level crossing project - engineers ireland · level crossing project as part of the railway safety...

109
LEVEL CROSSING PROJECT as part of the RAILWAY SAFETY PROGRAMME PRESENTED BY CONOR MCGUINNESS SENIOR PROJECTS MANAGER

Upload: phamtuyen

Post on 14-Apr-2018

215 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

LEVEL CROSSING PROJECT

as part of theRAILWAY SAFETY PROGRAMME

PRESENTED BY

CONOR MCGUINNESS

SENIOR PROJECTS MANAGER

Page 2: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

LEVEL CROSSING PROJECTLEVEL CROSSING PROJECT

1.1. INTRODUCTIONINTRODUCTION

2.2. DEVELOPMENT OF RISK ASSESSMENT MODELDEVELOPMENT OF RISK ASSESSMENT MODEL

3.3. COLLECTION OF DATA FOR MODELCOLLECTION OF DATA FOR MODEL

4.4. RISK ASSESSMENT RESULTSRISK ASSESSMENT RESULTS

5.5. STRATEGY FOR INVESTMENT PROGRAMME STRATEGY FOR INVESTMENT PROGRAMME

6.6. METHODOLOGYMETHODOLOGY

7.7. EXAMPLES OF COMPLETED PROJECTSEXAMPLES OF COMPLETED PROJECTS

8.8. PROGRESS TO DATEPROGRESS TO DATE

9.9. FUTURE DEVELOPMENTSFUTURE DEVELOPMENTS

Page 3: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

1. INTRODUCTION1. INTRODUCTION

• OVER 2500 CROSSINGS ON ALL LINES

INCLUDING CLOSED LINES

• OVER 2000 CROSSINGS ON USED LINES

• 1600 CROSSINGS ON PASSENGER LINES

• 85% OF CROSSINGS ARE USER WORKED

CROSSINGS

Page 4: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

TYPES OF CROSSINGSTYPES OF CROSSINGS

• USER WORKED – THE PERSON USING THE

CROSSING HAS TO OPEN AND CLOSE THE GATES

THEMSELVES EACH TIME THE CROSSING IS USED.

NO RAILWAY SIGNALS LINKED TO THESE

CROSSINGS

• RAILWAY WORKED – THESE CROSSINGS ARE

AUTOMATICALLY OPERATED BY THE PASSAGE OF

TRAINS OR MANNED BY RAILWAY STAFF WHO

OPEN AND CLOSE THE GATES FOR EACH

MOVEMENT

Page 5: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

Field Type CrossingField Type Crossing

Page 6: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

Occupation Type CrossingOccupation Type Crossing

Page 7: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

Occupation Type Crossing on Public roadOccupation Type Crossing on Public road

Page 8: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

Crossings manned by Railway staff Crossings manned by Railway staff ––C/CX/CNC/CX/CN

Page 9: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

Automated Crossings Automated Crossings –– Automatic Half Barrier Automatic Half Barrier (AHB(AHB))

Page 10: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

Automated Crossings Automated Crossings -- 4 Barrier monitored by 4 Barrier monitored by CCTV(CCTV)CCTV(CCTV)

Page 11: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

Automated Open Crossing Automated Open Crossing –– No BarriersNo Barriers

Page 12: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

2. DEVELOPMENT OF RISK ASSESSMENT MODEL2. DEVELOPMENT OF RISK ASSESSMENT MODEL

National averages for crossing type• Average vehicle /

train utilisation• Average historic

safety performance

National averages for crossing type• Average vehicle /

train utilisation• Average historic

safety performance

Crossing specific data• Utilisation• Risk factors

– condition– views– gates left open– train speed

Crossing specific data• Utilisation• Risk factors

– condition– views– gates left open– train speed

LEVEL CROSSING

MODEL

LEVEL CROSSING

MODEL

OUTPUTS PREDICTED

• Accident rate• Fatality rate• Individual risk

(regular user)

OUTPUTS PREDICTED

• Accident rate• Fatality rate• Individual risk

(regular user)

Page 13: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

• The basis of the model is Fault Tree whose Top

Event is “train - vehicle collision”, and an Event

Tree showing consequences of a collision event

Risk factors: Affecting chanceof user error

– Incentive to take risk– Insufficient information– Unable to correct error in time– Low familiarity with task

