WORK ORDER REQUEST
Description Date Received Est. Start Date Status
1 10-Jan-13 16-Jan-13 1 WEEK COMPLETE
2 10-Jan-13 13-Jan-13 2-3 Days COMPLETE
3 13-Jan-13 23-Jan-13 12 WEEKS COMPLETE
4 13-Jan-13 19-Feb-13 2 WEEKS COMPLETE
5 15-Jan-13 13-Feb-13 3 WEEKS COMPLETE
6 15-Jan-13 20-Feb-13 3 WEEKS ON GOING
7 15-Jan-13 19-Jan-13 2 WEEKS COMPLETE
8 15-Jan-13 9-Jan-13 1 YEAR COMPLETE
9 17-Jan-13 29-Jan-13 1 WEEK COMPLETE
10 17-Jan-13 13-Feb-13 1 WEEK COMPLETE
WORK ORDER NO. Work
Duration
To Machine Flange Adapter (Relief Valve)
To transfer Project Materials
Provide Blasting Painting Manpower for Offshore Touch Up Painting Maintenance Work
Inspection of V-2326 at CKP Platform
Punchlist Clearance for CM3 at CKR Platform
Punchlist Clearance for BMA/BLA/SYA Platforms
Flare tip rectification
Provide a dedicated project management team (PMT)
Switch-gear support at CKP
Fabricate and Install the Sand Monitoring Cabinet Support Stand
11 23-Jan-13 18-Feb-13 2 WEEKS COMPLETE
12 23-Jan-13 3-Feb-13 1 WEEK COMPLETE
13 23-Jan-13 19-Feb-13 1 WEEK COMPLETE
14 2-Apr-13 10-Aug-13 14 DAYS COMPLETE
15 23-Jan-13 2-Feb-13 8 WEEKS COMPLETE
16 23-Jan-13 4-Feb-13 3 DAYS COMPLETE
17 23-Jan-13 17-Feb-13 3 DAYS COMPLETE
18 6-Feb-13 19-Feb-13 7 DAYS COMPLETE
19 CANCEL
20 12-Feb-13 18-Feb-13 4 DAYS COMPLETE
To install additional fastener and support on the membrane area module 5 & 6 wall clading
Repair weldment crack on the hot water tank
Base modification for refrigeration condenser.
Flare Tip Rectification Work
Hook Up and Commissioning for SYA Flowlines
Provide welder and fitter for offshore work
Positive Isolation for Shutdown Work
Drip Ring for Level Transmitter
WORK ORDER CANCELLED
Teletest Inspection of Flare Tip Piping
21 17-Feb-13 2-Mar-13 8 WEEKS COMPLETE
22 17-Feb-13 4-Mar-13 1 WEEK COMPLETE
23 17-Feb-13 2-Jun-13 2 WEEKS COMPLETE
24 21-Feb-13 16-Mar-13 4 WEEKS COMPLETE
25 27-Feb-13 4-Apr-13 1 WEEK COMPLETE
26 28-Feb-13 4-Mar-13 2 WEEKS COMPLETE
27 28-Feb-13 16-Apr-13 4 WEEKS CANCEL
28 28-Feb-13 16-Mar-13 1 WEEK COMPLETE
29 28-Feb-13 11-Mar-13 6 WEEKS COMPLETE
30 5-Mar-13 11-Mar-13 2 WEEKS COMPLETE
31 5-Mar-13 11-Mar-13 2 WEEKS COMPLETE
ONSHORE FABRICATION OF TEST LOOP WET GAS VENTURI METERING SYSTEM FOR CKA, CKB AND CKC
To replace 24 VDC Beacons with 240 VAC Type
Install 17 DVC and Test Point for Gas Detector
Bumi Boat Landing Modification
Replacement BLA Sampling Valve
Provide phone line at CM3
To provide work boat for BUMI ractification work
20" Blind Flange Reinstatement work at SYA
Provide scaffold for the touch up painting work
Cradle Support Modification For SGC#3 REV 1
Provide Hydraulic Torque Wrench for V-2326
32 21-Mar-13 2-Apr-13 2 WEEKS COMPLETE
33 21-Mar-13 2-Apr-13 2 WEEKS CANCEL
