lecture on project management

Upload: dkvyas007

Post on 25-Feb-2018

221 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/25/2019 lecture on project management

    1/17

    1

    CE 233Construction Management

    Lecture 8_2

    Primavera P3

    Setting Up a New Project

    Dr. Jae-Ho Pyeon

    2

    Primavera Project Planner

    A widely used interactive construction

    scheduling and planning software

    Graphical screens and output

    Simplifies the interpretation of the

    scheduling documentsLeads to more effective project

    management

  • 7/25/2019 lecture on project management

    2/17

    3

    What You Should Learn from This

    Lesson

    1. How to create a new project

    2. How to add project activity data

    3. How to add relationship input

    4. How to schedule the project

    5. How to back up the project file

    6. How to restore the backup file7. How to open an existing project

    4

    Sample Project Data

    1154Start Up and Test Elect and Mech Sys.125

    757Finish Site Work135

    125, 1351Final Inspection145

    95, 10521Mech and Elect Finish115

    85, 9528Interior Finish105

    8521Rough In Elect and Mech95

    7518Interior Partitions85

    6528Exterior Closure75

    55 FS=720Roof Slab and Beams65

    455Columns55

    25, 357Ground Floor Slab45

    25 SS=34Under Slab Utilities35

    1514Foundations25

    510Clearing15

    1Start Project5

    PredecessorsOriginal

    duration

    Act iv it y descr ip tionAct iv it y ID

  • 7/25/2019 lecture on project management

    3/17

    5

    Open Primavera Project Planner

    Select File

    Select New

    To begin a new project:

    Creating a Project

    File

    New

    6

    Enter a 4

    character project

    name (required)

    Set the planning

    unit and work

    week

    Project Title and Company name is optional

    Do not enter

    A finish date

    Select Add to initiate project

    Enter the planned

    project start date

  • 7/25/2019 lecture on project management

    4/17

    7

    Select + to enter an activity

    The project should open with

    this screen of the classic

    schedule

    layout.

    Activity Input

    8

    Enter the first activity ID number.

    Start with a number other than 1, in case

    you have to add another activity.

    Activity Input: ID

  • 7/25/2019 lecture on project management

    5/17

    9

    Select the field under the column heading

    activity description. Enter a description for

    the activity.

    Activity Input: Description

    10

    Select the field under the column heading

    Orig. Dur. Enter the duration of the activity.

    Activity Input: Duration

  • 7/25/2019 lecture on project management

    6/17

    11

    Hit the enter key to complete the activity

    entry. Note that the activity now appears

    on the bar chart.

    12

    Repeat the procedure to enter additional

    activities. Note that Primavera automatically

    numbers the new activities with ID numbers.

    In this example the interval is 10.

    Enter Additional Activities

  • 7/25/2019 lecture on project management

    7/17

    13

    An activity form window can be displayed

    At the bottom of the screen by selecting,

    View, Activity Form.

    The activity form is used to enter and display

    Activity data.

    Activity Form

    14

    Activity Form Window

  • 7/25/2019 lecture on project management

    8/17

    15

    Relationship Input

    Open the Predecessors window

    Pred Click + Select Activities

    16

    After entering all activities,

    predecessors can be assigned.

    Select Pred on the Activity Form

    Menu bar.

    Start with your first activity.

    Select + to add a predecessor

    to the highlighted activity.

  • 7/25/2019 lecture on project management

    9/17

    17

    The first activity does not have apredecessor. Move to the next

    activity.

    Select the scroll down arrow to

    view a listing of all activities.

    18

    Select the correct predecessor

    from the list.

  • 7/25/2019 lecture on project management

    10/17

    19

    Note that by default, the FS

    relationship is used with a

    lag of 0. However, both the

    relationship and the lag may

    be changed.

    20

    Continue through the

    activity list, entering the

    predecessors for each activity.

    Some activities may have more

    than one predecessor.

  • 7/25/2019 lecture on project management

    11/17

    21

    Note that we have selected a

    SS with a 3 day lag for the

    Under Slab Utilities. This is to

    permit the foundation work to

    advance for 3 days prior to

    starting the Under Slab Utilities.

    22

    A FS with a 7 day lag

    was used to allow sufficient

    concrete strength gain.

  • 7/25/2019 lecture on project management

    12/17

    23

    Calculating the Schedule

    Tools Schedule

    24

    After listing all activities and

    entering predecessors, the

    schedule calculation is obtained

    by selecting the schedule icon

    on the upper menu bar.

  • 7/25/2019 lecture on project management

    13/17

    25

    You must select a schedule

    date. This should be theplanned start date for a new

    schedule.

    26

    Normally we want

    to view the schedule

    on screen first.

  • 7/25/2019 lecture on project management

    14/17

    27

    A schedule report is

    generated.

    You should have only one

    activity with no predecessor

    and only one activity with no

    successor.

    This report will help you

    identify errors in your

    network logic.

    It also gives you the scheduledcompletion date.

    28

    Before ending your work,

    you should backup your

    file to a diskette.

    Select Tools,

    Project Utilities,Back Up.

    Backing Up a Project

    Tools Project Utilities Back Up

  • 7/25/2019 lecture on project management

    15/17

    29

    You mustselect your

    project and click

    on the box in

    the back up

    column.

    Compress files

    (One PRX file)

    30

    To restore a project,

    select the Tools command

    followed by Project

    Utilities/Restore options.

    Restoring a Project

    Tools Project Utilities Restore

  • 7/25/2019 lecture on project management

    16/17

    31

    Again, you must select your project and click

    on the box.

    32

    To open a project on the hard drive,

    select the File command

    followed by the Open option.

    Opening an Existing Project

    File Open

  • 7/25/2019 lecture on project management

    17/17

    33

    Then select

    your project

    from the list.

    Note that

    projects can not

    be opened from

    the back up

    diskette.

    They must first

    be restored.