WORK ORDER REQUEST Status 1 10-Jan-13 16-Jan-13 1 WEEK COMPLETE 2 10-Jan-13 13-Jan-13 2-3 Days COMPLETE 3 13-Jan-13 23-Jan-13 12 WEEKS COMPLETE 4 13-Jan-13 19-Feb-13 2 WEEKS COMPLETE 5 15-Jan-13 13-Feb-13 3 WEEKS COMPLETE 6 15-Jan-13 20-Feb-13 3 WEEKS ON GOING 7 15-Jan-13 19-Jan-13 2 WEEKS COMPLETE 8 15-Jan-13 9-Jan-13 1 YEAR COMPLETE 9 17-Jan-13 29-Jan-13 1 WEEK COMPLETE 10 17-Jan-13 13-Feb-13 1 WEEK COMPLETE WORK ORDER NO. Descripti on Received Date Duration Machine Flange Adapter (Relief To transfer Project Materials Provide Blasting Painting Manpower for Offshore Touch Up Painting Maintenan ce Work n of V- 2326 at CKP Punchlist Clearance for CM3 at CKR Platform Clearance for BMA/BLA/S YA Flare tip rectifica tion Provide a dedicated project managemen t team (PMT) Switch- gear support at CKP and Install the Sand Monitorin g Cabinet Support

Upload: syahroslizam-suhaimi

Post on 27-Nov-2014

40 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: List of Work Order

WORK ORDER REQUEST

Description Date Received Est. Start Date Status

1 10-Jan-13 16-Jan-13 1 WEEK COMPLETE

2 10-Jan-13 13-Jan-13 2-3 Days COMPLETE

3 13-Jan-13 23-Jan-13 12 WEEKS COMPLETE

4 13-Jan-13 19-Feb-13 2 WEEKS COMPLETE

5 15-Jan-13 13-Feb-13 3 WEEKS COMPLETE

6 15-Jan-13 20-Feb-13 3 WEEKS ON GOING

7 15-Jan-13 19-Jan-13 2 WEEKS COMPLETE

8 15-Jan-13 9-Jan-13 1 YEAR COMPLETE

9 17-Jan-13 29-Jan-13 1 WEEK COMPLETE

10 17-Jan-13 13-Feb-13 1 WEEK COMPLETE

WORK ORDER NO. Work

Duration

To Machine Flange Adapter (Relief Valve)

To transfer Project Materials

Provide Blasting Painting Manpower for Offshore Touch Up Painting Maintenance Work

Inspection of V-2326 at CKP Platform

Punchlist Clearance for CM3 at CKR Platform

Punchlist Clearance for BMA/BLA/SYA Platforms

Flare tip rectification

Provide a dedicated project management team (PMT)

Switch-gear support at CKP

Fabricate and Install the Sand Monitoring Cabinet Support Stand

Page 2: List of Work Order

11 23-Jan-13 18-Feb-13 2 WEEKS COMPLETE

12 23-Jan-13 3-Feb-13 1 WEEK COMPLETE

13 23-Jan-13 19-Feb-13 1 WEEK COMPLETE

14 2-Apr-13 10-Aug-13 14 DAYS COMPLETE

15 23-Jan-13 2-Feb-13 8 WEEKS COMPLETE

16 23-Jan-13 4-Feb-13 3 DAYS COMPLETE

17 23-Jan-13 17-Feb-13 3 DAYS COMPLETE

18 6-Feb-13 19-Feb-13 7 DAYS COMPLETE

19 CANCEL

20 12-Feb-13 18-Feb-13 4 DAYS COMPLETE

To install additional fastener and support on the membrane area module 5 & 6 wall clading

Repair weldment crack on the hot water tank

Base modification for refrigeration condenser.

