    PT. SEMEN TONASA INDONESIA

    PROJECT

    :

    :

    CONTRACTOR :

    LOCATION : PART NO. :

    DRAWING NO. :

    SCALE :

    :DATECLIENT

    2 x 35 MW TONASA COAL FIRED POWER PLANT

    PT. REKAYASA INDUSTRI

    BIRINGKASSI, PANGKEP, SOUTH SULAWESI, INDONESIA

    JULY 22, 2011

    RIGGING PLAN

    RIGGING ENGINEER SITE MANAGER

    H GUNAWAN

    PREPARED BY PT. GAKA KARYA ENGINEERING

    DIMENSIONS IN MILLIMETERS

    CONSTRUCTION MANAGER

    APPROVED. BY

    PT SEMEN TONASA

    SITE MANAGERCONSTRUCTION MANAGER

    S T

    RIGGING DEPARTMENT

    THINK SAFEDO SAFELY

    SAFETY FIRST

    G2001-HG-2.35-SS-1.1

    1 : 1

    / 4

    INSTALLATION STEEL STRUCTURE

    01

  • 8/3/2019 Lifting Sequence Boiler Steel Structure

    2/18

    PT. SEMEN TONASA INDONESIA

    PROJECT

    :

    :

    CONTRACTOR :

    LOCATION : PART NO. :

    DRAWING NO. :

    SCALE :

    :DATECLIENT

    2 x 35 MW TONASA COAL FIRED POWER PLANT

    PT. REKAYASA INDUSTRI

    BIRINGKASSI, PANGKEP, SOUTH SULAWESI, INDONESIA

    JULY 22, 2011

    RIGGING PLAN

    RIGGING ENGINEER SITE MANAGER

    H GUNAWAN

    PREPARED BY PT. GAKA KARYA ENGINEERING

    DIMENSIONS IN MILLIMETERS

    CONSTRUCTION MANAGER

    APPROVED. BY

    PT SEMEN TONASA

    SITE MANAGERCONSTRUCTION MANAGER

    S T

    START

    DATA MATERIAL1. DIMENSION

    2. WEIGHT

    RIGGING DEPARTMENTANALYZE AND PLANED ACTIVITY FOR

    LIFTING AND ERECTION WORK

    REFERENCE1. RIGGING BOOK

    2. EQUIP. MANUAL3. B30.24-2003 Safety Standard

    4. B30.21-2005 manually lever operated hoist5. Australian Standard, AS 3569--1989, Wire ropes6. Australian Standard, AS 2759--1985, Wire ropes

    7. NAVFAC P-307, June 20038. Construction Industry Crane Safety Summit, 2009

    NEED DUO CRANEYes

    No

    MONO CRANETAILING DESIGN

    JOB SAFETY ANALISYS

    Safe

    Risk

    FINISH

    Final Inspection byGKE & REKIN

    Prepare Final Report for ApprovaL

    Handover

    No

    Yes

    RIGGING PLAN

    ACTION

    CONTROL

    G2001-HG-2.35-SS-1.1

    1 : 1

    / 4

    INSTALLATION STEEL STRUCTURE

    01

  • 8/3/2019 Lifting Sequence Boiler Steel Structure

    3/18

    RIGGING PROCEDURE

    01. OBJECTIVERigging Study Steel Structure Component

    02. SCOPE OF APPLICATIONRigging study is describe the guidelines and operating step of lifting Steel Structure Componentat Boiler 2 x 35 MW TONASA COAL FIRED POWER PLANT Project.

    03. REFERENCE1. RIGGING BOOK

    2. EQUIP. MANUAL

    3. B30.24-2003 Safety Standard

    4. Australian Standard, AS 3569--1989, Wire ropes

    5. Australian Standard, AS 2759--1985, Wire ropes

    04. EQUIPMENTNo Equipment Qty Capacities Remark

    01 CRANE CRAWLER 1 unit 150 ton NEW

    02 CRANE CRAWLER 1 unit 80 ton NEW

    03 MOBILE CRANE 1 unit 45 ton NEW

    04 LOW BAD 1 unit

    05. RIGGING TOOLSNo Equipment Qty Capacities Remark

    01 Wire Sling 1.5 inch x 5.500m 4 pcs 17.7 ton

    02 Omega Type Shackle 4 pcs 10 ton

    03 Chain BLock 4 pcs 10 ton

    06. SAFETY REQUIREMENTSNo Equipment Qty

    01 Safety Barricade Red White 75 mtr

    02 Safety Cone 7 pcs

    PT. SEMEN TONASA INDONESIA

    PROJECT

    :

