LHCB
# Stato generale di LHCb# Stato dei progetti italiani
# (RRB Aprile 2005)# Gestione overcosti MU e RICH Money-Matrix # profili di spesa CORE e CF
G. Martellotti - CSN1 – 5/4/2005
Stato generale LHCb
Summary
Detector construction globally progressing well, but few areas of concern
Sizable overcosts in the RICH and MUON systems
Beam pipe Production progressing, expected okay
Magnet Operating according to specification
Vertex Locator Vacuum system okay, detector production to start (tight)
Trigger Tracker Delay with OB2 sensors, critical
Inner Tracker Production starting, expected okay for installation
Outer Tracker Production ongoing, expected okay for installation
RICH1 First component in production, but very tight planning
RICH2 Pre-assembly progressing, okay for installation
PS/SPD Production ongoing, expected on time for installation
ECal & HCal Production completed, installation starting
Muon Detector MWPC: serious delay, possibly incomplete at start up
Warm magnetAl coils 6000 Amps Yoke 1500 tons∫Bdl = 4 Tm
Magnet
Commissioned Nov’04Magnetic field precision measurements performed
Vertex Locator
Assembly and testing of complete system @ NIKHEF until October ’05
Installation in UX85 November ‘05
Detectors
Detectors production to start – schedule is TIGHT
Plans for detectors :o Production of modules from
April ’05 until end ’05 o Alignment of complete half detectors
in test beam in April ’06o Installation in UX85 in Q3 ‘06
Outer Tracker production progressing smoothly
~ 40% of total
Heidelberg
WarsawNIKHEF
TT
IT
OT
~ 5 m
3 stationsStraw tubes
B
Silicon Tracker: Trigger Tracker TTFour planes with stereo angle 0o,±5o,0o
Sensors: CMS OB2 type, ~1000 piecesLong Kapton interconnect cables bring signals to the FE electronics outside acceptance
Status:o Due to additional CMS orders, delivery of LHCb sensors delayed by about
6 months to October ‘05!!o Need to evaluate production yield by August - discussion with CMS o Any further delay would jeopardize the readiness of the TT stationo Installation of TT in UX85 in July ‘06
PS+SPD 32 super modules
Assembly cradleSuper Module
ECAL chariots installed in UX85
HCAL chariots in UX85
Calorimetry
Construction in very advanced stage on schedule
Stato progetti “Italiani”
- RICH - Trigger- MUONI
HPD
• Preseries of 9 HPDs received and tested
• Difficulties in producing assemblies at VTT overcome
• Series production of HPDs at DEP starting (contract
signature imminent, side orders placed through RAL)
- monthly rate ~30 tubes
RICH
Photodetectors
RICH1
Magnetic Shield
Beam Pipe
Photodetectors
Spherical Mirror
Flat Mirror
Gas Enclosure
Readout Electronics
2 * 3 * 1 m3
2 Radiators : - Aerogel - C4F10 gas
Status:o Magnetic shield: in productiono Gas enclosure: PRR in Dec 04o Be Mirrors: waiting for prototype (in production) - severe delayo Other items: design work ongoing
Overall schedule very tightInstallation end ’05 Q3 ‘06(interleaved with beam pipe inst)
AEROGEL Milano
Pre-series production :6 liters (3 tiles 20x20x5 cm3) july 2004all within specifications n=1.029-1.031 at =400 nm
Final production : 4 liters now13 liters 30/9/2005 6 liters (spare) 31/12/2005 or later
PRR will be organized
RICH2
Spherical Mirror
Photon funnel+Shielding
Central Tube
Support Structure
Flat mirror
Status: Preassembly in hall 156 progressing Mounting of mirrors now Alignment of mirrors in hall 156 Transport and installation in UX85 in July ’05, followed by alignment check in-situ
Attivita` italiane nel RICH-2
Genova: supporti dei fotorivelatori : meccanica, raffreddamento, connessioni agli HPD
I test di ottobre hanno evidenziato alcune modifiche da apportare al progetto (es: anodizzazione nera del telaio) ma Genova riesce a stare nel budget attuale – non fa richieste ulteriori 2005
Milano: Schermi magnetici - globali: consegnati al CERN ottobre 2004 - locali (mumetal) : in corso di ottimizzazione Ottica (test, allineamento) Elettronica (HV, LV boards, isolamento mumetal)
Milano chiede lo sblocco del SJ per le board HV e LV (30 kE)
# Optical Transmitters- Single Channel - Multi Channel mezzanine boardThe prototypes are ready and tested.The Bit Error Rate has been preliminary tested at the level of 10-13.Mezzanine boards have been delivered to the users.Production is starting By June we will start testing the entire production.In September the mezzanines can be delivered
# Selection Boards
L0 Calorimeter Trigger (Bologna)
(Detect a local high ET cluster in ECAL or HCAL)
Selection Board
• Final prototype presently under construction.• Board expected in May. Test will start in June.• Start the production of 12 boards by January 2006.• Boards should be ready and tested in four months time.
