linac coherent light source (lcls) low level rf status
DESCRIPTION
Linac Coherent Light Source (LCLS) Low Level RF Status. Safety First and Second and Third…..to Infinity. Hazards in the LLRF system RF 1kW at 120Hz at 5uS = 0.6 Watts average, 2 Watt average amps at 2856MHz, 60W average amps at 476MHz Hazards – RF Burns / Cataracts - PowerPoint PPT PresentationTRANSCRIPT
Ron Akre, Dayle Kotturi
Lehman Review [email protected], [email protected]
October 24-26, 2006
Linac Coherent Light Source (LCLS)
Low Level RF Status
Ron Akre, Dayle Kotturi
Lehman Review [email protected], [email protected]
October 24-26, 2006
Safety First and Second and Third…..to Infinity
Hazards in the LLRF systemRF 1kW at 120Hz at 5uS = 0.6 Watts average, 2 Watt average amps at 2856MHz, 60W average amps at 476MHz
Hazards – RF Burns / CataractsMitigation – Avoid contact with center conductor of energized connectors. All employees working with LLRF systems are required to have the proper training.
110VAC ConnectorHazards - Shock Mitigation - Don’t touch conductors when plugging into outlet.All chassis are inspected by UL trained inspector.
Ron Akre, Dayle Kotturi
Lehman Review [email protected], [email protected]
October 24-26, 2006
Status of Hardware for Injector Turn-onLinac Sector 0 RF Upgrade
All 3 RF Chassis completed and Installed (Master Oscillator, Master Amp, PEP phase ShifterControl Module ready for test – higher phase noise levels if not installed
Sector 20 RF distribution systemPhase and Amplitude Controllers (PAC) – 5 unitsPhase and Amplitude Detectors (PAD) – 2 unitsPhased Locked Oscillator – Use SPPS unit for Turn OnLO Generator – Complete - 75% tested – looks good so farMultiplier – 476MHz to 2856MHz – Complete4 distribution chassis – Complete 102MHz, 2056MHz, 2830.5MHzLaser Phase Lock – Needs testing – Only high risk itemDistribution Amplifiers – 10W, 2850MHz due Oct 25, 102MHz Amp being built
LLRF Control and Monitor System1 kW Solid State S-Band Amplifiers – 5 units – Design Complete, In FabPAD – 12 units – 6 required for turn on PAC – 6 unitsBunch Length Monitor Interface – Will use PAD to collect data
Beam Phase CavityWill use 2 channels of PAD ChassisPill box cavity with 2 probes and 4 tuners – 2805MHz 3 units Complete
Ron Akre, Dayle Kotturi
Lehman Review [email protected], [email protected]
October 24-26, 2006
Status of Software for Injector Turn-onPAD Software
OperationalPAC Software
OperationalLocal Feedback (in VME)
Data analysis shows simple feedback algorithm will work.Optimization of algorithm continues.Time measurement: measure time needed for data acq, for transfer to VME, for VME processing, for transfer to PAC.Time measurement: needed for multiple local loops. Eg. Measure scalability from 1 to N instances.
RF Gun Temperature FeedbackIn Design
Calibration and TestOperational
High Level ApplicationsIn progress (This means we are working on specifications.)
Storing of boot params, serial numbers, etc in flash or on the board for PAD and PAC
Ron Akre, Dayle Kotturi
Lehman Review [email protected], [email protected]
October 24-26, 2006
Status of Documentation + Reviews
LLRF Control Design SpecificationThis Engineering Specification Document was signed off by Project Office on 9/27/2006.
LLRF Final Design ReviewThis review was held on 9/19/2006.The scope of the review covered:
RF Distribution Reference System for Injector Commissioning RF System for Injector Commissioning
PAD PAC VME
The goals of the review were: Injector turn on is January 3, 2007. The designs of the prototype PADs and PACs have been built and tested. Fabrication is scheduled for October, 2006. Please review analysis of test data and the proposed design and comment on the proposed systems' ability to meet LCLS specifications. Review our test plans and suggest improvements
Ron Akre, Dayle Kotturi
Lehman Review [email protected], [email protected]
October 24-26, 2006
LCLS Layout
P. Emma
Ron Akre, Dayle Kotturi
Lehman Review [email protected], [email protected]
October 24-26, 2006
LCLS RF Jitter Tolerance BudgetLCLS RF Jitter Tolerance Budget
RMS tolerance budget for <12% rms peak-current jitter or
<0.1% rms final e− energy jitter. All tolerances are rms levels and the voltage and
phase tolerances per klystron for L2 and L3 are Nk larger,
assuming uncorrelated errors, where Nk is the number of
klystrons per linac.
