lhc status and plans

31
LHC Status and Plans Eric Prebys Fermi National Accelerator Laboratory Director, US LHC Accelerator Research Program (LARP) 1/10/2012

Upload: ouida

Post on 23-Feb-2016

77 views

Category:

Documents


0 download

DESCRIPTION

LHC Status and Plans. Eric Prebys Fermi National Accelerator Laboratory Director, US LHC Accelerator Research Program (LARP). Outline. Background and overview Current status Near term plans Long term plans US role - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: LHC Status and Plans

LHC Status and PlansEric PrebysFermi National Accelerator LaboratoryDirector, US LHC Accelerator Research Program (LARP)

1/10/2012

Page 2: LHC Status and Plans

Outline Background and overview Current status Near term plans Long term plans US role

Note: as usual, this workshop takes place just before the annual LHC Performance Workshop (Chamonix, Feb 6-10, 2012), so some things will be a lot more concrete in a few weeks.

1/10/2012Eric Prebys - CMS Data Analysis School 2

Page 3: LHC Status and Plans

A Word about LARP The US LHC Accelerator Research Program (LARP) coordinates

US R&D related to the LHC accelerator and injector chain at Fermilab, Brookhaven, SLAC, and Berkeley (with a little at J-Lab and UT Austin)

LARP has contributed to the initial operation of the LHC, but much of the program is focused on future upgrades.

The program is currently funded ata level of about $12-13M/year, dividedamong: Accelerator research Magnet research Programmatic activities, including support

for personnel at CERN Ask me about the Toohig Fellowship!

(I’m not going to say much specifically about LARP in this talk)

NOT to be confused with this “LARP” (Live-Action Role Play), which has led to some interesting emails

“Dark Raven”

1/10/2012 3Eric Prebys - CMS Data Analysis School

Page 4: LHC Status and Plans

Evolution of the Energy Frontier

~a factor of 10 every 15 years

1/10/2012 4Eric Prebys - CMS Data Analysis School

Page 5: LHC Status and Plans

LHC Layout

8 crossing interaction points (IP’s) Accelerator sectors labeled by which points they go between

ie, sector 3-4 goes from point 3 to point 41/10/2012 5Eric Prebys - CMS Data Analysis School

Page 6: LHC Status and Plans

Nominal LHC Parameters Compared to Tevatron

Parameter Tevatron “nominal” LHC

Circumference 6.28 km (2*PI) 27 kmBeam Energy 980 GeV 7 TeVNumber of bunches 36 2808Protons/bunch 275x109 115x109

pBar/bunch 80x109 -Stored beam energy

1.6 + .5 MJ 366+366 MJ*

Magnet stored energy

400 MJ 10 GJ

Peak luminosity 3.3x1032 cm-2s-1

1.0x1034 cm-2s-1

Main Dipoles 780 1232Bend Field 4.2 T 8.3 TMain Quadrupoles ~200 ~600Operating temperature

4.2 K (liquid He)

1.9K (superfluid He)

*Each beam = TVG@150 km/hr very scary numbers

1.0x1034 cm-2s-1 ~ 50 fb-1/yr= ~5 x total TeV data

Increase in cross section of up to 5 orders of magnitude for some physics processes

1/10/2012 6Eric Prebys - CMS Data Analysis School

Page 7: LHC Status and Plans

Reminder: “The Incident”Nine days after the 2008 startup, a quench developed into an arc, causing a great deal of Helium to boilThe resulting pressure did a great deal of damage, and kept the machine off for more than a year.

Beam Screen (BS) : The red color is characteristic of a clean copper

surface

BS with some contamination by super-isolation (MLI multi layer

insulation)

BS with soot contamination. The grey color varies depending on the thickness of the soot, from grey to

dark.

