lisa pathfinder: mission status · 2011-12-20 · lisa pathfinder lpf development approach lpf is a...

35
LISA Pathfinder: Mission Status Paul McNamara LISA Pathfinder Project Scientist

Upload: others

Post on 08-Aug-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: LISA Pathfinder: Mission Status · 2011-12-20 · LISA Pathfinder LPF Development Approach LPF is a Pathfinder for spaceborne gravitational wave detectors – System design is for

LISA Pathfinder: Mission Status

Paul McNamaraLISA Pathfinder Project Scientist

Page 2: LISA Pathfinder: Mission Status · 2011-12-20 · LISA Pathfinder LPF Development Approach LPF is a Pathfinder for spaceborne gravitational wave detectors – System design is for

LISA Pathfinder

Introduction

LISA Pathfinder (LPF) is a technology validation mission for NGO1

– LPF was approved by ESA to demonstrate the concept of low frequency gravitational wave detection in space

LISA Pathfinder will test in flight:– Inertial sensors (a.k.a. Gravitational Reference Sensor)– Interferometry between free floating test masses– Drag Free and Attitude Control System (DFACS)– Micro-Newton propulsion technologyThe basic idea of LISA Pathfinder is to squeeze one arm of the NGO constellation from 1 million km to a few tens of cm!– Fully tests NGO local interferometry

1 When approved by the Science Programme Committee, LISA Pathfinder was a dedicated technology validation mission for the LISA mission. In the mean time, LISA has been reformulated and renamed NGO

Page 3: LISA Pathfinder: Mission Status · 2011-12-20 · LISA Pathfinder LPF Development Approach LPF is a Pathfinder for spaceborne gravitational wave detectors – System design is for

LISA Pathfinder

Mission Concept

Page 4: LISA Pathfinder: Mission Status · 2011-12-20 · LISA Pathfinder LPF Development Approach LPF is a Pathfinder for spaceborne gravitational wave detectors – System design is for

LISA Pathfinder

Mission Concept

Page 5: LISA Pathfinder: Mission Status · 2011-12-20 · LISA Pathfinder LPF Development Approach LPF is a Pathfinder for spaceborne gravitational wave detectors – System design is for

LISA Pathfinder

Mission Concept

Page 6: LISA Pathfinder: Mission Status · 2011-12-20 · LISA Pathfinder LPF Development Approach LPF is a Pathfinder for spaceborne gravitational wave detectors – System design is for

LISA Pathfinder

Mission Concept

Page 7: LISA Pathfinder: Mission Status · 2011-12-20 · LISA Pathfinder LPF Development Approach LPF is a Pathfinder for spaceborne gravitational wave detectors – System design is for

LISA Pathfinder

Mission Concept

Page 8: LISA Pathfinder: Mission Status · 2011-12-20 · LISA Pathfinder LPF Development Approach LPF is a Pathfinder for spaceborne gravitational wave detectors – System design is for

LISA Pathfinder

LISA Pathfinder consists of:– Spacecraft

• Provided by ESA– Industrial Prime Contractor: Astrium UK

• s/c also includes the drag free control software (DFACS) and micro-Newton thrusters

– Payloads• The LISA Technology Package (LTP)

– Provided by European member states and ESA– Consists of inertial sensors, and interferometric readout

• The Disturbance Reduction System (DRS)– Provided by NASA– Consists of processor running drag-free

control software and micro-Newtonthrusters

LTP Core Assembly

LPF

LISA Pathfinder

Page 9: LISA Pathfinder: Mission Status · 2011-12-20 · LISA Pathfinder LPF Development Approach LPF is a Pathfinder for spaceborne gravitational wave detectors – System design is for

LISA Pathfinder

DFACS Principle

Page 10: LISA Pathfinder: Mission Status · 2011-12-20 · LISA Pathfinder LPF Development Approach LPF is a Pathfinder for spaceborne gravitational wave detectors – System design is for