34 10-Mar-13 13-Mar-13 1 DAY COMPLETE
35 27-Mar-13 2-Apr-13 2 WEEKS COMPLETE
36 3-Apr-13 5-Apr-13 2 WEEKS COMPLETE
37 27-Mar-13 9-Apr-13 3 WEEKS COMPLETE
38 27-Mar-13 2-Apr-13 1 WEEK COMPLETE
39 2-Apr-13 2-Aug-13 4 WEEKS CANCEL
40 3-Apr-13 10-Aug-13 10 DAYS COMPLETE
41 3-Apr-13 10-Aug-13 10 DAYS COMPLETE
42 3-Apr-13 10-Aug-13 10 DAYS COMPLETE
43 3-Apr-13 9/8.2009 10 DAYS COMPLETE
Fabricate and Install Valves with Elbow and Flanges for Level Transmitter / Gauge at CKP
Purchase and Install Split Unit Aircond At SYA Platform
HSE Management Workshop
Erect Scaffolding below BLA and CKP HVAC
To erect scaffolding at CKR
To replace New bolt and Rubber Seal For Hatch Cover
To supply services of safe house habitat
Install 3rd propane Condenser (Offshore)
Install Drip Ring Level Transmitter (Offshore)
Install Mercury Catch Pot
To fabricate and Install The Isolation Valve & Test Port For PSV
20" GRE Pipe Repair Work
44 3-Feb-13 5-Apr-13 2 DAYS COMPLETE
45 10-Apr-13 2-May-13 2 WEEKS COMPLETE
46 13/03/2009 Receive 14/4/20092-May-13 2 WEEKS COMPLETE
47 CANCELLED CANCEL
48 16-Apr-13 2-Aug-13 3 WEEKS COMPLETE
49 16-Apr-13 2-Aug-13 3 WEEKS COMPLETE
50 16-Apr-13 2-Aug-13 3 WEEKS COMPLETE
51 5-May-13 16-May-13 2 WEEKS COMPLETE
52 12-May-13 15-May-13 12 WEEKS COMPLETE
53 16-May-13 19-May-13 1 WEEK COMPLETE
54 16-May-13 2-Aug-13 3 WEEKS COMPLETE
Modification of Container to secure the engine
Vessel Cleaning For Condensate Surge Drum, V-3000
Insulation Work at CKP Platform
Install Test Loop Wet Gas Venturi Metering at CKA
Install Test Loop Wet Gas Venturi Metering at CKC
CKA Conductor Hatch Cover
To relocate the pressure gauge and pressure transmitter tubing line at CKA/CKB/CKC
Provide Blasting Painting Manpower for Touch Up Painting Maintenance Work
To erect Scaffolding at the 24" PG Line at CKP
To Provide Scaffolding set and Erect of Scaffolding
55 22-May-13 2-Jul-13 2 WEEKS ON GOING
56 22-May-13 30-Mar-13 3 MONTHS COMPLETE
57 22-May-13 10-Aug-13 2 WEEKS COMPLETE
58 22-May-13 10-Aug-13 2 WEEKS COMPLETE
59 22-May-13 10-Aug-13 1 WEEK CANCEL
60 23-May-13 10-Aug-13 1 WEEK COMPLETE
61 23-May-13 10-Aug-13 2 WEEKS COMPLETE
62 23-May-13 10-Aug-13 2 WEEKS COMPLETE
63 23-May-13 10-Aug-13 2 WEEKS COMPLETE
64 23-May-13 10-Aug-13 2 WEEKS COMPLETE
65 23-May-13 10-Aug-13 2 WEEKS COMPLETE
WHCP Modification Work at BMA, BLA and SYA
Provide Scaffold for the touch up painting work at CKP
To replace CKA DBB Diverter ValvesTo replace Jiulong Valves on 3 pig receivers
To erect Scaffolding at CKR-XV-2901 for Sealant Injection
Sale Gas Compressor #3 Labyrinth Seal Changeout
Vessel Cleaning for CKP-V-5500, Closed Drain Drum
Vessel Internal Inspection for CKR-V-5500, Closed Drain Drum
Inspection of Exchanger Tube CKP-E-4002A/B, Fuel Gas Heater