    :

    CONTRACTOR :

    LOCATION : PART NO. :

    DRAWING NO. :

    SCALE :

    :DATECLIENT

    2 x 35 MW TONASA COAL FIRED POWER PLANT

    PT. REKAYASA INDUSTRI

    BIRINGKASSI, PANGKEP, SOUTH SULAWESI, INDONESIA

    JULY 22, 2011

    RIGGING PLAN

    RIGGING ENGINEER SITE MANAGER

    H GUNAWAN

    PREPARED BY PT. GAKA KARYA ENGINEERING

    DIMENSIONS IN MILLIMETERS

    CONSTRUCTION MANAGER

    APPROVED. BY

    PT SEMEN TONASA

    SITE MANAGERCONSTRUCTION MANAGER

    S T

    G2001-HG-2.35-SS-1.1

    1 : 1

    / 4

    INSTALLATION STEEL STRUCTURE

    01

  • 8/3/2019 Lifting Sequence Boiler Steel Structure

    4/18

    START

    Steel Structure Component INSTALLATION

    Move Steel Structure Component by Trailer to Site

    Moving Preparation by Rigger Crew

    LAYDOWNACT

    IVITY

    Inspection Quality

    by QC & SafetyNo

    Yes

    Connected all Sling

    for LiftingPREPARINGACTIVITYINSITE

    Lifting Steel Structure Component

    Lifting Equipmentto Target Elevation

    From ELev. 0.000To ELev. 47.800

    Connected Steel Structure Component

    to Column by Bolt

    FINISH

    Cleaning Steel Structure Component

    PT. SEMEN TONASA INDONESIA

    PROJECT

    :

    :

    CONTRACTOR :

    LOCATION : PART NO. :

    DRAWING NO. :

    SCALE :

    :DATECLIENT

    2 x 35 MW TONASA COAL FIRED POWER PLANT

    PT. REKAYASA INDUSTRI

    BIRINGKASSI, PANGKEP, SOUTH SULAWESI, INDONESIA

    JULY 22, 2011

    RIGGING PLAN

    RIGGING ENGINEER SITE MANAGER

    H GUNAWAN

    PREPARED BY PT. GAKA KARYA ENGINEERING

    DIMENSIONS IN MILLIMETERS

    CONSTRUCTION MANAGER

    APPROVED. BY

    PT SEMEN TONASA

    SITE MANAGERCONSTRUCTION MANAGER

    S T

    ERECTIONACTIVITY

    Control Position of Steel Structure Component

    to be Lifted by Rigging Supervisor

    G2001-HG-2.35-SS-1.1

    1 : 1

    / 4

    INSTALLATION STEEL STRUCTURE

    01

  • 8/3/2019 Lifting Sequence Boiler Steel Structure

    5/18

    PT. SEMEN TONASA INDONESIA

    PROJECT

    :

    :

    CONTRACTOR :

    LOCATION : PART NO. :

    DRAWING NO. :

    SCALE :

    :DATECLIENT

    2 x 35 MW TONASA COAL FIRED POWER PLANT

    PT. REKAYASA INDUSTRI

    BIRINGKASSI, PANGKEP, SOUTH SULAWESI, INDONESIA

    JULY 22, 2011

    RIGGING PLAN

    RIGGING ENGINEER SITE MANAGER

    H GUNAWAN

    PREPARED BY PT. GAKA KARYA ENGINEERING

    DIMENSIONS IN MILLIMETERS

    CONSTRUCTION MANAGER

    APPROVED. BY

    PT SEMEN TONASA

    SITE MANAGERCONSTRUCTION MANAGER

    S T

    G2001-HG-2.35-SS-1.1

    1 : 500

    / 21

    INSTALLATION FOR STEEL STRUCTURE

    01

    EQUIPMENT:CRANE CRWLER 1 UNIT

    MOBILE CRANE 1 UNIT

    LOW BAD 1 UNIT

    TOOLS:OHMEGA SHACLE 4 UNIT

    WIRE SLING 1 INCH x 8.8 METER 4 PCS

    SECTION 1:1. Install firs column by rough terrain crane 45 ton.2. Install 2nd tier by crawler crane 80 ton.