Test station
Bologna chiede l’anticipo al 2005 di 60 kE per l’acquisto dei componenti
Time schedule
This is OK
Buying the components by Q3 or Q4 of 2005 …
… we will respect the schedule
IntegrazioneElettronicaGEM Stato produzione MWPC
MUON DETECTOR
(Cagliari, Ferrara, Firenze, LNF, Roma1+ Potenza, Roma2)
iron filter
M1 M2-M5
supporting structureelectronics&gas racks
chambers
beam plugs
Aluminiumsupporting
walls
iintegrationIntegrazione Mu
II Muon System Integration Review 7 october 2004
1. Support structures- General support structure for M2-M5; - Chamber support structures, including chamber installation and alignment
2. Installation, Access and Interfaces3. Chamber Interfaces and various Services
- Chamber Faraday Cage and interfaces;- Cabling and grounding;- Gas system distribution; - Cooling.
4. Organizational aspects
Review Panel:• Chairperson for the Review: Hans-Juergen Hilke• Engineering aspects: Claude Giraud • Access and Integration: Daniel Lacarrere• Interface to the beam pipe: Juan Knaster • Alignment issues: Christian Lasseur • Cabling and Grounding: Vincent Bobiller • Gas System aspects: Ferdinand Hahn• Cooling aspects: Daniel Gasser• Safety issues: Mario Da Silva• Schedule: Rolf Lindner
(mancanza di man power per l’integrazione di M1 tra il RICH e il preshower Annecy)
CHAMBER
Iron filter3
80
mm
24mm
75mm10mm
9mm
old wall
Nuove pareti di honeycomb Allum. per M1-M5 Gara conclusa (LNF)
secondo le aspettative (108 kE)
Balconies on support structure allow mounting the chambers at the required precision (±1 mm in R1). Different spacers under foot allow tuning of the
different heights
Chamber fixation & positioning
space for cabling
Light hooks on the top ensure chamber stability
Da completare entro l’anno con l’avanzo della gara delle pareti (25kE)
Front end on-chamber connections
SPBCARDIACOPB
LVPS regulator board
•Safety ground must be connected to FC through a low impedance path (copper braid)
•Faraday Cage is the chamber signal ground
Ground connection
LVPS connector
CARDIAC connector
Faraday cage
UX85 – Detector Area
LEFT SIDE RIGHT SIDEIP8
LHC RingCenter
ECAL
MAGNETCRYO
POINT 7
POINT 1
MF4
LHC BEAM AXIS
QRLSEQUENZA DI INSTALLAZIONEcryo line junction 6/5assemblaggio MF4assemblaggio ECAL installazione gantryassemblaggio HCAL installazione struttura mu 8/5RICH2 7-10/5pareti alluminio M2-M5 9-11/5misura campo magnetico cavi 11/5–2/6gas 10-12/5racks 10/5elettronica 11/5-4/6PSD/PS 11/5-6/6installazione camere dx 2-4/6beam pipe 5-6/6installazione camere sn 9-11/6LHC sector test 11/6parete alluminio M1 12/6camere M1 1-2/7chiusura area 4/7
HCAL
RICH2
1 wafer contiene: 800 CARIOCA, 400 DIALOG, 200 SYNC, 200 CARIOCAGEM
SYNC conteneva importanti modifiche CARIOCAGEM è una nuova versione del CARIOCA
Il Production run è stato lanciato il 20 MarzoI wafer saranno consegnati per la fine di Maggio
La gara per l’impacchettamento ed il test dei circuiti è attualmente in corso Apertura buste per la fine di Aprile.
Dall’ Engineering run:• Prodotti 6 wafers
Tutti i circuiti sono stati testati con esito positivo
(non era scontato)
Circuiti integrati (Cagliari + CERN)
Elettronica Mu
Front-end (Cagliari + Roma1/Potenza)
La gara per la produzione ed il test delle 8000 schede CARDIAC è in fase conclusiva (apertura buste questa settimana)
Per inizio Maggio una pre-produzione di circa 300 schede
Produzione di massa da Luglio a Dicembre(~2000 al mese)
Le Spark Protection Boards sono già prodotte
CARDIAC (MPWC)
CARDIAC x GEM
La produzione di chip e schede resta sul percorso critico e va coordinata con molta attenzione.
