linac4 emittance measurements

19
LINAC4 emittance measurements BI Day Divonne, 24 th November 11/24/2011 B.Cheymol, E. Bravin, D. Gerard, U. Raich, F. Roncarolo BE/BI 1

Upload: alta

Post on 24-Feb-2016

98 views

Category:

Documents


1 download

DESCRIPTION

LINAC4 emittance measurements. BI Day Divonne, 24 th November. Outline. Introduction LINAC4 emittance measurement Source and LEBT commissioning Slit design for 3 and 12 MeV commissioning phase Summary and outlook. Slit & Grid system. Scanning slit position For each slit position - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: LINAC4  emittance  measurements

LINAC4 emittance measurements

BI DayDivonne, 24th November

11/24/2011 B.Cheymol, E. Bravin, D. Gerard, U. Raich, F. Roncarolo BE/BI 1

Page 2: LINAC4  emittance  measurements

Outline

• Introduction• LINAC4 emittance measurement• Source and LEBT commissioning• Slit design for 3 and 12 MeV commissioning

phase• Summary and outlook

11/24/2011 B.Cheymol, E. Bravin, D. Gerard, U. Raich, F. Roncarolo BE/BI 2

Page 3: LINAC4  emittance  measurements

Slit & Grid system

Scanning slit position

For each slit position – profile monitor gives beamlet

divergence

Transverse phase space reconstruction

11/24/2011 B.Cheymol, E. Bravin, D. Gerard, U. Raich, F. Roncarolo BE/BI 3

Page 4: LINAC4  emittance  measurements

Emittance measurement in LINAC4

• Slit and grid will be used during commissioning phase– In the low energy section (45 keV)– At 3 (RFQ and Chopper line) and 12 MeV (1st DTL Tank)

11/24/2011 B.Cheymol, E. Bravin, D. Gerard, U. Raich, F. Roncarolo BE/BI 4

•Determination of source beam emittance•Determination of matching parameters•Study of the accelerator optics

• Issue of the system:• @ 45 KeV

• Large beam sizes and divergence• Space charge forces• Background from beam dump

• @ 3 and 12 MeV• Thermal load on the slit

Page 5: LINAC4  emittance  measurements

Low energy emittance meter

11/24/2011 B.Cheymol, E. Bravin, D. Gerard, U. Raich, F. Roncarolo BE/BI 5

Page 6: LINAC4  emittance  measurements

Emittance-Meter: background reduction

11/24/2011 B.Cheymol, E. Bravin, D. Gerard, U. Raich, F. Roncarolo BE/BI

Faraday’s cup plate

6

• Emittance measurement can be perturbed by SE from beam dump positioned downstream the emittance meter

• Rings can be polarized to reduce number of particles travelling backward

• Dump can be used as a Faraday cup

Page 7: LINAC4  emittance  measurements

Configuration considered initially:

VP1>0 , VP2<0

11/24/2011 7

Emittance-Meter: background reduction simulations

- 500 V+ 1200 V Configuration proposed after simulations:VP1,VP2, VCUP > 0 minimizes perturbation due to FC and P1 electrons biasing the FC forbids charge measurements at the

same time as emittance measurements

+ 500 V

P1 P2

Faraday’s CupElectrons trajectories as simulated by CST Microwave Studio

Page 8: LINAC4  emittance  measurements

Emittance-Meter: bias rings setup with beam

During Emittance Measurement-all biases > 0 clearly optimizes the wire signal

11/24/2011 B.Cheymol, E. Bravin, D. Gerard, U. Raich, F. Roncarolo BE/BI 8

During Beam charge measurement at the Faraday’s Cup (H- 35 keV)-Need VP2 < 0 to retain secondary electrons that would escape the CUP

All well in agreement with MWS simulations

Page 9: LINAC4  emittance  measurements

Source and LEBT commissioning

11/24/2011 B.Cheymol, E. Bravin, D. Gerard, U. Raich, F. Roncarolo BE/BI 9

Page 10: LINAC4  emittance  measurements

LEBT Commissioning Stages

11/24/2011 B.Cheymol, E. Bravin, D. Gerard, U. Raich, F. Roncarolo BE/BI 10

Completed with 35 keV H- and 45 keV Protons

Completed with 45 keV Protons

1

2

3

- Stage 4 completed- Now: will re-check stage 1 while re-arranging LEBT to host

RFQ (beginning of 2012)