LISA Pathfinder

x1 interferometer

Page 11: LISA Pathfinder: Mission Status · 2011-12-20 · LISA Pathfinder LPF Development Approach LPF is a Pathfinder for spaceborne gravitational wave detectors – System design is for

LISA Pathfinder

x1 Drag Free

Page 12: LISA Pathfinder: Mission Status · 2011-12-20 · LISA Pathfinder LPF Development Approach LPF is a Pathfinder for spaceborne gravitational wave detectors – System design is for

LISA Pathfinder

x2-x1 Interferometer

Page 13: LISA Pathfinder: Mission Status · 2011-12-20 · LISA Pathfinder LPF Development Approach LPF is a Pathfinder for spaceborne gravitational wave detectors – System design is for

LISA Pathfinder

X2 low frequency control

Page 14: LISA Pathfinder: Mission Status · 2011-12-20 · LISA Pathfinder LPF Development Approach LPF is a Pathfinder for spaceborne gravitational wave detectors – System design is for

LISA Pathfinder

DFACS

Page 15: LISA Pathfinder: Mission Status · 2011-12-20 · LISA Pathfinder LPF Development Approach LPF is a Pathfinder for spaceborne gravitational wave detectors – System design is for

LISA Pathfinder

LPF Development Approach

LPF is a Pathfinder for spaceborne gravitational wave detectors– System design is for NGORelaxation of performance requirements is only allowed to make testing conditions achievable. It shall not affect the design.Implications:– When one subsystem reaches a given level of readiness for LISA

Pathfinder (CDR, QR, FAR, etc) it reaches the same level of readiness for NGO too.

– All the development risks up to that stage are consequently retired also for NGO

– Risk of unforeseen system level problems (estimated to be low) is finally retired by the flight.

Page 16: LISA Pathfinder: Mission Status · 2011-12-20 · LISA Pathfinder LPF Development Approach LPF is a Pathfinder for spaceborne gravitational wave detectors – System design is for

LISA Pathfinder

NGO basic design items

Free flying test mass subject to very low parasitic forces:– Drag free control of spacecraft (non-contacting spacecraft)– Low noise microthruster to implement drag-free– Large gaps, heavy masses with caging mechanism– High stability electrical actuation on cross degrees of freedom– Non contacting discharging of test-masses– High thermo-mechanical stability of S/C– Gravitational field cancellation

Precision interferometric, local ranging of test-mass and spacecraft:– pm resolution ranging, sub-mrad alignments– High stability monolithic optical assemblies

Precision 1 million km spacecraft to spacecraft precision ranging:– High stability telescopes– High accuracy phase-meter– High accuracy frequency stabilization– Constellation acquisition– Precision attitude control of S/C

Page 17: LISA Pathfinder: Mission Status · 2011-12-20 · LISA Pathfinder LPF Development Approach LPF is a Pathfinder for spaceborne gravitational wave detectors – System design is for

LISA Pathfinder

Items that can only be validated in flight

Free flying test mass subject to very low parasitic forces:– Drag free control of spacecraft (non-contacting spacecraft)– Low noise microthruster to implement drag-free– Large gaps, heavy masses with caging mechanism– High stability electrical actuation on cross degrees of freedom– Non contacting discharging of test-masses– High thermo-mechanical stability of S/C– Gravitational field cancellation

Precision interferometric, local ranging of test-mass and spacecraft:– pm resolution ranging, sub-mrad alignments– High stability monolithic optical assemblies

Precision 1 million km spacecraft to spacecraft precision ranging:– High stability telescopes– High accuracy phase-meter– High accuracy frequency stabilization– Constellation acquisition– Precision attitude control of S/C

Page 18: LISA Pathfinder: Mission Status · 2011-12-20 · LISA Pathfinder LPF Development Approach LPF is a Pathfinder for spaceborne gravitational wave detectors – System design is for