Flare Tip Rectification Work

Hook Up and Commissioning for SYA Flowlines

Provide welder and fitter for offshore work

Positive Isolation for Shutdown Work

Drip Ring for Level Transmitter

WORK ORDER CANCELLED

Teletest Inspection of Flare Tip Piping

Page 3: List of Work Order

21 17-Feb-13 2-Mar-13 8 WEEKS COMPLETE

22 17-Feb-13 4-Mar-13 1 WEEK COMPLETE

23 17-Feb-13 2-Jun-13 2 WEEKS COMPLETE

24 21-Feb-13 16-Mar-13 4 WEEKS COMPLETE

25 27-Feb-13 4-Apr-13 1 WEEK COMPLETE

26 28-Feb-13 4-Mar-13 2 WEEKS COMPLETE

27 28-Feb-13 16-Apr-13 4 WEEKS CANCEL

28 28-Feb-13 16-Mar-13 1 WEEK COMPLETE

29 28-Feb-13 11-Mar-13 6 WEEKS COMPLETE

30 5-Mar-13 11-Mar-13 2 WEEKS COMPLETE

31 5-Mar-13 11-Mar-13 2 WEEKS COMPLETE

ONSHORE FABRICATION OF TEST LOOP WET GAS VENTURI METERING SYSTEM FOR CKA, CKB AND CKC

To replace 24 VDC Beacons with 240 VAC Type

Install 17 DVC and Test Point for Gas Detector

Bumi Boat Landing Modification

Replacement BLA Sampling Valve

Provide phone line at CM3

To provide work boat for BUMI ractification work

20" Blind Flange Reinstatement work at SYA

Provide scaffold for the touch up painting work

Cradle Support Modification For SGC#3 REV 1

Provide Hydraulic Torque Wrench for V-2326

Page 4: List of Work Order

32 21-Mar-13 2-Apr-13 2 WEEKS COMPLETE

33 21-Mar-13 2-Apr-13 2 WEEKS CANCEL

34 10-Mar-13 13-Mar-13 1 DAY COMPLETE

35 27-Mar-13 2-Apr-13 2 WEEKS COMPLETE

36 3-Apr-13 5-Apr-13 2 WEEKS COMPLETE

37 27-Mar-13 9-Apr-13 3 WEEKS COMPLETE

38 27-Mar-13 2-Apr-13 1 WEEK COMPLETE

39 2-Apr-13 2-Aug-13 4 WEEKS CANCEL

40 3-Apr-13 10-Aug-13 10 DAYS COMPLETE

41 3-Apr-13 10-Aug-13 10 DAYS COMPLETE

42 3-Apr-13 10-Aug-13 10 DAYS COMPLETE

43 3-Apr-13 9/8.2009 10 DAYS COMPLETE

Fabricate and Install Valves with Elbow and Flanges for Level Transmitter / Gauge at CKP

Purchase and Install Split Unit Aircond At SYA Platform

HSE Management Workshop

Erect Scaffolding below BLA and CKP HVAC

To erect scaffolding at CKR

To replace New bolt and Rubber Seal For Hatch Cover

To supply services of safe house habitat

Install 3rd propane Condenser (Offshore)

Install Drip Ring Level Transmitter (Offshore)

Install Mercury Catch Pot

To fabricate and Install The Isolation Valve & Test Port For PSV

20" GRE Pipe Repair Work

Page 5: List of Work Order

44 3-Feb-13 5-Apr-13 2 DAYS COMPLETE

45 10-Apr-13 2-May-13 2 WEEKS COMPLETE

46 13/03/2009 Receive 14/4/20092-May-13 2 WEEKS COMPLETE

47 CANCELLED CANCEL

48 16-Apr-13 2-Aug-13 3 WEEKS COMPLETE

49 16-Apr-13 2-Aug-13 3 WEEKS COMPLETE

50 16-Apr-13 2-Aug-13 3 WEEKS COMPLETE

51 5-May-13 16-May-13 2 WEEKS COMPLETE

52 12-May-13 15-May-13 12 WEEKS COMPLETE

53 16-May-13 19-May-13 1 WEEK COMPLETE

54 16-May-13 2-Aug-13 3 WEEKS COMPLETE

Modification of Container to secure the engine

Vessel Cleaning For Condensate Surge Drum, V-3000

Insulation Work at CKP Platform

Install Test Loop Wet Gas Venturi Metering at CKA

Install Test Loop Wet Gas Venturi Metering at CKC

CKA Conductor Hatch Cover

To relocate the pressure gauge and pressure transmitter tubing line at CKA/CKB/CKC