To Change out Bolt and Nuts on receivers
To change out bolt and nuts on Train 1 Inlet cooler
66 23-May-13 10-Aug-13 2 WEEKS COMPLETE
67 23-May-13 10-Aug-13 2 WEEKS COMPLETE
68 23-May-13 16-Jun-13 2 WEEKS COMPLETE
69 23-May-13 16-Jul-13 2 WEEKS ON GOING
70 9-Jun-13 10-Jun-13 1 WEEK COMPLETE
71 12-Jun-13 10-Aug-13 2 WEEKS COMPLETE
72 12-Jun-13 10-Aug-13 2 WEEKS COMPLETE
73 12-Jun-13 10-Aug-13 2 WEEKS COMPLETE
74 12-Jun-13 10-Aug-13 2 WEEKS COMPLETE
75 13-Jun-13 10-Aug-13 2 WEEKS COMPLETE
76 13-Jun-13 10-Aug-13 1 WEEK COMPLETE
77 18-Jun-13 10-Aug-13 1 WEEK COMPLETE
To Install Butterfly Valves at Sea water booster pump piping
Replacemet of the MOV-HV-2814
Fabricate Cradle Support for Solar Turbines
Reinstatement work at CKP/CKR/CKC
To supply Services of Safe House Habitat
To change out Bolt and Nuts on Vibration Transmitter
To change out Bolt and Nuts on Downstream Dehydrator
To change out Bolt and Nuts on Membrane (Cluster 5&6)
To change out Bolt and Nuts on Compression Module 3
To assist Choke Valve Vendor
To transfer DCS Consoles
To supply 20" Insulation Gasket
78 23-Jun-13 10-Aug-13 2 WEEKS COMPLETE
79 23-Jun-13 24-Aug-13 1 WEEK COMPLETE
80 27-Jun-13 2-Aug-13 3 WEEKS COMPLETE
81 27-Jun-13 16-Sep-13 3 WEEKS COMPLETE
82 27-Jun-13 27-Jun-13 3 WEEKS COMPLETE
83 27-Jun-13 16-Oct-13 3 WEEKS ON GOING
84 27-Jun-13 16-Oct-13 4 WEEKS COMPLETE
85 27-Jun-13 16-Nov-13 3 WEEKS ON GOING
86 14-Jul-13 10-Aug-13 2 WEEKS COMPLETE
87 21-Jul-13 25-Jul-13 1 WEEK COMPLETE
88 22-Jul-13 9-Aug-13 2 WEEKS COMPLETE
Positive Isolation nd Nitrogen Purging for August Shutdown
Service Water Pump and Sea Water Lift Pump Cradle Support
To fabricate and Install New Pipe Supports and Structures at CKP
To fabricate and Install New Access Platform at FSO
Modification of Crane Boom Rest
Lighting Improvement at CKP
Extension Deck and Service Platform at CKP
York Refrigeration Compressor Shelter
Miscellaneous Work For August Shutdown
To Install 20" MOV HV-0904 at SYA
Insulation Work At K-4200 Compressor and PSV
89 25-Jul-13 9-Aug-13 2 WEEKS COMPLETE
90 31-Jul-13 31-Jul-13 1 WEEK COMPLETE
91 25-Aug-13 NOV 10 WEEKS ON GOING
92 26-Aug-13 SEPT 4 WEEKS COMPLETE
93 28-Aug-13 SEPT 4 WEEKS COMPLETE
94 28-Aug-13 OCT 2 WEEKS COMPLETE
95 2-Sep-13 SEPT 2 WEEKS COMPLETE
96 5-Sep-13 SEPT 1 WEEK COMPLETE
97 9-Sep-13 9-Sep-13 1 YEAR ON GOING
98 9-Sep-13 29-Sep-13 2 WEEKS COMPLETE
Mercury Exposure Monitoring
Weight Balancing & Bundle Removal Bracket
Hook up and Commissioning of Bumi Shallow Flowlines
SYA REPAIR WORK
To convert Jet A1 Fuel Skid into PCHE Cleaning Equipment
To change out Dehydrator Vessels Sorbead (V-2423& V-2424)
To provide Painting and Scaffolding crews for Post Shutdown Work