    3. Completed steel structure 1st & 2nd tier by

    crawler crane 80 ton.

  • 8/3/2019 Lifting Sequence Boiler Steel Structure

    6/18

    PT. SEMEN TONASA INDONESIA

    PROJECT

    :

    :

    CONTRACTOR :

    LOCATION : PART NO. :

    DRAWING NO. :

    SCALE :

    :DATECLIENT

    2 x 35 MW TONASA COAL FIRED POWER PLANT

    PT. REKAYASA INDUSTRI

    BIRINGKASSI, PANGKEP, SOUTH SULAWESI, INDONESIA

    JULY 22, 2011

    RIGGING PLAN

    RIGGING ENGINEER SITE MANAGER

    H GUNAWAN

    PREPARED BY PT. GAKA KARYA ENGINEERING

    DIMENSIONS IN MILLIMETERS

    CONSTRUCTION MANAGER

    APPROVED. BY

    PT SEMEN TONASA

    SITE MANAGERCONSTRUCTION MANAGER

    S T

    G2001-HG-2.35-SS-1.1

    1 : 500

    / 21

    INSTALLATION FOR STEEL STRUCTURE

    01

    EQUIPMENT:CRANE CRWLER 1 UNIT

    MOBILE CRANE 1 UNIT

    LOW BAD 1 UNIT

    TOOLS:OHMEGA SHACLE 4 UNIT

    WIRE SLING 1 INCH x 8.8 METER 4 PCS

    SECTION 1:1. Install firs column by rough terrain crane 45 ton.2. Install 2nd tier by crawler crane 80 ton.

    3. Completed steel structure 1st & 2nd tier by

    crawler crane 80 ton.

  • 8/3/2019 Lifting Sequence Boiler Steel Structure

    7/18

    PT. SEMEN TONASA INDONESIA

    PROJECT

    :

    :

    CONTRACTOR :

    LOCATION : PART NO. :

    DRAWING NO. :

    SCALE :

    :DATECLIENT

    2 x 35 MW TONASA COAL FIRED POWER PLANT

    PT. REKAYASA INDUSTRI

    BIRINGKASSI, PANGKEP, SOUTH SULAWESI, INDONESIA

    JULY 22, 2011

    RIGGING PLAN

    RIGGING ENGINEER SITE MANAGER

    H GUNAWAN

    PREPARED BY PT. GAKA KARYA ENGINEERING

    DIMENSIONS IN MILLIMETERS

    CONSTRUCTION MANAGER

    APPROVED. BY

    PT SEMEN TONASA

    SITE MANAGERCONSTRUCTION MANAGER

    S T

    G2001-HG-2.35-SS-1.1

    1 : 500

    / 21

    INSTALLATION FOR STEEL STRUCTURE

    01

    EQUIPMENT:CRANE CRWLER 1 UNIT

    MOBILE CRANE 1 UNIT

    LOW BAD 1 UNIT

    TOOLS:OHMEGA SHACLE 4 UNIT

    WIRE SLING 1 INCH x 8.8 METER 4 PCS

    SECTION 2:1. Continue Install 2nd tier by crawler crane 80 ton.

    2. Completed steel structure 2nd tier by crawler

    crane 80 ton.

    3. Preparing material for 3rd tier.

  • 8/3/2019 Lifting Sequence Boiler Steel Structure

    8/18

    PT. SEMEN TONASA INDONESIA

    PROJECT

    :

    :

    CONTRACTOR :

    LOCATION : PART NO. :

    DRAWING NO. :

    SCALE :

