Levels of Portfolio Management in a Lean Software Enterprise

@ Cloud 2011/Q2 review14.6.2011

Jarno Vähäniitty ([email protected])Software Process Research GroupSoberIT

To see all Aalto WP2 results per quarter, Google for

”Aalto WP2 results”

Five topic alternatives for today:

• “Levels of portfolio management in a lean software enterprise” (10 votes)

• ”How the product backlog really works - results from a systematic study of research and practitioner literature” (8 votes)

• “Towards agile product and portfolio management” (5)• “Backlog management tool requirements for the lean

software enterprise” (2)• “Transparent collaboration and progress follow-up of

research themes in Aalto WP#2 using Agilefant” (1)

Audience demographics

• Please raise your hand if…– You are a university-paid researcher– You are an industrial participant

Overview of this ”collaboration thread”

Cloud Software Program2011 Deliverable:

BP for Scaling Agile

Collaboration Thread:

Linking Strategy with Action in Lean/agile R&D OrganizationsJarno Vähäniitty

Publication:

”Towards Agile Product and Portfolio Management” (Ph.D. Jarno Vähäniitty, submitted to preliminary examination 6/2011)

Aalto University

Software Process Research Group (SPRG)

Focus area:

Software Product Management

Publication:

”Blind Men and the Product Backlog” Submission to Journal of Empirical Software Engineering in Q3-Q4/2011

Presentation:

”Levels of Portfolio Management in a Lean Software Enterprise” (Q2/2011 review)

Today

For all results by Aalto WP2 per quarter, Google for

”Aalto WP2 results”

WP#2:

Lean Software Enterprise

”Cloud Makes R&D Harder”

The Product Backlog – Far From Simple!

“Product backlog as a prioritized, constantly emerging list of work” (Ambler 2008b)

The Product Backlog – Far From Simple!

Sections in the product backlog, adapted from (Schiel 2009)

The Product Backlog – Far From Simple!T

he product planning iceb

erg, adapted from

(K

eith 2010) – w

ho got it from (C

ohn 2

009)

Blind Men and the Product Backlog• ”It is a …”

– List of ”everything that needs to be done”• but idea pool kept separate

– Transcends any single release; sections:• Ongoing iteration• Up next• Ongoing release• Future releases

– Prioritized & elaborated just-in-time• Driven by vision => product & business goals• Ongoing iteration / Immediate future

– Ordered sequentially– Estimated in man-hours

• Further ahead– Estimated in abstract units– Order ”less sequential”

• A flat list … and a hierarchy!

“Product roadmap” = a View of the High Level Goals in PBL

(Vähäniitty 2011)

Planning levels in Agile SW Development(S

mits 20

07, Cohn 200

5)

Planning Levels and Work Item Hierarchy(V

ähäniitty 2011

)

Levels of Portfolio Management in a Lean Software Enterprise

(Vähäniitty 2011)

Portfolio Management as Business Level Investment Setting

Mail59 %

Picasa23 %

Reader10 %

Wave8 %

Portfolio Management as High Level Goal Setting

Portfolio Management as Project Resourcing Decisions

Adapted from (Shalloway 2009)

Feature A1

Feature B1

Feature C1

Feature D1

Project A

Project B

Project C

Project D

Feature A2

Feature A3

Feature A4

Feature A5

Feature A6

Feature B2

Feature B3

Feature B4

Feature C2

Feature C3

Feature C4

Feature C5

Feature D2

Feature D3

Feature D4

Time

Levels of Portfolio Management in a Lean SW Enterprise(Vähäniitty 2011)

Levels of Portfolio Management in a Lean SW Enterprise(Vähäniitty 2011)