UNITED STATES MARINE CORPS ENGINEER EQUIPMENT INSTRUCTION COMPANY
MARINE CORPS DETACHMENT
686 MINNESOTA AVE
FORT LEONARD WOOD, MISSOURI 65473-5850
LESSON PLAN
GCS900 GRADE CONTROL SYSTEM
NCOO-B02
ENGINEER EQUIPMENT OPERATOR NCO
A16ACX1
REVISED 10/30/2013
APPROVED BY ______________________ DATE ___________________
2
INTRODUCTION (15 MIN)
(ON SLIDE # 1)
1. GAIN ATTENTION: As a Heavy Equipment Operators there will be times where you will be required to perform blade
operations, requiring very accurate and precise end states.
The purpose of the Marine Corps Grade Control System
(GCS900) is to achieve a quick and expeditionary means to
accomplish precise horizontal construction. Implementation
of an efficient operator and the GCS900 will enhance the
capability of a unit’s ability to support horizontal
construction efforts, by providing vertical, or vertical&
horizontal instruction of where the blade needs to go to
get to grade. This period of instruction will provide you
with safe and efficient engineer equipment operations.
___________________________________________________________
___________________________________________________________
_______________________________________________________
_________
(ON SLIDE # 2)
2. OVERVIEW: Good morning/afternoon, my name is _____ _.
The purpose of this period of instruction is to provide you
with the knowledge, skills, ability to operate and employ
the GCS900.
(ON SLIDE # 3)
3. LEARNING OBJECTIVE(S):
a. TERMINAL LEARNING OBJECTIVE:
(1) Provided an engineer equipment requirement and
references, operate equipment with a Grade Control System,
To safely meet operational requirements with no injury to
personnel or damage to the equipment. (1345-HEOP-2006)
b. ENABLING LEARNING OBJECTIVE(S):
INSTRUCTOR NOTE
Introduce learning objectives.
3
(1) Provided a Grade Control System 900 Laser and GPS
system, 120M Motor Grader, 850JR MCT and references,
install the GCS 900 Laser system and GPS system, per the TM
11907B-OR/1. (1315-HEOP-2006a)
(2) Provided a Grade Control System 900 Laser and GPS
system, 120M Motor Grader, 850JR MCT and references,
perform the measure up for the 120M and 850JR MCT with the
GCS 900 Laser system and GPS system, per the TM 11907B-
OR/1. (1315-HEOP-2006b)
(3) Provided a Grade Control System 900 Laser and GPS
system, 120M Motor Grader, 850JR MCT and references,
perform calibration of the GCS 900 Laser system and GPS
system, per the TM 11907B-OR/1. (1315-HEOP-2006c)
(4) Provided a Grade Control System 900 Laser and GPS
system, 120M Motor Grader, 850JR MCT and references,
perform site set up of the GCS 900 Laser system and GPS
system, per the TM 11907B-OR/1. (1315-HEOP-2006d)
(5) Provided a Grade Control System 900 Laser and GPS
system, 120M Motor Grader, 850JR MCT and references,
perform leveling operations, per the TM 11907B-OR/1. (1315-
HEOP-2006e)
(ON SLIDE # 4)
4. METHOD/MEDIA: This lesson will be taught by using the
lecture method with the aid of computer aided graphics,
video clips, computer generated simulator, Instructor
Demonstrations, and Practical Applications.
(ON SLIDE #5)
(ON SLIDE # 5)
5. EVALUATION: You will be evaluated by a written exam and
a practical application exam at the times indicated on the
training schedule.
INSTRUCTOR NOTE
Explain Instructional Rating Forms to the students.
4
(ON SLIDE # 6)
6. SAFETY/CEASE TRAINING (CT) BRIEF: All instructors and
students will use caution when walking around the equipment
lot during equipment operations. Sun block should be used
to avoid sunburn. Issue students bug spray if required.
Encourage students to stay hydrated as temperatures can
reach 100 degrees plus during the summer months. In the
event of a casualty, emergency services (911) will be
called and all students will move to the classroom and
await further instruction.
TRANSITION: Are there any questions on what we will be
covering or how you will be evaluated? Then let’s first
discuss the GSC900 Grade Control System Overview.
___________________________________________________________
___________________________________________________________
___________________________________________________________
BODY: (39 Hours 40 Min)
INSTRUCTOR NOTE:
Have the students get out their filed reference guide and
go over it briefly with them.
(ON SLIDE # 7)
1. GCS900 GRADE CONTROL SYSTEM OVERVIEW: (50 Mins)
a. GCS900 is a system designed to aid the operator in an
array of construction and grading operation. The system
provides both vertical or vertical and horizontal
instruction of where the blade needs to go to be at grade.
This can be displayed as directional lights for manual
adjustments to be made by the operator. Or it can also be
sent to a hydraulic valve to move the blade automatically.
(ON SLIDE # 8)
b. The utilization of grade control can improve
production by increasing the accuracy; thus minimizing the
number of passes required to get to grade; also reducing
fuel consumption and machine wear.
c. The system gives the operator the ability to run the
machine in manual assist or auto blade control, while
5
monitoring project design progress on the control box in
front of them. Grade Control System is just as effective in
either day or night operations.
(ON SLIDE # 9)
d. There are many different grade control applications
such as Runway/Taxiways, Aircraft parking aprons, Landing
zones, HLZ’s, Road and route missions, Building pads,
Vehicle parking lots and facilities, General grading and
drainage.
(ON SLIDE # 10)
e. The GCS900 is designed for the Marine Corp’s 120M
grader and 850JR MCT dozer. The 120M is capable of slope
only, sonic, laser and GPS operations. The MCT is only ca-
pable of laser and GPS operations.
(ON SLIDE # 11)
f. The GCS900 uses electronic components such as
rotation, slope, sonic, laser and GPS sensors to provide
accurate blade positioning and automatic blade control.
These sensors need to be calibrated by the operator in
order to be accurate.
(1) Rotation, slope, and sonic sensors: These sensors
all work together measuring each component separately
and using algorithms to calculate the exact blade
location.
(a) Rotation Sensor: The rotation sensor is
mounted to the circle components for the blade of the 120M.
There is no rotation sensor on the MCT. This sensor
measures the rotation angle of the blade, allowing the
operator full function of rotating the blade while
operating.
(b) Slope Sensor: The slope sensor measures the
slope of a component on the tractor. The same sensor can be
mounted to various components. It has arrows on it which
indicate the direction of the measurement. The 120M
utilizes three of these sensors. One will be mounted to the
mainframe of the tractor which measures the main fall
slope. Another sensor is mounted to the circle of the blade
which measures the slope of the blade. The third slope
sensor is added to the blade itself on a bracket between
the mast bracket and riser. This sensor measure blade
6
pitch/roll, which allows the operator more control of his
blade while operating. The MCT only uses one sensor to
measure the slope of the blade while operating.
(c) Sonic Tracer: The sonic tracer sensor is used
to provide elevation control. The system is designed for
use on motor graders for tracing string line, curbs and
previous pass. It also has lights that indicate whether the
blade is on or off grade. This sensor allows the operator
to easily extend an existing surface, cut or fill to
desired depths, or create new surfaces with more consistent
slopes for drainage.
(2) Laser: Consist of the GL722 laser transmitter,
machine laser receiver and rod receiver.
(a) The GL722 projects a level or sloping plane of
laser light above the job site area. Using a laser receiver
mounted to the blade the operator can grade the surface to
match level or sloping plane.
(b) The machine laser receiver guides the operator
on grade by providing adjustment either up or down. This
receiver can be used manually, but with low accuracy. It is
also utilized automatically which allows the tractor to
adjust the blade for the operator keeping the laser in the
middle of the receivers range improving accuracy.
(c) The rod receiver allows the operator or a
supervisor to check the accuracy of the machine on a job
site. The laser and receiver can be as accurate as 1/16 of
an inch or about the width of a pen tip. This receiver can
also be used to plan and estimate a jobsite by measuring
cuts and fills. The grade rod reads in tenths of a foot
commonly known as survey feet. To help better understand
this type of measurement, know that by dividing 12 inches
by 10 tenths equals 1.2 inches per tenth. Example: 3 tenths
of a foot equals 3.6 inches.
(3) Global Positioning Sensors (GPS): Consist of base
station/radio and machine receiver/radio. The system uses
more than 50 satellites orbiting in space to calculate the
machine vertical and horizontal location on earth.
(a) The base station, receiver and radio, is set
up over a hub. A hub is a point with known location such as
northing, easting, and elevation. Setting up the base
station over a known hub allows for more consistent work
for multiple day projects. The radio is used to communicate
to the machine radio for more accurate positioning of the
7
machine. The accuracy for the GPS is one tenth of a foot.
This is equivalent to the width of a golf ball. Most
vehicle and hand held GPS devices, including cell phones,
are only accurate to within 32 feet.
(b) The machine receiver and radio are used to
calculate the position of the machine by receiving its own
GPS coordinates and relaying them back to the base station
for corrections.
(ON SLIDE # 12)
(4) Using the on board control box the operator can
create common designs such as HLZ, runways, pads and V-
ditches. If a mission requires, this allows the operator to
construct projects without the external help of surveyors.
The GCS-900 can be used manually by the operator following
the guidance of the provided adjustment lights. Or, the
operator can select automatic mode which allows the tractor
to control horizontal movement of the blade. When time
permits or a complicated design needs to be created by
surveyors, the design can be loaded into the control box.
This allows for the construction of complex designs such as
roads with multiple turns and slopes and even one design
with multiple pads or sites.
(ON SLIDE # 13)
2. How it Works: Historically, the first laser system was
developed and implemented into the construction world in
1965. The conventional method required numerous stakes and
man hours to prepare a work site. Unavoidably resulting in
a congested construction site. By utilizing the grade con-
trol system all the congestion is eliminated, by the use of
the onboard control box. The control box displays the pro-
jected target instate with the guidance to go from current
grade to projected grade.
(ON SLIDE # 14)
(a) “Slope only” refers to the three sensors on the
machine that calculate the actual position of the blade.