Risk factors: Affecting chanceof user error

– Incentive to take risk– Insufficient information– Unable to correct error in time– Low familiarity with task

Train - VehicleCollision

Train - VehicleCollision

VehicleUser

Consequences

VehicleUser

Consequences

PassengerConsequences

Severity

PassengerConsequences

Severity

FatalityFatality

No FatalityNo Fatality

HighHigh

MediumMedium

LowLow

ANDAND

Numberof UsersNumberof Users

ProbError by

User

ProbError by

User

ProbTrain

Approach

ProbTrain

Approach

Event Tree

Faul

t Tre

e

Page 14: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

3. MEASUREMENT OF THE PROBLEM3. MEASUREMENT OF THE PROBLEM

• Need to look at condition and use of

every crossing

• Site Visit Form developed to record

similar data for each type of crossing

• All crossings visited in 1998 and data

collected

Page 15: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

User Worked Crossings User Worked Crossings –– Data Data collectedcollected

• Type of users -familiar

• Type of usage- regular, seasonal

• Condition of crossing – views, surface,

gradients

• Types of vehicles using crossing

• Type of railway traffic- speeds etc.

Page 16: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

Railway worked crossingsRailway worked crossings-- Data collectedData collected

• Approach road – speed, width, view of

crossing

• Crossing location-bend, close to junction

• Visibility – sun dazzle, fog

• Ability to stop

• Road usage

• Railway usage

Page 17: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager
Page 18: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager
Page 19: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

Example of Risk Assessment Model

OP-- User Worked Crossing on Public Road

Page 20: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

1 User Characteristics

1.1 Describe the majority of road user types at the crossing.

1.2 Is there heavy seasonal use of the crossing ?

1.3 Are gates left open a known problem at the crossing ?

Regular / Familiar

Seasonal use

Yes, Frequent

Page 21: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

2 Crossing Characteristics

2.1 Are the crossing user's views of the railwayline poor ?

2.2 Is the crossing surface poor ?

2.3 Is there a gradient across the crossing ?

2.4 Are there additional factors which could worsen the effects of a train/vehicle collision?

2.5 Is fog a problem at the crossing?

No

Adequate

Adequate

i) e .g. o bs truc tio ns limiting view o f line o r views les s than '11' s eco nds ;ii) take tra in s peed into acco unt.

e .g. lo w leve l o f fill o r lo o s e fill.

P o tentia l fo r gro unding o r impeding vehic le mo vement.

Adequate

Up S ide Down S ide

e.g. embankment, co mplex track layo ut

No

Some problem

Page 22: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

3 Road Utilisation

3.1 Estimate the total average daily road vehicle utilisation (sum of both directions).

45.

3.2 Estimate the total average daily pedestrian utilisation (sum of both directions).

0.

3.3How many vehicles under 3.1 are laden buses?

3.4 Are tractors or farm machinery used on the crossing ?

3.5 Are tailbacks across the crossing a problem?

Yes

Take into acco unt va ria tio ns due to time o f day and s eas o ns .

i) Take into acco unt varia tio ns due to time o f day and s eas o ns .ii) Do no t inc lude c ro s s ings o n fo o t during vehic le c ro s s ings .

Take into acco unt va ria tio ns due to time o f day and s eas o ns .

e .g. if a ro ad junc tio n o r turning may res tric t the us er's exit fro m the c ro s s ing

(O,OP and OP* only)

No problem No problem

Up S ide Down S ide

Page 23: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

4 Railway Utilisation

4.1 Estimate the total average daily number of laden passenger trains through the crossing.

28.

4.2 Estimate the total average daily number of rail movements, other than laden passenger trains,

9.

through the crossing.

4.3 Estimate the highest train speed at the level crossing. > 50 mph

Take into acco unt varia tio ns due to time o f day and s eas o ns .

Page 24: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

Output from Risk Assessment Output from Risk Assessment ModelModel

OP ResultsOP Results

Page 25: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

1 Crossing Fatality Rates

Scientific Format

Standard Format

Vehicle User Fatalities (per year) 1.75E-03 0.00175

Pedestrian Fatalities (per year) 9.08E-05 0.0000908

Total Fatalities (per year) 1.84E-03 0.00184

Page 26: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

2 Individual Risk of Fatality

Scientific Format

Standard Format

Risk 1 in ...