To erect scaffolding and Working Platform for GG Removal
To provide Painting Crew and Scaffolder at CKP
To provide Manpower for Valve Hydrotest
99 9-Sep-13 29-Sep-13 2 WEEKS COMPLETE
100 10-Sep-13 29-Sep-13 2 WEEKS CANCEL
101 12-Sep-13 16-Sep-13 2 WEEKS COMPLETE
102 18-Sep-13 26-Sep-13 2 WEEKS COMPLETE
103 18-Sep-13 26-Sep-13 2 WEEKS COMPLETE
104 18-Sep-13 26-Sep-13 3 WEEKS COMPLETE
105 #REF! 2-Aug-13 3 WEEKS COMPLETE
106 1-Oct-13 6-Oct-13 4 WEEKS COMPLETE
107 18-Sep-13 26-Sep-13 3 WEEKS COMPLETE
108 #REF! 2-Oct-13 3 WEEKS 0
To upgrade pressure gauge and modify collection point at mercury catch pots
To fabricate and install handrail at BMA, BLA & SYA
To complete wiring and perform instrument loop testing
To replace Crack 8" GRE Deluge pipe at CKP
To erect scaffolding & cable pulling for HVAC at BMA & SYA
To install lifting lugs at BMA Main & Cellar Deck
Install Test Loop Wet Gas Venturi Metering at CKB
To install protection guard on the diverter valve at CKA
To close out UCUA findings on CKPTO INSTALL ONE UNIT OF 3 PHASE SOCKET OUTLET AT CKP
109 6-Oct-13 DEC 4 MONTHS ON GOING
110 8-Oct-13 8-Oct-13 20 DAYS COMPLETE
111 20-Oct-13 26-Oct-13 I2 MONTHS ON GOING
112 15-Oct-13 15-Oct-13 20 DAYS COMPLETE
113 20-Oct-13 27-Oct-13 1 MONTH ON GOING
114 27-Oct-13 27-Oct-13 1 WEEK COMPLETE
115 21-Oct-13 6-Nov-13 1 MONTH COMPLETE
116 23-Oct-13 8-Nov-13 1 WEEK COMPLETE
117 23-Oct-13 24-Oct-13 2 WEEKS COMPLETE
118 28-Oct-13 6-Nov-13 2 WEEKS COMPLETE
To fabricate and install Bumi deep pilot well
To machine Xmas tree valve thread protection
To provide one porta cabin for CSR/PMT office at CKPTo install Acrylic Stem Protector
To carry out inspection, cleaning or replace tubings at the CKP, CKR, CKA, CKB & CKA
To close all 4 ISO corners on CKA-V-41110A (Propoane Vessel)
To install 2 units of IR detectors for each GQ-7500 and 20 Diesel Fuel Skids
Solar Engine Change Out and RVDT Upgrade
Installation of TLQ and Associated facilities at CKP upper deck
To perform cleaning work on PCHE gas cooler train 1&2 with jet A1 Pump Skid
119 3-Nov-13 10-Nov-13 1 WEEK COMPLETE
120 11-Nov-13 14-Nov-13 2 MONTHS COMPLETE
121 11-Nov-13 13-Nov-13 1 DAY COMPLETE
122 17-Nov-13 18-20/11 3 DAYS COMPLETE
123 25-Nov-13 19-Jan-13 1 WEEK COMPLETE
124 19-Nov-13 21-Nov-13 2 WEEKS COMPLETE
125 25-Nov-13 2-Dec-13 2 WEEK COMPLETE
126 25-Nov-13 6-Dec-13 2 WEEKS COMPLETE
127 2-Dec-13 11-Jan-13 2 WEEKS 0
To fabricate and replace CKP-Topside hatch cover
To replace all corroded and worn out grating
To organize joint HSE Day for 150k manhours without LTI at Legend Hotel, Cherating, Kuantan
To repair the boat landing structure on UFCB Jati 1
To remove existing air dryer and install 2 new dryer units at FSO