LISA Pathfinder

Free flying test mass subject to very low parasitic forces:– Drag free control of spacecraft (non-contacting spacecraft)– Low noise microthruster to implement drag-free– Large gaps, heavy masses with caging mechanism– High stability electrical actuation on cross degrees of freedom– Non contacting discharging of test-masses– High thermo-mechanical stability of S/C– Gravitational field cancellation

Precision interferometric, local ranging of test-mass and spacecraft:– pm resolution ranging, sub-mrad alignments– High stability monolithic optical assemblies

Precision 1 million km spacecraft to spacecraft precision ranging:– High stability telescopes– High accuracy phase-meter– High accuracy frequency stabilization– Constellation acquisition– Precision attitude control of S/C

Items benefiting from in-flight validation

Page 19: LISA Pathfinder: Mission Status · 2011-12-20 · LISA Pathfinder LPF Development Approach LPF is a Pathfinder for spaceborne gravitational wave detectors – System design is for

LISA Pathfinder

Free flying test mass subject to very low parasitic forces:– Drag free control of spacecraft (non-contacting spacecraft)– Low noise microthruster to implement drag-free– Large gaps, heavy masses with caging mechanism– High stability electrical actuation on cross degrees of freedom– Non contacting discharging of test-masses– High thermo-mechanical stability of S/C– Gravitational field cancellation

Precision interferometric, local ranging of test-mass and spacecraft:– pm resolution ranging, sub-mrad alignments– High stability monolithic optical assemblies

Precision 1 million km spacecraft to spacecraft precision ranging:– High stability telescopes– High accuracy phase-meter– High accuracy frequency stabilization– Constellation acquisition– Precision attitude control of S/C

NGO Design Items Validated By LISA Pathfinder

Page 20: LISA Pathfinder: Mission Status · 2011-12-20 · LISA Pathfinder LPF Development Approach LPF is a Pathfinder for spaceborne gravitational wave detectors – System design is for

LISA Pathfinder

LTP Salient Features

LISA Technology Package (LTP) is the European instrument payload of LPF

Two Au:Pt test masses housed in separate vacuum enclosuresRelative position of test masses read-out by:– Heterodyne laser interferometry on

sensitive axis– Capacitive sensing on all axesFour interferometers on ultra-low expansion optical bench– x1, x2-x1, Frequency noise, reference

interferometer

Page 21: LISA Pathfinder: Mission Status · 2011-12-20 · LISA Pathfinder LPF Development Approach LPF is a Pathfinder for spaceborne gravitational wave detectors – System design is for

LISA Pathfinder

LTP Status

All electronic units have been delivered and integrated to the spacecraft– Laser, laser modulator, phasemeter, payload computer, UV lamp unit,

ISS front-end electronics, diagnostics

Reference Laser Unit Phasemeter

Payload Computer ISS Front-End Electronics LPF during AIT at Astrium UK

Page 22: LISA Pathfinder: Mission Status · 2011-12-20 · LISA Pathfinder LPF Development Approach LPF is a Pathfinder for spaceborne gravitational wave detectors – System design is for

LISA Pathfinder

LTP Status

Most of the components of the LTP Core Assembly are ready, however subsequent integration has been delayed.– Optical bench– Inertial sensor

• Test Masses• Vacuum enclosure• Grabbing, positioning and release

mechanism

Optical Bench Test Mass Grabbing, positioning and Release Mechanism (GPRM)

Uncoated Au:Pt Test Mass

Page 23: LISA Pathfinder: Mission Status · 2011-12-20 · LISA Pathfinder LPF Development Approach LPF is a Pathfinder for spaceborne gravitational wave detectors – System design is for

LISA Pathfinder

LTP Status

Delays in the integration, and delivery, of the LTP Core Assembly are due to problems with the test mass launch lock– Original (hydraulic) launch lock

failed during testing– A new design has now been

selected, and flight units are being manufactured

• New design is a much simpler, single-shot mechanism utilising a paraffin actuator