Individual Risk of Fatality to a Regular Vehicle User (per year)

5.32E-05 0.0000532 18,800

Individual Risk of Fatality to a Regular Pedestrian User (per year)

6.91E-07 0.0000007 1,450,000

Page 27: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

3 Collision Frequency

Scientific format

Standard Format

Frequency of Train/Vehicle Collisions (per year)

4.55E-03 0.00455

Frequency of Laden Passenger Train/Vehicle Collisions (per year)

3.45E-03 0.00345

Severity Factor Medium

Page 28: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

4 Graph of Crossing Fatality Rates

Vehic le Us er P edes trian Us er To ta l

Average for crossingtypeThis crossing

1 in 100

1 in 1000

1 in 10

1 in 10,000,000

1 in 1,000,000

1 in 100,000

1 in 10,000

Page 29: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

5 Graph of Individual Risk of Fatality for a Regular User

Vehic le Us er P edes trian Us er

Average for crossing type

This Crossing

1 in 100

1 in 1000

1 in 10,000,000

1 in 1,000,000

1 in 100,000

1 in 10,000

Page 30: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

4. RISK ASSESSMENT RESULTS4. RISK ASSESSMENT RESULTS

• Risk Acceptability criteria established in

line with international norms

• Crossings to be prioritized based on

results

• High Risk crossings primarily user

worked.

Page 31: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

• 4

Results of Risk Assessment programme

Results of Risk Assessment programme

Crossings requiring priority

investment

Crossings requiring priority

investment

Crossings not requiring priority

investment

Crossings not requiring priority

investment

CRITERIA

RISK

ACCEPTABILITY

Page 32: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

• 4

Either Individual risk of fatality for regular users ≥ 1 in 10,000 per annum

Or Divisional Engineer identifies factors giving intolerable situation

Crossing requires mitigation – "BLACK AREA".

Either Individual risk of fatality for regular user < 1 in 10,000 but ≥ 1 in 20,000 per annum

Or Collision rate ≥ 1 in 100 years

Or Crossing is in poor maintenance condition

Crossings requiring further evaluation - "GREY AREA".

Both Individual risk of fatality for a regular user < 1 in 20,000 per annum

And Collision rate < 1 in 100 years

Crossing currently not requiring mitigation on risk grounds

Page 33: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

• 4

“Black Area”“Black Area”

“Grey Area”“Grey Area”

“Black Area”Require mitigation

on risk grounds

“Black Area”Require mitigation

on risk grounds

“White Area”Do not

currently require priority mitigation on risk grounds

“White Area”Do not

currently require priority mitigation on risk grounds

Evaluation FactorsEvaluation Factors

• small number of users with higher than average number traverses

•cattle•poor condition• long crossing time compared to view time

•peaky seasonal use•peaky daily use•vulnerable groups•UWC is a short cut• crossing difficult to operate• train speed >75mph•hazardous goods

•small number of users with higher than average number traverses

•cattle•poor condition• long crossing time compared to view time

•peaky seasonal use•peaky daily use•vulnerable groups•UWC is a short cut• crossing difficult to operate• train speed >75mph•hazardous goods