Provide Blasting Painting Manpower for Touch Up Painting Maintenance Work

To erect Scaffolding at the 24" PG Line at CKP

To Provide Scaffolding set and Erect of Scaffolding

Page 6: List of Work Order

55 22-May-13 2-Jul-13 2 WEEKS ON GOING

56 22-May-13 30-Mar-13 3 MONTHS COMPLETE

57 22-May-13 10-Aug-13 2 WEEKS COMPLETE

58 22-May-13 10-Aug-13 2 WEEKS COMPLETE

59 22-May-13 10-Aug-13 1 WEEK CANCEL

60 23-May-13 10-Aug-13 1 WEEK COMPLETE

61 23-May-13 10-Aug-13 2 WEEKS COMPLETE

62 23-May-13 10-Aug-13 2 WEEKS COMPLETE

63 23-May-13 10-Aug-13 2 WEEKS COMPLETE

64 23-May-13 10-Aug-13 2 WEEKS COMPLETE

65 23-May-13 10-Aug-13 2 WEEKS COMPLETE

WHCP Modification Work at BMA, BLA and SYA

Provide Scaffold for the touch up painting work at CKP

To replace CKA DBB Diverter ValvesTo replace Jiulong Valves on 3 pig receivers

To erect Scaffolding at CKR-XV-2901 for Sealant Injection

Sale Gas Compressor #3 Labyrinth Seal Changeout

Vessel Cleaning for CKP-V-5500, Closed Drain Drum

Vessel Internal Inspection for CKR-V-5500, Closed Drain Drum

Inspection of Exchanger Tube CKP-E-4002A/B, Fuel Gas Heater

To Change out Bolt and Nuts on receivers

To change out bolt and nuts on Train 1 Inlet cooler

Page 7: List of Work Order

66 23-May-13 10-Aug-13 2 WEEKS COMPLETE

67 23-May-13 10-Aug-13 2 WEEKS COMPLETE

68 23-May-13 16-Jun-13 2 WEEKS COMPLETE

69 23-May-13 16-Jul-13 2 WEEKS ON GOING

70 9-Jun-13 10-Jun-13 1 WEEK COMPLETE

71 12-Jun-13 10-Aug-13 2 WEEKS COMPLETE

72 12-Jun-13 10-Aug-13 2 WEEKS COMPLETE

73 12-Jun-13 10-Aug-13 2 WEEKS COMPLETE

74 12-Jun-13 10-Aug-13 2 WEEKS COMPLETE

75 13-Jun-13 10-Aug-13 2 WEEKS COMPLETE

76 13-Jun-13 10-Aug-13 1 WEEK COMPLETE

77 18-Jun-13 10-Aug-13 1 WEEK COMPLETE

To Install Butterfly Valves at Sea water booster pump piping

Replacemet of the MOV-HV-2814

Fabricate Cradle Support for Solar Turbines

Reinstatement work at CKP/CKR/CKC

To supply Services of Safe House Habitat

To change out Bolt and Nuts on Vibration Transmitter

To change out Bolt and Nuts on Downstream Dehydrator

To change out Bolt and Nuts on Membrane (Cluster 5&6)

