to all customers.
10. On Site Dynamic balancing Rotating Equipments.
FIELD OF SERVICES
-
8/12/2019 Lecture on CTW - Copy
16/103
In addition to all Thermal Power Station of Wapda PowerGeneration System this Workshop is also extending the
repair facilities to more than 100 organisations of Private
and Government Sector, some important are as
following:-1. Kot Addu Power Company Kot Addu.
2. Karachi Electric Supply Corporation.
3. Pakistan Aeronautical Complex Kamra.
4. Sui Northern Gas Pipe Lines.
5. Attock Oil Refinery.
6. Pakistan Ordinance Factories Wah Cantt.
7. Rousch Power Plant Abdul Hakeem.
8. Pak Arab Fertilisers Multan.
9. Pak-American Fertilizer Daud Khail.
SERVICES TO PRIVATE &GOVERNMENT ORGANIZATIONS
-
8/12/2019 Lecture on CTW - Copy
17/103
10. Pakistan Petroleum Limited.
11. Dawood Herculees Sheikhupura.
12. Packages Limited, Lahore.
13. Chenab Industries, Faisalabad.14. Kohinoor Power Company, Faisalabad.
15. CPC Rafhan Maize Products, Faisalabad.
16. Kohinoor Sugar Mill, Joaharabad.
17. Army Welfare Sugar Mill, Badin.18. Shakargang Sugar Mill, Jhang.
19. Baba Farid Sugar Mill, Okara
20. Sheikhoo Sugar Mill, Kabirwala.
21. Fauji Power Complex, Kabirwala.22. Saba Power Plant, Sheikhupura.
23. Oil and Gas Development Limited.
24. Engro Chemicals.
25. Pakistan ordinance Factory Wah.
-
8/12/2019 Lecture on CTW - Copy
18/103
FLOW DIAGRAM OF REPAIR OF PARTS
Preliminary Inspection
Chemical Cleaning
Dis-Assembling
N.D.T
Annealing
Grinding Welding Grinding
N.D.T
Assembling
Despatch Point
Mech. Cleaning
Inspect. Dept.
-
8/12/2019 Lecture on CTW - Copy
19/103
A. MACHINE SHOP.
MACHINES AVAILABLE.
1. CNC heavy duty horizontal lathe machine up to4 Meter swing dia.
2. Vertical turning lathe machine ranging up to
3.3 Meter swing dia.
3. Vertical lathe machine up to 1.4 Meter swing dia.4. Horizontal boring & facing machine.
5. Valve lapping machine for globe & gate valve.
INTRODUCTION OF REPAIR SHOPS
-
8/12/2019 Lecture on CTW - Copy
20/103
7 Radial arm drilling machine.
8. Precision lathe machine.
9. Milling machine.
10. Metal cutting handsaw.11. Valve grinding machine.
12. Metal plate roller.
13. Manual hydraulic mounting press.
14. 80 tons overhead crane.15. Metal sheet cutter up to 12 mm S.S Sheets.