• Delivery of FMs is scheduled for September 2012

ESA Presentation | 30/NOV/2011 | Slide 10

ESA UNCLASSIFIED – For Official Use

Page 24: LISA Pathfinder: Mission Status · 2011-12-20 · LISA Pathfinder LPF Development Approach LPF is a Pathfinder for spaceborne gravitational wave detectors – System design is for

LISA Pathfinder

TOQM

In-lieu of the LCA, a Thermal-Optical Qualification Model (TOQM) was created to allow the environmental testing of the spacecraft to proceed– Consists of a flight optical bench, with flight mounting struts, and

thermal mass dummies of the inertial sensors

Page 25: LISA Pathfinder: Mission Status · 2011-12-20 · LISA Pathfinder LPF Development Approach LPF is a Pathfinder for spaceborne gravitational wave detectors – System design is for

LISA Pathfinder

LPF Spacecraft Bus

All units of the spacecraft bus have been delivered and integrated– Only units not yet integrated are the micro-thrusters (which are

mounted on the outside on the spacecraft)System environmental tests are now complete

Following closed-loop tests in January, spacecraft will be put into storage awaiting the delivery of the LCA

Page 26: LISA Pathfinder: Mission Status · 2011-12-20 · LISA Pathfinder LPF Development Approach LPF is a Pathfinder for spaceborne gravitational wave detectors – System design is for

LISA Pathfinder

System Test Campaigns

Sine Vibration Transfer Orbit Thermal Test

EMC On-Station Thermal Test

Page 27: LISA Pathfinder: Mission Status · 2011-12-20 · LISA Pathfinder LPF Development Approach LPF is a Pathfinder for spaceborne gravitational wave detectors – System design is for

LISA Pathfinder

OSTT Sequence

0 2 4 6 8 10 12 14 16 18 20 22

Time (Days)

Max. Hot

Min. Cold

Amb. TP0

TP1

TP3

TP21

TP4 TP5 TP7 & 8

Pum

p D

own

TB H

ot L

TP

scie

nce

Tran

sfer

to

Hot

TB C

old

LTP

Sc

ienc

e

TB H

ot D

RS

Sc

ienc

e &

TO

QM

S

peci

fic

IST02 Hot

IST03 Cold

LEO

P C

yclin

g &

TOQ

M S

peci

fic

Tran

sfer

to

Col

d O

pera

tion

TP10

War

m-U

p

TP19

TB C

old

DR

S Sc

ienc

e

PFM

SC

M N

oise

C

hara

cter

isat

ion

Test Completion

TP9

TP13

TP11TP2

TP17&18

Re-

Pres

suris

atio

n

SCM

Tes

t Seq

uenc

e

TP20

TP16 TP14 TP12

TO

QM

Spe

cific

TOQ

M

Spec

ific

TP6

TOQ

M

S pec

ific

TP15

TOQ

M S

peci

fic

TOQ

M S

peci

fic

0 2 4 6 8 10 12 14 16 18 20 22

Time (Days)

TOQM Testing TB Test Phases TV/IST Test Phases Noise Characterisation Testing Initial/ Final SFTs @ Ambient

Max. Hot

Min. Cold

Amb.

TO

QM

Tes

t Seq

uenc

e TOQ

M H

ot

Per

form

ance

M

easu

rem

ent I

TOQ

M H

ot

Per

form

ance

C

omm

issi

onin

g

TOQ

M C

old

Per

form

ance

m

easu

rem

ent

TOQ

M

Dia

gnos

tic

Ther

mal

Sta

bilis

atio

n of

LC

A S

truct

ure

Non

-Per

form

ance

TO

QM

Pre

p

OM

S re

spon

se

to th

erm

al n

oise

ch

arac

teris

atio

n

TOQ

M H

ot

Per

form

ance

M

easu

rem

ent I

I

OM

S C

hara

cter

isat

ion

OM

S

Cha

ract

eris

atio

n

TOQ

M H

ealth

&

Sta

tus

Che

ck

LTP

SC

OE

C

heck

OM

S C

hara

cter

isat

ion

Re-

Pres

suris

atio

n

Test CompletionOM

S F

acili

ty N

oise

C

hara

cter

isat

ion

Page 28: LISA Pathfinder: Mission Status · 2011-12-20 · LISA Pathfinder LPF Development Approach LPF is a Pathfinder for spaceborne gravitational wave detectors – System design is for