To change out Bolt and Nuts on Compression Module 3

To assist Choke Valve Vendor

To transfer DCS Consoles

To supply 20" Insulation Gasket

Page 8: List of Work Order

78 23-Jun-13 10-Aug-13 2 WEEKS COMPLETE

79 23-Jun-13 24-Aug-13 1 WEEK COMPLETE

80 27-Jun-13 2-Aug-13 3 WEEKS COMPLETE

81 27-Jun-13 16-Sep-13 3 WEEKS COMPLETE

82 27-Jun-13 27-Jun-13 3 WEEKS COMPLETE

83 27-Jun-13 16-Oct-13 3 WEEKS ON GOING

84 27-Jun-13 16-Oct-13 4 WEEKS COMPLETE

85 27-Jun-13 16-Nov-13 3 WEEKS ON GOING

86 14-Jul-13 10-Aug-13 2 WEEKS COMPLETE

87 21-Jul-13 25-Jul-13 1 WEEK COMPLETE

88 22-Jul-13 9-Aug-13 2 WEEKS COMPLETE

Positive Isolation nd Nitrogen Purging for August Shutdown

Service Water Pump and Sea Water Lift Pump Cradle Support

To fabricate and Install New Pipe Supports and Structures at CKP

To fabricate and Install New Access Platform at FSO

Modification of Crane Boom Rest

Lighting Improvement at CKP

Extension Deck and Service Platform at CKP

York Refrigeration Compressor Shelter

Miscellaneous Work For August Shutdown

To Install 20" MOV HV-0904 at SYA

Insulation Work At K-4200 Compressor and PSV

Page 9: List of Work Order

89 25-Jul-13 9-Aug-13 2 WEEKS COMPLETE

90 31-Jul-13 31-Jul-13 1 WEEK COMPLETE

91 25-Aug-13 NOV 10 WEEKS ON GOING

92 26-Aug-13 SEPT 4 WEEKS COMPLETE

93 28-Aug-13 SEPT 4 WEEKS COMPLETE

94 28-Aug-13 OCT 2 WEEKS COMPLETE

95 2-Sep-13 SEPT 2 WEEKS COMPLETE

96 5-Sep-13 SEPT 1 WEEK COMPLETE

97 9-Sep-13 9-Sep-13 1 YEAR ON GOING

98 9-Sep-13 29-Sep-13 2 WEEKS COMPLETE

Mercury Exposure Monitoring

Weight Balancing & Bundle Removal Bracket

Hook up and Commissioning of Bumi Shallow Flowlines

SYA REPAIR WORK

To convert Jet A1 Fuel Skid into PCHE Cleaning Equipment

To change out Dehydrator Vessels Sorbead (V-2423& V-2424)

To provide Painting and Scaffolding crews for Post Shutdown Work

To erect scaffolding and Working Platform for GG Removal

To provide Painting Crew and Scaffolder at CKP

To provide Manpower for Valve Hydrotest

Page 10: List of Work Order

99 9-Sep-13 29-Sep-13 2 WEEKS COMPLETE

100 10-Sep-13 29-Sep-13 2 WEEKS CANCEL

101 12-Sep-13 16-Sep-13 2 WEEKS COMPLETE

102 18-Sep-13 26-Sep-13 2 WEEKS COMPLETE

103 18-Sep-13 26-Sep-13 2 WEEKS COMPLETE

104 18-Sep-13 26-Sep-13 3 WEEKS COMPLETE

105 #REF! 2-Aug-13 3 WEEKS COMPLETE

106 1-Oct-13 6-Oct-13 4 WEEKS COMPLETE

107 18-Sep-13 26-Sep-13 3 WEEKS COMPLETE

108 #REF! 2-Oct-13 3 WEEKS 0

To upgrade pressure gauge and modify collection point at mercury catch pots

To fabricate and install handrail at BMA, BLA & SYA

To complete wiring and perform instrument loop testing

To replace Crack 8" GRE Deluge pipe at CKP

To erect scaffolding & cable pulling for HVAC at BMA & SYA

To install lifting lugs at BMA Main & Cellar Deck

Install Test Loop Wet Gas Venturi Metering at CKB

To install protection guard on the diverter valve at CKA

To close out UCUA findings on CKPTO INSTALL ONE UNIT OF 3 PHASE SOCKET OUTLET AT CKP

Page 11: List of Work Order

109 6-Oct-13 DEC 4 MONTHS ON GOING

110 8-Oct-13 8-Oct-13 20 DAYS COMPLETE

111 20-Oct-13 26-Oct-13 I2 MONTHS ON GOING

112 15-Oct-13 15-Oct-13 20 DAYS COMPLETE

113 20-Oct-13 27-Oct-13 1 MONTH ON GOING

114 27-Oct-13 27-Oct-13 1 WEEK COMPLETE

115 21-Oct-13 6-Nov-13 1 MONTH COMPLETE

116 23-Oct-13 8-Nov-13 1 WEEK COMPLETE

117 23-Oct-13 24-Oct-13 2 WEEKS COMPLETE

118 28-Oct-13 6-Nov-13 2 WEEKS COMPLETE

To fabricate and install Bumi deep pilot well

To machine Xmas tree valve thread protection

To provide one porta cabin for CSR/PMT office at CKPTo install Acrylic Stem Protector