Page 34: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

Ranking the CrossingsRanking the Crossings

• Priority Rating given to all ‘black’ crossings

• Priorities range from 0 to 15

• Priorities based on combination of 2 factors

• Individual risk of fatality to a regular user

per annum

• Frequency of accidents per annum

Page 35: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

Priority Score 1 Priority Score 1 ––Individual RiskIndividual Risk

1-Below 1 in 100,000

2-1 in 100,000 to 1 in 20,000

3No1 in 20,000 to 1 in 10,000

4Yes1 in 20,000 to 1 in 10,000

9-1 in 10,000 to 1 in 2000

10-> 1 in 2,000

Priority Score 1Additional Factors

give rise for concern

Individual Risk of Fatality

for Individual User - Range

Page 36: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

Priority Score 2 Priority Score 2 ––Collision FrequencyCollision Frequency

1<0.005 per year

20.0005 to 0.001 per year

30.001 to 0.005 per year

40.005 to 0.01 per year

5>0.01 per year

Priority Score 2Predicted Collision

Frequency – Range

Priority Score = Priority Score 1 + Priority Score 2 ,

Max =15 Score of 10 or more indicates an intolerable risk

Page 37: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

Black Crossings by TypeBlack Crossings by Type

» Total 608

1141

131 FieldOccupationAttendedAutomatic

424

Page 38: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

5. 5. STRATEGY FOR INVESTMENT PROGRAMMESTRATEGY FOR INVESTMENT PROGRAMME

• AIM: To reduce risk to user at all

crossings to an acceptable level

• FOCUS ON: Highest Risk crossings

and busiest lines first

• METHOD: To eliminate as many

crossings as possible

Page 39: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

Additional requirementsAdditional requirements

• Close all unprotected crossings on double

track lines- Dublin-Cork, Dublin-Belfast,

DART

• Focus on other high speed, high traffic

density lines – Portarlington-Athlone,

Limerick – Limerick junction

• Avail of opportunities to close other

crossings

Page 40: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

ResourcesResources

• Project team – in house – Project

Manager, engineers, technician

• Design team – external for construction

works/ planning applications/site works

• Property Surveyors/negotiators

• Solicitor to draft legal agreements

• Part time financial & planning resources

Page 41: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

6 METHODOLOGY6 METHODOLOGY

• All crossing closures to be reached by agreement

as no compulsory powers to close crossings

• Where works involved –negotiations with users,

design of works and tender phase and planning

applications proceeding in parallel

• Programme needs to be flexible to substitute

other crossings if progress delayed or no

agreement possible

Page 42: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

Solutions consideredSolutions considered

• Land search to check if ownership is split

• Buy rights to crossing

• Buy cross-track property (resale)

• Provide alternative access

• Land swaps

• Protect crossing (gates, signals)

• Bridge or underpass

• Upgrade, where appropriate

Page 43: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager
Page 44: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

Need to Follow the Paper trailNeed to Follow the Paper trail

• Legal Process to be completed by user

and IE and CIE Boards

• Legal Rights to be given up

• Paperwork flow to be managed

• Solicitor must be involved on both sides if

land is involved

• New rights of way need to be mapped and

registered

Page 45: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

How A Crossing is ClosedHow A Crossing is Closed

• Visit Crossing User –assess needs• Check folio in Land registry• Reach agreement on closing crossing• Send formal offer letter outlining terms• User agrees terms• Lodge planning application if required• Fast track approval where compensation/

land purchase/ works below certain level• High Cost closures must be approved by

the Board

Page 46: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

How A Crossing is Closed(2)How A Crossing is Closed(2)

• Brief Solicitor on terms agreed

• Solicitor drafts closure documents & sends to

Users Solicitor

• Cheque requisitioned –sent to Users Solicitor

• Solicitor checks title to land being purchased

• User signs closure documents

• If works required, works can now commence

• Crossing physically closed – money released

Page 47: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

Time for CompletionTime for Completion

• For Right of Way only < 2 months

• 6 months min if land involved

• 12-18months where works are involved as land

purchase and planning permission usually needed

• Up to 2 years or longer if probate has to be taken out

on land

• Taking out Probate always involves payment of Tax

• Timescale is completely dependent on Users Solicitor

looking at documents and contacting his client

Page 48: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

7. EXAMPLES OF COMPLETED PROJECTS7. EXAMPLES OF COMPLETED PROJECTS

• XC117-121 –overbridge & cattlepass

• XA21 – Land deal

• XB12 -5 span overbridge Belfast line

• XR 7 & 9- 2 underpasses on DART line

• XW132/4/5 -2 underpasses & 800m

access road

• XA72-3 Public road underpass

• Various others

Page 49: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

OB236a CORK to replace 6 Field crossings

Page 50: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

UB236b Cork line - Cattle pass at XC119

Page 51: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

XA21 –land purchased to close crossing 35a €317,000

Page 52: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

Construction of OB99a to replace XB12 Construction of OB99a to replace XB12 Reillys Belfast lineReillys Belfast line