Stato schede Off-Detector IB (LNF):1) Prototipi finali in fase di assembleaggio (pre-produzione) (con nuova ACTEL
FPGA); 2) Gia` ricevuti i tipi 1 e 2; 3) Test in corso. Il sistema di test per la produzione e` in fase di assemblaggio
ODE (LNF): Sono in corso i test di validazione :• Test di Qualita` dei link ottici: OK • Misure di Clock jitter (out QPLL): entro specifiche; • Tests di trasmissione attraverso il GOL nessuna anomalia• DAQ link test: Trovate delle discrepanze rispetto alle specifiche del GOL
Necessarie modifiche sul layout della scheda.Resta da fare:1) Ripetere misure di jitter 2) Test sulla trasmissione I2C col nuovo SYNC3) Modifiche al progetto del controllore (triple voting)4) Modifiche al board layout per il QPLL4 5) Modifiche al board layout per GOL – VCSEL
Non si vedono problemi per la schedula di produzione
SB (Roma):Pronte per la produzione
GEM for M1 inner region(Cagliari, LNF)
The M1R1 detector figures: - 12 chambers constituted by two triple-GEM detectors (+3spares) - active area 20x24 cm2
- pad size: 1.x2.5 cm2 192 pad/chamber
The milestones of the project:
- Feb. 2004: LHCb-TB approves GEM for M1R1 - June 2004: 1st TDR draft ready - May-Dec 2004: final detector design
Carioca-GEM chip & Cardiac-GEM production sites preparation
- Feb. 2005: Engineering Detector Review (not originally planned) - Mar. 2005: TB approves GEM EDR
start material procurement - May 2005: start chamber production
Construction tools and procedureshave been defined
Construction is performed in clean room
Frames & components preparation
GEM framing
Chamber assembly
Coupling of the two chambers
12
34
5
6
7
Chamber quality control defind
Before the construction check - cathode and pad PCB - GEM foil
On assembled detector test - Gas chamber leakage - Gain uniformity with X-ray
FEE board: CARIOCA & Cardiac GEMCARIOCA-GEM get rid of tail cancellation + increase the gain (x 1.5)CARDIAC-GEM (new design) 3 prototype boards assembled
HV passive divider studied
GEM electronics
Non si vedono problemi per la schedula di produzione e installazione
tracking with Cosmic Rays
Stato produzione MWPC
Roma 2 test stand
Container in LNF (~100 ch.)
Total: 333 chambers (23 %) built and tested (at least gas or HV)
Updated 1.04124
5
100
41
23
40
200
271
146
205
197
94
0 50 100 150 200 250 300 350
PNPI1
PNPI2
LNF
Ferrara
Firenze
CERN
Cham bers
All sites are now in production close to nominal rates Slow startup of PNPI-2
Ci approntiamo a definire in dettaglio la preparazione e i test finali delle camere prima della installazione
1. In labs: FE electronics, LV and Faraday Cage assembled on chambers- Chambers equipped and tested as soon as CARDIAC boards will be available.2. Shipping of MWPCs: INFN chambers to CERN: in special trolleys3. at CERN: Storage about 200 m2 available. Chambers stored under gas flux. check no-damage in transportation: test FEE and last test with HV
Test sistematici di qualita` delle camere prodotte
Ai LNF i test procedono a pieno ritmo con le stazioni di Roma1 e Frascati (tutte le nuove camere M5R3, 40/40 sono OK)
A Ferrara e Firenze i test non sono ancora del tutto a regime. Solo parte delle camere sono state testate in sede e parte sono state spedite e testate a Roma2 e LNF. Ci si sta organizzando
- il tavolo di test con sorgente radioattiva di Roma2 sta ora a Ferrara - anche Firenze sta mettendo a punto un tavolo automatico di test.