    :DATECLIENT

    2 x 35 MW TONASA COAL FIRED POWER PLANT

    PT. REKAYASA INDUSTRI

    BIRINGKASSI, PANGKEP, SOUTH SULAWESI, INDONESIA

    JULY 22, 2011

    RIGGING PLAN

    RIGGING ENGINEER SITE MANAGER

    H GUNAWAN

    PREPARED BY PT. GAKA KARYA ENGINEERING

    DIMENSIONS IN MILLIMETERS

    CONSTRUCTION MANAGER

    APPROVED. BY

    PT SEMEN TONASA

    SITE MANAGERCONSTRUCTION MANAGER

    S T

    G2001-HG-2.35-SS-1.1

    1 : 500

    / 21

    INSTALLATION FOR STEEL STRUCTURE

    01

    EQUIPMENT:CRANE CRWLER 1 UNIT

    MOBILE CRANE 1 UNIT

    LOW BAD 1 UNIT

    TOOLS:OHMEGA SHACLE 4 UNIT

    WIRE SLING 1 INCH x 8.8 METER 4 PCS

    SECTION 2:1. Continue Install 2nd tier by crawler crane 80 ton.

    2. Completed steel structure 2nd tier by crawler

    crane 80 ton.

    3. Preparing material for 3rd tier.

  • 8/3/2019 Lifting Sequence Boiler Steel Structure

    9/18

    PT. SEMEN TONASA INDONESIA

    PROJECT

    :

    :

    CONTRACTOR :

    LOCATION : PART NO. :

    DRAWING NO. :

    SCALE :

    :DATECLIENT

    2 x 35 MW TONASA COAL FIRED POWER PLANT

    PT. REKAYASA INDUSTRI

    BIRINGKASSI, PANGKEP, SOUTH SULAWESI, INDONESIA

    JULY 22, 2011

    RIGGING PLAN

    RIGGING ENGINEER SITE MANAGER

    H GUNAWAN

    PREPARED BY PT. GAKA KARYA ENGINEERING

    DIMENSIONS IN MILLIMETERS

    CONSTRUCTION MANAGER

    APPROVED. BY

    PT SEMEN TONASA

    SITE MANAGERCONSTRUCTION MANAGER

    S T

    G2001-HG-2.35-SS-1.1

    1 : 500

    / 21

    INSTALLATION FOR STEEL STRUCTURE

    01

    EQUIPMENT:CRANE CRWLER 1 UNIT

    MOBILE CRANE 1 UNIT

    LOW BAD 1 UNIT

    TOOLS:OHMEGA SHACLE 4 UNIT

    WIRE SLING 1 INCH x 8.8 METER 4 PCS

    SECTION 3:1. Continue Install 2nd and 3rd tier by crawler

    crane 80 ton.

    2. Completed steel structure 2nd and 3rd tier by

    crawler crane 80 ton.

    3. Preparing material for 4th tier.

  • 8/3/2019 Lifting Sequence Boiler Steel Structure

    10/18

    PT. SEMEN TONASA INDONESIA

    PROJECT

    :

    :

    CONTRACTOR :

    LOCATION : PART NO. :

    DRAWING NO. :

    SCALE :

    :DATECLIENT

    2 x 35 MW TONASA COAL FIRED POWER PLANT

    PT. REKAYASA INDUSTRI

    BIRINGKASSI, PANGKEP, SOUTH SULAWESI, INDONESIA

    JULY 22, 2011

    RIGGING PLAN

    RIGGING ENGINEER SITE MANAGER

    H GUNAWAN

    PREPARED BY PT. GAKA KARYA ENGINEERING

    DIMENSIONS IN MILLIMETERS

    CONSTRUCTION MANAGER

    APPROVED. BY

    PT SEMEN TONASA

    SITE MANAGERCONSTRUCTION MANAGER

    S T

    G2001-HG-2.35-SS-1.1

    1 : 500

    / 21

    INSTALLATION FOR STEEL STRUCTURE

    01

    EQUIPMENT:CRANE CRWLER 1 UNIT

    MOBILE CRANE 1 UNIT

    LOW BAD 1 UNIT

    TOOLS:OHMEGA SHACLE 4 UNIT

    WIRE SLING 1 INCH x 8.8 METER 4 PCS

    SECTION 3:1. Continue Install 2nd and 3rd tier by crawler

    crane 80 ton.

    2. Completed steel structure 2nd and 3rd tier by

    crawler crane 80 ton.