The operator can input the desired cross slope into the
control box. Once the input is loaded the control box cal-
culates the difference from the operator input and the ac-
tual position of the blade. From there corrections are sent
to the hydraulic valve to move the blade to the correct po-
sition, in order to achieve the desired grade slope.
8
(ON SLIDE # 15)
The slope and sonic sensor: Conventionally, one way to do
what the sonic tracer does, is to run a string between two
points and mark with grade stakes the cuts and fills. (ON
SLIDE # 17) The sonic tracer was introduced later in the
mid 1980’s. This allowed the operator to extend an existing
surface and cut/fill more accurately and faster. This saves
both time and money.
(ON SLIDE # 16)
(b) “Sonic tracer” is positioned over a reference
such as a curb or string-line.
(ON SLIDE # 19)
The operator then presses the reset (bench) on the
control box. A sound wave then travels down to the
target and back to the tracer. The tracer now knows
its distance from the target based on the amount of
time sound waves took to reflect back; and then
maintains this distance from the target until it is
reset.
(ON SLIDE # 17-21)
(c) Laser System:
(1) A laser beam is shaped using optics to hold a
small diameter spot over distances. The laser beam
is then rotated at 600 RPM which creates 360 degree
plane of light above the work site. The laser beam
must then strike the center of the laser receiver
for the blade to be on grade. If the beam strikes
high or low the blade will automatically raise or
lower to get on grade.
(ON SLIDE # 22)
(d) GPS Grade control (3D): In 1999 the first designs
for GPS guidance where being introduced. (ON SLIDE # 26)
Before GPS was introduced surveyors relied on, and still
utilize, robotics to survey an area. This technology was
introduced for machine control but GPS proved more ad-
vantages to a wider variety of projects. The conventional
method of robotics only allows for one machine to be con-
trolled by one total station.
9
(ON SLIDE # 23)
GPS grade control method allows for multiple tractors to
work simultaneously to together on a project. These trac-
tors can even be working at different elevations from rough
cutting/filling with a scraper or dozer to final passes on
grade with a grader or compactor.
(ON SLIDE # 24)
(a) The system uses more than 50 satellites orbiting in space to calculate the vertical and horizontal location
of the blade within +/-.1’.
(ON SLIDE # 25)
(b) A DTM or digital terrain model is designed on a computer and then uploaded to the control box.
(ON SLIDE #26)
The DTM is designed by surveyors for multiple slope pro-
jects. This design can be loaded into multiple tractors and
each tractor can work on the project at the same time.
(ON SLIDE # 27-29)
(c) The GPS receiver calculates where you are on earth.
(d) The control box determines the difference be-tween where you are (using GPS coordinates) and where you
want to be on the project design (DTM).
(e) A signal is sent to the hydraulic valves to move the blade to match the project design.
(ON SLIDE # 30)
(e) Field Reference guide: Is an operators quick
reference tool designed to assist the operator in the
field. It provides a check list for all critical task which
are required to get the system up and running. The field
reference guide is continually updated; therefore the
operator should ensure that he has the latest available
version. Currently the Marine Corps has both Version V11
and V12.
10
INSTRUCTOR NOTE:
Have the students get out their filed reference guide and
go over it briefly with them.
(ON SLIDE # 31)
(f) CB430 Control Box: Is a the machines on board
computer, which consist of a display and keyboard in
one box, and is mounted in front of the operators
chair. The system is used to configure, calibrate and
operate the system. It has the ability to store and
transfer information about multiple machines. The
operator has the ability to design projects on the
screen and it displays the blade and machine positions
in real-time in relation to the designed project.
(ON SLIDE # 32)
TRANSISTION: Now that we talked about what and how the
Grade Control System is and works, are there any questions
at this point? I have some for you.
OPPORTUNITY FOR QUESTIONS:
1. QUESTIONS FROM THE CLASS:
2. QUESTIONS TO THE CLASS:
a. What does the Slope sensors measure?
The cross slope of the blade.
b. What is one type of design an operator can create on
the control box?
HLZ pad, runway, v-ditch.
(ON SLIDE # 37)
c. “Slope only” refers to what?
It refers to the three sensors on the machine that
calculate the actual position of the blade.
11
d. What is a DTM?
Digital terrain model.
(10 Min. Break)
(ON SLIDE # 33)
TRANSITION: We have just the covered how the GCS900 Grade
Control System works. Are there any questions? If there are
no further questions, let’s take a ten minute break before
we move on to the Installation, Configuration and
Calibration.
(ON SLIDE # 34)
2. Installation, Configuration, and Calibration(50 Minutes)
A. Grader component installation: Is the process of
installing the GCS Main components to the Machine.
(ON SLIDE # 35)
USMC tractors are pre-installed from the manufac-
turer with internal wiring and external brackets.
“Blade Slope Sensor” attaches to bracket on the back of
the circle
12
(ON SLIDE # 36)
(1) Mount “Main-fall Slope Sensor” to bracket under
goose-neck
(ON SLIDE # 37)
(2) Mount “Radio” on the back of the cab
13
(ON SLIDE # 38)
(3) Attach the “ Mast Mount” to the left side of the
blade
Note: ¾” tap may be required to remove excess paint
(ON SLIDE # 39)
(4) Attach “Mast Riser” and “Blade Roll Bracket” to
“Mast Mount”
14
(ON SLIDE # 40)
(5) Mount “Blade Roll Sensor” to mast bracket (bolt
from bottom of sensor)
Note: Connector must face toward the left blade tip
15
(ON SLIDE # 41)
(6) Attach “Electric Mast” to the “Shock Mount”
(ON SLIDE # 42)
(7) Attach Control Box Brackets and Place in Dash
Mount
16
(ON SLIDE # 43)
INSTRUCTOR NOTE:
Play 120M Install Video.
(ON SLIDE # 44)
a. Dozer component installation:
(ON SLIDE # 45)
(1) “Blade Slope Sensor” to bracket on the back of
blade
17
(ON SLIDE # 46)
(2) Mount “Radio” on the back of the cab
(ON SLIDE # 47)
(3) Attach the “Mast Mount” on the Center Mast Plate
Note: 10mm tap may be required to remove excess paint
18
(ON SLIDE # 48)
(4) Attach “Control Box” to bracket
INTERIM TRANSITION: Are there any questions on what we just
covered? If not let’s move onto the video of the component
installation.
(ON SLIDE # 49)
INSTRUCTOR NOTE
Instructor will play MCT installation video.
(ON SLIDE # 50)
INTERIM TRANSITION: Are there any questions before we move
on to the demonstration?
19
INSTRUCTOR NOTE
Perform the following demonstration.
1. DEMONSTRATION: (30 min) The purpose of this demonstra-
tion is to show the students how to conduct component in-
stallation. Before the demonstration the Instructor will
have a MCT, 120M components and all tools layed out. One
instructor is required for this demonstration.
STUDENT ROLE: The students will gather around the equipment
with student handouts and observe the instructors demon-
stration. Students will be encouraged to ask questions.
INSTRUCTOR(S) ROLE: The instructor will conduct a detailed
demonstration of how to install the GCS900 components on
the MCT and 120M.
1. Safety Brief: Instructor will cover ORAW. Hard hats will
be worn while on the lot. Each student and Instructor will
have hearing protection. Ensure all personnel are clear of
the equipment prior to starting or moving the equipment.
Ground guides will be utilized when necessary. In case of
mishap students will move to the classroom and instructor
will call emergency personnel.
2. Supervision and Guidance: The instructor will demon-
strate the following.
(1) Introduction to the components and required tools and
hardware.
(2) Install components.
(3) Remove components.
3. Debrief: Allow students the opportunity to comment on
what they experienced and/or observed. Provide overall
feedback, guidance on any misconceptions, and review the
learning points of the demonstration.
INSTRUCTOR NOTE
Instructor will reiterate the safety brief prior to the
students Practical Application.
20
INTERIM TRANSITION: Are there any questions on the
demonstration that we have just covered? If not let’s move
onto the Practical Application for component installation.
INSTRUCTOR NOTE
Perform the following Practical Applications. Allow
students to take breaks as needed. For more hands on
time the instructor can have the students remove the
components at the end of every day and re-install every
morning.
1. PRACTICAL APPLICATION: (1 HRS) The purpose of this Prac-
tical Application is to allow the students the opportunity
to practice installing GSC900 components. Before the prac-
tical application the Instructor will have (1) MCT, (1)
120M, components, tools and hardware laid out. One instruc-
tor is required.
PRACTICE: Student will be broken down into two groups and
assigned a piece of equipment to install the GSC900 compo-
nents on; additional student will be assigned as the tool
custodian. Students are allowed to use hand outs and ask
questions. The students will practice the following task.
(1) Identify GCS900 components
(2) Install GSC900 components on the MCT
(3) Install GSC900 components on the 120M
(4) Remove the components
PROVIDE-HELP: The Instructor will assist students through-
out the practical application and will ensure the students
are properly installing the GCS900 components.
1. Safety Brief: Instructor will cover ORAW. Hard hats will
be worn while on the lot. Each student and Instructor will
have hearing protection. Ensure all personnel are clear of
the equipment prior to starting or moving the equipment.
Ground guides will be utilized when necessary. In case of
mishap students will move to the classroom and instructor
will call emergency personnel.
21
2. Supervision and Guidance: Brief the students of their
responsibilities during the practical application. The In-
structor will be on the lot observing operations, assisting
students and answering questions.
3. Debrief: Allow students the opportunity to comment on
what they experienced and/or observed. Provide overall
feedback, guidance on any misconceptions, and review the
learning points of the Practical Application.
(ON SLIDE # 51)
INTERIM TRANSITION: Are there any questions on the
Practical applications of component installation? If not
then we will move on to Machine Configuration.
(ON SLIDE # 52)
B. Machine configuration:
Machine configuration is the input of information, which
tells the control box what type of machine is being
utilized and which GCS is being installed. The
configuration information identifies the equipment type,
serial number, project information (i.e. Name) and type of
GCS installed.
(ON SLIDE # 53)
INSTRUCTOR NOTE
Instructor will introduce the emulator to the student’s;
this program will be run on the Trimble laptop.
