Agenda for tonight
• The Project Overview– Where are we at now?– What can we expect in the next 6 months? – Other updates
From last Meeting
• PCL provided all sub contractors with routes to access the site – exit at Carling not Parkdale
• PCL is installing signs to remind contractors they cannot park in Ruskin lot
• Submissions to City for traffic calming measures on Melrose – they intend to make the east side of Melrose no stopping for the duration of the re-location ambulance entrance on Melrose
What has been done so far?
Assessments of houses completed Moving Hydro Duct Bank on campus New ambulance entrance – Melrose New access to 190 Melrose completedWater filtration has started Upgrades to the Power Plant Work has started on Loading Docks
New ambulance entrance – Melrose – recent changes made to slope the side walk for easy access by stretchers
And what is next?
• New Ambulance Entrance in use as of July 2• Work internal to TOH (Linen, Processing)• Schedule revisions
– Same end dates (Jan 2018 for Tower; Fall 2019 for new entrance and project completion)
– But excavation for the Tower will start October 2015.
Other Items
• Parking lot on Ruskin will be resurfaced over the summer – Plan is to close part for 4 weeks and the entire lot
for 3 weeks– Will be flag men and others available to direct
patients to other parking lots– Start date is June 22, 2015