P. Emma
Lowest Noise Floor Requirement 0.5deg X-Band = 125fSStructure Fill time = 100nSNoise floor = -111dBc/Hz @ 11GHz 10MHz BW-134dBc/Hz @ 476MHz
X-bandX-band XX--
0.500.50
Ron Akre, Dayle Kotturi
Lehman Review [email protected], [email protected]
October 24-26, 2006
Slow Drift Tolerance LimitsSlow Drift Tolerance Limits
Gun-Laser TimingGun-Laser Timing 2.4*2.4* deg-Sdeg-S
Bunch ChargeBunch Charge 3.23.2 %%
Gun RF PhaseGun RF Phase 2.32.3 deg-Sdeg-S
Gun Relative VoltageGun Relative Voltage 0.60.6 %%
L0,1,X,2,3 RF Phase (approx.)L0,1,X,2,3 RF Phase (approx.) 55 deg-Sdeg-S
L0,1,X,2,3 RF Voltage (approx.)L0,1,X,2,3 RF Voltage (approx.) 55 %%
(Top 4 rows for (Top 4 rows for // < 5%, bottom 4 limited by feedback dynamic range) < 5%, bottom 4 limited by feedback dynamic range)
* for synchronization, this tolerance might be set to * for synchronization, this tolerance might be set to 1 ps (without arrival-time measurement)1 ps (without arrival-time measurement)
(Tolerances are peak values, not rms)(Tolerances are peak values, not rms) P. Emma, J, WuP. Emma, J, Wu
Ron Akre, Dayle Kotturi
Lehman Review [email protected], [email protected]
October 24-26, 2006
Linac Sector 0 RF Upgrade
PEP PHASE SHIFT ON MAIN DRIVE LINE MDL RF with TIMING Pulse – Sync to DR
Master Oscillator is located 1.3 miles
from LCLS Injector
1.3 Miles to LCLS Injector
LCLS must be compatible with the existing linac operation including PEP timing shifts
Measurements on January 20, 2006at Sector 21show 30fS rms jitter in a bandwidth from 10Hz to 10MHz
MASTERAMPLIFIERS
IQPAUPEP ControlCamac Module
MAIN LINAC (SECTOR 0) RF/TIMING SYSTEM
1
476MHz MASTEROSCILLATOR
PEP PHASE SHIFTER+-720 Degrees in 0.5mS
SLC COUNTDOWNCHASSIS 476MHzDivide to 8.5MHz
Master TriggerGenerator MTGSyncs Fiducial to8.5MHz Damping Ringand 360Hz Power Line
8.5MHz
360Hz LineSync.
476MHz
360Hz
Fiducial GeneratorSyncronized to:360Hz Power Line8.5MHz Damping Ring476MHz RF Distribution
SumFiducialto RF
Ron Akre, Dayle Kotturi
Lehman Review [email protected], [email protected]
October 24-26, 2006
RF Distribution Lab vs. MDL Measurements
John Byrd LBNL
LCLS Reference System Lab Measurements
20fS rms Jitter 10Hz to 10MHz
Existing Linac MDL Sector 0
126fS rms Jitter 10Hz to 10MHz
If PEP IQPAU Chassis is not commissioned we may not meet LCLS specifications
Ron Akre, Dayle Kotturi
Lehman Review [email protected], [email protected]
October 24-26, 2006
Sector 20 RF Distribution
LO and 102MHz resync by adjusting 2856MHz PAC while monitoring S21 2856MHz
Laser resync with laser PAC while monitoring difference in 119MHz laser and FIDO out
MDL from Sector 0
RF CONTROLSPAC
380-208-22476MHz to 2856MHzMULTIPLIER
2830.5MHz LO Gen
RF MONITORPAD
119MHz Phase
119MHz
RF HUT Coupler476MHz Ref. 80uW
LASERReference
4x 476MHz13dBm OUT
ExistingTIMING SYSTEMFIDO Output
LCLS 476MHz PLL120HzTRBR
+13dBm in
Track/HoldTRBR
2856MHz16 Way Distribution20dBm each
GunL0AL0BL0TCAVL1SL1X
+17dBm out
2856MHz10 Watt Amplifier
102MHz16 Way Dist22dBm each
476MHzLASER LOCKReference
119MHz0dBm OUT
LO Phase Monitor
102MHz5Watt Amplifier
RF MONITOR PAD
RF CONTROLSPAC
GunL0AL0BL0TCAVL1SL1XLINACEXPERIMENTS
Sample and Hold PLLwith DAC offset adjustand Error Monitor
RF CONTROLSPAC
2830.5MHz10 Watt Amplifier
380-208-22476MHz to 2856MHzMULTIPLIER
2830.5MHz LO16 Way Distribution20dBm each
2856MHz in
IQ Modulator to adjust2830.5MHz to 2856MHz Phase
Divide 112 to 25.5MHzSSB Mix to 2830.5MHz4X to 102MHz
25.5MHz out
102MHz out 2830.5MHz out
RF CONTROLSPAC
GunL0AL0BL0TCAVL1SL1X
+13dBm in
LO Phase Monitor
LO Phase Monitor
RF CONTROLSPAC
RF MONITORPAD
+17dBm out
RF MONITOR PAD
FSJ4-50 0.8dB/30ft
2856MHz from Sector 21
LCLS LLRF 476MHz Linac Ref.