22
(1) Press “MENU”
INSTUCTOR NOTE
Instructor should utilise the the cursor to press the
correct keys on the simulator, do not demomstate in mouse
click mode. Also note the steps listed below are general in
nature and may change with version updates.
a. 120M configuration:
(1) Press “Installation” Soft-key
(2) Select “Machine Settings” and Press “OK”
(3) Press “F6” Soft key to Edit Machine
(4) Enter “Machine Name” such as 120M SR# 612849
INSTRUCTOR NOTE
NOTE: The control box must be in manager’s mode to change
display settings.
Turn “OFF” box
Press and Hold “OK”
Press “POWER” once
Release “OK” when screen changes
23
(5) Press “F6” Soft-Key
(6) Machine Type Select “Grader” and Press “F6” Soft-Key
(7) Machine Model Select “Default” and press “F6” Soft-Key
(8) Select Mast Positions and Press “F6” Soft-Key
(9) Select “Mast Type” and Press “F6” Soft-Key
(10) Select “NO” for Support ATS600 and Press “F6” Soft-Key
(11) Select “Fixed Sensors” and Press “F6” Soft-Key
INSTRUCTOR NOTE
Ensure a check is applied for desired selections.
(12) Select “Mainfall Sensor Mounting” position and Press “F6” Soft-Key
(13) Select “NO” for Third Party Radio and Press “F6” Soft-Key
(14) Select “SNRxxx” for Wireless Comms type and Press “F6” Soft-Key
(15) Select “Auto-Lift” for Grade Control and Press “F6” Soft-Key
(16) Select “Caterpilliar A4:M1” Lift Valve Module and Press “OK”
(17) Enter “0.66ft.” Auto Controls Range Limits and Press “OK”
INSTRUCTOR NOTE
Auto control range limit is a safety device which kick the
auto off when blade is moved out of the predetermined
range.
24
(18) Select “External” Light bar and Press “F6” Soft-Key
(19) Press “F6” Soft-Key for Finished
(20) Press “ESC” to return to main MENU
(21) Go to “Grader Measure-up” Field Referance Guide
INSTRUCTOR NOTE
Ensure to ESC to the main screen prior to moving on to the
measure up.
b. 850JR Dozer Configuration:
(1) Press “MENU”
(2) Press “Installation” Soft-key
(3) Select “Machine Settings” and Press “OK”
(4) Press “Edit Machine” Soft-Key
(5) Enter “Machine Name” such as 850JR SR# 612849
(6) Press “OK”
(7) Select “Machine Type” and Press “OK”
(8) Select “John Deer D850JR” Machine Model and Press “OK”
(9) Select Mast Positions and Press “OK”
(10) Select “Mast Type” and Press “OK”
(11) Select “Fixed Sensors” and Press “OK”
INSTRUCTOR NOTE
Ensure a check is spplied for desired selection.
(12) Select “SNRxx” Positioning Radio Type and Press “OK”
25
(13) Select “NO Wireless Communications” and Press “OK”
(14) Select “Auto-Lift/Tilt” Grade Control and Press “OK”
(15) Select “VM420” Lift Valve Module and Press “OK”
(16) Select “Pilot Series ll” Lift Valve Type and Press “OK”
(17) Select “0.66 ft” Auto Controls Range Limits and Press “OK”
INSTRUCTOR NOTE
Auto control range limit is a safety device which kick the
auto off when blade is moved out of the pre determined
range.
(18) Select “External” Lightbar and Press “OK”
(19) Press “Finished”
(20) Press “ESC”
(21) Go to “Dozer Measure-up” Field Referance Guide
INSTRUCTOR NOTE
Ensure to ESC to the main screen prior to moving on to the
measure up.
(ON SLIDE # 54)
INTERIM TRANSITION: Are there any questions on what we just
covered? If not let’s move onto the demonstration of the
configuring the 120M and MCT.
26
INSTRUCTOR NOTE
Perform the following demonstration.
2. DEMONSTRATION: (30 min) The purpose of this demonstra-
tion is to show the students how to configure the 120M and
MCT. Before the demonstration the Instructor will have (1)
120M and (1) MCT and (2) CB430 control boxes laid out. One
instructor is required for this demonstration.
STUDENT ROLE: The students will gather around the equipment
with student handouts and observe the instructors demon-
stration. Students will be encouraged to ask questions.
INSTRUCTOR(S) ROLE: The instructor will conduct a detailed
demonstration of how to configure the 120M and MCT.
1. Safety Brief: Instructor will cover ORAW. Hard hats will
be worn while on the lot. Each student and Instructor will
have hearing protection. Ensure all personnel are clear of
the equipment prior to starting or moving the equipment.
Ground guides will be utilized when necessary. In case of
mishap students will move to the classroom and instructor
will call emergency personnel.
2. Supervision and Guidance: The instructor will demon-
strate the following.
(1) Introduction to the control box.
(2) Configuration of the 120M.
(3) Configuration of the MCT
3. Debrief: Allow students the opportunity to comment on
what they experienced and/or observed. Provide overall
feedback, guidance on any misconceptions, and review the
learning points of the demonstration.
INSTRUCTOR NOTE
Instructor will reiterate the safety brief prior to the
students Practical Application.
27
INTERIM TRANSITION: Are there any questions on the
demonstration that we have just covered? If not let’s move
onto the Practical Application for configuring the CB430
control box.
INSTRUCTOR NOTE
Perform the following Practical Applications. Allow
students to take breaks as needed
2. PRACTICAL APPLICATION: (1 HRS) The purpose of this Prac-
tical Application is to allow the students the opportunity
to practice configuring the CB430 for the 120M and MCT. Be-
fore the practical application the Instructor will have (1)
120M and (1) MCT and (2) CB430 control boxes laid out. One
instructor is required.
PRACTICE: Student will be broken down into two groups and
assigned a piece of equipment to configure the CB430 con-
trol box; an additional student will be assigned as the
tool custodian. Students are allowed to use hand outs and
ask questions. The students will practice the following
task.
(1) Identify the control box.
(2) Configure the 120M.
(3) Configure the MCT
PROVIDE-HELP: The Instructor will assist students through-
out the practical application and will ensure the students
are properly configuring each piece of equipment.
1. Safety Brief: Instructor will cover ORAW. Hard hats will
be worn while on the lot. Each student and Instructor will
have hearing protection. Ensure all personnel are clear of
the equipment prior to starting or moving the equipment.
Ground guides will be utilized when necessary. In case of
mishap students will move to the classroom and instructor
will call emergency personnel.
2. Supervision and Guidance: Brief the students of their
responsibilities during the practical application. The In-
28
structor will be on the lot observing operations, assisting
students and answering questions.
3. Debrief: Allow students the opportunity to comment on
what they experienced and/or observed. Provide overall
feedback, guidance on any misconceptions, and review the
learning points of the Practical Application.
INTERIM TRANSITION: Are there any questions on the
Practical applications of machine configuration? If not
lets move on to Machine measure up.
(ON SLIDE # 55-56)
C. DISPLAY SETTINGS, SENSOR CALIBRATION & VALVE
CALIBRATION: The following steps are required in order to
ensure accurate guidance information is generated.
(ON SLIDE # 57)
a. Grader and Dozer Display Settings: are a precursor for the both the sensor calibration and the valve
calibration.
INSTRUCTOR NOTE
Instructor will utilize the Trimble laptop walk the
students thru the display settings, and both calibrations.
(1) Press “Menu”
(2) Press “Mode: 3D”
(3) Select “Increment switch Adjustment” and press “ok”
(4) Change Vertical offset increment: For the 120M set to .02 meters and the 850J to .05 meters.
(5) Select “Text Item” and Press “OK”
(6) Select “Cut/Fill Left”, “Offline(3D)” and “Cut/Fill Right” in this order
29
(7) Press “Cross-Section” Soft-key
(8) Select “Cut/Fill Left”, “Offline(3D)” and “Cut/Fill Right” in this order
(9) Press “Profile View” Soft-key
(10) Select “Cut/Fill Left”, “Offline(3D)” and “Cut/Fill Right” in this order
(11) Press “Text View 1” Soft-key
(12) Unlock All Items
(13) Select “Heading(3D)”, “Main-fall” and “Cross Slope” in this order
(14) Press “Text View2” Soft-key
(15) Select “Northing(3D)”, “Easting (3D)”, “Elevation(3D)”, “Station(3D)”, “MA Offset(3D)” in this
order
(16) Press “OK”
(17) Go to “Sensor Calibration” Field Reference Guide
(ON SLIDE #58-62)
b. 120M Grader Sensor Calibration:
(1) Press “Menu”
(2) Select “Blade Roll” and Press “OK” (if not installed skip to #4)
(3) Select “Yes” and Press “OK”
(4) Select “Calibration Sensors” and Press “OK”
(5) Select “Main fall, Blade slope, Rotation Sensor” and Press “OK” Read the Sensors Calibration Screen
INSTRUCTOR NOTE
Measure ups must be complete and entered into the control
box prior to conducting calibrations.
