LHC Data Challenges and Physics Analysis
Jim ShankJim Shank
Boston UniversityBoston University
VI DOSAR WorkshopVI DOSAR Workshop
16 Sept., 200516 Sept., 2005
J. Shank VI DOSAR Workshop 16 Sept. 2005 J. Shank VI DOSAR Workshop 16 Sept. 2005 2
Overview
• I will concentrate on ATLAS, with some CMSI will concentrate on ATLAS, with some CMS
• ATLAS Computing timelineATLAS Computing timeline
• ATLAS Data Challenge 2ATLAS Data Challenge 2
• CMS DC04CMS DC04
• The LHC Service ChallengesThe LHC Service Challenges
• Distributed AnalysisDistributed Analysis• PanDA
• ATLAS Computing System CommissioningATLAS Computing System Commissioning
J. Shank VI DOSAR Workshop 16 Sept. 2005 J. Shank VI DOSAR Workshop 16 Sept. 2005 3
ATLAS Computing Timeline2003 • POOL/SEAL release (done)
• ATLAS release 7 (with POOL persistency) (done)
• LCG-1 deployment (done)
• ATLAS complete Geant4 validation (done)
• ATLAS release 8 (done)
• DC2 Phase 1: simulation production (done)
• DC2 Phase 2: intensive reconstruction (only partially done…)
• Combined test beams (barrel wedge) (done)
• Computing Model paper (done)
• Computing Memoranda of Understanding (ready for signatures)
• ATLAS Computing TDR and LCG TDR (done)
• Computing System Commissioning
• Physics Readiness Report
• Start cosmic ray run• GO!
2004
2005
2006
2007
J. Shank VI DOSAR Workshop 16 Sept. 2005 J. Shank VI DOSAR Workshop 16 Sept. 2005 4
ATLAS Production Runs (2004-2005)
Grid ProductionGrid Production WorldwideWorldwide U.S.U.S. U.S. Tier 2U.S. Tier 2
Jobs (k)Jobs (k) Events (M)Events (M) Jobs (k)Jobs (k) Events (M)Events (M) Percentage of U.S. Jobs Percentage of U.S. Jobs
done by three U.S. T2 done by three U.S. T2
sitessites
Data Challenge 2 Data Challenge 2
(DC2)(DC2)334334 8181 117117 2828 55%55%
Rome Physics Rome Physics
WorkshopWorkshop573573 2828 138138 77 60%60%
• Over 400 physicists attended Rome workshop, 100 papers presented based on the data produced during DC2 and Rome production
• Production during DC2 and Rome established a hardened Grid3 infrastructure benefiting all participants in Grid3
J. Shank VI DOSAR Workshop 16 Sept. 2005 J. Shank VI DOSAR Workshop 16 Sept. 2005 5
Rome Grid ProductionSuccessful Job Count at 83 ATLAS sites
Southwest T2
BNL T1
Boston T2
Midwest T2
J. Shank VI DOSAR Workshop 16 Sept. 2005 J. Shank VI DOSAR Workshop 16 Sept. 2005 6
U.S. Grid Production (Rome/DC2 combined)
20 different sites used in the U.S.
ATLAS Tier 2’s played dominant role
BNL T122%
Boston T220%
UM3%
UBuf2%
PSU3%
Southwest T224%
FNAL4%
PDSF4%
Midwest T213%
Other US sites (7)4%
UCSD1%
(3 sites)
(2 sites)
J. Shank VI DOSAR Workshop 16 Sept. 2005 J. Shank VI DOSAR Workshop 16 Sept. 2005 7
ATLAS Production on Grid3
<Capone Jobs/day> = 350
Max # jobs/day = 1020
US ATLAS dominated all other VOs in use of Grid3
2004 2005
8
CMS
Data
and
Service
Challenges
• CMS is organizing a series of Data Challenges and participating in the LCG service challengesCMS is organizing a series of Data Challenges and participating in the LCG service challenges
Each is a step in the preparation for the start LHC data takingEach is a step in the preparation for the start LHC data taking Data Challenge 2004 (DC04) was the first opportunity to test all the components of reconstruction, data transfer and
registration in a real-time environment
Goal was for 25Hz of reconstruction and transfer of events to Tier-1 centers for archivingGoal was for 25Hz of reconstruction and transfer of events to Tier-1 centers for archiving
First of the LCG Service Challenges started in FY05First of the LCG Service Challenges started in FY05 Transfer data from disk to disk from CERN to Tier-1 centers
Second LCG Service Challenge Second LCG Service Challenge Transfer data using
Service Challenge 3 is in progress
Use experiment services to demonstrate the functionality of the Tier-0, Tier-1 and Tier-2 services Use experiment services to demonstrate the functionality of the Tier-0, Tier-1 and Tier-2 services
