lehigh steel assign

15
Managerial Accounting and Control-II Case: Lehigh Steel Date of submission: 16 December 2011 Sec: E Group: 4 Group Members: Anand Muralidharan Divay Manhas Nallaballe Mayur Dharmendra S Sumit Kumar Saha Susmita Lakra Sangana Vinod Babu

Upload: vinod-sangana

Post on 23-Sep-2014

120 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: LEhigh Steel Assign

Managerial Accounting and Control-II

Case: Lehigh Steel

Date of submission: 16 December 2011

Sec: E Group: 4

Group Members:

Anand MuralidharanDivay Manhas

Nallaballe MayurDharmendra S

Sumit Kumar SahaSusmita Lakra

Sangana Vinod Babu

Page 2: LEhigh Steel Assign

Executive Summary:

Lehigh Steel is a company specialised in the production of specialty steels for high strength, high

use applications. In 1988 the company experienced record profits, but then in 1991, it reported

record losses due to the decreasing demand as a result of recession. After the crisis, the demand

rose again, but Lehigh Steel could not transform its revenue into profits. Therefore the

management at Lehigh decided to rationalize the product mix to address the issue. The company

was initially using the standard costing following which they adopted the Activity Based Costing.

They believed that this would enable them to identify profitable products and hence select the right

mix. Though ABC approach illustrated that the product profits were significantly different from that

computed by standard costing approach the results were somewhat counterintuitive. To address

this problem the management decided to employ a new approach called Theory Of Constraints

which focussed on the constraint that affected the entire operation. The results of this method

were different from those obtained from ABC method. The management was now faced with the

task of assessing the pros and cons of the various methods and arrive at a method that will help

them achieve the right product mix which will in turn boost their bottomline.

It is recommended that the best possible option would be to employ a combination of the ABC and

TOC methods. Based on this method only high speed (machine coil) is profitable and therefore

should be included in the mix.

Page 3: LEhigh Steel Assign

1.1 The Company:

Lehigh Steel founded in 1913, enjoyed a niche position as a manufacturer of speciality steels for high strength, high use applications. Its products included high-speed, tool and die, structural, high temperature, corrosion resistant and bearing steels available in wide range of grades in a variety of shapes and finishes. Its market included various industries, aerospace, energy. Lehigh enjoyed a premium position because of its ability to produce high quality customized products. Palmer a global manufacturer of bearing and alloy steels acquired Lehigh in 1975 primarily for the specialized equipment, Continuous Rolling Mill (CRM)

Lehigh operated under a matrix organization structure. General Managers of different departments, Vice President of sales, Director of operation and planning and the CFO reported to the company President. Performance was measured by product contribution margin calculated using standard costs: revenue less materials, direct labour, direct manufacturing costs, such as utilities and maintenance; and other overhead was considered beyond their control. The goal was to deliver quality product within specified lead time at the lowest cost.

1.2 Industry Structure Conduct and Performance:

Speciality steel comprised of 10% of the US steel industry and offered an excellent growth opportunity. Speciality steel varied in metallic composition and manufacturing process and were defined based on different attributes (grade, product, surface finish, size, structural and surface quality) most important of which was grade as it was a primary indicator of product performance. The industry was capital intense due to ‘lumpy’ and expensive capacity addition, changing cost structure because of newer technologies and also the knowledge work performed by metallurgists and the other technical specialists which formed a significant portion of the cost structure. The focus strategy (You choose to make product which can make better than the completion) employed helped to protect volume and capital investments.

Maintaining high quality at competitive costs was essential in the industry. Producers were small, fragmented price takers in a market dominated by sophisticated customers however niches provided some protection. Cost was a significant competitive weapon in determining share and profits. Efficient short production runs were required in order to avoid inventory build up of customized products. Industry profitability fluctuated widely ranging from -16.7% to 5.0%.

Page 4: LEhigh Steel Assign

1.3 Market and Products:

Customers were classified into 33 market segments ranging from original equipment manufacturers to forge shops, distributors to metal workers.

Lehigh had 7 product lines – Alloy, Bearing, Conversion, Corrosion, Die Steel, High Speed and High Temp – of which three – Alloy, Die Steel and High Speed comprised 70% of sales.

Die steel was steel strengthened for use in machine dies and molds. High speed products served endurance applications, such as mental cutting and punching,

and were narrower in focus. Alloys were used in aerospace frames, landing gears, missile cases and fasteners. Lehigh also carried niche products lines - Bearing, Corrosion and High temp – whose volume

fluctuated with market conditions.