30
(6) Position and Mark Position of the Grader
(7) Follow the instruction on the screen
(8) Press “Finished” when complete
(9) Select “Blade Pitch Sensor” and Press “OK” (If not installed skip to #12)
(10) Press “OK” to caliber and Press “Finished” when completed
(11) Select “Electric Mast (S)” and Press “OK”
(12) Press “OK” to calibrate and Press “Finished” when completed
(13) Press “ESC” to return to main Menu
(14) Go to “Valve Calibration” Field Reference Guide
c. 850 JR Dozer Sensor Calibration:
(1) Press “Menu”
(2) Select “Calibrate Sensors” and Press “OK”
(3) Select “Blade Slope Sensors and Press “OK”
(4) Level the blade with a water level
(5) Enter “0.00%” in Measure blade slope and Press “Calibrate”
(6) Press “ESC” twice to return to main Menu
(7) Go to “Valve Calibration” Field Reference Guide
d. 120M Grader Valve Calibration:
(1) Press “Menu”
(2) Press “Installation” and Press “OK”
(3) Select “Valve Calibration” and Press “OK”
(4) Select “Left” valve and Press “OK”
31
(5) Read the “Left Valve Calibration Setup” instructions and Press “OK”
(6) Follow the instructions on each screen
(7) Press “Finished” when complete
(8) Select “Right” Valve and Press “OK”
(9) Read the “Right Valve Calibration Setup” instructions and Press “OK”
(10) Follow the instructions on each screen
(11) Press “Finished” when Complete
(12) Select “Save Settings” and Press “OK”
(13) Select “Display Settings” and Press “OK”
(14) Enter “Name” of Grader such as “120M Grader 7548” and Press “OK”
(15) Select “Machine Settings” and Press “OK”
(16) Enter “Name” of Grader such as “120M Grader 7548” and Press “OK”
(17) Press “OK” to return to the main menu and Press “ESC” to return to Operation Screen
e. 850JR Dozer Valve Calibration:
(1) Press “Menu”
(2) Press “Installation” Soft-key
(3) Select “Valve Calibration/Valve Tune” and Press “OK”
(4) Select “Valve Calibration” and Press “OK”
(5) Select “Lift” valve and Press “OK”
(6) Mount Slope Sensor so the connector is toward the left while sitting in the seat
(7) Follow the instructions on each screen
(8) Select “Tilt” valve and Press “OK”
32
(9) Mount Slope Sensor so the connector is toward the Cab
(10) Follow the instructions on each screen
(11) Press “Finished” when complete
(12) Select “Electric Mast(s) and Press “OK” (skip to step 14 if using SR300)
(13) Press “OK” to calibrate and Press “Finished” when completed
(14) Select “Save Settings” and Press “OK”
(15) Select “Display Settings” and Press “OK”
(16) Enter “Name” of the Dozer such as “850JR 7548” and Press “OK”
(17) Select “Machine Settings” and Press “OK”
(18) Enter “Name” of the Dozer such as “850JR 7548” and Press “OK”
(19) Press “OK” to return to Main Menu and Press “ESC” to return to Operation Screen
(ON SLIDE # 63)
INTERIM TRANSITION: Are there any questions on what we just
covered? If not let’s move onto the demonstration of the
display settings and calibrations.
INSTRUCTOR NOTE
Perform the following demonstration.
33
3. DEMONSTRATION: (30 mins) The purpose of this demonstra-
tion is to show the students how to Set the display set-
tings, sensor calibration and valve calibration for the
120M and the MCT. Before the demonstration the Instructor
will prepare (1) 120M and (1) MCT. One instructor is re-
quired for this demonstration.
STUDENT ROLE: The students will gather around the equipment
with student handouts and observe the instructors demon-
stration. Students will be encouraged to ask questions.
INSTRUCTOR(S) ROLE: The instructor will conduct a detailed
demonstration of how to, set the display settings, and con-
duct both sensor calibration and valve calibration for the
120M and the MCT.
1. Safety Brief: Instructor will cover ORAW. Hard hats will
be worn while on the lot. Each student and Instructor will
have hearing protection. Ensure all personnel are clear of
the equipment prior to starting or moving the equipment.
Ground guides will be utilized when necessary. In case of
mishap students will move to the classroom and instructor
will call emergency personnel.
2. Supervision and Guidance: The instructor will demon-
strate the following.
(1) Reintroduce the CB 430 control box.
(2) Set display settings for the 120M
(3) Set display settings for the MCT
(4) Conduct sensor calibration for the 120M
(5) Conduct sensor calibration for the MCT
(6) Conduct valve calibration for the 120M
(7) Conduct valve calibration for the MCT
3. Debrief: Allow students the opportunity to comment on
what they experienced and/or observed. Provide overall
feedback, guidance on any misconceptions, and review the
learning points of the demonstration.
INSTRUCTOR NOTE
Instructor will reiterate the safety brief prior to the
students Practical Application.
34
INTERIM TRANSITION: Are there any questions on the
demonstration that we have just covered? If not let’s move
onto the Practical Application for setting the display
settings, sensor calibration and valve calibration on the
120M and the MCT.
INSTRUCTOR NOTE
Perform the following Practical Applications. Allow
students to take breaks as needed
3. PRACTICAL APPLICATION: (2 HRS) The purpose of this Prac-
tical Application is to allow the students the opportunity
to practice setting the display settings, and conducting
sensor calibration and valve calibration for the 120M and
the MCT. Before the demonstration the Instructor will pre-
pare (1) 120M and (1) MCT. One instructor is required.
PRACTICE: Students will be broken down into two groups and
assigned a piece of equipment to set the display settings,
and conduct sensor calibration and valve calibration for
the 120M and the MCT. Students are allowed to use hand outs
and ask questions. The students will practice the following
task.
(1) Setting display settings for the 120M
(2) Setting display settings for the MCT
(3) Conduct sensor calibration for the 120M
(4) Conduct sensor calibration for the MCT
(5) Conduct valve calibration for the 120M
(6) Conduct valve calibration for the MCT
PROVIDE-HELP: The Instructor will assist students through-
out the practical application and will ensure the students
are properly configuring and conducting measure up/input on
the MCT.
1. Safety Brief: Instructor will cover ORAW. Hard hats will
be worn while on the lot. Each student and Instructor will
have hearing protection. Ensure all personnel are clear of
the equipment prior to starting or moving the equipment.
Ground guides will be utilized when necessary. In case of
35
mishap students will move to the classroom and instructor
will call emergency personnel.
2. Supervision and Guidance: Brief the students of their
responsibilities during the practical application. The In-
structor will be on the lot observing operations, assisting
students and answering questions.
3. Debrief: Allow students the opportunity to comment on
what they experienced and/or observed. Provide overall
feedback, guidance on any misconceptions, and review the
learning points of the Practical Application.
(ON SLIDE # 64)
TRANSITION: Are there any questions on the Practical
applications of Setting display settings, or conducting
sensor calibration and valve calibration for the 120M and
the MCT? If not I have some for you, before moving on to
Laser Operation.
OPPORTUNITY FOR QUESTIONS:
1. QUESTIONS FROM THE CLASS
2. QUESTIONS TO THE CLASS:
A. What are the two required calibration types?
Valve Calibration and Sensor Calibration.
B. What is required prior to conducting any
calibrations?
Measure up entered into the control box
C. The MCT’s, blade Slope Sensor is located where on the
blade?
On the back of blade.
D. The 120M’s, blade slope sensor is located where on
the 120?
36
On the bracket on the back of circle.
(ON SLIDE # 65)
E. What is the CB430?
Control Box
F. Machine configuration is the input of information,
which tells the control box what?
What type of machine is being utilized and which GCS
components are being installed.
(10 MIN BREAK)
TRANSITION: Are there any further questions before we move
on to Laser Operation.
___________________________________________________________
___________________________________________________________
___________________________________________________________
(ON SLIDE # 66)
3. Slope Only and sonic Operation: (20 MIN)
1. Grade Control System Slope Only: The AS400 Slope
Sensor is mounted on the circle behind the blade, and
measures the slope across the blade. The Rotation Sensor is
mounted on the turn table and measures the rotation of the
blade from perpendicular. The Main-fall Sensor is mounted
on the goose neck and measures the slope of the machine in
the direction of travel. The three sensors on the machine
calculates the actual position of the blade on the project.
The operator inputs the design cross slope into the control
box. The operator then controls the elevation on one side
(typically the toe). The control box then calculates the
difference from the design slope and actual slope of the
blade. Corrections are sent to the hydraulic valve to
automatically move the blade to the design slope.
(ON SLIDE # 67-68)
Slope-Only Components in the Machine: Slope only
operation is (Referenced in the field Reference Guide).
Operator in puts the slope of the project, then selects
which side of the blade will be controlled by the slope
sensor.
37
(ON SLIDE # 69)
2.CB430 Sonic Tracer: Sonics are used in conjunction
with slope control for dual control. This allows the grader
to trace an existing surface, such as a runway or fixed pad
to extend the surface.
a. Sonic Components and Operations: The Sonic tracer
is positioned over a surface to trace string line, curb,
existing hard ball, ect. The operator lowers the cutting
edge to the desired elevation and presses the reset on the
Control Box. A sound wave travel down to the target and
back to the tracer, the tracer now knows the distance from
the target based on the amount of time the sound wave took
to reflect back. The Tracer will maintain this distance
from the target until it is reset by the operator.
b.Slope only: Slope only allows the operator to enter
a cross slope value into the control box to automatically
control one side of the grader blade.
(1) Press “F1” Soft-key until “Slope” symbols is displayed on the Right side
(2) Press “Menu”
(3) Select “Vertical Setup” and Press “OK”
(4) Input Target Cross Slope or Press “Level” for Flat Pads and Press “OK”
(5) Select Automatic swap “No” and Press “OK”
(6) Press “ESC” to return to main Menu (7) Manually control the Left Side Blade
(8) To switch Sides Press “F1” Soft-key until “Slope” symbol is displayed on the left side
(ON SLIDE # 70)
c. Sonic Tracer machine Setup: The operator will
positions the blade to a finished grade elevation, then
position the Sonic Tracer over the target area to be
traced. The operator will input the target slope of the
38
project. Finally the operator will bench the sonic sensor
prior operation.
(ON SLIDE # 71, 72)
(1) Press “F1” Soft-key until “Slope” symbols is displayed on the Right side
(2) Press “Menu”
(3) Select “Vertical Setup” and Press “OK”
(4) Input Target Cross Slope or Press “Level” for Flat pads and Press “OK”
(5) Select Automatic swap “No” and Press “OK”
(6) Press “ESC” to return to main Menu
(7) Select “Bench” and Press “OK”
(8) Place Blade in working position
(9) Position Right Blade Tip to desired elevation
(10) Level left blade tip until “Current Cross Slope”
reads desired slope
(11) Check Right Blade Tip elevation
(12) Place Sonic Tracer over Target
(13) Enter “Reference elevation” example “1.00ft”
(14) Press “OK” to Bench
(15) Press “ESC” to return to operation Screen
(16) Use “V. Offset” Soft-key to Offset Elevation
above or below Bench Elevation
(ON SLIDE # 73)
TRANSITION: Are there any questions on what we just
covered? If not I have some for you and then we will move
onto Laser Operations.
A. When using slope only, which side of th blade is
controlled by the operator?
39
The Operator decides which side for automatic mode and
manual depending on the situation. The operator must select
the desired side for automatic cross slope in the control
box.