LISA Pathfinder

Fit to OSTT Performance

Page 29: LISA Pathfinder: Mission Status · 2011-12-20 · LISA Pathfinder LPF Development Approach LPF is a Pathfinder for spaceborne gravitational wave detectors – System design is for

LISA Pathfinder

Micro-thrusters

LPF will carry two sets of micro-thrusters– The NASA supplied Colloidal Thrusters– European supplied thrustersThe baseline thruster for LPF is the Cs Field Emission Electric Propulsion (FEEP) thrusterDue to delays in the qualification schedule of the FEEPs, the project has recently instigated a review of the use alternative thrusters for LPF– Cold Gas thrusters (the GAIA thruster)– Micro Radio-frequency Ionisation Thrusters (µ-RIT)

Page 30: LISA Pathfinder: Mission Status · 2011-12-20 · LISA Pathfinder LPF Development Approach LPF is a Pathfinder for spaceborne gravitational wave detectors – System design is for

LISA Pathfinder

Micro-Thrusters

Review Board Conclusions (May 2011):– Continue FEEP development, culminating in two tests demonstrating the LPF

lifetime (600Ns) by June 2012– Industry to study the cold gas thrusters, with PDR to be held in October 2011– Industry to study micro-RIT thrusters with SRR in September 2011, and PDR

by the end of the year

As of now:– Cold Gas PDR was successful

• Major issue is the schedule for the delivery of the thruster units

• Board recommended to start the procurement of the long-lead items before the decision is made on the flight thruster technology

– Micro-RIT• SRR has been held• Development of the technology will

continue up to PDR level

Measured thrust noise of GAIA thrusters

Page 31: LISA Pathfinder: Mission Status · 2011-12-20 · LISA Pathfinder LPF Development Approach LPF is a Pathfinder for spaceborne gravitational wave detectors – System design is for

LISA Pathfinder

Micro-Thrusters

Review Board requested that the FEEP tests continue into next year– Culminating in two thruster assembly endurance tests, both of which

must demonstrate the full LPF total impulse requirements.After thorough investigation, the FEEP thruster head has been redesigned to limit caesium leakage from the emitter slit– Achieved in part by narrowing the slit width from 1.3µm to 0.7µm

Ongoing thruster unit validation test is demonstrating that the new design of thruster is working perfectly!!

Downselect on which thruster to take to flight will be made in June 2012.

Page 32: LISA Pathfinder: Mission Status · 2011-12-20 · LISA Pathfinder LPF Development Approach LPF is a Pathfinder for spaceborne gravitational wave detectors – System design is for

LISA Pathfinder

Micro-Thrusters

NB: As of today, total impulse now at ~300Ns (~900hours). Equivalent to ~50% of LPF total impulse requirement

Page 33: LISA Pathfinder: Mission Status · 2011-12-20 · LISA Pathfinder LPF Development Approach LPF is a Pathfinder for spaceborne gravitational wave detectors – System design is for

LISA Pathfinder

LPF Performance The LISA Pathfinder Mission 7

1 10 1000.1

Frequency [mHz]

1

10

100

SpectralDensity

� fms−2/√

Hz

TotalDirect Forces

OMSAngular

ElectrostaticActuation

Thrusters

OMSSensing

Star

Tracker

Figure 1. The differential acceleration noise budget arising from the requirementson the individual groups of noise sources. The grey areas are out of the measurementband for LPF but are interesting for LISA.

construction of the flight hardware has begun and are, as such, necessarily conservative.