-
8/12/2019 Lecture on CTW - Copy
21/103
B. N.D.T SHOP.
1. Magnetic Particle Inspection
2. Universal AC hand yokes.
3. Penetrant Flouricent Inspection under UVL
4. Penetrant Inspection in day light
5. Ultrasonic flaw detector.
6. Radiography and X-ray equipment.
7. Crack depth meter.
8. Eddy current testing equipment
-
8/12/2019 Lecture on CTW - Copy
22/103
C. GRINDING SHOP.
1. Burr grinding & re-sharpening machine.
2. Electric discharge machine.3. Grinding and cutting discs and carbide burrs.
4. Pneumatic and electrical grinders.
5. Carbide burrs of different shapes and sizes.
6. Portable electric / pneumatic grinders.
-
8/12/2019 Lecture on CTW - Copy
23/103
D. HEAT TREATMENT SHOP.
1. Vacuum Heat Treatment Furnace.
2. Induction Heating Equipment.
3. Electric Heaters Heat Treatment Furnace
-
8/12/2019 Lecture on CTW - Copy
24/103
E. CLEANING SHOP.
1. Vapour Blasting Machine.2. Sand Blasting Machine.
3. Steam Jet Cleaner.
4. Turco Cleaning Cycle, Turco 4181, 4338C.
-
8/12/2019 Lecture on CTW - Copy
25/103
F. ROTOR BALANCING SHOP.
1. Heavy Duty Balancing Machine 60 Ton.
2. End Driven & Belt Driven Balancing Machine from 50 To 3000 Kgs.
3. Moment Weighing Machine For GE F-5 Blades.
4. Universal Vibration Measuring Instrument.
5. Portable Vibration Analyzer.
6. Onsite Balancing Equipment.
-
8/12/2019 Lecture on CTW - Copy
26/103
G. WELDING SHOP.
1. TIG Welding Equipment.
2. Stationary Spot Welding Machine.3. Weld Heat Treatment Equipment.
4. Electric Welding.
5. Oxy-Acetylene Welding.
-
8/12/2019 Lecture on CTW - Copy
27/103
H- ELECTRICAL AND INSTRUMENT SHOPS.
1. Maggers2. Relay Test Set.3. Inductance Measuring Equipment4. LRC Data Bridge.
5. Digital Multi Meters.6. Motor Winding Equipment.7. Cable Testing Set
-
8/12/2019 Lecture on CTW - Copy
28/103
REWINDING OF GENERATOR ROTOR TPS KOTRI
-
8/12/2019 Lecture on CTW - Copy
29/103
REWINDING OF 6.6 KV MOTOR STATOR
-
8/12/2019 Lecture on CTW - Copy
30/103
MOTORS OF DIFFERENT POWER STATIONS UNDER REPAIR
-
8/12/2019 Lecture on CTW - Copy
31/103
1. Carbon.It is a foremost alloy element of steel and has for
reaching influence in it. In addition to carbon
every unalloyed steel contains silicon
manganese, phosphorus and sulphur. As the
carbon contents rises the mechanical strength
and hardening propertiesof the steel improves
but the elasticity, forging welding and cuttingproperties suffer.
MATALURGY OF SUPER ALLOYS
-
8/12/2019 Lecture on CTW - Copy
32/103
2. Coblat.Melting point of this material is 1500 C. It improves theresistance to tempering and the hot tensile strength..
3. Chromium.Melting point 1920 C. It increases the hardness and
strength and only reduces the elasticity. It improves the
resistance to heat and non acting properties. With higher
chromium contents the steel becomes corrosionresistance and with carbon forms high wearresistancecarbide. The welding properties deteriorate inpure chromium steel and with increasing chromium
contents.
-
8/12/2019 Lecture on CTW - Copy
33/103
4. Manganese.
The melting point of this material is 1250 C. itimproves the strengthen property of steel but only
slightly improves its elasticityit has favourableinfluence on welding properties.
5. Molybdenum.The melting point of this metal is 2610 C. it improves
the tensile strength and elasticity and heatresistanceand has favourable influence on thewelding properties..
-
8/12/2019 Lecture on CTW - Copy
34/103
6. Nickel.The melting point of this metal is 1453 C. it raises the
strength of steel but drops the elasticity. It ensureshardnesswhen the steel contains chromium.
7. Silicon.The melting of this metal is 1410 C. It is present in all
steel since the iron ores used in their manufacturing
contain varying amount of it. Silicon increasemechanical strength, the resistance to scaling.
-
8/12/2019 Lecture on CTW - Copy
35/103
8. Vanadium.The melting of this metal is 1730 C. A small addition improves the
hot hardness. It is strong carbide former increases tensilestrength and yieldpoint.
9. Tungsten.The melting of this metal is 3380 C. It improves the strength
properties and also responsible for high heat resistancevalues.10. Zirconium.The melting of this metal is 1860 C. It increases the life of heat
conducting steels.
-
8/12/2019 Lecture on CTW - Copy
36/103
Gas Tungsten Arc Welding (GTAW).