(ON SLIDE # 74)
4. GL722 LASER OPERATION: (1 HRS 45 Mins)
Is a self leveling laser transmitter that is capable of
transmitting a 360 degrees laser plane in two axes. The two
axes are identified by an open wedge and a closed wedge
printed on the top of the GL722. These wedges indicate
the direction the laser plane is sloping in each axis
INSTRUCTOR NOTE
Instructor will cover the following in classroom
utilizing the following components.
(ON SLIDE # 75-77)
a. Laser Transmitter Components:
(1) GL722 Grade Laser:
(2) Tripod Adapter:
(3) Tripod:
(4) Remote:
(5) Charger:
(6) Grade Rod and Bipod:
(7) CR Rod Receiver:
b. Machine Laser Components:
(1) SR300 Laser Receiver: three foot tall, 360 degree laser receiver designed for machines
(2) EM400 Electric Mast: four foot telescoping mast used in conjunction with the LR400 laser receiver
40
(3) LR400 Laser Receiver: ten inch 360 degree laser receiver, is the new machine receiver
(ON SLIDE # 78-79)
c. Keyboard Lay-out:
d. Mount GL722 to Tripod:
(ON SLIDE # 80-81)
e. Demonstrate the Laser Planes:
INSTRUCTOR NOTE
The instructor will demonstrate Laser plane in the class
room.
1 Set the GL722 on the tripod
2 Turn the light off in the room (dark as possible)
3 Turn the laser on to show the students the 360 degree
beam of light.
4 Configure the GL722 with a single slope applied
5 Configure the GL722 with a dual slope applied
6 Set up and explain axis alignment
7 Set up and explain grade match
41
(ON SLIDE # 82)
(1) Level Surface: Flat plane with no sloping surface (building pad).
(a) Locate an area at the same level or slightly
higher than the elevation of the work site
(b) Move the Grader close to the tripod to
determine the proper height
(c) Raise tripod legs before raising the
elevation column
(d) Attach the GL722 to the Tripod using the
quick release handle
(e) Raise Antenna
(f) Press “Power” and verify the “Battery Level”
and “RPMs” during start-up
(g) Power on “Remote” verify the slope in the
“Open Wedge” is “0.00”
(h) Press “Mode” and verify Close Wedge is “0.00”
(i) Raise Elevating Column so the Laser clears
the Cab of the Grader
(j) Verify Tripod Legs are tied-down or sand-
bagged and tighten Elevating Column
(ON SLIDE # 83)
(2) Single Slope Surface: Is surface that slopes in only one direction (HLZ pad).
(a) Locate an area at the same level or slightly
higher than the elevation of the work site
(b) Move the Grader close to the Tripod to deter-
mine proper height
42
(c) Raise Tripod Legs before raising the Elevat-
ing Column
(d) Attach the GL722 to the Tripod using the
Quick Release handle
(e) Press “Power” and verify the “Battery Level”,
“RPMs” and “Axis Alignment”
(f) Press both Right and Left “Axis Alignment”
Buttons at the same time for 3 seconds
(g) Rotate Laser so Closed Wedge slope direction
is aligned in the proper direction
(h) Manually aim the using the Sights on top of
the GL722
(i) Power on “Remote”
(j) Input Slope in “Closed Wedge”
(k) Verify Tripod Legs are tied –down or sand-
bagged and tighten Elevating Column
(ON SLIDE # 84)
(3) Dual Slope Surface: A surface that slopes in two
directions. (The slope of the center line of a runway is
one direction and the cross fall left or right is the
second direction.
(a) Place Tripod on at one end of the Center-Line
(b) Move the Grader close to the Tripod to deter-
mine proper height
(c) Raise Tripod Legs before raising the Elevat-
ing Column
(d) Attach the GL722 to the Tripod using the
Quick Release handle
(e) Press “Power” and verify the “RPMs”, “Axis
Alignment” and “Battery Level”
(f) Press both Right and Left “Axis Alignment”
Buttons at the same time for 3 seconds
43
(g) Rotate Laser so Open Wedge slope direction is
aligned to Center-Line
(h) Manually aim the Laser using the Sights on
top of the GL722
(i) Power on “Remote”
(j) Input Slope in “Open Wedge”
(k) Press “Mode” to change to Open Wedge
(l) Input Slope
(m) Press “Mode” to change to Closed Wedge
(n) Input Slope
(o) Verify Tripod Legs are tied –down or sand-
bagged and tighten Elevating Column
INTERIM TRANSITION: Are there any questions before we take
a break?
(ON SLIDE # 85)
(10 Min. Break)
INTERIM TRANSITION: Are there any more questions before we
talk about axis alignment?
(ON SLIDE # 86-87)
(4) Axis Alignment: allows the operator to automatically sight the GL722 laser accurately along the
sloping surface grade line.
(a) Power on Grade Rod Laser Receiver and Remote
(b) Attach Laser Receiver to Grade Rod
(c) Attach Coil Cord to Remote and Laser Receiver
(d) Move Grade Rod to within 3-5’ of the GL722
Transmitter
(e) Raise Grade Rod until Laser On-Grade is de-
tected, lock
44
(f) Grade Rod Height
(g) Move Grade Rod 250-500’ along the axis to be
aligned
(h) Stabilize Grade Rod with Bipod
(i) Press “Mode” on Remote until “Axis Align”,
Press “Up Arrow” to select Open or Closed Wedge
(k) Press “E” for Enter Screen will say “Please Wait”
until “Complete”
(ON SLIDE # 88-89)
(5) Grade Match: Automatically adjust the grade of
the selected axis to match an unknown grade. The laser
searches vertically until the grade rod receiver detects
the laser beam.
(a) Power on Grade Rod Laser Receiver and Remote
(b) Attach Laser Receiver to Grade Rod
(c) Attach Coil Cord to Remote and Laser Receiver
(d) Move Grade Rod to within 3-5’ of the GL722
Transmitter
(e) Raise Grade Rod until Laser On-Grade is de-
tected, lock grade Rod Height
(f) Move Grade Rod to the surface to be matched
(g) Stabilize Grade Rod with Bipod
(h) Press “Mode” on Remote until “Grade Match”,
Press “Up Arrow” to select Open or Closed Wedge
(i) Press “E” for Enter Screen will say “Please
Wait” until “Complete”
(ON SLIDE # 90-91)
(6) Grade Reverse: Used on dual slope surfaces grade
reverse allows the operator to reverse the cross slope,
from the cab utilizing the GL722 remote control. (for
45
example: when building a crowned surface I.E. runway or
road)
Note: Grade Reverse controls the Closed Axis only
(a) Power on Grade Rod Laser Receiver and Remote
(b) Attach Laser Receiver to Grade Rod
(c) Attach Coil Cord to Remote and Laser Receiver
(d) Move Grade Rod to within 3-5’ of the GL722
Transmitter
(e) Raise Grade Rod until Laser On-Grade is de-
tected, lock Grade Rod Height
(f) Move Grade Rod to the surface to be matched
(g) Stabilize Grade Rod with Bipod
(h) Press “Mode” on Remote until “Grade Reverse”
(i) Press “E” for Enter Screen will say “Please
Wait” until “Complete”
(ON SLIDE # 92)
f. Laser Setup on the Machine: The operator must input
the slope of the project, set the Laser Receiver height
using a benchmark (this referred to as “bench or
benching”). The Operator will then input any offset
between the benchmark and the project surface.
(ON SLIDE # 93)
g. Laser System Operation:
(1) Laser Receiver: controls lift function and elevation accuracy
(2) Slope Sensors: controls tilt function and accounts for blade pitch
(3) Operator must drive parallel to the slope in the Lasers line of site.
(4) The machine should be moving and the blade near grade before enabling the Automatics (within an inch or two
46
of grade) Failure to reach the desired depth may result in
tractor bog and an inaccurate final grade
(5) If the machine begins to bog down under a heavy load the Operator can assist by raising the blade while in
Auto
h . SR300 Laser Setup:
(1) Press “F1” Soft-key until both “Laser and Slope”
symbols are displayed
(2) Press “Menu”
(3) Select “Vertical Setup” and Press “OK”
(4) Input Target Cross Slope or Press “Level” for Flat Pads and Press “OK”
(5) Select Automatic swap “No” and Press “OK”
(6) Press “ESC” to return to main Menu
(7) Select “Bench” and Press “OK”
(8) Place Blade Tip on Bench Mark
(9) Plumb Mast, Level Right Blade Tip until Current Cross Slope reads “0.00”
(10) Press “OK” to Bench
(11) Press “ESC” to return to main Menu
(12) Press “Menu” and Select “Bench”
(13) Verify Current and Target Blade Slope match Press “OK” to Bench
(14) Press “ESC” to return to Operation Screen
Use “V. Offset” Soft-key to Offset Elevation above
or below Bench Elevation
INTERIM TRANSITION: Are there any questions on the GL722
Laser Operation? If there are none we will move on to
demonstration of the slope, sonic and laser operations.
______________________________
47
____
INSTRUCTOR NOTE
Perform the following demonstration. Allow students to
take breaks as needed.
4. DEMONSTRATION: (1.5 HRS) The purpose of this demonstra-
tion is to show the students how to conduct slope only,
sonic tracer, and laser operations. Before the demonstra-
tion the Instructor will have the slope sensors, sonic
tracer, GL722 laser and accessories and (1)120M, and/or (1)
MCT with CB460’s installed and staged. One instructor is
required for this demonstration.
STUDENT ROLE: The students will gather around the laser
base station and machines; with student handouts and ob-
serve the instructors demonstration. Students will be en-
couraged to ask questions.
INSTRUCTOR(S) ROLE: The instructor will conduct a detailed
demonstration of how to conduct slope, sonic and Gl722 la-
ser setup /operations and CB460 laser operation.
1. Safety Brief: Instructor will cover ORAW. Hard hats will
be worn while on the lot. Each student and Instructor will
have hearing protection. Ensure all personnel are clear of
the equipment prior to starting or moving the equipment.
Ground guides will be utilized when necessary. In case of
mishap students will move to the classroom and instructor
will call emergency personnel.
2. Supervision and Guidance: The instructor will demon-
strate the following.