simultaneously simultaneously Transfer, Publishing and Verify Consistency of data, Run example analysis jobs against transferred data
J. Shank VI DOSAR Workshop 16 Sept. 2005 J. Shank VI DOSAR Workshop 16 Sept. 2005 9
J. Shank VI DOSAR Workshop 16 Sept. 2005 J. Shank VI DOSAR Workshop 16 Sept. 2005 10
J. Shank VI DOSAR Workshop 16 Sept. 2005 J. Shank VI DOSAR Workshop 16 Sept. 2005 11
J. Shank VI DOSAR Workshop 16 Sept. 2005 J. Shank VI DOSAR Workshop 16 Sept. 2005 12
SC3
Service Challenges – ramp up to LHC start-up
SC2
LHC Service OperationFull physics run
2005 20072006 2008
first physicsfirst beams
cosmics
June05 - Technical Design Report
Sep05 - SC3 Service Phase
May06 – SC4 Service Phase
Sep06 – Initial LHC Service in stable operation
SC4
SC2 – Reliable data transfer (disk-network-disk) – 5 Tier-1s, aggregate 500 MB/sec sustained at CERNSC3 – Reliable base service – most Tier-1s, some Tier-2s – basic experiment software chain – grid data throughput 500 MB/sec, including mass storage (~25% of the nominal final throughput for the proton period)SC4 – All Tier-1s, major Tier-2s – capable of supporting full experiment software chain inc. analysis – sustain nominal final grid data throughputLHC Service in Operation – September 2006 – ramp up to full operational capacity by April 2007 – capable of handling twice the nominal data throughput
Apr07 – LHC Service commissioned
Jon Bakken DOE/NSF-2005 Review March 3, 2005 13
Service Challenge 1SC1 was an extremely valuable system integration exercise
It showed that the currently deployed system has a high degree of usability.
•SC1 demonstrated a 10x higher throughput (25 TB/day WAN) than prior use in fairly realistic deployment [c.f. CDF LAN rate is ~30 TB/day]
Many problems exposed due to high number of transfers and high rate. Problems were fixed, or new features added or system redesigned, before proceeding with tests
Rate results:• Using a fully integrated system, rate - 300 MB/sec, CERN to FNAL, disk to
disk
• Using dcache-java-class gridftp script - 500 MB/sec, no disk at FNAL
• Using dcache-java-class gridftp script - 400 MB/sec, to dCache disks
• 20 parallel streams per transfer, each with 2 MB buffers is optimal tune
These transfer rates were only possible using the Starlight research networks.
Jon Bakken DOE/NSF-2005 Review March 3, 2005 14
Service Challenge 1Data written in SC1 by srmcp transfers in November
2004.
Jon Bakken DOE/NSF-2005 Review March 3, 2005 15
Service Challenge IIContinue the goal of making transfers robust and reliable, understand
and fix problems rather than just restart
Only use SRM managed transfers to FNAL dCache pools using 3rd party gridftp transfers. No special/contrived transfer scripts.
Continue to use the deployed CMS dCache infrastructure and the Starlight network links. Real data transfers have to coexist with users, service challenge should do so as well. This exposed many bugs in SC1.
Sustain 50 MB/s to tape from CERN to FNALTransfer ~10 MB/s of user data from Castor to tape at FNAL ~5 tapes/dayTransfer 40 MB/s of fake data from CERN OPLAPRO lab to FNAL tape, but recycle tapes quickly
•Use PhEDEx for both user and fake data transfers - Exercising PhEDEx and making it a robust tool is a goal of SC2
Plan to participate in of 500 MB/s SRM managed transfers to CMS's resilient or volatile pools over the Starlight network links.
Jon Bakken DOE/NSF-2005 Review March 3, 2005 16
Service Challenge IIUSCMS Tier 1 to Tier 2 Complement of SC2
•US CMS Tier 2 sites want some of the data we are transferring. Plan on delivering these data sets to them as part of this challenge also using PhEDEx
•Initially expect low rate to each, to 3-4 Tier 2 sites•End-to-end functionality test of many components•Rate can grow as Tier 2 can accept data
•UF, UCSD and Caltech Tier 2s already have resilient dCache + SRM deployed. Each site is installing PhEDEx daemons.
•Will use PhEDEx for these transfer as well.