This is a process in which joining of metals isproduced by heating them with an arc between a
tungsten (non consumable) electrodes and the
work. It is generally done by using single
electrode. Shielding of the electrode and weld
zone is done by a gas or as gas mixture. It is
some times called TIG. Following of the main
equipment required for TIG welding:-1. Power force.
2. Welding holder & tungsten electrodes.
3. Shielding by argon & control.
-
8/12/2019 Lecture on CTW - Copy
37/103
Principal of Operation.The heat from TIG welding is obtained by an arc
between the tungsten electrode and work piece. High
frequency equipment installed in the weldingmachine helps the arc to jump from tungsten to work
piece when the holder is brought at certain distance
from the work piece once arc is established the
welding can be done as per job requirements. During
welding inert gas shield is provided.
Advantages.
It is an excellent welding method due to excellent
control of heat in put and gives high quality welding
free of welding defects.
-
8/12/2019 Lecture on CTW - Copy
38/103
Limitations.
1. Slower than consumable electrode arc
welding process.
2. Transfer of molten tungsten from the
electrode to the weld causescontamination. The resulting tungsten
inclusion is hard and brittle.
3. Repair cost is much higher than
ordinarily welding equipment.
4. Use of argon or helium increases the
repair cost.
-
8/12/2019 Lecture on CTW - Copy
39/103
GAS TUNGSTEN ARC WELDING
-
8/12/2019 Lecture on CTW - Copy
40/103
RE-BABBITING OF
BEARINGS
-
8/12/2019 Lecture on CTW - Copy
41/103
-
8/12/2019 Lecture on CTW - Copy
42/103
COMPOSITION AND TEMPERATURES
Major portion of R-11 is Tin which is about 87%ofwhole alloy. Remaining 13% are Cu, lead, Antimony &
Bismith etc.
Melting point of R-11 is about 384 C.
Another metal which provides a bond material between
base metal of Bearings and Babbitt material is pure tin.
Fore re-babbiting of Bearing Oxy Acetylene Method
methods is commonly used.
-
8/12/2019 Lecture on CTW - Copy
43/103
REPAIR PROCEDURE
In order to re-Babbitt a Bearing following steps arenecessary:-
i) Removal Of Used White Metal Of Bearings.
Ii) Cleaning Of The Bearing Surface With Zincand Amonium Chlorides .
Iii) Tinning Of Bearing Surface.Iv) Finally Re-babbiting With White Metal.
During repair process close watch on thetemperature of Bearing surface is necessary toavoid the over heating of tin.
-
8/12/2019 Lecture on CTW - Copy
44/103
-
8/12/2019 Lecture on CTW - Copy
45/103
RE-METALLING OF JOURNAL BEARING
-
8/12/2019 Lecture on CTW - Copy
46/103
RE-METALLING OF JOURNAL BEARING
I W k h t hit t l i d b
-
8/12/2019 Lecture on CTW - Copy
47/103
In Workshop extra white metal is removed bygrinding
NDT is carried out to check the Bonding of whitemetal with the bearing shell .
After machining ultrasonic testing is carried outto check the bonding of the white metal with theshell.
Strict quality control is maintained by inspectiondepartment. Porosity, pin holes & lack ofbonding is not allowed. If a Bearing passsatisfactorily through all these process.