To carry out inspection, cleaning or replace tubings at the CKP, CKR, CKA, CKB & CKA

To close all 4 ISO corners on CKA-V-41110A (Propoane Vessel)

To install 2 units of IR detectors for each GQ-7500 and 20 Diesel Fuel Skids

Solar Engine Change Out and RVDT Upgrade

Installation of TLQ and Associated facilities at CKP upper deck

To perform cleaning work on PCHE gas cooler train 1&2 with jet A1 Pump Skid

Page 12: List of Work Order

119 3-Nov-13 10-Nov-13 1 WEEK COMPLETE

120 11-Nov-13 14-Nov-13 2 MONTHS COMPLETE

121 11-Nov-13 13-Nov-13 1 DAY COMPLETE

122 17-Nov-13 18-20/11 3 DAYS COMPLETE

123 25-Nov-13 19-Jan-13 1 WEEK COMPLETE

124 19-Nov-13 21-Nov-13 2 WEEKS COMPLETE

125 25-Nov-13 2-Dec-13 2 WEEK COMPLETE

126 25-Nov-13 6-Dec-13 2 WEEKS COMPLETE

127 2-Dec-13 11-Jan-13 2 WEEKS 0

To fabricate and replace CKP-Topside hatch cover

To replace all corroded and worn out grating

To organize joint HSE Day for 150k manhours without LTI at Legend Hotel, Cherating, Kuantan

To repair the boat landing structure on UFCB Jati 1

To remove existing air dryer and install 2 new dryer units at FSO

To replace all missing gratings at BLA Sea Deck area

To perform MPI test on Oilfab Cabin and Metal Basket

To modify existing CKR CM1 and CM2 Lube Oil drain line

To fabricate 2 new pumps enclosure (Bolted SS type)

Page 13: List of Work Order

128 8-Dec-13 11-Dec-13 3 WEEKS CANCEL

129 10-Dec-13 9-Mar-10 2 WEEKS 0

130 10-Dec-13 1-Jan-14 3 WEEKS COMPLETE

131 10-Dec-13 21-Jan-14 2 WEEKS 0

132 10-Dec-13 22-Jan-14 2 WEEKS COMPLETE

133 30-Dec-13 1-7/2/10 1 WEEK COMPLETE

134 30-Dec-13 11-Jan-14 1 WEEK COMPLETE

135 30-Dec-13 9-Jan-14 1 WEEK COMPLETE

To survey, evaluate & propose to CH the valve repair workshop

To repair minor damage to BLA Jacket Leg

To support sorbead change out for V2321 & v2322 Dehydrator Vessel

To repair & replacement of damaged cold insulation for membrane housing T1C3 & pipe spool

To repair kick plate, drain line & stair step at skid beam at ckc

To replace valves on CKC production manifold & test header (DBB & Ball Valves)

Blasting & painting weir pump special tools and big blind flanges

To erect scaffolding for Drop Spools site survey at CM3 Area

Page 14: List of Work Order

136 30-Dec-13 11-Jan-14 1 WEEK COMPLETE

137 7-Jan-14 1-Feb-14 3 WEEKS COMPLETE

138 9-Jan-14 16-Feb-14 2 WEEKS COMPLETE

139 15-Jan-14 22-Jan-14 2 WEEKS ON HOLD

140 #REF! #REF! #REF! COMPLETE

141 16-Jan-14 26-Jan-14 2 WEEKS COMPLETE

142 23-Jan-14 2-Jan-14 1 YEAR ON GOING

143 23-Jan-14 26-Jan-14 3 DAYS COMPLETE

144 27-Jan-14 2-Apr-14 1 WEEK COMPLETE

To perform MPI and Load Test for pad eyes in FSO Pump Room

To support Sorbead change out for V2325 & V 2326 Dehydrator Vessels

To fabricate metal container for york refrigeration

To perform power tooling and painting on upper deck (condensate MRU area)

