lithium ion batteries in stationary application - ieee …...the cpc project started as a design...
TRANSCRIPT
![Page 1: Lithium Ion Batteries in Stationary Application - IEEE …...The CPC project started as a design build in spring 2012 – PEEC space is at a premium – The incumbent technology •](https://reader033.vdocument.in/reader033/viewer/2022050306/5f6e808804bdcc74d6053f1e/html5/thumbnails/1.jpg)
José A. Marrero SME Southern Company Generation
Lithium Ion Batteries in Stationary Application
COMPACT POWER CENTER (CPC)
![Page 2: Lithium Ion Batteries in Stationary Application - IEEE …...The CPC project started as a design build in spring 2012 – PEEC space is at a premium – The incumbent technology •](https://reader033.vdocument.in/reader033/viewer/2022050306/5f6e808804bdcc74d6053f1e/html5/thumbnails/2.jpg)
COMPACT POWER CENTER (7 KW-CPC)
![Page 3: Lithium Ion Batteries in Stationary Application - IEEE …...The CPC project started as a design build in spring 2012 – PEEC space is at a premium – The incumbent technology •](https://reader033.vdocument.in/reader033/viewer/2022050306/5f6e808804bdcc74d6053f1e/html5/thumbnails/3.jpg)
Development of the CPC system is the summation of several years worth of research & design, collaboration and negotiation with : Spectral Technologies- Toronto Canada Saft- Corporate and Jacksonville Florida plant Crim Engineering and Sales- Birmingham Alabama Southern Company Technical Services Electrical Design
![Page 4: Lithium Ion Batteries in Stationary Application - IEEE …...The CPC project started as a design build in spring 2012 – PEEC space is at a premium – The incumbent technology •](https://reader033.vdocument.in/reader033/viewer/2022050306/5f6e808804bdcc74d6053f1e/html5/thumbnails/4.jpg)
![Page 5: Lithium Ion Batteries in Stationary Application - IEEE …...The CPC project started as a design build in spring 2012 – PEEC space is at a premium – The incumbent technology •](https://reader033.vdocument.in/reader033/viewer/2022050306/5f6e808804bdcc74d6053f1e/html5/thumbnails/5.jpg)
• Energy Source for remote loads
• capable of providing seven (7KW) loads for two (2) hours on battery reserve.
• Load types are 5kW inverter (120VAC Loads ) and 2KW (125VDC) loads.
AC Distribution Panel– 118-122Vac from no load to full load DC Distribution Panel– 100 – 140Vdc from no load to full load. • Unit is to be equipped with an electrostatic shielded
transformer for the dual AC inputs and Inverter Bypass.
![Page 6: Lithium Ion Batteries in Stationary Application - IEEE …...The CPC project started as a design build in spring 2012 – PEEC space is at a premium – The incumbent technology •](https://reader033.vdocument.in/reader033/viewer/2022050306/5f6e808804bdcc74d6053f1e/html5/thumbnails/6.jpg)
![Page 7: Lithium Ion Batteries in Stationary Application - IEEE …...The CPC project started as a design build in spring 2012 – PEEC space is at a premium – The incumbent technology •](https://reader033.vdocument.in/reader033/viewer/2022050306/5f6e808804bdcc74d6053f1e/html5/thumbnails/7.jpg)
Integrated and centralized power unit, with AC & DC distribution centers incorporating an energy source capable of providing seven (7kW) loads for two (2) hours. Load Needs
AC: ~ 5kW via inverter for DCS/DAS DC: ~ 2kW for switch gear loads
Our typical/designed profile
COMPACT POWER CENTER (7 KW-CPC)
Period
Time (Mins.)
Load
1
119.5
55.00 A
2
0.5
150.00 A
![Page 8: Lithium Ion Batteries in Stationary Application - IEEE …...The CPC project started as a design build in spring 2012 – PEEC space is at a premium – The incumbent technology •](https://reader033.vdocument.in/reader033/viewer/2022050306/5f6e808804bdcc74d6053f1e/html5/thumbnails/8.jpg)
COMPACT / CRITICAL POWER CENTER (7 KW-CPC)
AC DISTRIBUTION PANEL
INVERTER MANUAL-BY-PASS
SWITCH & ALT/Bypass BKR
CONTROLLER RECTIFIER SHELVES
MAIN BREAKERS
RECTIFIER REAKERS
DC DISTRIBUTION PANEL
INVERTER Input BKR
Input & Control power Transformers
ALARM TERMINAL BLOCK
A- BATTERY BLOCK
DC CONTACTORS & Management Controllers
B- BATTERY BLOCK
Load testing Plugs
![Page 9: Lithium Ion Batteries in Stationary Application - IEEE …...The CPC project started as a design build in spring 2012 – PEEC space is at a premium – The incumbent technology •](https://reader033.vdocument.in/reader033/viewer/2022050306/5f6e808804bdcc74d6053f1e/html5/thumbnails/9.jpg)
The CPC project started as a design build in spring 2012 – PEEC space is at a premium – The incumbent technology
• low cost VRLA • VLA with dedicated room
– SAFT IntensiumFlex solution provides: • Integral cell/module/string/battery monitoring • 14 years life at constant 104°F (40°C) • 5,000 CH/DCH cycles to 80% DoD • ~6x smaller volume than VRLA • ~12x lighter than VRLA
Critical Power (5kVA to 7kVA) Vmin: 105Vdc Vmax: 140Vdc Load: 7kWb for 2 hours Temp.: 40°F (minimum) 120°F (maximum)