-
8/12/2019 Lecture on CTW - Copy
48/103
MACHINING OF JOURNAL BEARING
-
8/12/2019 Lecture on CTW - Copy
49/103
ULTRASONIC INSPECTION OF JOURNAL BEARINGS
-
8/12/2019 Lecture on CTW - Copy
50/103
JOURNAL BEARING AFTER FINAL MACHINING
OVERALL VIEW OF PARTS REPAIRED
-
8/12/2019 Lecture on CTW - Copy
51/103
OVERALL VIEW OF PARTS REPAIREDFROM 1982 TO 06/2009
S/N DESCRIPTION QTY.1 Turbine Moving Buckets. 12756
2 Combustion Liners. 2993
3 Transition Pieces. 2352
4 Cross Fire Tubes. 2515
5 Shrouds Blocks. 1915
6 Bearings. 1606
7 Compressor Blades. 15138 Retainer Plates. 1645
9 Floating Seals. 1191
10 Bearing Pads. 1072
11 Swirl Tips 918
-
8/12/2019 Lecture on CTW - Copy
52/103
11 Swirl Tips. 918
12 End Seals. 907
13 Vane Segments. 682
14 Scrapper Chain Links. 517
15 Bull Horns. 664
16 Light / Heavy Motors. 370
17 Turbine Nozzle Support Rings 33918 Turbine Nozzle. 325
19 Pressure Gauges. 300
20 Turbine Diaphragms. 257
21 Electronic Cards. 203
22 Track Block. 181
23 Labyrinth Seals. 134
24 Turbine Rotors. 138
26 Stuffing Box Seals. 83
-
8/12/2019 Lecture on CTW - Copy
53/103
6 S u g o Sea s 83
27 Bushes. 64
28 Contactors. 75
29 Generator Rotors. 6330 Pumps. 62
31 Slip Rings. 55
32
Steam Turbine Diaphragm Support
Ring.
49
33 Heavy Duty Shafts. 44
34 Hydrogen Seals. 60
35 Impellers. 3436 Pressure Switches 28
37 Gears. 21
38 Diffusers. 21
39 Control Valves. 19
-
8/12/2019 Lecture on CTW - Copy
54/103
40 Solenoid Valves. 18
41 Multiple Disc Jaw Clutches. 15
42 Shaft Sleeves. 28
43 Combustor Wrapper. 13
44 Turbine Nozzle Discs. 14
45 Spring Seals. 13
46 Shaft Sleeves. 14
47 Wiper Seal. 2
48 Casing. 4
-
8/12/2019 Lecture on CTW - Copy
55/103
SOME MAJOR WORKS DONE
RE-BLADING OF 210 MW LP STEAM TURBINE ROTOR
REPAIR OF 35 MW GENERATOR TOROR TPS QUETTA
REBLADING OF 100MW GAS TURBINE COMPRESSOR
-
8/12/2019 Lecture on CTW - Copy
56/103
RE-BLADINGOF 210 MW
L.P TURBINE ROTOR
OF TPS GUDDU
-
8/12/2019 Lecture on CTW - Copy
57/103
CASE STUDY
During major overhauling of 210 MW Steam Turbine PowerPlant at TPS Guddu, it was observed outer four stages(2+2) of LP Turbine Rotor have damaged and needreplacement with new ones.
They sent the Rotor to Central Gas Turbine MaintenanceWorkshop Faisalabad.
TECHNICAL DIMENSIONS OF ROTOR
-
8/12/2019 Lecture on CTW - Copy
58/103
TECHNICAL DIMENSIONS OF ROTOR
STATION: THERMAL POWER STATION
GUDDU RATING: 210 MW (UNIT NO.3)
TYPE: LOW PRESSURE
WEIGHT: 25000 KG.
DIA METER: 3050 MM LENGTH: 7320 MM
MANUFACTURED BY: LENIN GRAD METAL WORKS USSR
SUPPLIED BY: M/S TECHNO PROME EXPORTS
USSR JOBS: REPLACEMENT OF L.P ROTOR
TURBINE BLADES OF STAGENOS.26, 27, 30 & 31 WITH NEWONES.
-
8/12/2019 Lecture on CTW - Copy
59/103
CUTTING OF DAMAGED BLADES WITH WELDING PROCESS
PROCEDURE ADOPTED FOR RE-BLADING
-
8/12/2019 Lecture on CTW - Copy
60/103
OF LP ROTOR
Cutting of damaged blades with welding process.
Loading of Rotor on CNC Heavy Duty Lathe Machine.
Machining of roots of blades.
Removal of pin portions left in turbine discs.
Fixing of blades in turbine wheels.