1/10/2012 7Eric Prebys - CMS Data Analysis School

Secondary arcs

Debris in beam vacuum pipe

Clean Insulation Soot

Page 8: LHC Status and Plans

Issues related to “The Incident” Bad joints

Test for high resistance and look for signatures of heat loss in joints

Warm up to repair any with signs of problems (additional three sectors)

Quench protection Old system sensitive to 1V New system sensitive to .3 mV (factor >3000)

Pressure relief Warm sectors (4 out of 8)

Install 200mm relief flanges Enough capacity to handle even the maximum credible incident

(MCI) Cold sectors

Reconfigure service flanges as relief flanges Reinforce floor mounts Enough to handle what happened, but not worst case

Beam re-started on November 20, 2009 Still limited to 3.5 TeV/beam until joints fully repaired/rebuilt1/10/2012 8Eric Prebys - CMS Data Analysis School

Page 9: LHC Status and Plans

Digression: Making Luminosity For identical, Gaussian colliding beams, luminosity

is given by

1/10/2012Eric Prebys - CMS Data Analysis School 9

RfNnRNnfL

N

revbb

bbrev

*2

2

2

44Geometric factor, related to crossing angle.

Revolution frequency

Number of bunchesBunch size

Transverse beam

sizeBetatron

function at collision point

Normalized beam emittance

Ns)(

Recall:

Page 10: LHC Status and Plans

Limits to LHC Luminosity*

RNNnfL

N

bbbrev*4

Total beam current. Limited by:• Uncontrolled beam loss!• E-cloud and other instabilities

at IP, limited by• magnet technology• chromatic effects

Brightness, limited by

• Injector chain• Max. beam-beam

*see, eg, F. Zimmermann, “CERN Upgrade Plans”, EPS-HEP 09, Krakow

If nb>156, must turn on crossing angle…

1/10/2012 10Eric Prebys - CMS Data Analysis School

Rearranging terms a bit…

…which reduces this

Page 11: LHC Status and Plans

Important features of the focal region

1/10/2012Eric Prebys - CMS Data Analysis School 11

*

2*)(

ss

small * means large (aperture) at focusing triplet

s

distortion of off-momentum particles 1/* (affects collimation)

Page 12: LHC Status and Plans

Reminder: 2010 Performance Reached full bunch intensity

1.1x1011/bunch Can’t overstate how important this milestone is.

Peak luminosity: ~2x1032 cm-2s-1

1/10/2012Eric Prebys - CMS Data Analysis School 12

Enough to reach the 1 fb-1 goal in 2011

Page 13: LHC Status and Plans

Happy Surprises in 2010 Crossing angle not an issue

Able to commission bunch trains earlier than planned Discovered LHC can live with much higher beam-

beam tuneshift than was thought -> Can go to larger than nominal bunches!

Emittances smaller than expected Good quality control on field quality Leads to larger effective aperture -> smaller *

1/10/2012Eric Prebys - CMS Data Analysis School 13

Page 14: LHC Status and Plans

Major Questions at the 2011 Chamonix Run through 2012?

Luminosity will likely still be increasing Answer: Yes (no brainer)

Increase Energy to 4 or 4.5? Can get same Higgs reach with ~20% less luminosity 5 discovery over entire allowed mass region with 10 fb-1

Answer: Raising the energy was considered too risky in 2011, so stay at 3.5 and revisit at 2012 Chamonix

Is it worth pursuing the HL-LHC upgrade? Given the demonstrated performance of the LHC so far, it’s

not unlikely that it could reach 2-3x1034 cm-2-s-1 in more or less it’s current configuration (once final collimation system is in place).

It’s unlikely the experiments can live with much more that 5x1034.

Answer: Still need to pursue upgrades to reach desired integrated luminosity by 2030. Goal is 5x1034 leveled luminosity

1/10/2012Eric Prebys - CMS Data Analysis School 14

Page 15: LHC Status and Plans

The Energy Decision*

1/10/2012Eric Prebys - CMS Data Analysis School 15*S. Myers, Chamonix 2011

Page 16: LHC Status and Plans

General Plan for 2011 Push bunch intensity

Achieved nominal bunch intensity of >1.1x1011 much faster than anticipated. Remember: LNb

2

Rules out many potential accelerator problems Increase number of bunches

Gone to nominal number (at 50 ns) Lower * as far as possible At all points, must carefully verify