Conversion process was also carried out which involved the processing the non Lehigh owned materials on the CRM. The company product hierarchy was in the following order: product lines, grades, shapes, SKUs.

1.4 Production Operations:

Scrap steel was the primary raw material which was recycled.

Production process involved 6 steps:

1. Melting: The scrap compound was melted in the Electric Arc Furnace, where high-powered (80 MW) electrical charges heated the solid metal.

2. Refining: The steel was further refined by Argon Oxygen Decarburization (AOD), in which oxygen or argon was bubbled through the molten metal to further burn off impurities.

3. Moulding: The molten steel was teemed from ladles into octagonal molds, forming ingots4. Breakdown: Ingots were then broken down into semi-finished rectangular shapes such as

billets and bars.5. Rolling: The billets and bars are transformed into finished shapes like wire rods and coils.6. Finishing: Finishing involved a variety of treatments. Most products were annealed a final

time to improve formability and make the surface more durable, and rough turned or straightened.

Page 5: LEhigh Steel Assign

Fig. Basic Steel Making Process

Other processes included pickling, polishing testing and inspection. Production and technical support activities also formed an important part of production. Maintenance, depreciation and utilities were basic costs amounting to 21% of the revenues.

1.5 The Problem:

In 1991, recessions marked the lowering of the market price near to or lower than product cost and it was increasingly difficult for Lehigh for selling at premium prices. Cost of production remaining the same with decline in the price and volume lead to lowering of profits. This meant that Lehigh was flush with inventories and cost. In an initial attempt to reduce the inventory cost the management decided to use the pull based marketing concept which proved to be a failure as it was difficult to eliminate the steps in production and changeover.

Later in 1992, the market recovered resulting in increased demand. But even with the increase in demand the company was not able to realize the profits. To overcome this situation the management decided to identify the right product mix that would enable the company to lever profits. They now emphasised on the use of ABC method to find out the desired product mix and later on shifted to the TOC method as the former provided counterintuitive results. Now the management is in a fix to determine the best possible method that would enable them to select the right product mix.

Page 6: LEhigh Steel Assign

1.6 Strategic Analysis:

The three methods employed by Lehigh to calculate its profit per product are analysed below:

1.6.1 Standard Costing:

Product weight (pounds) was the primary driver for standard cost, which included materials, labour, direct manufacturing expense and overhead cost categories. The indirect manufacturing and administrative costs were allocated to products based on pounds produced. As a result, this approach considers that each of the five product lines uses manufacturing and administrative overhead equally (unitary costs = $0.64 per pound). Standards for materials and direct labour were allocated based and included yield factors for scrap and rework. Direct manufacturing costs were allocated to products based on machine hours.

According to Standard Costing method, all products except alloys and roller wires generate operating losses. Roller wire recorded 0% profit. Standard costing is averaging the diverse resource use by products and that is the reason that ‘alloy’ comes out to be most profitable even though it is heavily promoted by marketing and sales teams. Despite the profits generated in ‘alloy’ product line, Lehigh is not able to generate profits (overall) during this period.

Therefore, Standard costs method is not recommended.

Refer Exhibit 2 for calculation of standard costing calculations.

1.6.2 Activity Based Costing:

Utilities, Maintenance and Depreciation are considered as direct manufacturing costs and are allocated based on machine minutes. For Technical Support number of skus was considered the cost driver. The product weight was considered as the driver for General and Administrative costs. The materials and direct labour have been allocated exactly the way they were allocated in Standard Costing system. Finally, Material Handling & Setup, Order Processing and Production Planning were based on number of orders as cost driver. Consequently, ABC overcomes the major issue of the Standard Costing system i.e. the inclusion of all overhead costs in a single cost pool.

According to this approach, alloys, roller wires and chipper knives and round bars present operating losses, while only high speeds showed operating profits of $0.03 per pound.

ABC does not take into consideration how smoothly material flowed through the plant and product profitability should reflect this kind of difference in resource consumption.

Therefore, ABC method is not recommended.

Refer Exhibit 3&4 for calculation of Activity Based Costing calculations.