    3. Preparing material for 4th tier.

  • 8/3/2019 Lifting Sequence Boiler Steel Structure

    11/18

    PT. SEMEN TONASA INDONESIA

    PROJECT

    :

    :

    CONTRACTOR :

    LOCATION : PART NO. :

    DRAWING NO. :

    SCALE :

    :DATECLIENT

    2 x 35 MW TONASA COAL FIRED POWER PLANT

    PT. REKAYASA INDUSTRI

    BIRINGKASSI, PANGKEP, SOUTH SULAWESI, INDONESIA

    JULY 22, 2011

    RIGGING PLAN

    RIGGING ENGINEER SITE MANAGER

    H GUNAWAN

    PREPARED BY PT. GAKA KARYA ENGINEERING

    DIMENSIONS IN MILLIMETERS

    CONSTRUCTION MANAGER

    APPROVED. BY

    PT SEMEN TONASA

    SITE MANAGERCONSTRUCTION MANAGER

    S T

    G2001-HG-2.35-SS-1.1

    1 : 500

    / 21

    INSTALLATION FOR STEEL STRUCTURE

    01

    EQUIPMENT:CRANE CRWLER 1 UNIT

    MOBILE CRANE 1 UNIT

    LOW BAD 1 UNIT

    TOOLS:OHMEGA SHACLE 4 UNIT

    WIRE SLING 1 INCH x 8.8 METER 4 PCS

    SECTION 4:1. Continue Install 3nd tier by crawler crane 80 ton.

    2. Completed steel structure 3rd tier by crawler

    crane 80 ton.

    3. Continue Install 4th tier by crawler crane 150 ton.

  • 8/3/2019 Lifting Sequence Boiler Steel Structure

    12/18

    PT. SEMEN TONASA INDONESIA

    PROJECT

    :

    :

    CONTRACTOR :

    LOCATION : PART NO. :

    DRAWING NO. :

    SCALE :

    :DATECLIENT

    2 x 35 MW TONASA COAL FIRED POWER PLANT

    PT. REKAYASA INDUSTRI

    BIRINGKASSI, PANGKEP, SOUTH SULAWESI, INDONESIA

    JULY 22, 2011

    RIGGING PLAN

    RIGGING ENGINEER SITE MANAGER

    H GUNAWAN

    PREPARED BY PT. GAKA KARYA ENGINEERING

    DIMENSIONS IN MILLIMETERS

    CONSTRUCTION MANAGER

    APPROVED. BY

    PT SEMEN TONASA

    SITE MANAGERCONSTRUCTION MANAGER

    S T

    G2001-HG-2.35-SS-1.1

    1 : 500

    / 21

    INSTALLATION FOR STEEL STRUCTURE

    01

    EQUIPMENT:CRANE CRWLER 1 UNIT

    MOBILE CRANE 1 UNIT

    LOW BAD 1 UNIT

    TOOLS:OHMEGA SHACLE 4 UNIT

    WIRE SLING 1 INCH x 8.8 METER 4 PCS

    SECTION 4:1. Continue Install 3nd tier by crawler crane 80 ton.

    2. Completed steel structure 3rd tier by crawler

    crane 80 ton.

    3. Continue Install 4th tier by crawler crane 150 ton.

  • 8/3/2019 Lifting Sequence Boiler Steel Structure

    13/18

    PT. SEMEN TONASA INDONESIA

    PROJECT

    :

    :

    CONTRACTOR :

    LOCATION : PART NO. :

    DRAWING NO. :

    SCALE :

    :DATECLIENT

    2 x 35 MW TONASA COAL FIRED POWER PLANT

    PT. REKAYASA INDUSTRI

    BIRINGKASSI, PANGKEP, SOUTH SULAWESI, INDONESIA

    JULY 22, 2011

    RIGGING PLAN

    RIGGING ENGINEER SITE MANAGER

    H GUNAWAN

    PREPARED BY PT. GAKA KARYA ENGINEERING

    DIMENSIONS IN MILLIMETERS

    CONSTRUCTION MANAGER

    APPROVED. BY

    PT SEMEN TONASA

    SITE MANAGERCONSTRUCTION MANAGER

    S T

    G2001-HG-2.35-SS-1.1

    1 : 500

    / 21

    INSTALLATION FOR STEEL STRUCTURE

    01

    EQUIPMENT:CRANE CRWLER 1 UNIT

    MOBILE CRANE 1 UNIT

    LOW BAD 1 UNIT

    TOOLS:OHMEGA SHACLE 4 UNIT

    WIRE SLING 1 INCH x 8.8 METER 4 PCS

    SECTION 5:1. Continue Install 4th tier by crawler crane 150 ton.