![Page 10: Lithium Ion Batteries in Stationary Application - IEEE …...The CPC project started as a design build in spring 2012 – PEEC space is at a premium – The incumbent technology •](https://reader033.vdocument.in/reader033/viewer/2022050306/5f6e808804bdcc74d6053f1e/html5/thumbnails/10.jpg)
CPC 7 KW
(~9.5 sqft)
58 – Battery Cells (300-400 Ahrs)
Charger A Inverter
DC Fuse Panel
Charger B
DC Distribution
Panel
AC Distribution
Panel
HVAC, H2 , Eye Wash Stations, Spill containment and so on
![Page 11: Lithium Ion Batteries in Stationary Application - IEEE …...The CPC project started as a design build in spring 2012 – PEEC space is at a premium – The incumbent technology •](https://reader033.vdocument.in/reader033/viewer/2022050306/5f6e808804bdcc74d6053f1e/html5/thumbnails/11.jpg)
WITH OVERALL DIMENSIONS OF 56 inches wide 24 inches deep 72 inches tall
THIS ELIMINATES THE NEED FOR: • LARGE BATTERY ROOMS • FUSE PANELS, DISTRIBUTION PANELS • SPILL CONTAINMENT • SAFETY SHOWERS • LARGE EXHAUST FANS AND HVAC UNITS
CIVIL DESIGN
ENGINEERING
MECHANICAL DESIGN
ENGINEERING
ELECTRICAL DESIGN
ENGINEERING
![Page 12: Lithium Ion Batteries in Stationary Application - IEEE …...The CPC project started as a design build in spring 2012 – PEEC space is at a premium – The incumbent technology •](https://reader033.vdocument.in/reader033/viewer/2022050306/5f6e808804bdcc74d6053f1e/html5/thumbnails/12.jpg)
![Page 13: Lithium Ion Batteries in Stationary Application - IEEE …...The CPC project started as a design build in spring 2012 – PEEC space is at a premium – The incumbent technology •](https://reader033.vdocument.in/reader033/viewer/2022050306/5f6e808804bdcc74d6053f1e/html5/thumbnails/13.jpg)
![Page 14: Lithium Ion Batteries in Stationary Application - IEEE …...The CPC project started as a design build in spring 2012 – PEEC space is at a premium – The incumbent technology •](https://reader033.vdocument.in/reader033/viewer/2022050306/5f6e808804bdcc74d6053f1e/html5/thumbnails/14.jpg)
![Page 15: Lithium Ion Batteries in Stationary Application - IEEE …...The CPC project started as a design build in spring 2012 – PEEC space is at a premium – The incumbent technology •](https://reader033.vdocument.in/reader033/viewer/2022050306/5f6e808804bdcc74d6053f1e/html5/thumbnails/15.jpg)
![Page 16: Lithium Ion Batteries in Stationary Application - IEEE …...The CPC project started as a design build in spring 2012 – PEEC space is at a premium – The incumbent technology •](https://reader033.vdocument.in/reader033/viewer/2022050306/5f6e808804bdcc74d6053f1e/html5/thumbnails/16.jpg)
![Page 17: Lithium Ion Batteries in Stationary Application - IEEE …...The CPC project started as a design build in spring 2012 – PEEC space is at a premium – The incumbent technology •](https://reader033.vdocument.in/reader033/viewer/2022050306/5f6e808804bdcc74d6053f1e/html5/thumbnails/17.jpg)
Summary : - Standardize Unit that Provides AC Power & DC Power
with its associated distribution - Shielded Dual AC Input for both chargers & inverters - All Components are Modular and can be replaced &
maintained online - Fully integrated into our DAS
- Alarms - System Status
- 20 Year Design on all components with minimal routine maintenance
![Page 18: Lithium Ion Batteries in Stationary Application - IEEE …...The CPC project started as a design build in spring 2012 – PEEC space is at a premium – The incumbent technology •](https://reader033.vdocument.in/reader033/viewer/2022050306/5f6e808804bdcc74d6053f1e/html5/thumbnails/18.jpg)
![Page 19: Lithium Ion Batteries in Stationary Application - IEEE …...The CPC project started as a design build in spring 2012 – PEEC space is at a premium – The incumbent technology •](https://reader033.vdocument.in/reader033/viewer/2022050306/5f6e808804bdcc74d6053f1e/html5/thumbnails/19.jpg)
![Page 20: Lithium Ion Batteries in Stationary Application - IEEE …...The CPC project started as a design build in spring 2012 – PEEC space is at a premium – The incumbent technology •](https://reader033.vdocument.in/reader033/viewer/2022050306/5f6e808804bdcc74d6053f1e/html5/thumbnails/20.jpg)
![Page 21: Lithium Ion Batteries in Stationary Application - IEEE …...The CPC project started as a design build in spring 2012 – PEEC space is at a premium – The incumbent technology •](https://reader033.vdocument.in/reader033/viewer/2022050306/5f6e808804bdcc74d6053f1e/html5/thumbnails/21.jpg)
![Page 22: Lithium Ion Batteries in Stationary Application - IEEE …...The CPC project started as a design build in spring 2012 – PEEC space is at a premium – The incumbent technology •](https://reader033.vdocument.in/reader033/viewer/2022050306/5f6e808804bdcc74d6053f1e/html5/thumbnails/22.jpg)
![Page 23: Lithium Ion Batteries in Stationary Application - IEEE …...The CPC project started as a design build in spring 2012 – PEEC space is at a premium – The incumbent technology •](https://reader033.vdocument.in/reader033/viewer/2022050306/5f6e808804bdcc74d6053f1e/html5/thumbnails/23.jpg)