(1) Introduction to the Gl722 Laser accessories and compo-
nents.
(2) Tool and battery requirements.
(3) Set up of the GL722 Laser.
(4) Configurations of the GL722 laser for operation.
(5) Conduct operation of the GL722 and CB430 control box,
laser operation.
(6) Utilization of the FRG (field reference guide)
48
3. Debrief: Allow students the opportunity to comment on
what they experienced and/or observed. Provide overall
feedback, guidance on any misconceptions, and review the
learning points of the demonstration.
INSTRUCTOR NOTE
Instructor will reiterate the safety brief prior to the
students Practical Application.
INTERIM TRANSITION: Are there any questions on the
demonstration that we have just covered? If not let’s move
onto the Practical Application for slope only, sonic
tracer, and laser operation.
INSTRUCTOR NOTE
Perform the following Practical Application. Allow
students to take breaks as needed
4. PRACTICAL APPLICATION: (12 HRS) The purpose of this
Practical Application is to allow the students the oppor-
tunity to practice conducting GL722 laser operation and
CB430 operation set up and operation. Before the practical
application the Instructor will have the GL722 la-
ser/components, (1)120M, (1)MCT with CB430’s installed
staged. One instructor is required.
PRACTICE: Students will be broken down into two groups to
conduct the GL722 laser operation and CB430 operation set
up and operation; an additional student will be assigned as
a ground guide for the student operating. Students are al-
lowed to use hand outs and ask questions. The students will
practice the following task.
(1) Identify the Gl722 Laser accessories and components.
(2) Identify tool and battery requirements.
(3) Set up of the GL722 Laser.
(4) Configure the GL722 laser for operation.
(5) Conduct operation of the GL722 and CB430 control box,
laser operation.
(6) Utilization of the FRG (field reference guide)
49
PROVIDE-HELP: The Instructor will assist students through-
out the practical application and will ensure the students
are properly operating the equipment.
1. Safety Brief: Instructor will cover ORAW. Hard hats will
be worn while on the lot. Each student and Instructor will
have hearing protection. Ensure all personnel are clear of
the equipment prior to starting or moving the equipment.
Ground guides will be utilized when necessary. In case of
mishap students will move to the classroom and instructor
will call emergency personnel.
2. Supervision and Guidance: Brief the students of their
responsibilities during the practical application. The In-
structor will be on the lot observing operations, assisting
students and answering questions.
3. Debrief: Allow students the opportunity to comment on
what they experienced and/or observed. Provide overall
feedback, guidance on any misconceptions, and review the
learning points of the Practical Application.
(ON SLIDE # 94)
TRANSITION: Are there any questions on the Practical
applications of GL722 laser operation, CB430 operation set
up and operation? If not I have some for you, then we will
move on to Machine units and Measure UP.
(ON SLIDE # 95)
OPPORTUNITY FOR QUESTIONS:
1. QUESTIONS FROM THE CLASS
2. QUESTIONS TO THE CLASS:
A. Give an example of a Single Slope Surface?
A surface that slopes in only one direction (HLZ
pad).
B. Describe Grade Match in your own words?
50
Automatically adjust the grade of the selected axis
to match an unknown grade. The laser searches vertically
until the grade rod receiver detects the laser beam.
C. What are two Laser Transmitter Components?
(1) GL722 Grade Laser (2) Tripod Adapter
(3) Tripod (4) Remote (5) Charger
(6) Grade Rod and Bipod (7) CR Rod Receiver
D. Where should you locate the Gl722 in relation to the
work site?
Locate an area at the same level or slightly higher
than the elevation of the work site
E. What is one machine laser component?
(1) SR300 Laser Receiver
(2) EM400 Electric Mast
(3) LR400 Laser Receiver
(10 MIN BREAK)
TRANSITION: Are there any further questions before we move
on to Machine units and Measure UP.
___________________________________________________________
___________________________________________________________
___________________________________________________________
_______________
(ON SLIDE # 96-97)
5. Machine units and Measure UP: (1 Hour)
Measure up identifies the exact locations of the sensors
and the exact dimensions of the machine.
(ON SLIDE # 98)
INSTUCTOR NOTE
51
Instructor will play the 120M and 850JR MCT measure up
videos.
a. 120M Grader Measure-Up:
(1) Press “Menu”
(2) Press “Installation” second Soft-Key
(3) Select “Units” and Press “OK”
(4) Select the units for each item on the list,
use up- down and right arrows
Distance “Metric”
Speed “MPH”
Grade “Percentage”
Cross Slope “Percentage”
Station Format “10+00.00”
UTC Offset “Based on your location” or
leave 0
(5) Press “OK”
(6) Select “Machine Dimensions” and Press “OK”
(7) Select “Mast Measurements” and Press “OK”
(8) Read Wizard instructions and press “OK”
(9) Select each “Bolt Hole Number” to be measured and
Press “OK” (count holes 1-7 from front to rear of Machine)
(10) At bottom of screen use Down Arrow to select
“Measure-up Tool”
INSTRUCTOR NOTE
All measurements must be made in metric, use x.xxx format
(meter. cm-mm)
52
(11) Press “F2” down arrow to “Back from cutting edge
bolts”
(12) Enter measurements and press “F2” down arrow to
“Above cutting edge bolts”
(13) Enter measurements and press “F2” down arrow “In
from blade tip”
(14) Enter measurement and press “F6”
(15) Press “Finished”
(16) Select “Machine Dimensions” and press “OK”
(17) Enter “Blade Height” press “Next”
(18) Enter “Blade width between tips” press “Next”
(19) Enter “Distance Between lift arms” press “Next”
(20) Enter “A-Frame Distance”
Note: A-Frame distance: Measure from the center of the
draft ball, at the head of the A-Frame to the center of the
rotation sensor, on top of the hydra swivel.
(21) Press “Cutting Edge” Soft-key
(22) Enter “Measure Bolt Hole” (same as above) Press
“Next”
(23) Enter “Cutting Edge Horizontal distance” Press
“Next”
(24) Enter “Cutting Edge Dimension” and press
“Ripper” Soft-key
(25) Enter “0” for “Ripper Dimensions” and press
“Machine Body” Soft-key
(26) Enter “Distance from the front of the machine to
the cutting edge” and press “Next”
(27) Enter “Distance from the back of the machine to
the cutting edge” and press “ESC”
(28) Press “ESC” and select Units and Press “OK”
53
(29) Select the units for each item on the list, use
up-down and right arrows
Distance “Us Survey Feet (FT)”
Speed “MPH”
Grade “Percentage”
Cross Slope “Percentage”
Station Format “10+00.00”
UTC Offset “Based on your location”
(CB460 only)
(30) Press “ok” and Press “ESC” to Main Screen
(31) Go to “Display Settings” Field reference Guide
b. 850JR Dozer Measure-Up:
(1) Press “Menu”
(2) Press “Installation” Soft-Key
(3) Select “Units” and Press “OK” (4) Select the units for each item on the list, use
up and down arrows
Distance “Metric”
Speed “MPH”
Grade “Percentage”
Cross Slope “Percentage”
Station Format “10+00.00”
UTC Offset “Based on your location”
(CB460 only)
(5) Press “OK”
(6) Select “Machine Dimensions” and Press “OK”
(7) Select “Mast Measurements” and Press “OK”
54
(8) Read Wizard instructions and press “OK”
(9) Select “Measure height to” method of “Mast Measurements”
(10) Enter measurements for each Mast Position required and press ”OK”
(11) Press “Finished”
(12) Select “Machine Dimensions”
(13) Enter “Blade Dimensions” and Press “Ripper” Soft-key
(14) Enter “Ripper Dimensions” and Press “Machine Body” Soft-key
(15) Enter “Machine Body Dimensions” and Press “OK”
(16) Press “ESC” twice to main menu Sec “Units” and press “OK”
(ON SLIDE # 99-102)
NOTE:
Metric system:
• 1 Meter = 1.000
• 10 Centimeters = 0.100
• 1 Centimeter = 0.010
• 1 Millimeter = 0.001
INSTRUCTOR NOTE
All measurements must be made in metric, use x.xxx format
(meter. cm-mm)
55
56
57
(ON SLIDE # 63-66)
(ON SLIDE # 103)
INTERIM TRANSITION: Are there any questions on what we just
covered? If not let’s move onto the demonstration of
machine units and measure up.
INSTRUCTOR NOTE
Perform the following demonstration.
5. DEMONSTRATION: (1 HRS) The purpose of this demonstration
is to show the students how to conduct measure up for the
120M and MCT. Before the demonstration the Instructor will
have a 120M, MCT prepared, and measure up tools laid out.
One instructor is required for this demonstration.
STUDENT ROLE: The students will gather around the equipment
with student handouts and observe the instructors demon-
stration. Students will be encouraged to ask questions.
INSTRUCTOR(S) ROLE: The instructor will conduct a detailed
demonstration of how to measure up the 120M and MCT.
1. Safety Brief: Instructor will cover ORAW. Hard hats will
be worn while on the lot. Each student and Instructor will
have hearing protection. Ensure all personnel are clear of
the equipment prior to starting or moving the equipment.
Ground guides will be utilized when necessary. In case of
mishap students will move to the classroom and instructor
will call emergency personnel.
2. Supervision and Guidance: The instructor will demon-
strate the following.
(1) Introduction to the required measure up tools.
(2) Conduct measure up for the 120M.
(3) Conduct measure up for the MCT.
(4) Inputting the measurements into the CB430 control box.
3. Debrief: Allow students the opportunity to comment on
what they experienced and/or observed. Provide overall
58
feedback, guidance on any misconceptions, and review the
learning points of the demonstration.
INSTRUCTOR NOTE
Instructor will reiterate the safety brief prior to the
students Practical Application.
INTERIM TRANSITION: Are there any questions on either of
the demonstrations that we have just covered? If not let’s
move onto the Practical Application for measure up.
INSTRUCTOR NOTE
Perform the following Practical Applications. Allow
students to take breaks as needed
5. PRACTICAL APPLICATION: (4 HRS) The purpose of this Prac-
tical Application is to allow the students the opportunity
to practice conducting measure up for the 120M and MCT. Be-
fore the practical application the Instructor will have (1)
120M, (1) MCT prepared and measure up tool laid out. One
instructor is required.