To replace all missing gratings at BLA Sea Deck area
To perform MPI test on Oilfab Cabin and Metal Basket
To modify existing CKR CM1 and CM2 Lube Oil drain line
To fabricate 2 new pumps enclosure (Bolted SS type)
128 8-Dec-13 11-Dec-13 3 WEEKS CANCEL
129 10-Dec-13 9-Mar-10 2 WEEKS 0
130 10-Dec-13 1-Jan-14 3 WEEKS COMPLETE
131 10-Dec-13 21-Jan-14 2 WEEKS 0
132 10-Dec-13 22-Jan-14 2 WEEKS COMPLETE
133 30-Dec-13 1-7/2/10 1 WEEK COMPLETE
134 30-Dec-13 11-Jan-14 1 WEEK COMPLETE
135 30-Dec-13 9-Jan-14 1 WEEK COMPLETE
To survey, evaluate & propose to CH the valve repair workshop
To repair minor damage to BLA Jacket Leg
To support sorbead change out for V2321 & v2322 Dehydrator Vessel
To repair & replacement of damaged cold insulation for membrane housing T1C3 & pipe spool
To repair kick plate, drain line & stair step at skid beam at ckc
To replace valves on CKC production manifold & test header (DBB & Ball Valves)
Blasting & painting weir pump special tools and big blind flanges
To erect scaffolding for Drop Spools site survey at CM3 Area
136 30-Dec-13 11-Jan-14 1 WEEK COMPLETE
137 7-Jan-14 1-Feb-14 3 WEEKS COMPLETE
138 9-Jan-14 16-Feb-14 2 WEEKS COMPLETE
139 15-Jan-14 22-Jan-14 2 WEEKS ON HOLD
140 #REF! #REF! #REF! COMPLETE
141 16-Jan-14 26-Jan-14 2 WEEKS COMPLETE
142 23-Jan-14 2-Jan-14 1 YEAR ON GOING
143 23-Jan-14 26-Jan-14 3 DAYS COMPLETE
144 27-Jan-14 2-Apr-14 1 WEEK COMPLETE
To perform MPI and Load Test for pad eyes in FSO Pump Room
To support Sorbead change out for V2325 & V 2326 Dehydrator Vessels
To fabricate metal container for york refrigeration
To perform power tooling and painting on upper deck (condensate MRU area)
To install additional grating, handrails and kick plate at CKP module 6
To assist in cable pulling & Installation of open path and point flame detectors
Provide a dedicated PMT for 2010
To identify the material grade for FSO pad eye
To replace endcap at C2 Flowline, CKC Platform
145 26-Jan-14 31-Jan-14 1 WEEK COMPLETE
146 27-Jan-14 16-Feb-14 2 WEEKS ON GOING
147 4-Feb-14 16-Feb-14 1 WEEK COMPLETE
148 4-Feb-14 26-Feb-14 1 WEEK COMPLETE
149 4-Feb-14 21-Feb-14 1 WEEK 0
150 4-Feb-14 6-Feb-14 7 WEEKS COMPLETE
151 4-Feb-14 18-Feb-14 2 WEEKS COMPLETE
152 4-Feb-14 11-Feb-14 2 WEEKS COMPLETE
153 5-Feb-14 11-Feb-14 2 WEEKS COMPLETE
To erect scaffolding planks & canvas to cover solar panel at BMA
To modify 2 existing monorails beams at fire water pumps area
Removal of King Post for Burner Test Boom on BMA
Removal of King Post for Burner Test Boom on SYA
To remove all the CKA main deck facilities that could be obstruction for T-10 Drilling Rig
To fabricate SS316 Foam Tank
To fabricate and install Kicker Plates at Life Boat A/B/C Platforms
To assemble choke valve missing parts and perform testing