-
8/12/2019 Lecture on CTW - Copy
61/103
FIXING OF ROTOR ON CNC HEAVY DUTY LATHE MACHINE
-
8/12/2019 Lecture on CTW - Copy
62/103
MACHINING OF ROTORS OF BLADE STAGE NO.26 & 30
-
8/12/2019 Lecture on CTW - Copy
63/103
-
8/12/2019 Lecture on CTW - Copy
64/103
Drilling of holes in blades.
Machining of 372 pins to be fixed in.
Fixing of pins in blades.
Fixing of lacing wire in blades.
Machining of turbine blades.
Sand blasting.
Non Destructive Testing.
Dynamic Balancing (final balancing results attached).
-
8/12/2019 Lecture on CTW - Copy
65/103
DRILLING OF HOLES IN BLADES STAGE NO.26, 27 30, & 31
-
8/12/2019 Lecture on CTW - Copy
66/103
MACHINING OF PINS TO BE FIXED IN BLADES
-
8/12/2019 Lecture on CTW - Copy
67/103
FIXING OF LACING WIRE IN BLADES
-
8/12/2019 Lecture on CTW - Copy
68/103
MACHINING OF TURBINE BLADE OF STAGE No.26 & 30
TO PROVIDE HOSING FOR SEALS OF STATOR
-
8/12/2019 Lecture on CTW - Copy
69/103
SAND BLASTING OF ROTOR
-
8/12/2019 Lecture on CTW - Copy
70/103
NDT OF THE ROTOR
-
8/12/2019 Lecture on CTW - Copy
71/103
DYNAMIC BALANCING OF THE ROTOR
-
8/12/2019 Lecture on CTW - Copy
72/103
REPAIR OF 35 MW
GENERATOR ROTORTPS QUETTA
-
8/12/2019 Lecture on CTW - Copy
73/103
DAMAGED WINDING IS BEING REMOVED
PROCEDURE ADOPTED FOR REPAIR OF
-
8/12/2019 Lecture on CTW - Copy
74/103
GENERATOR ROTOR Run out was checked
Ultrasonic inspection was carried out
Special fixtures were fabricated to remove coupling
Both cooling fans & Generator Rotor Retaining Rings(GRRR) were removed
Special fixture was fabricated to hold the winding coilsduring their removal from Rotor slots.
Wedges were removed from the Rotor body slots.
-
8/12/2019 Lecture on CTW - Copy
75/103
Winding links of three coils were de-brazed.
Damaged turns of all winding coil were removed
Damaged insulation was removed from each turn of coils
Broken turns were brazed and checked by NDT
New lining of Rotor slots was done with fibber glass.
Nomax paper of proper size was cut and pasted
All coils were inserted back into their respective slots
Special jacks were fabricated to press each coil and werefitted on the slots in order to press the coil turns.
Two special circular fixtures were fabricated to press thehanging portion of the windings
-
8/12/2019 Lecture on CTW - Copy
76/103
NDT of new Generator Rotor Retaining Rings (GRRR) wascarried out (report attached).
The winding of the Rotor was heated up to 180oC by electriccurrent method and were pressed with special jack method.
Both GRRR and coiling fans were fitted on the both side of the
Generator Rotor.
Insulation strength of the generator was checked and wasfound satisfactory.
Dynamic balancing of the Rotor was performed.
After the completion of repair work complete electrical testingwas carried out according to standard and it was found OK.
After installation of rotor in machine some sort of vibrationwas observed which was rectified on site.