Beam collimation Beam protection Beam abort

Remember: TeV=1 week for cold repair LHC=3 months for cold repair

1/10/2012Eric Prebys - CMS Data Analysis School 16

Example: beam sweeping over abort

Page 17: LHC Status and Plans

Reminder: The Plan for 2011*

1/10/2012Eric Prebys - CMS Data Analysis School 17

*S. Myers, Chamonix 2011

Page 18: LHC Status and Plans

Reminder: The Goal for 2011

1/10/2012Eric Prebys - CMS Data Analysis School 18

*S. Myers, Chamonix 2011

Page 19: LHC Status and Plans

Actual 2011 Performance

Peak Luminosity: ~3.6x1033 cm-2s-1 (36% of nominal)

Integrated Luminosity: ~6.7 fb-1/experiment

1/10/2012Eric Prebys - CMS Data Analysis School 19

Tevatron Record

2011 Goal

Page 20: LHC Status and Plans

p-Pb Running Challenge: Common RF

frequency Velocities of two beams are the same -> momenta are slightly different Sit at slightly different equilibrium

orbits in the two rings Nevertheless, it worked

perfectly

1/10/2012Eric Prebys - CMS Data Analysis School 20

Page 21: LHC Status and Plans

Significant Achievments in 2011 Achieved ->nominal bunch intensity Achieved standard 1380 bunch operation (limit at

50 ns) Achieved operational *=1m

Probably the limit at this energy

1/10/2012Eric Prebys - CMS Data Analysis School 21

Page 22: LHC Status and Plans

Lingering Issue: UFO’s*• Since July 2010, 35 fast loss events led to a beam dump.

18 in 2010, 17 in 2011.Over the two years:

13 around MKIs.6 dumps by

experiments.1 at 450 GeV.

• Typical characteristics:• Loss duration: about 10

turns• Often unconventional loss

locations (e.g. in the arc)

• The events are believed to be due to (Unidentified) Falling Objects (UFOs)

Spatial and temporal loss profile of UFO on 23.08.2010

*T. Baer, Evian Operations Workshop

Page 23: LHC Status and Plans

• In 2011: 16,000 candidate UFOs below dump threshold found.

• Measured distribution of BLM signal is consistent with measured dust distribution in SM12/Bat113.

Linear dependency of UFO signal on particle volume shown by N. Fuster et al., IPAC’11, MOPS017.

Below Threshold UFOs

∝ 𝒙−𝟎.𝟗𝟐

4513 arc UFOs (≥cell 12) at 3.5 TeV with signal RS01 > 1∙10-3 Gy/s.

courtesy of J. M. Jimenez

∝ 𝒙−𝟎.𝟗𝟕

Page 24: LHC Status and Plans

Decrease of UFO rate from ≈10 UFOs/hour to ≈2 UFOs/hour.

Looks OK for 2012 and Beyond

UFO rate 2011

5242 candidate arc UFOs (≥ cell 12) during stable beams between 14.04. and 31.10.2011. Fills with at least 1 hour stable beams are considered. Signal RS04 > 2∙10-4 Gy/s.

TS #2(09. – 13.05.2011)

TS #3(04. – 08.07.2011)

1380 bunches

TS #4(29.08 – 02.09.2011)

25ns, 60b

Page 25: LHC Status and Plans

Questions for Chamonix Energy

Are we confident enough to go to 4 TeV? Bunch spacing

25 or 50 ns? Luminosity goals for 2012?

There’s a limit to how much higher they can go.

1/10/2012Eric Prebys - CMS Data Analysis School 25

Page 26: LHC Status and Plans

General plan for next few years Now:

Run at 3.5 or 4.0 TeV Push luminosity as high as possible

First Long Shutdown (LS1): ~2013 Fix all all joints Add dispersion collimation around IR3?