Page 7: LEhigh Steel Assign

1.6.3 Theory of Constraints:

TOC proposed a simple operational measure to carry out the decision-making process - Throughput. Generally it is calculated as sales less direct variable cost and more commonly as sales less material cost which is comparable to contribution margin. According to this method profits can be increased by maximizing throughput per unit of the constrained resource. As already mentioned, the rolling process (CRM) is the bottleneck of the plant. This approach considers that the efficient management of the constrained resource is the most important factor to increase profitability. According to this approach, high speeds and alloys were the products that showed higher “contribution margins”: $25.00 and $17.70 per minute of rolling machine (constrained resource) used.Theory of Constraints only takes into consideration the material costs, leaving aside all the other relevant costs that could be allocated to each product according to ABC approach. In other words, TOC method does not reflect the real operating profits.Hence, this method is also not recommended.

Refer Exhibit 5 for Theory of Constraints calculations.

1.7 Recommendation

The ideal method would be a combination of the TOC and ABC methods as it has been clearly shown that both these methods suffer from certain drawbacks that can be eliminated by considering the two approaches together.

1.7.1 Combined approach of TOC & ABC:

This method of combining TOC & ABC overcomes the shortcomings of the other three methods mentioned above. Unitary operating profit per product is calculated based on the ABC model. This operating profit eliminates the major issue concerning the Standard Costing system as mentioned above.

Incorporating time as a factor used in Lehigh’s decision-making is necessary. Based on the information from the operations staff, CRM can be identified as the constraint of the plant. Therefore throughput per unit of the constrained process (Rolling - CRM) can be computed by diving the unitary ABC cost ($/lb) by the machine time for the rolling process (lb/min). This process shows that only high speed (machine coil) is profitable and others are not. Therefore only this product must be included in the company’s product mix.

Page 8: LEhigh Steel Assign

1.8 Financial Analysis:

Exhibit -1 (Sample Product Data)

Alloy : Condition round

Conversion: Roller Wire

Die Steel: Chipper Knife

Die Steel: Round Bar

High Speed: Machine Coil

Production (lbs) 478679 2081543 2413299 6697682 2530552Number of SKU 311 473 418 172 102Number of order 957 4163 3218 3349 1012 Bill of Material Steel Scrap 1.00 0.00 1.00 1.00 1.00Alloys 0.01 0.00 0.01 0.01 0.01 Machine Time (min/lb; crew=1) Melting (Electric Arc Furnace) 0.20 0.00 0.09 0.09 0.09Refining (VOD) 0.21 0.00 0.10 0.10 0.10Molding/ Breakdown (Ingot/PFF) 0.12 0.00 0.07 0.08 0.07Rolling (CRM) 0.10 0.15 0.33 0.09 0.03Finishing (Multiple) 0.06 0.02 0.07 0.08 0.05Total time 0.69 0.17 0.66 0.44 0.34

Exhibit -2 (Standard Costing)

Standard cost ($/lb)

Alloy : Condition round

Conversion: Roller Wire

Die Steel: Chipper Knife

Die Steel: Round Bar

High Speed: Machine Coil

Price 2.31 0.77 1.02 0.93 2.33Materials 0.54 0.00 0.12 0.21 1.58Direct Labour 0.29 0.07 0.28 0.18 0.14Direct manufacturing expense 0.24 0.06 0.23 0.16 0.12Contribution margin 1.24 0.64 0.39 0.38 0.49Contribution margin (%) 53.68 83.12 38.24 40.86 21.03Total Contribution 593562 1332188 941187 2545119 1239970

Manufacturing and administrative overhead 0.64 0.64 0.64 0.64 0.64

Operating profit 0.60 0.00 (0.2

5) (0.2

6) (0.

15)

Operating profit (%) 26.0 0.00 (24.

51) (27.

96) (6.

44)

Total Operating profit 287207 0.00 (603,32

5) (1,741,39

7) (379,58

3)

Page 9: LEhigh Steel Assign

Exhibit -3 (Activity cost pool and Driver rate)

Activity DriverDriver

Volume Amount Driver rate UnitsMelting: Depreciation melt machine min 5145632 2139865 0.42

1.00 $/min/lbMelting:Maintanence melt machine min 5145632 975130 0.19Melting: Utilities melt machine min 5145632 2036477 0.40Refining: Depreciation refine machine min 5691042 1711892 0.30

0.74 $/min/lbRefining:Maintanence refine machine min 5691042 780104 0.14Refining: Utilities refine machine min 5691042 1745551 0.31Molding: Depreciation mold machine min 4226965 427973 0.10

0.26 $/min/lbMolding:Maintanence mold machine min 4226965 390052 0.09Molding: Utilities mold machine min 4226965 290925 0.07Rolling: Depreciation roll machine min 8258382 2995811 0.36