PRACTICE: Student will be broken down into two groups and
assigned a piece of equipment to conduct measure up; an
additional student will be assigned as the tool custodian.
Students are allowed to use hand outs and ask questions.
The students will practice the following task.
(1) Identify the required measure up tools.
(2) Conduct measure up for the 120M.
(3) Conduct measure up for the MCT.
(4) Inputting the measurements into the CB430 control box.
PROVIDE-HELP: The Instructor will assist students through-
out the practical application and will ensure the students
are properly conducting measure up.
59
1. Safety Brief: Instructor will cover ORAW. Hard hats will
be worn while on the lot. Each student and Instructor will
have hearing protection. Ensure all personnel are clear of
the equipment prior to starting or moving the equipment.
Ground guides will be utilized when necessary. In case of
mishap students will move to the classroom and instructor
will call emergency personnel.
2. Supervision and Guidance: Brief the students of their
responsibilities during the practical application. The
Instructor will be on the lot observing operations, assist-
ing students and answering questions.
3. Debrief: Allow students the opportunity to comment on
what they experienced and/or observed. Provide overall
feedback, guidance on any misconceptions, and review the
learning points of the Practical Application.
TRANSITION: Are there any questions on the Practical
applications of machine units and measure up? If not then I
have some for you, before moving on to display settings and
calibration.
OPPORTUNITY FOR QUESTIONS:
1. QUESTIONS FROM THE CLASS:
2. QUESTIONS TO THE CLASS:
(ON SLIDE # 104)
a. Measure up identifies the exact locations of the
what?
The sensors and the exact dimensions of the machine.
b. What is done with the measurements from the measure
up?
There uploaded to the CB430 control box.
(10 MIN BREAK)
60
TRANSITION: Are there any further questions on the
Practical applications of machine units and measure up? If
not let’s move on to display settings and calibration.
(ON SLIDE # 105-106)
6. GPS BASE STATION: (30 MIN)
Choosing an optimal location for the base station is very
important for a few reasons. The Base station must be at
location where there are minimal obstructions to the sky,
it should be on a elevated area if possible. It should also
be placed at a location that can be utilized throughout the
project without having to relocate; a safe stand off from
the working project is a must. Always ensure that the
battery is fully charged the day before intended use.
(ON SLIDE # 107-108)
a. GPS Components: The GPS base station is a GPS receiver placed over a permanent fixed point on or near the job
site. Its internal radio transmits position correction
information to the operating equipment on the job site.
61
(ON SLIDE # 109)
GPS Base Station Set-up:
(1) Press “Power” 1 time to start Base Station Receiver
(2) Wait until at least “SV8” (8 satellites) appear on the display
(3) Press “Enter” 3 times until “Base Station” with “Edit Current” below it is displayed
(4) Press “Right” 1 time until “Edit Current” begins to flash
(5) Press “down” 1 time until “New Base (Here)” is displayed
(6) Press “Enter” 1 time to accept change and “Base Name” is displayed
(7) Press “Right” 1 time, the first character of the “Base Name” begins to flash
(8) Use “Up or Down Arrow” to change the character. Press “Right arrow” to move the cursor to the next
character
(9) Press “Enter” 1 time to accept the change and Base Code” (description) is displayed
(10) Press “Right” 1 time, the first character of the “Base Code” begins to flash
(11) Use “Up or Down Arrows to change the character, Press “Right arrow” to move the cursor to the next
character
(12) Press “Enter” 1 time to accept change and “Base Latitude” is displayed
(13) Press “Enter” 1 time to accept “Latitude”
(14) Press “Enter” 1 time to accept “Longitude”
(15) Press “Enter” 1 time to accept “Point Height”
62
(16) Press “Enter” until “Antenna Type” is displayed
(17) “Zephyr GEO Mdl2” should be displayed Press “Right Arrow” to edit
(18) Press “Enter” to accept
(19) Press “Enter” until “Measured To” is displayed
(20) Press “Right Arrow” until cursor is flashing
(21) Press “Down Arrow” until “Bottom of the Antenna
Mount” is displayed
(22) Press “Enter” 1 time to accept change and
“Antenna Height” is displayed
(23) Press “Right Arrow” to select number to edit
“Point Height”
(24) Use “Up or Down Arrow” to change to “2.000
Meters” Press “Enter” to change
(25) Press “Enter” and “Port Format” is displayed
(26) Press “Right Arrow” and use “Up or Down Arrow”
to change PORT to “Radio” Press “Enter”
(27) Press “Down Arrow” and Press “Right Arrow” to
change Format to “RTK CMR+”
(28) Press “Enter” to accept
(29) Press “Enter” to go to “Radio Network” on the
Machines Press “Enter”
(30) Verify “Radio Network” matches the “Radio
Network” on the Machines Press “Enter”
(31) Press “Power” 1 time to return to the Home
Screen
(ON SLIDE # 110)
INTERIM TRANSISTION: Now that we discussed the GPS base
station. Are there any questions at this point? Let’s move
on to the demonstration.
63
INSTRUCTOR NOTE
Perform the following demonstration.
6. DEMONSTRATION: (.5 HRS) The purpose of this demonstra-
tion is to show the students how to identify and set up the
GPS base station. The Instructor will have the GPS base
station staged. One instructor is required for this
demonstration.
STUDENT ROLE: The students will gather around the GPS bas-
tion with student handouts and observe the instructors
demonstration. Students will be encouraged to ask ques-
tions.
INSTRUCTOR(S) ROLE: The instructor will conduct a detailed
demonstration of how to conduct GPS base station set up.
1. Safety Brief: Instructor will cover ORAW. Hard hats will
be worn while on the lot. Each student and Instructor will
have hearing protection. Ensure all personnel are clear of
the equipment prior to starting or moving the equipment.
Ground guides will be utilized when necessary. In case of
mishap students will move to the classroom and instructor
will call emergency personnel.
2. Supervision and Guidance: The instructor will demon-
strate the following.
(1) Introduction to the GPS base station components.
(2) Tool requirements and battery requirements.
(3) Set up of the GPS base station.
3. Debrief: Allow students the opportunity to comment on
what they experienced and/or observed. Provide overall
feedback, guidance on any misconceptions, and review the
learning points of the demonstration.
64
INSTRUCTOR NOTE
Instructor will reiterate the safety brief prior to the
students Practical Application.
INTERIM TRANSITION: Are there any questions on the
demonstration that we have just covered? If not let’s move
onto the Practical Application for the GPS base station set
up.
INSTRUCTOR NOTE
Perform the following Practical Application. Allow
students to take breaks as needed
6. PRACTICAL APPLICATION: (4 HRS) The purpose of this Prac-
tical Application is to allow the students the opportunity
to practice conducting GPS base station set up. Before the
practical application the Instructor will have the GPS base
station staged. One instructor is required.
PRACTICE: Students will be broken down into two groups to
conduct the GPs base station set up. Students are allowed
to use hand outs and ask questions. The students will prac-
tice the following task.
(1) Identify GPS base station components.
(2) Identify tool and battery requirements.
(3) Set up of the GPS base station.
PROVIDE-HELP: The Instructor will assist students through-
out the practical application and will ensure the students
are properly operating the equipment.
1. Safety Brief: Instructor will cover ORAW. Hard hats will
be worn while on the lot. Each student and Instructor will
have hearing protection. Ensure all personnel are clear of
the equipment prior to starting or moving the equipment.
Ground guides will be utilized when necessary. In case of
65
mishap students will move to the classroom and instructor
will call emergency personnel.
2. Supervision and Guidance: Brief the students of their
responsibilities during the practical application. The In-
structor will be on the lot observing operations, assisting
students and answering questions.
3. Debrief: Allow students the opportunity to comment on
what they experienced and/or observed. Provide overall
feedback, guidance on any misconceptions, and review the
learning points of the Practical Application.
TRANSITION: Are there any questions on what we just
covered? Then I have a few for you, then move on to GPS
Operation.
OPPORTUNITY FOR QUESTIONS:
1. QUESTIONS FROM THE CLASS:
2. QUESTIONS TO THE CLASS:
(ON SLIDE # 111)
a. The Base station must be at location where there are
minimal obstructions to the what?
Sky
b. When should you charge the base station?
Always ensure that the battery is fully charged the
day before intended use.
(10 MIN BREAK)
TRANSITION: Are there any further questions? If not let’s
move onto the GPS operation.
66
(ON SLIDE # 112-113)
7. GPS Operation: (25 Mins)
Switch between GPS 3D and Laser 2D: Before you can use
3d mode you must first convert your control box. The
following steps are how to do this.
(1) Press “Menu”
(2) Press “Mode: 3D 1x GPS” to change to “Mode: 2D”
(3) Press “Mode: 2D” change to “Mode: 3D 1x GPS”
Press “Esc” to return to Operation Screen
a. Machine Components:
(6) MS992 Machine GPS Receiver: Is a GPS receiver mounted to the blade of the machine and provides the actual
location of the blade on the job site to the control box.
(7) SNR900 Machine Radio: Receives correction information from the base station to improve the machines
accuracy.
67
(ON SLIDE # 114)
b. Machine Operation: When utilizing the GPS system the operator has the ability to create a design on the
fly; within the CB430 control box or the operator can
upload a Digital Terrain Model (DTM).
INSTRUCTOR NOTE:
Instructor will now utilize the emulator to load operations
from thier field reference guides.