3 ch/week now in LNF
Fi close to nominal rate
Fe at nominal rate
Last 8 weeks total average rate about 11 ch/week
M2-M5 completed
M1
Se LHC mantiene la schedula ufficiale e` possibile che alla partenza la stazione M1 sia solo parzialmente installata
Gestione overcosti MU e RICH # Money-Matrix
MoU RRB Spares CORE Spares "INST"
Aprile04 ovc
Common Fund 400 (6%) (5%)
CERN ( 3%) 200 650 (9%) * + 360 90 (13%)
INFN ( 71%) 4850 5450 (79%) * 130 + 600 220 230 (77%)
PNPI ( 8%) 560 430 (6%) (5%)
Brasil (18%) 1220 0
TOTAL FUND 6830 6930 130 + 960 220 320Underfund 620 0
CERN-Iron 4000 4000
TOTAL COST 11450 10930 11060 11890 12560
MU
FUNDING / COSTI (kCHF) CSN1 - Settembre 2004
Richiesta all’ INFN +1050 (compresi “spare / M&O-B”)
* + 110 special new cash for Russia, + 340 reshuffling from other saves
* + 600 new cash dalla contingenza
MoU RRB-April Now Cern 1000 (13%) 1186 1559 (16%) Italy 1000 (13%) 1000 1230 (12.5%) U.K. 5700 (74%) 6300 7018 (71.5%) Total 7700 8486 9807 reshuffling new money
# CSN1 di Ottobre 2004 (leggera revisione di costi rispetto a Settembre - risparmio su housing HPD / Genova)
Fondi aggiuntivi Cern + 373 (28%) OK necessari Italy + 230 (17%) (richieste INFN)rispetto U.K. + 718 (54%) (richieste PPARK) al MoU Total +1321
RICH
richiesta all’INFN + 230 kCHF
Richieste della CSN1 a LHCb dopo Assisi
1) al gruppo Mu: - Dimostrare in pieno la capacita` di produz. di MWPC - Stabilizzare la stima dei costi/contenere le spese 2) al management LHCb: Proporre una soluzione di collaborazione al problema degli underfunding / overcosti. In particolare per il rivelatore MU per cui il problema e` determinato in gran parte dalla inadempienza del Brasile
Stima extracosti Sett 2004 Oggi
Meccanica 330 possibile riduz (- 40 ?)GAS 180 conferma per MWPC
prob riduz per GEM (~25)Camere 550 confermatoElettronica (+ spare) 220 - 90 (al 20/12/04) Contingenza cabling 100 forse non tutta necess.Varie (GEM,PNPI,manP.) 120 sembrano confermate
TOTALE 1500 kCHF oggi sembra probabile una piccola riduzione (100-200?) le stime si sono stabilizzate
1) Richiesta al gruppo MU : # Produzione camere salto qualitativo # Contenere le spese / Stabilizzare la stima dei costi
costo funding underfund MoU 7450 6830 - 620Add. TDR 6980 - 150 Russia - 130 Cern new funds + 110 CF (nuova prop) + 20
Il gruppo Mu deve gestire gli unerdfunding/overcosti rimanenti
+ conting. INFN
2) Richiesta al Management LHCb:# proporre una soluzione di collaborazione
Nuova proposta di LHCb
Brasile - 1220 azzerato l’ effetto CF (gia` approvati) + 400 Brasile con intervento CF (nuova prop) + 820 di collaborazione (CF)
New cash INFN + 600 (dalla contingenza) gia` approvato + 130 (per spare / M&O-B)
L’ overcosto residuo da gestire nel gruppo Mu e` diventato (minore o uguale di) 1000 kCHF
funding MoU new prop. Costo under fund
Italia 4850 4850 Cern 200 310Russia 560 430Brasile 1220 -Com Fund - 1240
6830 8560 - 1730
Nuova situazione di partenza senza Brasile:
La richiesta attuale per il MU :
CERN + 185 + 220 (aumento spare “M&O-B”)
INFN + 815 + 595 forse non tutti necessari a seguito dell’ aggiornamento dei costi
(“contingenza” residua = 400)
La richiesta per il RICH :
CERN + 373 , UK + 718 (PPARK ???)INFN + 230
resta in sospeso in attesa di sviluppi con UK e delle trattative con USA – (S. Stone da BTeV)
MoU RRB Spares new CORE+IN Spares
Aprile04 Aprile05 ovc
Common Fund 400 1240 (14.5%) 840CERN ( 3%) 200 200+340 reshuffl 495 (~6%) -155CERN spec Russia 110 new m.PNPI ( 8%) 560 430 430 (~5%)INFN ( 71%) 4850 5450 130 6395 (<~75%) 595 220
Brasil (18%) 1220 0TOTAL FUND 6830 6930 130 8560 1280 220
Underfund 620 0
CERN-Iron 4000 4000
TOTAL COST 11450 10930 130 12560 12210 220