0.59 $/min/lbRolling:Maintanence roll machine min 8258382 975130 0.12Rolling: Utilities roll machine min 8258382 872776 0.11Finishing: Depreciation finish machine min 4057311 1283919 0.32

0.72 $/min/lbFinishing:Maintanence finish machine min 4057311 780104 0.19Finishing: Utilities finish machine min 4057311 872776 0.22General and administrative pounds 50299420 5400955 0.11 0.11 $/poundMaterial handling and setup orders 57147 4936068 86.37 86.37 $/orderOrder processing orders 57147 3953709 69.18 69.18 $/orderProduction planning orders 57147 3339500 58.44 58.44 $/orderTechnical support SKU 6642 5766579 868.20 868.20 $/SKU

Exhibit -4 (Activity Based Costing)

ABC cost ($/lb)Alloy : Condition round

Conversion: Roller Wire

Die Steel: Chipper Knife

Die Steel: Round Bar

High Speed: Machine Coil

Price 2.31 0.77 1.02 0.93 2.33Materials 0.54 0.00 0.12 0.21 1.58Direct Labour 0.29 0.07 0.28 0.18 0.14Direct manufacturing expense 0.24 0.06 0.23 0.16 0.12Manufacturing and administrative overhead Melting (Electric Arc Furnace) 0.20 0.00 0.09 0.09 0.09Refining (VOD) 0.16 0.00 0.07 0.07 0.07Molding/ Breakdown (Ingot/PFF) 0.03 0.00 0.02 0.02 0.02Rolling (CRM) 0.06 0.09 0.19 0.05 0.02Finishing (Multiple) 0.04 0.01 0.05 0.06 0.04General and administrative 0.11 0.11 0.11 0.11 0.11Material handling and setup 0.17 0.17 0.12 0.04 0.03Order processing 0.14 0.14 0.09 0.03 0.03

Page 10: LEhigh Steel Assign

Production planning 0.12 0.12 0.08 0.03 0.02Technical support 0.56 0.20 0.15 0.02 0.03

Contribution margin (0.

35) (0.

20) (0.58

) (0.15) 0.

03

Contribution margin (%) (15.

13) (25.

34) (56.8

9) (16.44

) 1.09

Exhibit -5 (Theory of Constraints)

TOC cost ($/lb)

Alloy : Condition round

Conversion: Roller Wire

Die Steel: Chipper Knife

Die Steel: Round Bar

High Speed: Machine Coil

Price 2.31 0.77 1.02 0.93 2.33Materials 0.54 0.00 0.12 0.21 1.58Throughput Contribution 1.77 0.77 0.9 0.72 0.75Contribution /min of the constrained resource 17.7 5.13 2.73 8 25

Exhibit -6 (Theory of Constraints and ABC combined)

ABC cost ($/lb)

Alloy : Condition round

Conversion: Roller Wire

Die Steel: Chipper Knife

Die Steel: Round Bar

High Speed: Machine Coil

Price 2.31 0.77 1.02 0.93 2.33 Contribution margin as per ABC approach

(0.35)

(0.20)

(0.58)

(0.15)

0.03

Minutes of the constrained resource (CRM) 0.1 0.15 0.33 0.09 0.03

Contribution from ABC/minute of the constrained resource

(3.49)

(1.30)

(1.76)

(1.70)

0.84

Note:

If the setup time is also furnished in addition to the processing time then it is possible to develop a GANTT Chart using the shortest time method to sequence the various product lines through the different machines such that the overall process time is minimized.

Exhibit -7 (Input for Gantt chart – Setup time not considered)

Page 11: LEhigh Steel Assign

GANTT CHART ST ET ST ET ST ET ST ET ST ET

MeltingMC RB CK CR

0 0.09 0.09 0.18 0.18 0.27 0.27 0.47

RefiningMC RB CK CR

0.09 0.19 0.19 0.29 0.29 0.39 0.47 0.68

MoldingMC RB CK CR

0.19 0.26 0.29 0.37 0.39 0.46 0.68 0.8

RollingRW MC RB CK CR

0 0.15 0.26 0.29 0.37 0.46 0.46 0.79 0.8 0.9

FinishingRW MC RB CK CR

0.15 0.17 0.29 0.34 0.46 0.54 0.79 0.86 0.9 0.96

ST- Start Time ET- End Time

MC- Machine Coil RB- Round Bar CK- Chipper Knife

RW- Roller Wire CR- Condition Round