4 x +13dBm out
380-208-38476MHz Amp30dB Gain 19dBm
102MHz16 Way Dist22dBm each
+7dBm out
+16dBm out+13dBm out
LASER DiodeMeasurement
Phase Noise and Timing
2856MHz and 119MHz
LASER DiodeOutput
LO Phase MonitorRF MONITOR PAD
RF MONITOR PADLO Phase Monitor
Ron Akre, Dayle Kotturi
Lehman Review [email protected], [email protected]
October 24-26, 2006
Lab Test SetupReference, PAC, PADThe LCLS RF system duplicated in the lab and used for testing of PADs and PACs.
At least two of each frequency generation chassis is built to measure phase noise levels.
Most components will have development chassis which can be used as a spare.
There is only one Dayle, spare is not in the budget.
Ron Akre, Dayle Kotturi
Lehman Review [email protected], [email protected]
October 24-26, 2006
LCLS New Reference System Lab Measurements
2856MHz : 22fSrms 10Hz to 10MHz 2830.5MHz : 22fSrms 10Hz to 10MHz
25.5MHz : 152fSrms 10Hz to 1MHz 102MHz : 281fSrms 10Hz to 10MHz
Lab Tests Show Reference System Noise Levels Meet All LCLS Requirements
2856MHz = 70fSrms
2830.5MHz = 70fSrms
25.5MHz = 2pSrms
102MHz = 2pSrms
John Byrd - LBNL
Ron Akre, Dayle Kotturi
Lehman Review [email protected], [email protected]
October 24-26, 2006
RF Cable Routing
RFHUT
All cables are routed from devices in temperature stabilized area to the centrally located, temperature stabilized, RF Hut in the linac gallery.
Picture taken from Carl Rago’s Talk
Cables run down through penetration 20-17 which is enclosed by the RF Hut
Ron Akre, Dayle Kotturi
Lehman Review [email protected], [email protected]
October 24-26, 2006
RF System Cables / Specifications
LCLS Specifications:Laser, RF Gun – 2.3pSL0A, L0B, L1S, L1X, L2, L3 – 5pS
Laser
RF Gun
L0A
Phase Cavity
L0B
L1S
L1X
L2 Ref
Laser
RF Gun
L0A
Phase Cavity
L0B
L1S
L1X
L2 Ref
Laser
RF Gun
L0A
Phase Cavity
L0B
L1S
L1X
L2 Ref
1
Number of cables per deviceReference cables are8ft and can drift +-50fS
1
2
4
2
2
2
5
RF HUT
+-240fS
+-310fS
+-370fS
+-290fS
+-500fS
+-160fS
+-140fS
+-240fS
Cable Drift Based onTemperature variationsand temp co of 5ppm/degCPADs
Reference2830.5MHzLO
Most Devicesare in Tunnel
LinacSector 0 RF
MDL
L2 - 4 SectorsSpecifications70fS rms jitter+-5pS drift
L3 - 6 SectorsSpecifications150fS rms jitter+-5pS drift
L0, L1 - 5 KlystronsSpecifications100fS rms jitter+-2.3pS drift
Ron Akre, Dayle Kotturi
Lehman Review [email protected], [email protected]
October 24-26, 2006
SLAC Linac RF – New ControlThe new control system will tie in to the IPA Chassis with 800W of drive power available. The RF Reference will be from the new RF reference system.
Solid State Sub-Booster PAC
I and Q will be controlled by the PAC chassis, running 16bit DACs at 102MHz. Waveforms to the DACs will be set in an FPGA through a microcontroller running EPICS on RTEMS.
Existing System
Klystron
Accelerator
SubBooster
MDL 476MHz
Next Sector
6 X2856MHz
Sub Drive Line
High PowerPhase ShifterAttenuator
SLED
Phase &AmplitudeDetector
ExistingPhaseReferenceLine
200MW-45dB
3kW
1mW1W
20mW
To NextKlystron
I
RF LO
Q
1
2
3
4
IPA
Ron Akre, Dayle Kotturi
Lehman Review [email protected], [email protected]
October 24-26, 2006
Linac Station 21-1 Tests
Ron Akre, Dayle Kotturi
Lehman Review [email protected], [email protected]
October 24-26, 2006
Linac 21-1 Test Set-up
Linac Ref Amp
MDL
6x Multiplier 2830.5MHzGenerator
PAC
102MHz 2830.5MHz
PADCLK LO
CLK OUT
CLK
SSSB
ExistingIPA
5045 KLYSTRON
RF
IN1
RF
OU
T2
KlystronForward RF
Accelerator x3
SLED
New Equipment AddedFor Tests
Power Coupled out from 476MHz MDL drives a 476MHz Amplifier which feeds a 6X Multiplier from 476MHz to 2856MHz.