MUNuova tabella FUNDING / COSTI (kCHF)- Aprile 2005
Distribuzione extra costi (rispetto ad Aprile 2004)
ITEM Total Overcost INFN Overc+ Cern+CF Overc+ PNPI+
+ Spare INST+ INST CernSpec
+ INST spare Russia
MWPC material 2200 500 1820 350 380 150
Mechanics/Integration 280 330 200 140 80 190
Gas system MWPC 310 180 150 310 30Gas system GEM 40 60 40 60
GEM 60 40 60 40
HV system 410 410 -235 235
Tooling & assembl PNPI-1 530 530
Tooling & assembl PNPI-2 230 -60 170 -60 50 10
(60 for PNPI-2 from INTAS)
Chamber System 4060 1050 2700 680 820 370 540
Contingen MWPC / cabling 150 150
Electronics 2870 2750 120
Electronics spares 130 220 130 220
M.P. CERN 1my@40ksf/y 40 40
M.P. PNPI (at CERN) 1my 40 40
Iron in kind 4000 4000
Total 11060 1500 5580 1050 -235 4940 450 235 540
Dettaglio costi / overcosti MU e proposta di sharing Modifiche :
SPESE CORE INFN Necessita`/ Richieste nel 2005 e Spese rimandabili
Trigger-Bo : 60 kE (~ 75 kCHF Core) in autunno 2005 per i componenti delle schede per partire subito nel 2006. Tutto il resto nel 2006
RICH : Nel 2005 non servono fondi aggiuntivi (il grosso al 2007)
Rivelatore MU : i soldi per le camere servono ~ tutti nel 2005.Si puo` rimandare al 2006 la meccanica M1, la contingenza cabling, il grosso della HV e il GAS (questo perche’ la parte Cern + CF e` disponibile e copre le necessita` per il 2005) - Si chiede la riassegnazione dell’avanzo gara delle pareti (25 kE) per il completamento dei supporti
Elettronica MU : Si possono rimandare al 2006 i TELL1, una “piccola” parte del cabling e poco altro. Il grosso serve nel 2005. Il Cern sta mandando un ordine centralizzato per i Crate (e Marathon). La spesa INFN puo` essere rimandata al 2006. Si tratta di stabilire le modalita` di restituzione al Cern (lettera di impegno a pagare nel 2006…)
INFN CORE spending profile (kCHF)
<2003 2004 2005 2005 2006 2007 Total
Common Fund 1170 500 500 680 2850
Detector Mu 1416 669 460 150 600 3295
Electronics Mu 475 1800 425 400 3100
RICH 330 430 20 450 1230?
Trigger Calo 50 200 75 105 430
DAH 10 860 870
TOTAL 2586 1524 2900 650 + 500
1125 + 500
1310 + 680
11775
3295 (a Settembre era 3530)3100 contiene anche gli spare (130+220), non e` cambiato 1230 contiene 230 di overcosti del RICH (a Settembre erano 265)
altre richieste 2005
Spare transp
2004 2005
DETECTOR
CALO 1,318 785DAH 696 920MAGNET 600 -OTR - 456INFRASTRUCTURE 800 1,500MUON 100 100
TOTAL 3,514 3,761
COMMON F. expected spending (kCH) - October 04
Totale CF ricevuti nel 2004 : 13227 / 18746 kCHF (L’ Italia ha dato 1171 / 2850)
Cat A M&O Estimate for 2006
Estimated Category A M&O Costs for LHCb 2006Items kCHF
Detector related costs 281Secretariat 185On-Call communications 9On-line Computing 360Test Beams 45Laboratory Operations 45General Services 530Total 1455
2006 Budget Sharing
FUNDING AGENCY PhD % PhD 2005 Power Total Cat A Equivs Equivs. Share Share plus Power
BRAZIL 14 4.13% 60,088 12,389 72,478CERN 52 15.34% 223,186 CHINA 3 0.88% 12,876 2,655 15,531FRANCE IN2P3 47 13.86% 201,726GERMANY BMBF 10 2.95% 42,920GERMANY MPG 7 2.06% 30,044ITALY INFN 55 16.22% 236,062NETHERLANDS 17 5.01% 72,965POLAND 13 3.83% 55,796ROMANIA 4 1.18% 17,168 3,540 20,708RUSSIA 32 9.44% 137,345 23,615 160,960SPAIN 15 4.42% 64,381SWITZERLAND 16 4.72% 68,673UK 50 14.75% 214,602UKRAINE 4 1.18% 17,168 3,540 20,708TOTAL 339 1 1,455,000 45,739
Forecast Cat A M&O Budgets for 2007-2009
Estimated Category A M&O Costs for LHCb 2007 2008 2009Item kCHF kCHF kCHF
Detector related costs 967 967 967Secretariat 205 205 205On-Call communications 9 9 9On-line Computing 740 740 740Test Beams 40 25 25Laboratory Operations 35 35 35General Services 536 486 486Total 2532 2467 2467
Power 600 903 903Grand Total 3132 3370 3370