    2. Completed steel structure 4th tier by crawler

    crane 150 ton.

    3. Continue Install 4th tier by crawler crane 150 ton.

    4. Install main girder by crawler crane 150 ton.

  • 8/3/2019 Lifting Sequence Boiler Steel Structure

    14/18

    PT. SEMEN TONASA INDONESIA

    PROJECT

    :

    :

    CONTRACTOR :

    LOCATION : PART NO. :

    DRAWING NO. :

    SCALE :

    :DATECLIENT

    2 x 35 MW TONASA COAL FIRED POWER PLANT

    PT. REKAYASA INDUSTRI

    BIRINGKASSI, PANGKEP, SOUTH SULAWESI, INDONESIA

    JULY 22, 2011

    RIGGING PLAN

    RIGGING ENGINEER SITE MANAGER

    H GUNAWAN

    PREPARED BY PT. GAKA KARYA ENGINEERING

    DIMENSIONS IN MILLIMETERS

    CONSTRUCTION MANAGER

    APPROVED. BY

    PT SEMEN TONASA

    SITE MANAGERCONSTRUCTION MANAGER

    S T

    G2001-HG-2.35-SS-1.1

    1 : 500

    / 21

    INSTALLATION FOR STEEL STRUCTURE

    01

    EQUIPMENT:CRANE CRWLER 1 UNIT

    MOBILE CRANE 1 UNIT

    LOW BAD 1 UNIT

    TOOLS:OHMEGA SHACLE 4 UNIT

    WIRE SLING 1 INCH x 8.8 METER 4 PCS

    SECTION 5:1. Continue Install 4th tier by crawler crane 150 ton.

    2. Completed steel structure 4th tier by crawler

    crane 150 ton.

    3. Continue Install 4th tier by crawler crane 150 ton.

    4. Install main girder by crawler crane 150 ton.

  • 8/3/2019 Lifting Sequence Boiler Steel Structure

    15/18

    PT. SEMEN TONASA INDONESIA

    PROJECT

    :

    :

    CONTRACTOR :

    LOCATION : PART NO. :

    DRAWING NO. :

    SCALE :

    :DATECLIENT

    2 x 35 MW TONASA COAL FIRED POWER PLANT

    PT. REKAYASA INDUSTRI

    BIRINGKASSI, PANGKEP, SOUTH SULAWESI, INDONESIA

    JULY 22, 2011

    RIGGING PLAN

    RIGGING ENGINEER SITE MANAGER

    H GUNAWAN

    PREPARED BY PT. GAKA KARYA ENGINEERING

    DIMENSIONS IN MILLIMETERS

    CONSTRUCTION MANAGER

    APPROVED. BY

    PT SEMEN TONASA

    SITE MANAGERCONSTRUCTION MANAGER

    S T

    G2001-HG-2.35-SS-1.1

    1 : 500

    / 21

    INSTALLATION FOR STEEL STRUCTURE

    01

    EQUIPMENT:CRANE CRWLER 1 UNIT

    MOBILE CRANE 1 UNIT

    LOW BAD 1 UNIT

    TOOLS:OHMEGA SHACLE 4 UNIT

    WIRE SLING 1 INCH x 8.8 METER 4 PCS

    SECTION 6:1. Completed steel structure 4th tier by crawler

    crane 150 ton.

    2. Install CycLone by crawler crane 150 ton. Tiling by

    Rough terrain crane 45 ton.