The 2856MHz out drives both the LO generator and the PAC.
The 2830.5MHz LO and 102MHz CLK Generator supplies the LO and CLK to the PAD. A CLK output of the PAD drives the PAC CLK.
The PAC output drives the SSSB.
The SSSB drives the existing IPA chassis
The klystron output coupler is used to measure phase and amplitude with the new PAD.
Ron Akre, Dayle Kotturi
Lehman Review [email protected], [email protected]
October 24-26, 2006
Linac 21-1 Test ResultsTests were done in the gallery with no temperature regulation on cables. Average RMS value of 2 second sliding average is 0.068 degrees.
Exponential Smoothing Yields the Following Results. Lowest noise is with a time constant of about 2 points.
Ron Akre, Dayle Kotturi
Lehman Review [email protected], [email protected]
October 24-26, 2006
LLRF Commissioning – no high power RF, no beamLow Level Lab Tests and Calibration PACs and PADs
Set at Operational TemperaturePAC Tests and Calibration – SSB Modulator : Set offsets and gainPAD Tests
ADC Board – SNR Cross Talk – Sine Wave histogramChassis – Two Tone or Single Tone - SNR, Noise Floor, IP3
Installation of PACs and PADs – Other systems required to be completeLLRF Racks - installedWater SystemTrigger systemAC Rack power
Test RF Cables - Measure Attenuation and Phase StabilityInstallation of Solid State Sub-Boosters (SSSB)Installation of RF VME Crate
Installation of network switchesGet devices booting from afsnfs2Test VME connectivity to PAD by sending I and Q avgs.Connection of PADs, PACs, and VME IOCs to network
Initial Set-up of PAC triggersAlign 119MHz trig to 102MHZ clocks for PACs and PADs
PAD CalibrationsEnter channel calibration factors (APCs, Power Scale Factors – coupler ratios…)
PAC CalibrationCalibration with spectrum analyzerCalibration with PAD channel
Phase Noise Measurements102MHz Clock : 2830.5MHz LO : 2856MHz RF : Laser Lock to RF
Ron Akre, Dayle Kotturi
Lehman Review [email protected], [email protected]
October 24-26, 2006
LLRF Commissioning - high power RF, no beam
Timing System setupLine up PAC and PAD triggers to existing modulator triggersAdjust PAC waveforms for 6 Klystron stationsAdjust PAD window length and offset to fit waveform
Commission local Feedback loopsGun TuneGun PhaseGun AmplitudeL0A PhaseL0A AmplitudeL0B PhaseL0B AmplitudeTcav PhaseTcav AmplitudeL1S PhaseL1S AmplitudeL1X PhaseL1X Amplitude
Test Standby Timing and BCS functions
Ron Akre, Dayle Kotturi
Lehman Review [email protected], [email protected]
October 24-26, 2006
LLRF Commissioning - high power RF, with beamTiming System setup
Adjust PAC and PAD triggers to align waveforms to beam time119MHz PAD/PAC triggers must move in increments of 14 ticks to keep all phases aligned (~117.6nS).PAD window must move in increments of four 102MHz cycles to keep phase reading the same. (~39.2nS). Increments of 9.8nS will cause 90 degree phase shifts in readings.
Commission local Feedback loopsGun Phase - Phase to beam (Rotate phase to get max beam energy)Gun Amplitude - Check Cal (RF power to maximum energy gain)L0A Phase - Phase to beamL0A Amplitude - Check CalL0B Phase - Phase to beamL0B Amplitude - Check CalTcav Phase - Phase to BeamTcav Amplitude - Check CalL1S Phase - Phase to BeamL1S Amplitude - Check CalL1X Phase - Phase to BeamL1X Amplitude - Check Cal
Ron Akre, Dayle Kotturi
Lehman Review [email protected], [email protected]
October 24-26, 2006
High Level ApplicationsGeneric
Correlation plotsCalibration of power levels using beam energy
Distribution SystemRotate Phase 360 degreesMonitor Phase Errors in DividersCorrect Divider Phase Errors
PACCalibration Mode OperationGenerate and Load WaveformsPanels for Phase and Amplitude Adjustment
PAD TestingCrosstalk, SNR, Noise FloorSine Wave HistogramPanels for Phase and Amplitude Monitoring
Local Feedback Control Panels
Ron Akre, Dayle Kotturi
Lehman Review [email protected], [email protected]
October 24-26, 2006
END of TALK