•Tier 2 sites do not have MSS, only disk cache, relatively cheap disk. The Tier 1 to Tier 2 operations are being investigated.
17
US ATLAS Tier 1 SC3 Performance
Plots and statistics taken fromPlots and statistics taken from BNL: Zhao and Yu
CERN: Casey and Shiers
Primary members of BNL teamPrimary members of BNL team Zhao, Liu, Deng, Yu, Popescu
18
Service Challenge 3 (Throughput Phase)
Primary goals: Primary goals: Sustained 150MB/s disk (T0) – disk (T1) transfers
Sustained 60MB/s disk (T0) – tape (T1) transfers
Secondary goal:Secondary goal: A few named T2 sites (T2 <=> T1) transfers at a few MB/s
Participating US ATLAS Tier 2 Sites Boston University University of Chicago Indiana University University of Texas Arlington
19
SC3 Services (and some issues)
Storage Element – Storage Element – US ATLAS production dCache US ATLAS production dCache systemsystem dCache/SRM (V1.6.5-2, with SRM 1.1 interface) Total 332 nodes with about 170 TB disks Multiple GridFTP, SRM, and dCap doors
Network to CERN Network to CERN Network for dCache at 2 x 1Gb/sec => OC48 (2.5 Gb/sec) WAN Shared link to CERN with Round Trip Time: >140 ms
RTT for European sites to CERN: ~ 20ms.
Occasional packet losses observed along BNL-CERN path which limited single stream throughput
1.5 Gb/s aggregated bandwidth observed by iperf with 160 TCP streams.
20
Disk to Disk Transfer Plot
DailyDaily
21
Disk to Disk Transfer Rates
Site Daily Average (MB/s)
ASCC 10
BNL 107
FNAL 185
GRIDKA 42
IN2P3 40
INFN 50
NDGF 129
PIC 54
RAL 52
SARA 111
TRIUMF 34
22
Disk to Disk Transfer Plot
23
Disk to Disk Transfer Plots Castor2 LSFCastor2 LSF
plug-in problemplug-in problem
Data routed through Data routed through GridFTP doorsGridFTP doors
24
Transfer component parameter Transfer component parameter settings influence successful settings influence successful transfer completions (timeouts, etc.)transfer completions (timeouts, etc.)
150 MB/sec rate achieved for one 150 MB/sec rate achieved for one hour with large numbers (> 50) of hour with large numbers (> 50) of parallel file transfers. CERN FTS parallel file transfers. CERN FTS original limit of 50 files per channel original limit of 50 files per channel was not enough to fill CERNwas not enough to fill CERN BNL BNL data channeldata channel
Data Transfer Status
25
Disk (T0) to Tape (T1) Transfer Plot
Sustained operation at target 60 MB/sec was achieved but Sustained operation at target 60 MB/sec was achieved but
glitches, primarily with tape HSM (HPSS), resulted in glitches, primarily with tape HSM (HPSS), resulted in
periods of stopped or reduced transfer periods of stopped or reduced transfer
26
Aggregate Disk to Disk Tier 2 Transfers
While average aggregate transfer to 4 sites at ~16 MB/sec While average aggregate transfer to 4 sites at ~16 MB/sec
was achieved (~4 MB/sec per site, meeting goal) Tier 2 was achieved (~4 MB/sec per site, meeting goal) Tier 2
availability limited consistencyavailability limited consistency
J. Shank VI DOSAR Workshop 16 Sept. 2005 J. Shank VI DOSAR Workshop 16 Sept. 2005 27
PanDA
• US ATLAS Production and Distributed AnalysisUS ATLAS Production and Distributed Analysis• Based on experience of DC2: redesign of job submission on the grid
• Very actively being worked on now, with aggressive schedule
• Integrates components that were separate in DC2• Distributed Data Management• Production (job submission/Workload management)• Distributed Analysis
J. Shank VI DOSAR Workshop 16 Sept. 2005 J. Shank VI DOSAR Workshop 16 Sept. 2005 28
J. Shank VI DOSAR Workshop 16 Sept. 2005 J. Shank VI DOSAR Workshop 16 Sept. 2005 29
J. Shank VI DOSAR Workshop 16 Sept. 2005 J. Shank VI DOSAR Workshop 16 Sept. 2005 30
ATLAS Computing System Commissioning
• Starts Early 2006Starts Early 2006
• Will test complete end-end ATLAS computing infrastructureWill test complete end-end ATLAS computing infrastructure• Including some key components missing from DC2:
• Scale: Production comparable to DC2