-
8/12/2019 Lecture on CTW - Copy
77/103
A FIELD WINDING COILS TURN ARE HELD ON FIXTURE AFTERPASTING NEW INSULATION PAPER
-
8/12/2019 Lecture on CTW - Copy
78/103
BRAZING OF DAMAGED ROTOR WINDING
-
8/12/2019 Lecture on CTW - Copy
79/103
CONNECTION LEAD IS UNDER REPAIR AFTER BRAZING
-
8/12/2019 Lecture on CTW - Copy
80/103
FIELD COIL INSULATION STRENGTH IS BEING CHECKED
-
8/12/2019 Lecture on CTW - Copy
81/103
DYNAMIC BALANCING OF GENERATOR ROTOR ONBALANCING MACHINE
-
8/12/2019 Lecture on CTW - Copy
82/103
100 MW GAS TURBINE
AXIAL COMPRESSORTPS GUDDU
-
8/12/2019 Lecture on CTW - Copy
83/103
TECHNICAL DIMENSIONS OF ROTOR
-
8/12/2019 Lecture on CTW - Copy
84/103
STATION: THERMAL POWER STATIONGUDDU
RATING: 100 MW (UNIT NO.4)
TYPE: AXIAL COMPRESSOR ROTOR
WEIGHT: 28600 KG.
DIA METER: 1917 MM LENGTH: 5030 MM
MANUFACTURED: GENERAL ELECTRIC
JOBS: REPLACEMENT OF BLADES OF
ALL SEVENTEEN STAGES WITH NEW ONES
RE BLADING OF 100 MW GAS TURBINEAXIAL COMPRESSOR ROTOR
-
8/12/2019 Lecture on CTW - Copy
85/103
DEFECT
One blade of 2nd stage was found broken from the rootand it has damaged all the blades of successive stages.
Cleaning of compressor Rotor blades was carried outwith CTC and its inspection was carried out.
Condition of all damaged blades revealed that all theseblades have damaged due to direct hitting and rubbingwith the broken blade.
-
8/12/2019 Lecture on CTW - Copy
86/103
PROCEDURE ADOPTED FORREBLADING OF COMPRESSOR
-
8/12/2019 Lecture on CTW - Copy
87/103
REBLADING OF COMPRESSOR
Sand blasting of Rotor.
NDT of the complete Rotor.
Complete run out check was performed.
Different reference marks were punched on the parts ofthe Rotor.
Record of different dimensions & measurements was
prepared for re-assembling of the Rotor.
Hydraulic bolt tensioning system for unbolting of tiebolts was arranged through tenders.
The compressor Rotor was held vertically in the under
ground pit
-
8/12/2019 Lecture on CTW - Copy
88/103
ground pit.
All seventeen-compressor Rotor discs were dismantled one
by one by self made fixture.
Damaged blades and spacers were removed from allcompressor discs.
The compressor wheels were cleaned and NDT of all thedisc & tie rod bolts was performed.
Balancing charts were prepared for the new moving blades.
New blades of all the stages were fitted in these wheels.
All compressor discs were re-assembled in vertical position
-
8/12/2019 Lecture on CTW - Copy
89/103
-
8/12/2019 Lecture on CTW - Copy
90/103
-
8/12/2019 Lecture on CTW - Copy
91/103
-
8/12/2019 Lecture on CTW - Copy
92/103
-
8/12/2019 Lecture on CTW - Copy
93/103
-
8/12/2019 Lecture on CTW - Copy
94/103
-
8/12/2019 Lecture on CTW - Copy
95/103
-
8/12/2019 Lecture on CTW - Copy
96/103
All tie rod bolts were tightened
-
8/12/2019 Lecture on CTW - Copy
97/103
The compressor rotor was brought in horizontal position.
The complete assembly was loaded on the turbine lathmachine and run out check was performed.
Stub shaft of the turbine was attached to the compressor
with the help of coupling bolts.
Dynamic balancing of the Rotor was carried out.
Stub shaft was disassembled from the compressor
The repair work was successfully completed with ourown Technical skill and saved foreign exchange ofmillions of Dollars.
-
8/12/2019 Lecture on CTW - Copy
98/103
-
8/12/2019 Lecture on CTW - Copy
99/103
-
8/12/2019 Lecture on CTW - Copy
100/103
-
8/12/2019 Lecture on CTW - Copy
101/103
-
8/12/2019 Lecture on CTW - Copy
102/103
-
8/12/2019 Lecture on CTW - Copy
103/103
THANKS