To install additional grating, handrails and kick plate at CKP module 6

To assist in cable pulling & Installation of open path and point flame detectors

Provide a dedicated PMT for 2010

To identify the material grade for FSO pad eye

To replace endcap at C2 Flowline, CKC Platform

Page 15: List of Work Order

145 26-Jan-14 31-Jan-14 1 WEEK COMPLETE

146 27-Jan-14 16-Feb-14 2 WEEKS ON GOING

147 4-Feb-14 16-Feb-14 1 WEEK COMPLETE

148 4-Feb-14 26-Feb-14 1 WEEK COMPLETE

149 4-Feb-14 21-Feb-14 1 WEEK 0

150 4-Feb-14 6-Feb-14 7 WEEKS COMPLETE

151 4-Feb-14 18-Feb-14 2 WEEKS COMPLETE

152 4-Feb-14 11-Feb-14 2 WEEKS COMPLETE

153 5-Feb-14 11-Feb-14 2 WEEKS COMPLETE

To erect scaffolding planks & canvas to cover solar panel at BMA

To modify 2 existing monorails beams at fire water pumps area

Removal of King Post for Burner Test Boom on BMA

Removal of King Post for Burner Test Boom on SYA

To remove all the CKA main deck facilities that could be obstruction for T-10 Drilling Rig

To fabricate SS316 Foam Tank

To fabricate and install Kicker Plates at Life Boat A/B/C Platforms

To assemble choke valve missing parts and perform testing

To fabricate the clamp with hook for bunkering hoses

Page 16: List of Work Order

154 5-Feb-14 5-Feb-14 4 WEEKS 0

155 5-Feb-14 4-Mar-14 2 WEEKS COMPLETE

156 11-Feb-14 2-Jul-14 3 WEEKS COMPLETE

157 11-Feb-14 2-Jul-14 3 WEEKS COMPLETE

158 11-Feb-14 2-Jul-14 3 WEEKS COMPLETE

159 11-Feb-14 2-Jul-14 3 WEEKS COMPLETE

160 11-Feb-14 2-Jul-14 3 WEEKS COMPLETE

161 #REF! #REF! #REF! #REF! CANCEL

162 18-Feb-14 2-Mar-14 3 MONTHS ON GOING

163 18-Feb-14 26-Feb-14 3 WEEKS COMPLETE

164 4-Mar-14 16-Mar-14 1 WEEK ON GOING

To replace clogged GRE piping on CKC open drain system

To replace leaking 16" MOV Valves at CKR metering system

To perform RFET/IRIS Inspection of Exchanger Tubes

Vessel Cleaning for V-2002, Inlet Separator

Vessel Cleaning for V-2052, Inlet Separator

Vessel Cleaning for V-5000, Knock-Out Drum

Vessel Cleaning for V-5500, Closed-Drain Drum (July shutdown)

Refurbish 20 Pcs of CKA Hatch Covers

To support Sorbead Change out for V2328 Dehydrator Vessel

To repair ARV fittings at firewater pump P 8000/8030

Page 17: List of Work Order

165 2-Mar-14 7-Mar-14 1 WEEK COMPLETE

166 6-Mar-14 2-Jul-14 2 WEEKS COMPLETE

167 30-Mar-14 16-Apr-14 2 WEEKS COMPLETE

168 7-Apr-14 16-Apr-14 1 WEEK CANCEL

169 10-Apr-14 26-Apr-14 2 WEEKS COMPLETE

170 28-Apr-14 29-Apr-14 75 days COMPLETE

171 23-Apr-14 23-Apr-14 1 week 0

172 28-Apr-14 29-Apr-14 75 days COMPLETE

173 27-Apr-14 7-May-14 1 day COMPLETE

Scramble nets and life raft for BMA & CKPTo install DBB Valves on BMA Production Manifold

To install temporary pump base and heavy duty hoses

To fabricate the push tool for offshore

To support sorbead change out for V2323/2324 Dehydrator vessel

Additional 2" venting line from Songkhla Launcher facilities to HP flare system (July 2010 Shutdown)

To fabricate circle shape Bakelite washer

Modification of Existing pipe with the additional drop spool for PCHE maintenance (July 2010 Shutdown)

