LNG Experience
Owner & Investor Project Management
Sample LNG Personnel
• Mike Britton – ex Conoco Director of Worldwide
Projects incl. PM for Freeport LNG, LNG Qatar ,
Alaska LNG, COP Curtis Island
• Mike Willams – Lead rotating Machinery Engr at
Gladstone LNG and ET Lake Charles LNG
• Dave Luetchford,P.E. – ex Exxon – OE on ET –Shell
LCLNG, PM on various Midstream Gas
Developments on Gulf Coast USA, ALNG2 Russia
with BOMESC China, Exxon Refining
• Jim Scott – Shell Global Practice Leader in Cost
Estimating and Benchmarking for Shell Intl.
• Bertrand Bernard – 35 Years with Shell including
PM for Sakhalin LNG 2, Russia, Qatar and Nigeria
DRL has 35 core team personnel, including eg:
DRL currently playing lead roles in several LNG Owner teams
at Shell Lake Charles and Freeport LNG
Project Management (Operator / Investor)
• Most mega projects fail to meet FID Cost & Schedule
• Contracting Strategies are not meeting the challenges
• Regulatory Permitting Activities are often under-estimated
• Tighter labor market coming
• Even for Co-Investor, governance entails similar liabilities
and responsibilities and therefore requires a spectrum of
capabilities similar to an operated business.
Owner Management – Where we can Help
– Feasibility and Approval Process
– Pre FID Evaluations• Contractor Selection Evaluations
• Scope Validation
• Execution Strategy– Modularization vs. Stick Build
• Cost Validation
• Schedule Validation
• Team size, structure and content (staffing – both
competency assessment and sourcing)
• Risk Identification
– Execution• Progress Monitoring and Control
• Risk Mitigation
OWNER PROJECT
MANAGEMENT SUPPORT
❖ PROJECT MANAGEMENT
❖ PROJECT DUE DILIGENCE
❖ COST REDUCTION METHODS
❖ EXECUTION PLANNING
❖ REGULATORY PLANNING
❖ CONTRACTING STRATEGY
❖ TENDER PACKAGE DEVELOPMENT
❖ FID ESTIMATE & BENCHMARKING
❖ SCHEDULE & BENCHAMARKING
❖ COST CONTROL & FORECASTING
❖ DEVELOPMENT OF WBS WORKPACKS
❖ SAFETY & RISK MANAGEMENT PLANS
❖ FACILITIES COMPLETION METHODS
❖ MOC PLAN
❖ COMMISSIONING & S/U PLANNING
DRL CAPABILITIES
WE HAVE MANAGED 110 JOBS IN USA
Examples of Review Activities
LNG PLANT Cost and Main Contractor
LNG PLANT Cost per tpa
LNG PLANT Cost per tpa
LNG PLANT Cost per tpa
LNG PLANT Cost per tpa
LNG PLANT Cost Drivers
• Major Cost Drivers include:
– Scope is the Biggest Driver
• Capacity / Functionality / Process
Selection / Layout
– Location
• Labor Availability / Weather
– Execution Strategy
– Legislation / Regulatory
– Market Conditions
– Performance
Minimum Process LNG Plant
Maximum Process LNG Plant
Some Differences :-
• Plant Location
• Cost of Labour
• Feed Gas Composition
• Product Specification
• a feed gas handling
and treating section
• a liquefaction section
• a refrigerant section
• a fractionation section
• an LNG storage section
• a marine and LNG
loading section
• a utility and offsite
section
LNG Plants : All Plants are Not Alike
LNG PLANT Cost Differences
Sabine Pass LNG Project
Comparison to Gorgon LNG
Sabine Pass LNG Gorgon LNG
LNG Plant Execution Duration vs. Capacity
Petronas PLNG 1 vs Prelude COSTS
LNG PLANT DATA
Onshore Plant and
Gas Transmission Pipeline
Cost Benchmarking
Onshore Plant Project Database
Onshore
Project Database
125 Plants
14 North American
Gas Transmission
Pipelines
Onshore Plant Cost Benchmarking
Onshore Plant Cost
Benchmarking
Oil Refineries, Gas
Processing Plants, LNG
Plants, Ethane
Crackers, MEG/EO
Plants
Onshore Plant Cost Benchmarking
Onshore Plant Cost
Benchmarking
Polyethylene,
Ammonia, UREA,
Methanol, Gas to
Liquids and Gas Fired
Power Stations
Onshore Gas Transmission Line Cost Benchmarking
“Owner Advisor / Engineer”