To fabricate the clamp with hook for bunkering hoses
154 5-Feb-14 5-Feb-14 4 WEEKS 0
155 5-Feb-14 4-Mar-14 2 WEEKS COMPLETE
156 11-Feb-14 2-Jul-14 3 WEEKS COMPLETE
157 11-Feb-14 2-Jul-14 3 WEEKS COMPLETE
158 11-Feb-14 2-Jul-14 3 WEEKS COMPLETE
159 11-Feb-14 2-Jul-14 3 WEEKS COMPLETE
160 11-Feb-14 2-Jul-14 3 WEEKS COMPLETE
161 #REF! #REF! #REF! #REF! CANCEL
162 18-Feb-14 2-Mar-14 3 MONTHS ON GOING
163 18-Feb-14 26-Feb-14 3 WEEKS COMPLETE
164 4-Mar-14 16-Mar-14 1 WEEK ON GOING
To replace clogged GRE piping on CKC open drain system
To replace leaking 16" MOV Valves at CKR metering system
To perform RFET/IRIS Inspection of Exchanger Tubes
Vessel Cleaning for V-2002, Inlet Separator
Vessel Cleaning for V-2052, Inlet Separator
Vessel Cleaning for V-5000, Knock-Out Drum
Vessel Cleaning for V-5500, Closed-Drain Drum (July shutdown)
Refurbish 20 Pcs of CKA Hatch Covers
To support Sorbead Change out for V2328 Dehydrator Vessel
To repair ARV fittings at firewater pump P 8000/8030
165 2-Mar-14 7-Mar-14 1 WEEK COMPLETE
166 6-Mar-14 2-Jul-14 2 WEEKS COMPLETE
167 30-Mar-14 16-Apr-14 2 WEEKS COMPLETE
168 7-Apr-14 16-Apr-14 1 WEEK CANCEL
169 10-Apr-14 26-Apr-14 2 WEEKS COMPLETE
170 28-Apr-14 29-Apr-14 75 days COMPLETE
171 23-Apr-14 23-Apr-14 1 week 0
172 28-Apr-14 29-Apr-14 75 days COMPLETE
173 27-Apr-14 7-May-14 1 day COMPLETE
Scramble nets and life raft for BMA & CKPTo install DBB Valves on BMA Production Manifold
To install temporary pump base and heavy duty hoses
To fabricate the push tool for offshore
To support sorbead change out for V2323/2324 Dehydrator vessel
Additional 2" venting line from Songkhla Launcher facilities to HP flare system (July 2010 Shutdown)
To fabricate circle shape Bakelite washer
Modification of Existing pipe with the additional drop spool for PCHE maintenance (July 2010 Shutdown)
To perform leak test for refrigeration condenser at CSB
174 27-Apr-14 2-May-14 2 weeks COMPLETE
175 30-Apr-14 16-Jun-14 30 days COMPLETE
176 27-Apr-14 27-Apr-14 2 weeks 0
177 27-Apr-14 2-May-14 2 weeks 0
178 28-Apr-14 1-Jul-14 9 days COMPLETE
179 28-Apr-14 22-Jun-14 18 days COMPLETE
180 28-Apr-14 29-Jun-14 20 days COMPLETE
To fabricate and install GRE pipe spool & pipe support at CKP
CM3 Alignment Work
To install kick plate for handrails ar upper deck module 5 & 6
To supply & install new curtains for CKP LQ
Condenser Removal and reinstatement for refrigeration condenser, E-4101 & E4021 (July 2010 Shutdown)
Insulation of piping spool for sea water booster pump (July 2010 shutdown)
Installation of new FGS cabinet and RPM in CKP IER (July 2010 Shutdown)
181 28-Apr-14 2-Jul-14 7 days COMPLETE
182 28-Apr-14 1-Jul-14 9 days CANCEL
183 29-Apr-14 2-Jul-14 10 days COMPLETE