  • 8/3/2019 Lifting Sequence Boiler Steel Structure

    16/18

    PT. SEMEN TONASA INDONESIA

    PROJECT

    :

    :

    CONTRACTOR :

    LOCATION : PART NO. :

    DRAWING NO. :

    SCALE :

    :DATECLIENT

    2 x 35 MW TONASA COAL FIRED POWER PLANT

    PT. REKAYASA INDUSTRI

    BIRINGKASSI, PANGKEP, SOUTH SULAWESI, INDONESIA

    JULY 22, 2011

    RIGGING PLAN

    RIGGING ENGINEER SITE MANAGER

    H GUNAWAN

    PREPARED BY PT. GAKA KARYA ENGINEERING

    DIMENSIONS IN MILLIMETERS

    CONSTRUCTION MANAGER

    APPROVED. BY

    PT SEMEN TONASA

    SITE MANAGERCONSTRUCTION MANAGER

    S T

    G2001-HG-2.35-SS-1.1

    1 : 500

    / 21

    INSTALLATION FOR STEEL STRUCTURE

    01

    EQUIPMENT:CRANE CRWLER 1 UNIT

    MOBILE CRANE 1 UNIT

    LOW BAD 1 UNIT

    TOOLS:OHMEGA SHACLE 4 UNIT

    WIRE SLING 1 INCH x 8.8 METER 4 PCS

    SECTION 6:1. Completed steel structure 4th tier by crawler

    crane 150 ton.

    2. Install CycLone by crawler crane 150 ton. Tiling by

    Rough terrain crane 45 ton.

  • 8/3/2019 Lifting Sequence Boiler Steel Structure

    17/18

    PT. SEMEN TONASA INDONESIA

    PROJECT

    :

    :

    CONTRACTOR :

    LOCATION : PART NO. :

    DRAWING NO. :

    SCALE :

    :DATECLIENT

    2 x 35 MW TONASA COAL FIRED POWER PLANT

    PT. REKAYASA INDUSTRI

    BIRINGKASSI, PANGKEP, SOUTH SULAWESI, INDONESIA

    JULY 22, 2011

    RIGGING PLAN

    RIGGING ENGINEER SITE MANAGER

    H GUNAWAN

    PREPARED BY PT. GAKA KARYA ENGINEERING

    DIMENSIONS IN MILLIMETERS

    CONSTRUCTION MANAGER

    APPROVED. BY

    PT SEMEN TONASA

    SITE MANAGERCONSTRUCTION MANAGER

    S T

    G2001-HG-2.35-SS-1.1

    1 : 550

    / 21

    INSTALLATION FOR STEEL STRUCTURE

    01

    EQUIPMENT:CRANE CRWLER 1 UNIT

    MOBILE CRANE 1 UNIT

    LOW BAD 1 UNIT

    TOOLS:OHMEGA SHACLE 4 UNIT

    WIRE SLING 1 INCH x 8.8 METER 4 PCS

    SECTION 7:1. Completed install CycLone by crawler crane 150 ton.

    Tiling by Rough terrain crane 45 ton.

    2. Completed installation by crawler crane 150 ton and

    Rough terrain crane 45 ton.

    3. Preparing for steam drum lifting.

  • 8/3/2019 Lifting Sequence Boiler Steel Structure

    18/18

    PT. SEMEN TONASA INDONESIA

    PROJECT

    :

    :

    CONTRACTOR :

    LOCATION : PART NO. :

    DRAWING NO. :

    SCALE :

    :DATECLIENT

    2 x 35 MW TONASA COAL FIRED POWER PLANT

    PT. REKAYASA INDUSTRI

    BIRINGKASSI, PANGKEP, SOUTH SULAWESI, INDONESIA

    JULY 22, 2011

    RIGGING PLAN

    RIGGING ENGINEER SITE MANAGER

    H GUNAWAN

    PREPARED BY PT. GAKA KARYA ENGINEERING

    DIMENSIONS IN MILLIMETERS

    CONSTRUCTION MANAGER

    APPROVED. BY

    PT SEMEN TONASA

    SITE MANAGERCONSTRUCTION MANAGER

    S T

    G2001-HG-2.35-SS-1.1

    1 : 550

    / 21

    INSTALLATION FOR STEEL STRUCTURE

    01

    EQUIPMENT:CRANE CRWLER 1 UNIT

    MOBILE CRANE 1 UNIT

    LOW BAD 1 UNIT

    TOOLS:OHMEGA SHACLE 4 UNIT

    WIRE SLING 1 INCH x 8.8 METER 4 PCS

    SECTION 7:1. Completed install CycLone by crawler crane 150 ton.

    Tiling by Rough terrain crane 45 ton.

    2. Completed installation by crawler crane 150 ton and

    Rough terrain crane 45 ton.

    3. Preparing for steam drum lifting.