Second Long Shutdown (LS2): ~2017 Complete collimation system

Involves 11 T dipoles to make room for dispersion collimators at several IR’s

Reach (at least) nominal luminosity after that Collimation limit >5x1034 cm-2s-1

Hi Luminosity Shutdown: ~2021 Install large aperture, high field Nb3Sn quads Crab cavities? Enable leveled 5x1034 cm-2s-1 operation

1/10/2012Eric Prebys - CMS Data Analysis School 26

Page 27: LHC Status and Plans

LARP and HiLumi The upgrades of the LHC have been organized under the HL-

LHC project. A subset of those activities has been captured in the HiLumi-

LHC effort, partially funded by the European Union. It has been agreed that LARP should be coordinated with this

project HiLumi Work Packages:

WP1: Management WP2: Beam Physics and Layout WP3: Magnet Design WP4: Crab Cavity Design WP5: Collimation and Beam Losses WP6: Machine Protection WP7: Machine/Experiment Interface WP8: Environment & Safety

To facilitate this, we have begun to hold joint collaboration meetings Fall: Europe, Spring: US 1/10/2012

Significant LARP and other US Involvement

LARP will be involved if crystal or e-beam included

27Eric Prebys - CMS Data Analysis School

Page 28: LHC Status and Plans

Relevance of LARP to CERN Upgrade*

1/10/2012

(…)

Letter to Dennis Kovar, Head, DOE Office of High Energy Physics, 17-August-2010

*letter suggested at review 28Eric Prebys - CMS Data Analysis School

Page 29: LHC Status and Plans

Overall US Plan for LHC Upgrades

1/10/2012

Memo to DOE - Office of High Energy Physics

From HL-LHC project and US leaders of various labs.

May 30, 2011

Activities for upgrading LHC performance have been recently organized at CERN in the High Luminosity LHC project, HL-LHCi. This project is the natural interface for all studies carried out in the United States on the LHC upgrade, both inside LARP or within the various basic programs in each of the laboratories. The upgrade studies for the LHC are complemented by a similar project structure for the LHC Injector complex Upgrade (LIU).

(…) There is a general consensus on the fact that the main equipment/systems that US laboratories could provide for the HL-LHC project are:

1. Superconducting magnets for the high luminosity Interaction Regions, namely the low triplets and/or the dipole separators; the system may be completed with the TAS-TAN and other important equipment, similar to what was done for the special US contribution for the LHC project;

2. Superconducting crab cavities to be installed in the Long Straight Sections of the two high luminosity insertions; possibly this may include also the powering and control equipment that make the complete RF system;

3. Equipment for the collimation system capable to deal with new level of luminosity and beam intensity:

a. Different types of collimators that are capable of operating at room temperature or at cryogenic temperature.

b. 11 tesla – 11 meter long superconducting dipole to replace LHC main dipoles and make room for collimator in the LHC arc (cold zone).

This list is not exhaustive; other items (like special wires for long range beam-beam compensation, a high bandwidth transverse feedback system for the SPS, special beam diagnostics, etc…) may be added.

(…) i See document of the CERN Director for Accelerators & TechnologyDG-DAT-2010-005 (Rev) of 15 December 2010

LARP

non-LARP

29Eric Prebys - CMS Data Analysis School

Page 30: LHC Status and Plans

Scope and Limits of LARP The “R” in LARP is for “Research”

LARP is an R&D organization ~Fixed budget scope and schedule contingency Not really set up for major hard deliverables

Lumi monitor, although ultimately very successful, was a cautionary tale

Model: Promising LARP R&D will be used to motivate separately funded and monitored projects Primary candidates:

Final focus triplets Crab Cavities

Other possibilities SPS feedback? Hollow electron beam collimation?

1/10/2012 30Eric Prebys - CMS Data Analysis School

Page 31: LHC Status and Plans

Summary The startup of the LHC has been a phenomenal

success (for the most part) Nevertheless, achieving the physics goals mean

that serious planning for the future has already begun.

Further reading The LHC Coordination Page is a good place to start

http://lpc.web.cern.ch/lpc/ In addition to accelerator information, it has links to other

things. Evian Operations Workshop (December 12-14, 2011)

https://indico.cern.ch/conferenceDisplay.py?confId=155520

LHC Performance Workshop (will take place Feb 6-10, 2012) https://indico.cern.ch/conferenceDisplay.py?

confId=164089 Special thanks to all the people I stole slides from!1/10/2012Eric Prebys - CMS Data Analysis School 31