• Location first visited in April 1999

• Survey carried out –single span designed

• Design tendered in Feb 2000 –cost €1.55m

• Scheme did not go ahead due to high cost

• Alternative Access sought – agreed in principle

with 2 landowners Nov 2000

• Unable to finalise agreement for this access

Page 53: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

XB12 Belfast –layout plan for OB 99a

Page 54: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

Construction of OB99a to replace XB12 Construction of OB99a to replace XB12 Reillys Belfast line (2)Reillys Belfast line (2)

• Agreement reached with different landowner for

access route from old N1

• Access route rejected by landowners

• Purchase of 175 acre farm and residences

rejected

• Bridge redesigned as 5 span bridge

• Scheme retendered October 2001-cost €1.46m

• Board deferred proposal Dec 2001-cheaper

options sought

Page 55: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager
Page 56: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

Construction of OB99a to replace XB12 Construction of OB99a to replace XB12 Reillys Belfast line (3)Reillys Belfast line (3)

• Board paper prepared considering whole life cost of all options considered

• Options considered : - 3 different access routes, underbridge, overbridge, farm purchase, CCTV crossing

• Acceptability of options outlined in paper• Bridge cheapest acceptable solution

based on whole life cost• Board approved bridge proposal Feb 2002• Main Landowners signed up 19th April

2002

Page 57: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager
Page 58: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

Construction of OB99a to replace XB12 Belfast line – completed May 2003

Page 59: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

Construction of OB99a Belfast line

Page 60: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

• Construction of OB 99a Belfast line

Page 61: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

OB99a Belfast line – XB12 Reillys in foreground

Page 62: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

Construction of OB99a to replace XB12 Construction of OB99a to replace XB12 Reillys Belfast line (4)Reillys Belfast line (4)

• Final clearance to go on site 4th June 2002

• Contract signed with SIAC 10th June 2002 at

€1.48m (1.5% increase)

• Works commenced on site 4th July 2002

• Bridge beams over track lifted in Oct 2002

• Bridge open 19th May 2003- crossing closed

• Works complete 27th May 2003- final cost €1.645

• Project Cost €1.902m -5.9% over budget

Page 63: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

OB99a Belfast line –Complete May 2003

Page 64: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

OB99a Why a 5 span bridge ?OB99a Why a 5 span bridge ?

• Poor Ground conditions

• Embankment would have taken 6 months to settle

or required ground improvement at additional

cost

• Too much land taken up by single span

embankment –user acceptance

• Potential Safety issue due to large volumes of fill

to be drawn across crossing

• 5 span €90k cheaper at tender than single span

Page 65: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager
Page 66: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

XR7 & 9 Woodbrook Golf club DART lineXR7 & 9 Woodbrook Golf club DART line

• 2 underpasses to be constructed – one suitable for machinery(4.5m x 4.5m), one for golfers only

• Construction of 2 underpasses were o be let as one contract – actually let as 2 separate contracts

• 3 temporary crossings of Dart line to be constructed for construction traffic and to keep golf links in operation

• Overhead electrification to be dealt with – isolations required at night for certainworks

Page 67: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

XR7/9 Woodbrook Golf club DART line (2)XR7/9 Woodbrook Golf club DART line (2)

• Services to be exposed, protected and supported during construction – live38 kv, ESAT. Signalling cables

• 38kv power supply switched off for some works

• 300mm gas main to be diverted for construction and rediverted post construction

• DART services to be cancelled for installation of underpasses

• Pumped drainage system to be installed

Page 68: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

XR7/9 Woodbrook Golf club DART line (3)XR7/9 Woodbrook Golf club DART line (3)

• Construction works had to be screened off from golf club

• Golf club set up liaison committee to ‘approve’ design details

• Clerk of Works appointed by Golf club to supervise works

• Extra drainage works carried out post completion to divert track drainage away from pumped system

• Construction cost €1.438m against tender of €1.014 due to splitting of contracts and accommodation works carried out by contractor

Page 69: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager
Page 70: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager
Page 71: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager
Page 72: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager
Page 73: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager
Page 74: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager
Page 75: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager
Page 76: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager
Page 77: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager
Page 78: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