184 29-Apr-14 29-Apr-14 3 days COMPLETE
185 29-Apr-14 21-May-14 2 weeks 0
186 29-Apr-14 2-May-14 2 weeks 0
187 6-May-14 2-Jul-14 7 days COMPLETE
188 30-Apr-14 16-May-14 1 Week 0
Relocation of Transmitter tapping point and replacement of transmitter (from displacer to guided wave radar) (July 2010 shutdown)
Install partial stroke facilities (scaffolding) for CKR-XV-2000 shutdown valve. (July 2010 shutdown)
DBB change out as SYA (July 2010 shutdown)
To cut a small section of H-beam at CKC mezz deck
To perform load test and stencil for all lifting padeyes at FSO
To fabricate the LQ foam nozzle piping supports
Modification of level transmitter (July 2010 Shutdown)
To replace 1" Air Supply Pipe at Open Drain Pump
189 5-May-14 4-Jul-14 5 days COMPLETE
190 13-May-14 21-May-14 2 Weeks 0
191 13-May-14 21-May-14 3 Weeks 0
192 8-May-14 9-Jun-14 1 Week ON GOING
193 15-May-14 10-Sep-14 3 Weeks ON GOING
194 15-May-14 4-Jul-14 1 WEEK COMPLETE
195 15-May-14 4-Jul-14 1 WEEK 0
196 22-May-14 4-Jul-14 2 Weeks COMPLETE
197 19-May-14 1-Jul-14 3 WEEKS COMPLETE
Instrument Gas System Modification at SYA
To repair badly corroded drip pan hole for propoane condenser package at top deck
To replace the protection cage at hot condy line at CKP
To Fabricate, Install and Commissioning of GRE Piping for New Bunkering Station
Standby Seawater Booster Pump
To separate the Instrument and Process Vent at SYA during July SD
To reinstate back the in line strainer at SGC#3 (Train 1 & 2) during July SD
Compressor Shaft Seal Replacement Work During July Shutdown
Miscellaneous Work for July 2010 Shutdown
198 21-May-14 16-May-14 2 Weeks COMPLETE
199 21-May-14 4-Jul-14 2 Weeks COMPLETE
200 27-May-14 6-Jun-14 1 WEEK 0
201 27-May-14 16-Jul-14 2 weeks 0
202 1-Jun-14 16-Aug-14 3 WEEKS ON GOING
203 1-Jun-14 1-Jul-14 9 days COMPLETE
204 9-Jun-14 10-Jun-14 2 months COMPLETE
205 9-Jun-14 4-Jul-14 12 Days COMPLETE
206 9-Jun-14 4-Jul-14 12 Days COMPLETE
To support sorbead change out for V2327 Dehydrator Vessel
Positive isolation and nitrogen purging for July 2010 SD
To remove ram skid from skid from CKC & reinstate the handrail
To install new condensed rubber at CKB & CKC boat landing fenders
To fabricate & install 8 leftover P2 post shutdown pipe support at CKP
To replace cracked GRE flanges at condenser heat exchanger
To provide and install liferaft for July S/D3rd party to supervise the 16" valve actuators installation during July S/D
3rd party for bolt tensioning activities during July shutdown
207 10-Jun-14 24-Jun-14 1 WEEK COMPLETE
208 19-Jun-14 4-Jul-14 12 Days CANCEL
209 19-Jun-14 31-Aug-14 2 WEEKS COMPLETE
210 19-Jun-14 21-Jul-14 2 WEEKS COMPLETE
211 19-Jun-14 25-Jun-14 1 WEEK ON GOING
212 16-Jul-14 Jul/14 3 DAYS COMPLETE