4

Page 11: LINAC4  emittance  measurements

Emittance-Meter Measurement Example (I)

11/24/2011 B.Cheymol, E. Bravin, D. Gerard, U. Raich, F. Roncarolo BE/BI 11

H3+

H0

H2+

Protons

Emittance-meter measurement after 1st solenoid

X

X’

45 keV Proton source: different charge states produced by the source are focused differently as they pass through the solenoid

80% of protons

Page 12: LINAC4  emittance  measurements

Emittance-Meter Measurement Example (II)

11/24/2011 B.Cheymol, E. Bravin, D. Gerard, U. Raich, F. Roncarolo BE/BI 12

Transverse distribution vs Source RF power Profiles extracted from Emittance Measurements (phase space projection on HOR axis)

Page 13: LINAC4  emittance  measurements

Profile measurements with emittance meter

11/24/2011 B.Cheymol, E. Bravin, D. Gerard, U. Raich, F. Roncarolo BE/BI 13

Profile Measurement performed after the second solenoid by measuring the FC current while scanning the slit position

This particular measurement proved Source reproducibility (red and blue measurements taken in different days) beam-solenoid misalignment (beam centroid depends on Solenoid current)

Page 14: LINAC4  emittance  measurements

Slit design for 3 and 12 MeV commissioning phase

11/24/2011 B.Cheymol, E. Bravin, D. Gerard, U. Raich, F. Roncarolo BE/BI 14

Page 15: LINAC4  emittance  measurements

Thermal load at 3 and 12 MeV

• Commissioning will be done with a 65 mA and 100 μs beam (4 x1013 particles per pulse)

• @ 3MeV:• Power (over pulse) => 0.31 MW.cm-2

• @ 12 MeV:• Power (over pulse) => 7.56 MW.cm-2

11/24/2011 B.Cheymol, E. Bravin, D. Gerard, U. Raich, F. Roncarolo BE/BI 15

• The blade is tilted to spread the energy deposition on a larger surface.

• Graphite has been chosen for thermal properties

θ

z

x

Page 16: LINAC4  emittance  measurements

B.Cheymol, E. Bravin, D. Gerard, U. Raich, F. Roncarolo BE/BI

16

Slit geometry

11/24/2011

  SRIM FLUKAAngle [deg] 90 90 45 15

MEBT 2673 K 2613 K 2065 K 1696 KDTL 4669 K 4594 K 3931 K 2790  K

Even with 15°, thermal load is too high for DTL case.Decided to move the slit 1 m downstream beam sizes increase by a factor 1.5 Temperature drops to 1520 K

Energy deposition along the z axis for three slit angles at 3 MeV(MEBT), in case of a Graphite slit.

Maximum in temperature for the three commissioning stages, as estimated by analytical model (SRIM) and numerical simulations (FLUKA) when considering a 65 mA, 100 μs pulse.

Page 17: LINAC4  emittance  measurements

High energy Slit design

• Graphite plates clamped on a copper block• Slit aperture adjustable at the assembly (100 or 200 μm)• Slit thickness equal to 1 mm.

11/24/2011 B.Cheymol, E. Bravin, D. Gerard, U. Raich, F. Roncarolo BE/BI 17

Page 18: LINAC4  emittance  measurements

Status

• Mechanical design Completed (done by CERN design office)

• Slit tank is under assembly (followed by D. Gerard)

• Emittance meter will be ready for RFQ commissioning (March-April 2012)

11/24/2011 B.Cheymol, E. Bravin, D. Gerard, U. Raich, F. Roncarolo BE/BI 18

Page 19: LINAC4  emittance  measurements

Summary and outlook• Source and LEBT test stand operated for two years

– Commissioning stages with 45 keV proton source completed

• Beam parameter and optics has been characterized– Faraday’s cups to validate transmission– Emittance meter to validate matching to nominal optics– Spectrometer SEM grid to measure energy spread

• RFQ and Chopper commissioning with proton beam in 2012• Commissioning of the new H- source and LEBT (with larger

aperture)

11/24/2011 B.Cheymol, E. Bravin, D. Gerard, U. Raich, F. Roncarolo BE/BI 19