To perform leak test for refrigeration condenser at CSB

Page 18: List of Work Order

174 27-Apr-14 2-May-14 2 weeks COMPLETE

175 30-Apr-14 16-Jun-14 30 days COMPLETE

176 27-Apr-14 27-Apr-14 2 weeks 0

177 27-Apr-14 2-May-14 2 weeks 0

178 28-Apr-14 1-Jul-14 9 days COMPLETE

179 28-Apr-14 22-Jun-14 18 days COMPLETE

180 28-Apr-14 29-Jun-14 20 days COMPLETE

To fabricate and install GRE pipe spool & pipe support at CKP

CM3 Alignment Work

To install kick plate for handrails ar upper deck module 5 & 6

To supply & install new curtains for CKP LQ

Condenser Removal and reinstatement for refrigeration condenser, E-4101 & E4021 (July 2010 Shutdown)

Insulation of piping spool for sea water booster pump (July 2010 shutdown)

Installation of new FGS cabinet and RPM in CKP IER (July 2010 Shutdown)

Page 19: List of Work Order

181 28-Apr-14 2-Jul-14 7 days COMPLETE

182 28-Apr-14 1-Jul-14 9 days CANCEL

183 29-Apr-14 2-Jul-14 10 days COMPLETE

184 29-Apr-14 29-Apr-14 3 days COMPLETE

185 29-Apr-14 21-May-14 2 weeks 0

186 29-Apr-14 2-May-14 2 weeks 0

187 6-May-14 2-Jul-14 7 days COMPLETE

188 30-Apr-14 16-May-14 1 Week 0

Relocation of Transmitter tapping point and replacement of transmitter (from displacer to guided wave radar) (July 2010 shutdown)

Install partial stroke facilities (scaffolding) for CKR-XV-2000 shutdown valve. (July 2010 shutdown)

DBB change out as SYA (July 2010 shutdown)

To cut a small section of H-beam at CKC mezz deck

To perform load test and stencil for all lifting padeyes at FSO

To fabricate the LQ foam nozzle piping supports

Modification of level transmitter (July 2010 Shutdown)

To replace 1" Air Supply Pipe at Open Drain Pump

Page 20: List of Work Order

189 5-May-14 4-Jul-14 5 days COMPLETE

190 13-May-14 21-May-14 2 Weeks 0

191 13-May-14 21-May-14 3 Weeks 0

192 8-May-14 9-Jun-14 1 Week ON GOING

193 15-May-14 10-Sep-14 3 Weeks ON GOING

194 15-May-14 4-Jul-14 1 WEEK COMPLETE

195 15-May-14 4-Jul-14 1 WEEK 0

196 22-May-14 4-Jul-14 2 Weeks COMPLETE

197 19-May-14 1-Jul-14 3 WEEKS COMPLETE

Instrument Gas System Modification at SYA

To repair badly corroded drip pan hole for propoane condenser package at top deck

To replace the protection cage at hot condy line at CKP

To Fabricate, Install and Commissioning of GRE Piping for New Bunkering Station

Standby Seawater Booster Pump

To separate the Instrument and Process Vent at SYA during July SD

To reinstate back the in line strainer at SGC#3 (Train 1 & 2) during July SD

Compressor Shaft Seal Replacement Work During July Shutdown

Miscellaneous Work for July 2010 Shutdown

Page 21: List of Work Order

198 21-May-14 16-May-14 2 Weeks COMPLETE

199 21-May-14 4-Jul-14 2 Weeks COMPLETE

200 27-May-14 6-Jun-14 1 WEEK 0

201 27-May-14 16-Jul-14 2 weeks 0

202 1-Jun-14 16-Aug-14 3 WEEKS ON GOING

203 1-Jun-14 1-Jul-14 9 days COMPLETE

204 9-Jun-14 10-Jun-14 2 months COMPLETE

205 9-Jun-14 4-Jul-14 12 Days COMPLETE

206 9-Jun-14 4-Jul-14 12 Days COMPLETE

To support sorbead change out for V2327 Dehydrator Vessel

Positive isolation and nitrogen purging for July 2010 SD

To remove ram skid from skid from CKC & reinstate the handrail

To install new condensed rubber at CKB & CKC boat landing fenders

To fabricate & install 8 leftover P2 post shutdown pipe support at CKP

To replace cracked GRE flanges at condenser heat exchanger

To provide and install liferaft for July S/D3rd party to supervise the 16" valve actuators installation during July S/D