(1) Create a level surface:
(a) Establish permanent Bench Point at the
beginning, near the new surface
(b) Place blade tip on the Bench Point
(c) Press “Menu” and “Select Design:” will be
highlighted
(d) Press “OK”
(e) Press “New Level” (first soft-key)
(f) Select “Auto create on load” for UTM
Coordination System Press “OK”
68
(g) Press “Blade:” to select which Tip “Right or
Left” is on Bench Mark (first soft-key
(h) Press “Here” (fifth soft-key) Elevation will
be established
(i) Press “OK”
(j) Enter “Name” of New Level Surface Press “OK”
(k) New Level Surface Name will be highlighted
Press “OK” to Load new design
(l) Press “ESC” to return to main operator
screen
(2) Create a 120X120 HLZ (2% Slope one Direction):
(a) Establish Point 1 at corner on high side of
Pad
(b) Drive to Point 2 corner on the high side (Note the Heading on Text Screen)
(c) Place blade tip on Point 1
(d) Press “Menu” and :Select Design” will be highlighted
(e) Press “OK”
(f) Press “New Slope” (second soft-key)
(g) Select UTM Coordinate System form list or
Press “Used last” Press “OK” (CB460 Only)
(h) Press “Method: 2 Point” 9last (soft-key)
until “Method: Pt/Dir” is displayed
(g)Press “Blade:” to select whish Tip “Right or
Left” is on Point 1 (fourth soft-key)
(i)Press “Here” Northing, Easting and Elevation
will be established
(j) Press “Direction” Enter Heading
(a) Press “Next”
69
(b) Enter “0.00” Grade for the slope of Point1 and Point 2 on the High Side of Pad
(c) Press “Cross Slope”
(d) Enter “2%” Left Select Slope Direction and Press “Next”
(e) Enter “2%” Right Select Slope Direction and Press “Next”
(f) Press “OK”
(g) Enter “Name” of New Slope Surface Press “OK”
(h) New Slope Surface Name will be Highlighted Press “OK” to load new design
(i) Press “ESC to return to main operator screen
(j) Press “H. Offset”
(k) Press “Alignment”
(l) Select “Master Alignment” and press “OK”
(m) Enter “120”
(n) Select “Left/Right” toward low side of Pad (-is Left and +is Right)
(y) Press “OK”
Point 1
120’
0%
120’
2%
Point 2
70
(8) Runway Extension PT/DIR Method:
(a) Establish a permanent bench point on the crown
line of the existing runway
(b) Drive parallel to the centerline of the runway
with the tip on the crown line
(c) Note the Heading, Main-fall (Grade) and Cross
Slope on the existing runway
(d) Place blade tip on Bench Point
(e) Press “Menu”
(f) “Select Design” will be highlighted Pres “OK”
(g) Press “New Slope” (second soft-key)
(h) Select “Auto create on load” for UTM
Coordinate System Press “OK”
(i) Press “Method: 2 Points” (last soft-key) until
“Method: Pt/Dir” is displayed
(j) Press “Blade” to select which Tip “Right or
Left” is on the Bench Mark (forth soft-key)
(k) Press “Here” (fifth soft-key) Northing,
Easting and Elevation will be established
(l) Press “Direction” Enter Heading
(m) Press “Next”
(n) Enter “Grade” (-Negative number for down
slope)
(o) Press “Cross Slope”
(p) Enter “Left Slope” and Press “Next”
INSTRUCTOR NOTE
NOTE: Measure and Stake both Point 1 and Point 2.
71
(q) Enter “Right Slope” and press “OK”
(r) Enter “Name” of New Slope Surface Press “OK”
(s) New Slope Surface Name will be highlighted
Press “OK” to load new design
(t) Press “ESC” to return to main operator screen
(9) V-Ditching:
(a)Establish permanent Bench Point at beginning
and of Ditch
(b) Place blade tip on Bench Point
(c) Press “Menu” and “Select Design:” will be
highlighted
(d) Press “OK”
(e) Press “New Slope” (second soft-key)
(f) Press “Blade:” to select which Blade Tip
“Right or Left” is on Bench Mark (fourth soft-key)
(g) Press “Here” (fifth soft-key) Northing, East-
ing and Elevation will be displayed
(h)Drive to end of Ditch place blade tip on Bench
Point
(i) Press “Point 2” and Press “Here” Northing,
Easting and Elevation will be displayed
(j) Press “Cross Slope”
(k) Enter “left Slope” and “Slope Direction”
to invert Left
(l)Press “Next”
(m) Enter “Right Slope” and “Slope Direction”
to invert Right
(n)Press “OK”
72
(o) Enter “Name” of New Slope Surface Press “OK”
(p) New Slope Surface Name will be highlighted
Press “OK” to load new design
(q) Press “ESC” to return to main operator screen
(10) Sloping surface:
(a) Establish permanent Bench Point at beginning
of Crown Line
(b) Place blade tip on Bench Point
(c) Press “Menu” and “Select Design:” will be
highlighted
(d) Press “OK”
(e) Press “New Slope” (second soft-key)
(f) Select UTM Coordinate System from list or
Press “Used last” Press “OK”
(g) Press “Blade:” to select which Blade Tip
“Right or Left” is on Bench Mark (fourth soft-key)
(h) Press “Here” (fifth soft-key) Northing, East-
ing and Elevation will be established for ”Point 1”
(i)Drive to second point place blade tip on Bench
Point
(j) Press “Point 2” and Press “Here” Northing,
Easting and Elevation will be established for “Point 2”
(k) Press “Cross Slope”
(l) Enter “left Slope” and Press “Next”
(m) Enter “Right Slope” and Press “OK”
(n) Enter “Name” of New Slope Surface Press “OK”
(o) New Slope Surface Name will be highlighted
Press “OK” to load new design
73
(p) Press “ESC” to return to main operator screen
(11) Cut and Fill mapping:
(a) Establish Start Point of Site
(b) Place blade tip on Start Point
(c) Press “Menu” and “Select Design:” will be
highlighted
(d) Press “OK”
(e) Press “New Level” (first soft-key)
(f) Press “Blade:” to select which Tip “Right or
Left” is on Start Point (first soft-key)
(g) Press “Here” (fifth soft-key) Elevation will
be established and Press “OK”
(h) Enter “Name” of New Level Surface Press “OK”
(i) New Level Surface Name will be highlighted
Press “OK” to load new design
(j) Select “Map Recording”
(k) Select “Cut and Fill”
(l) Press “Ok”
(m) Press “Esc” to Main Screen
(n) Use “C/F Mapping” Soft-key to turn On and Off
(ON SLIDE # 115)
INTERIM TRANSITION: Are there any questions on what we just
covered? If not let’s move on to the demonstration for GPS
operation.
INSTRUCTOR NOTE
Perform the following demonstration.
74
7. DEMONSTRATION: (.5 HRS) The purpose of this demonstra-
tion is to show the students how to conduct GPS operation.
Before the demonstration the Instructor will have the GPS
base station, (1) 120M and (1) MCT staged. One instructor
is required for this demonstration.
STUDENT ROLE: The students will gather around the instruc-
tor; with student handouts and observe the instructors
demonstration. Students will be encouraged to ask ques-
tions.
INSTRUCTOR(S) ROLE: The instructor will conduct a detailed
demonstration of how to conduct GPS operation.
1. Safety Brief: Instructor will cover ORAW. Hard hats will
be worn while on the lot. Each student and Instructor will
have hearing protection. Ensure all personnel are clear of
the equipment prior to starting or moving the equipment.
Ground guides will be utilized when necessary. In case of
mishap students will move to the classroom and instructor
will call emergency personnel.
2. Supervision and Guidance: The instructor will demon-
strate the following.
(1) Introduction to the GPS operation.
(2) Set ups for various GPS operations.
(3) Operation of the GPS base station.
3. Debrief: Allow students the opportunity to comment on
what they experienced and/or observed. Provide overall
feedback, guidance on any misconceptions, and review the
learning points of the demonstration.
INSTRUCTOR NOTE
Instructor will reiterate the safety brief prior to the
students Practical Application.
INTERIM TRANSITION: Are there any questions on the
demonstration that we have just covered? If not let’s moe
onto the Practical Application for the GPS operation.
75
INSTRUCTOR NOTE
Perform the following Practical Application. Allow
students to take breaks as needed
7. PRACTICAL APPLICATION: (4 HRS) The purpose of this Prac-
tical Application is to allow the students the opportunity
to practice conducting GPS operations. Before the practical
application the Instructor will have the GPS base station,
(1)120M, (1) MCT prepared. One instructor is required.
PRACTICE: Students will be broken down into two groups to
conduct the GPs operation; an additional student will be
assigned to each piece of equipment as a ground guide for
the student operating. Students are allowed to use hand
outs and ask questions. The students will practice the fol-
lowing task.
(1) Identify GPS operation.
(2) Set ups for various GPS operations.
PROVIDE-HELP: The Instructor will assist students through-
out the practical application and will ensure the students
are properly operating the equipment.
1. Safety Brief: Instructor will cover ORAW. Hard hats will
be worn while on the lot. Each student and Instructor will
have hearing protection. Ensure all personnel are clear of
the equipment prior to starting or moving the equipment.
Ground guides will be utilized when necessary. In case of
mishap students will move to the classroom and instructor
will call emergency personnel.
2. Supervision and Guidance: Brief the students of their
responsibilities during the practical application. The In-
structor will be on the lot observing operations, assisting
students and answering questions.
3. Debrief: Allow students the opportunity to comment on
what they experienced and/or observed. Provide overall
feedback, guidance on any misconceptions, and review the
learning points of the Practical Application.
(ON SLIDE # 116)
76
TRANSITION: Now that we have covered the GCS900 in detail
are there any further questions?
OPPORTUNITY FOR QUESTIONS:
1. QUESTIONS FROM THE CLASS:
2. QUESTIONS TO THE CLASS:
a. What is the MS992?
Is a GPS receiver mounted to the blade of the machine
and provides the actual location of the blade on the job
site to the control box.
b. What is the SNR900?
It is the machines radio that receives correction
information from the base station to improve the machines
accuracy.
(ON SLIDE # 117)
SUMMARY (5 MIN)
During this period of instruction we have covered all
the equipment and a variety of the utilizations of the
GCS900. Although as a 1345 Engineer Equipment Operator you
may not always have access to this System, there is a high
probability that you may be responsible for the training
and employment at some point during your career. This
lesson has given you a basic understanding of how to best
utilize the GCS900 and incorporate it into your unit’s
mission.
(10 MIN BREAK)
INSTRUCTOR NOTE
Ensure to collect all IRF’s and safety questionnaires hand-
ed out.
REFRENCES:
TM 11907B-OR/1 -OPERATOR’S AND FIELD MAINTENANCE MANUAL
WITH REPAIR PARTS AND SPECIAL TOOLS LISTING