Once the hardware is built and tested in realistic settings, we get more reliable estimates

of the performance of individual subsystems. In addition, a detailed understanding of

the differences in the environment under which the subsystems are tested compared to

the environment expected in orbit could lead to further improvements. As well as the

testing and analysis of flight hardware, studies of the system as a whole can lead to data

analysis methods and system identification techniques (see, for example, [10, 11])which

will allow the system to be optimised in orbit, resulting in reductions of the coupling

of some noise sources to differential force on the test-masses. Some examples of these

improvements are given below.

3.1.1. Measured performance of the electrostatic actuators The electrostatic actuation

is used to control the position of TM2 to ensure that it tracks the free-falling TM1. When

estimating the differential acceleration of the two test-masses, this commanded actuation

is removed (see [12]). As such, any fluctuations in the applied actuation force which

are not present in the commanded actuation will not be removed and will be a direct

contributor to the estimated differential acceleration. These fluctuations ultimately

arise in fluctuations of the dc voltages applied to produce a dc force that counteracts

any gravitational imbalance within the SC. The flight models of the electronics which

produce the dc voltages have now undergone direct measurement and have shown that

the fluctuations are at the level of 3 − 8 ppm/√Hz at 1mHz. Together with detailed

modelling of the expected gravitational imbalances (estimated to be around 0.65 nm s−2),

this performance lead to a lower estimate for the expected force noise fluctuations.

Further discussion of this can be found in [13]. Panel (a) of figure 2 shows (in red) the

The LISA Pathfinder Mission 11

1 10 1000.1

Frequency [mHz]

1

10

100

SpectralDensity

� fms−2/√

Hz

TotalDirect ForcesElectrostaticActuation

Thrusters

OMSSensing

StarTracker

Requirements

Figure 3. The differential acceleration noise budget arising from the best-case orexpected performance of the individual subsystems. The grey areas are out of themeasurement band for LPF but are interesting for LISA.

improves upon the LISA Goal in the LPF measurement band, and is only about a

factor of 3 away at the lower end of the LISA band.

1 10 1000.1

Frequency [mHz]

1

10

100

SpectralDensity

� fms−2/√

Hz

� 1000

LPF Mission RequirementsLISA Mission RequirementsLPF Performance (Subsystem Requirements)LPF Performance (Best Estimate)LPF Performance (Free-Flight)

Figure 4. A comparison of different performance estimates for the LPF Mission. Weshow the performance expected if all systems perform as per their requirements, thecurrent best estimate performance, and the estimated performance for the free-flightexperiment. Also shown are the overall mission requirements for LPF and LISA.

Extensive performance noise model has been developed by both the PI and industryThe main goal of LPF is to validate this noise modelModel is updated as ground test results become availableCurrent Best Estimate of LPF is now approaching the NGO requirements!

Requirements noise projection

Current Best Estimate

Page 34: LISA Pathfinder: Mission Status · 2011-12-20 · LISA Pathfinder LPF Development Approach LPF is a Pathfinder for spaceborne gravitational wave detectors – System design is for

LISA Pathfinder

In Summary

All environmental tests completeThe caging mechanism launch lock drives the critical pathResults from OSTT (TOQM) demonstrate performance better than requirementsCold Gas thrusters are a viable alternative to the FEEPs.The project will enter hibernation at the beginning of next year– Hibernation is scheduled to last

~15months

Launch is scheduled for June 2014.

Page 35: LISA Pathfinder: Mission Status · 2011-12-20 · LISA Pathfinder LPF Development Approach LPF is a Pathfinder for spaceborne gravitational wave detectors – System design is for

LabenCarlo Gavazzi SpaceALTAARCSContravesKaiser ThredeNTESCISYSSpacebelSRONTechnologicaTESATZARMJPLNASA GoddardBUSEK

Thank youESA ESTECESA ESACESA ESOCEADS Astrium UKEADS Astrium GmbHUniversity of TrentoAlbert Einstein InstituteUniversity of GlasgowUniversity of BirminghamImperial College LondonETH ZurichInstitut d-Estudis Espacials de CatalunyaUniversidad Politecnica de Barcelona APC ParisIFR Stuttgart