213 17-Jul-14 22-Jul-14 7 days ON GOING
214 21-Jul-14 2-Sep-14 14 days 0
215 22-Jul-14 22-Jul-14 1 WEEK COMPLETE
To install DBB Valves on CKB Production Manifold
3rd party to supervise the 16" valve actuators installation during July S/D
To overhaul Snr. Orifice & Tube inspection at metering system
To replace exisiting cracked weld neck flange & reinstall spool at CKA
To modify cradle for sea water lift pump 4350
To preserve 8 nos of 16" metering valve
To provide scaffold at CKB B-7300
To perform Passive Fire Protection (PFP) application at CCR roof
To supply and fabricate add. Beam support for monorail load testing
216 22-Jul-14 22-Jul-14 1 WEEK 0
217 28-Jul-14 31-Jul-14 1 WEEK 0
218 4-Aug-14 29-Sep-14 1 WEEK 0
219 4-Aug-14 21-Aug-14 2 WEEKS 0
220 4-Aug-14 Feb/15 4 WEEKS 0
221 4-Aug-14 Feb/15 5 Weeks 0
222 4-Aug-14 Feb/15 2 WEEKS 0
To relocate temporarily discharge line of wilden pump from cellar deck to new tie-in point at upper deck
To modify existing Gre piping for additional drop spool at inlet cooling medium coolers (CKP-E-4580)
To erect scaffolding and assist solar FSR to perform engine and RGB change out
To provide acces platform at SGC 3 glass window
To replace all corroded and worn out grating on sea deck area ( CKC platform)
To paint black and yellow stripes at the main beam boat landing (CKB, CKC, BMA, BLA and SYA)
To fabricate and install pipe support
223 4-Aug-14 5-Aug-14 1 WEEK COMPLETE
224 6-Aug-14 16-Sep-14 6 WEEKS 0
225 28-Aug-14 29-Aug-14 1 WEEK COMPLETE
226 25-Aug-14 Dec/14 3 WEEKS 0
227 26-Aug-14 27-Aug-14 1 WEEK ON GOING
228 26-Aug-14 28-Aug-14 1 WEEK COMPLETE
229 28-Aug-14 Dec/14 4 WEEKS 0
230 28-Aug-14 Dec/14 1 WEEK 0
231 31-Aug-14 Feb/15 2 WEEKS 0
To replace pipe spool on pin hole leaking elbow at CKP liquid leg lines
Extension platform for VSAT antenna at LQ CKP
Vessel cleaning V-3702
Installation of produce water reinjection well flowlines
To close the ISO corner holes of the propane tank skid (CKA-V-4110C)
To assist well services on valves and blinds installation
To remove and reinstall wellheads chocke valve (CKA/CKB/CKC/SYA/BMA) for inspection purpose
To secure transmitters capillary tube with proper support (CKP-LIT-2003 and CKP-LIT-2053)
Installation of additional R.O. water maker at CKP-XQ-6012
232 31-Aug-14 Feb/15 2 WEEKS 0
233
TOTAL
NOS Amount
232 #REF!
#REF! #REF!
#REF! #REF!
#REF! #REF!
168 #REF!
20 #REF!
12
31
-
Crane exhaust modification at BMA/BLA/SYA
Total Work Order Request To Date
Total Work Order Proposal
Total Outstanding Work Order Proposal
Total Work Order Approved
Approved Completed Work Order Amount
Amount Work Order On-Going
Total Work Order Cancel
Total Work Order Not Yet Start
Variance (Amount Can't be Utilised)