XW132/4/5 Ryans & KnockwilliamXW132/4/5 Ryans & Knockwilliam

• Construction of 2 underpasses –one for cattle, one for machinery

• Construction of 800m of access roads parallel beside railway

• Access roads linked both underpasses and 4 landowners fields

• 3 Crossings closed• Drainage – major issue

Page 79: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

XW137 Knockwilliam – rockbreaking for cattlepass

Page 80: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

XW137 Knockwilliam –installation of cattlepass

Page 81: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

XW137 Knockwilliam –fitting units together

Page 82: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

XW132/4/5 –construction of access road beside track

Page 83: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

XW132/4/5 Access road parallel to track

Page 84: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

XW132/4/5 _flooding of lands at Ballyhale

Page 85: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

Construction of UB53a at Erry Construction of UB53a at Erry --Portarlington/Athlone linePortarlington/Athlone line

• Closure of 2 unattended public road crossings

• Largest underpass yet constructed 7.5m wide by 4.8m box

• New public road constructed to link to existing road network

• Separate access purchased for overheight vehicles

Page 86: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager
Page 87: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

Construction of Underpass at Erry Portarlington/Athlone line October 2001

Page 88: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

Installation of underpass at Erry Portarlington/Athlone line October 2001

Page 89: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager
Page 90: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager
Page 91: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager
Page 92: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

8. PROGRESS TO DATE8. PROGRESS TO DATE

• 473 Crossings closed out of 2000

• 130 + land purchases, 1,060 acres

purchased

• 20 - overbridges built

• 20 - underbridges built

• 38 access roads built or purchased– 3 for

public road crossings

Page 93: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

Cost of ProgrammeCost of Programme

• Programme costed in September 1998

• Total Cost of Programme €136m

• €112m to be spent in first 5 years 1999-

2003

• Expenditure at end of 2003 €71.8m spent

• €82.9 to be spent in second 5 years 2004-

2008 -€17.2 spent to end of 2005

Page 94: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

Crossings Closed to dateCrossings Closed to date-- Feb 2006Feb 2006

Total Closures 473

• Release 149

• Split Ownership 86

• Land deal 132

• Bridge 68

• Alternative Access 38

Page 95: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

Solutions to date Solutions to date -- Feb 2006Feb 2006

3831

37

132149

86

Access RoadsUnderbridgesOverbridgesLand DealsReleaseSplit

Page 96: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

High Speed /High Density routesHigh Speed /High Density routes

• Dublin/Cork 72 closed 40 left

• Dublin/Belfast 8 closed 2 left

• Portarlington/Athlone 62 closed 22 left

• DART lines – 2 closed, 1 unsignalled left

• Limerick/Limerick jn. 13 closed 38 left

Page 97: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

ProgrammeProgramme RisksRisks

• User can always change mind until legal agreement

signed & does.

• 3 pronged approach where works involved

- Progress negotiations, submit planning application,

develop design to tender at the same time

• Principle risk – user changes mind, effort wasted

• Be prepared to walk away if price gets too high

• Target extra crossings as many deals don’t get finished

• Land deals always take more time to complete

Page 98: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

Underpass at XR32 Kellys Wexford line –Completed 2000

Page 99: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

UB157b Galway line -Teagasc Athenry

Page 100: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

Overbridge at Bunnahinly to replace XA114/5/6

Page 101: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

Pouring concrete to foundations Clonshanny –XA74-77 Port/Athlone

Page 102: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

Construction of Reinforced Earth abutment at XA30-31 Port/Athlone

Page 103: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

Bridge nearing completion at XA30-31 Port/Athlone

Page 104: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

Overbridge at Stonepark 110 1/4mls Sligo line

Page 105: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

OB 347a Cork line to replace XC228 Hanlons

Page 106: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager

9. Future Strategy9. Future Strategy

• Crossings getting harder to close – deals more expensive and more complicated

• Railway Safety Act 2005 gives powers to close crossings and acquire land compulsorily

• Implementation of ‘Draft Guidelines for the Design of Railway Infrastructure…’ may limit speed through user worked crossings to 130km/hr

• Consider use of Railway Works order if reopening closed lines

Page 107: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager
Page 108: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager
Page 109: LEVEL CROSSING PROJECT - Engineers Ireland · level crossing project as part of the railway safety programme presented by conor mcguinness senior projects manager