Linklaters’ test management and risk mitigation programme
Jason Conner
November 2011
![Page 2: Linklaters’ test management and risk mitigation programme · Linklaters’ test management and risk mitigation programme Jason Conner ... BPCA can help with mitigating risk and](https://reader034.vdocument.in/reader034/viewer/2022052608/5adf1a8b7f8b9ac0428bc375/html5/thumbnails/2.jpg)
1
Linklaters Overview
> 2,200 lawyers
> Over 500 partners
in 27 offices
across 19 countries
> Income over £1bn
![Page 3: Linklaters’ test management and risk mitigation programme · Linklaters’ test management and risk mitigation programme Jason Conner ... BPCA can help with mitigating risk and](https://reader034.vdocument.in/reader034/viewer/2022052608/5adf1a8b7f8b9ac0428bc375/html5/thumbnails/3.jpg)
2
Our SAP Implementation
In 2003 we rolled out to all our offices
> R/3 4.6c, CRM3.1, BW3.0
Upgrades
> 2005 CRM 4.0, BW 3.5
> 2006 ECC5
> 2007 CRM 5.0
> 2008 Unicode
> 2010 BI7.0 EhP 1, ERP6.0 EhP4
> 2011 Bobj XI 3.1
![Page 4: Linklaters’ test management and risk mitigation programme · Linklaters’ test management and risk mitigation programme Jason Conner ... BPCA can help with mitigating risk and](https://reader034.vdocument.in/reader034/viewer/2022052608/5adf1a8b7f8b9ac0428bc375/html5/thumbnails/4.jpg)
3
Why are we exploring this?
Mitigate risk – more targeted testing
> Currently have over 90 automated test scripts
> Reflect critical business processes
> Used in R/3 upgrade, O/S migration project, R/3 quarterly and weekly releases
Respond quicker to business demands
> New functionality
BPCA can help with mitigating risk and responding quicker
![Page 5: Linklaters’ test management and risk mitigation programme · Linklaters’ test management and risk mitigation programme Jason Conner ... BPCA can help with mitigating risk and](https://reader034.vdocument.in/reader034/viewer/2022052608/5adf1a8b7f8b9ac0428bc375/html5/thumbnails/5.jpg)
4
Mitigate risk - QA test scripts status monitor
QTP automated test scripts
90 Scripts covering:
> Finance
> HR
> Marketing
> CNCT
![Page 6: Linklaters’ test management and risk mitigation programme · Linklaters’ test management and risk mitigation programme Jason Conner ... BPCA can help with mitigating risk and](https://reader034.vdocument.in/reader034/viewer/2022052608/5adf1a8b7f8b9ac0428bc375/html5/thumbnails/6.jpg)
5
Our Starting Point
![Page 7: Linklaters’ test management and risk mitigation programme · Linklaters’ test management and risk mitigation programme Jason Conner ... BPCA can help with mitigating risk and](https://reader034.vdocument.in/reader034/viewer/2022052608/5adf1a8b7f8b9ac0428bc375/html5/thumbnails/7.jpg)
6
How we began
SolMan in place
> SolMan 7.0 EhP1
> Separating documentation and process structures
SAP Consultant in for 5 days to “start us on our way”
> Begin process of building project
> Allow us to continue to progress at our own pace
Attending EGIs
> BPCA
> Service level reporting
![Page 8: Linklaters’ test management and risk mitigation programme · Linklaters’ test management and risk mitigation programme Jason Conner ... BPCA can help with mitigating risk and](https://reader034.vdocument.in/reader034/viewer/2022052608/5adf1a8b7f8b9ac0428bc375/html5/thumbnails/8.jpg)
7
Building our project in SolMan
> Installed SAP standard Business Blueprint project
> Ran our prod usage against this project
![Page 9: Linklaters’ test management and risk mitigation programme · Linklaters’ test management and risk mitigation programme Jason Conner ... BPCA can help with mitigating risk and](https://reader034.vdocument.in/reader034/viewer/2022052608/5adf1a8b7f8b9ac0428bc375/html5/thumbnails/9.jpg)
8
SAP standard usage - summary
![Page 10: Linklaters’ test management and risk mitigation programme · Linklaters’ test management and risk mitigation programme Jason Conner ... BPCA can help with mitigating risk and](https://reader034.vdocument.in/reader034/viewer/2022052608/5adf1a8b7f8b9ac0428bc375/html5/thumbnails/10.jpg)
9
Linklaters structure
Modified structure to reflect Linklaters’ specific trans and terminology
> Validated by functional consultants
![Page 11: Linklaters’ test management and risk mitigation programme · Linklaters’ test management and risk mitigation programme Jason Conner ... BPCA can help with mitigating risk and](https://reader034.vdocument.in/reader034/viewer/2022052608/5adf1a8b7f8b9ac0428bc375/html5/thumbnails/11.jpg)
10
Linklaters Project Structure
> Re run the analysis
![Page 12: Linklaters’ test management and risk mitigation programme · Linklaters’ test management and risk mitigation programme Jason Conner ... BPCA can help with mitigating risk and](https://reader034.vdocument.in/reader034/viewer/2022052608/5adf1a8b7f8b9ac0428bc375/html5/thumbnails/12.jpg)
11
Linklaters Project Analysis
![Page 13: Linklaters’ test management and risk mitigation programme · Linklaters’ test management and risk mitigation programme Jason Conner ... BPCA can help with mitigating risk and](https://reader034.vdocument.in/reader034/viewer/2022052608/5adf1a8b7f8b9ac0428bc375/html5/thumbnails/13.jpg)
12
TBOMs
Kept master project in place
> Created subset project of key processes to run TBOMs as a test
> TBOMs created manually
![Page 14: Linklaters’ test management and risk mitigation programme · Linklaters’ test management and risk mitigation programme Jason Conner ... BPCA can help with mitigating risk and](https://reader034.vdocument.in/reader034/viewer/2022052608/5adf1a8b7f8b9ac0428bc375/html5/thumbnails/14.jpg)
13
BPCA results
Change Impact Analysis queries
![Page 15: Linklaters’ test management and risk mitigation programme · Linklaters’ test management and risk mitigation programme Jason Conner ... BPCA can help with mitigating risk and](https://reader034.vdocument.in/reader034/viewer/2022052608/5adf1a8b7f8b9ac0428bc375/html5/thumbnails/15.jpg)
14
BPCA results
Business process steps affected
Items below project level
![Page 16: Linklaters’ test management and risk mitigation programme · Linklaters’ test management and risk mitigation programme Jason Conner ... BPCA can help with mitigating risk and](https://reader034.vdocument.in/reader034/viewer/2022052608/5adf1a8b7f8b9ac0428bc375/html5/thumbnails/16.jpg)
15
Linklaters structure
![Page 17: Linklaters’ test management and risk mitigation programme · Linklaters’ test management and risk mitigation programme Jason Conner ... BPCA can help with mitigating risk and](https://reader034.vdocument.in/reader034/viewer/2022052608/5adf1a8b7f8b9ac0428bc375/html5/thumbnails/17.jpg)
16
Next steps
Complete master project
> Generate full list of TBOMs
![Page 18: Linklaters’ test management and risk mitigation programme · Linklaters’ test management and risk mitigation programme Jason Conner ... BPCA can help with mitigating risk and](https://reader034.vdocument.in/reader034/viewer/2022052608/5adf1a8b7f8b9ac0428bc375/html5/thumbnails/18.jpg)
17
Next steps
Incorporate in release process
> Upgrade to Solution Manager 7.1
> Automate the creation and maintenance of TBOMs utilising
workflow and QTP scripts
> Business Process Monitoring