3rd party for bolt tensioning activities during July shutdown

Page 22: List of Work Order

207 10-Jun-14 24-Jun-14 1 WEEK COMPLETE

208 19-Jun-14 4-Jul-14 12 Days CANCEL

209 19-Jun-14 31-Aug-14 2 WEEKS COMPLETE

210 19-Jun-14 21-Jul-14 2 WEEKS COMPLETE

211 19-Jun-14 25-Jun-14 1 WEEK ON GOING

212 16-Jul-14 Jul/14 3 DAYS COMPLETE

213 17-Jul-14 22-Jul-14 7 days ON GOING

214 21-Jul-14 2-Sep-14 14 days 0

215 22-Jul-14 22-Jul-14 1 WEEK COMPLETE

To install DBB Valves on CKB Production Manifold

3rd party to supervise the 16" valve actuators installation during July S/D

To overhaul Snr. Orifice & Tube inspection at metering system

To replace exisiting cracked weld neck flange & reinstall spool at CKA

To modify cradle for sea water lift pump 4350

To preserve 8 nos of 16" metering valve

To provide scaffold at CKB B-7300

To perform Passive Fire Protection (PFP) application at CCR roof

To supply and fabricate add. Beam support for monorail load testing

Page 23: List of Work Order

216 22-Jul-14 22-Jul-14 1 WEEK 0

217 28-Jul-14 31-Jul-14 1 WEEK 0

218 4-Aug-14 29-Sep-14 1 WEEK 0

219 4-Aug-14 21-Aug-14 2 WEEKS 0

220 4-Aug-14 Feb/15 4 WEEKS 0

221 4-Aug-14 Feb/15 5 Weeks 0

222 4-Aug-14 Feb/15 2 WEEKS 0

To relocate temporarily discharge line of wilden pump from cellar deck to new tie-in point at upper deck

To modify existing Gre piping for additional drop spool at inlet cooling medium coolers (CKP-E-4580)

To erect scaffolding and assist solar FSR to perform engine and RGB change out

To provide acces platform at SGC 3 glass window

To replace all corroded and worn out grating on sea deck area ( CKC platform)

To paint black and yellow stripes at the main beam boat landing (CKB, CKC, BMA, BLA and SYA)

To fabricate and install pipe support

Page 24: List of Work Order

223 4-Aug-14 5-Aug-14 1 WEEK COMPLETE

224 6-Aug-14 16-Sep-14 6 WEEKS 0

225 28-Aug-14 29-Aug-14 1 WEEK COMPLETE

226 25-Aug-14 Dec/14 3 WEEKS 0

227 26-Aug-14 27-Aug-14 1 WEEK ON GOING

228 26-Aug-14 28-Aug-14 1 WEEK COMPLETE

229 28-Aug-14 Dec/14 4 WEEKS 0

230 28-Aug-14 Dec/14 1 WEEK 0

231 31-Aug-14 Feb/15 2 WEEKS 0

To replace pipe spool on pin hole leaking elbow at CKP liquid leg lines

Extension platform for VSAT antenna at LQ CKP

Vessel cleaning V-3702

Installation of produce water reinjection well flowlines

To close the ISO corner holes of the propane tank skid (CKA-V-4110C)

To assist well services on valves and blinds installation

To remove and reinstall wellheads chocke valve (CKA/CKB/CKC/SYA/BMA) for inspection purpose

To secure transmitters capillary tube with proper support (CKP-LIT-2003 and CKP-LIT-2053)

Installation of additional R.O. water maker at CKP-XQ-6012

Page 25: List of Work Order

232 31-Aug-14 Feb/15 2 WEEKS 0

233

TOTAL

NOS Amount

232 #REF!

#REF! #REF!

#REF! #REF!

#REF! #REF!

168 #REF!

20 #REF!

12

31

-

Crane exhaust modification at BMA/BLA/SYA

Total Work Order Request To Date

Total Work Order Proposal

Total Outstanding Work Order Proposal

Total Work Order Approved

Approved Completed Work Order Amount

Amount Work Order On-Going

Total Work Order Cancel

Total Work Order Not Yet Start

Variance (Amount Can't be Utilised)